Saudi Arabia evaluates bus rapid transport bids
4 March 2025

Saudi Arabia’s Al-Madinah Region Development Authority (MDA), through the National Centre for Privatisation & PPP (NCP), has been evaluating bids it received in November for a contract to develop and operate a bus rapid transit (BRT) network in Medina.
The project scope involves financing, procuring and delivering depots, rolling stock and intelligent transportation systems (ITS). It also covers the bus fleet’s operation and maintenance and fare collection.
According to an industry source, the firms that submitted bids for the contract include a team of France's RATP Dev and the local Saptco, a team of the UK's National Express and the local Hafil, and a team comprising France's Transdev and Nesma.
The NCP issued the Medina BRT project tender in February last year, as MEED reported. It will be implemented using a public-private partnership (PPP) framework.
Forty-three companies expressed interest in the contract to develop the BRT project in July 2023. The MDA subsequently prequalified three consortiums and seven individual companies to bid for the contract.
The planned Medina BRT comprises three corridors with a total length of 64.6 kilometres (km) and a feeder bus network.
The project has an estimated capacity of 1,800 passengers an hour.
The first route, which will stretch 16.2km from Ohud to Quba Mosque, will have 12 stops and two park-and-ride facilities.
The second and main route will be 38km long. It will start from Medina’s Prince Mohammed Bin Abdulaziz International airport, pass the Prophet’s Mosque and terminate at Miqat Mosque. The route will have 24 stations and three park-and-ride bus stops.
The third corridor starts from the eastern terminus on Al-Qassim Road and runs to Prince Abdul Majeed Mosque. It is 10.4km long, with 10 stations and a park-and-ride facility.
The project will be developed on a design, build, finance, operate and maintain basis.
A consortium of French engineering firms Egis and Systra will provide project consultancy services for the Medina BRT project.
Pioneering transport PPP
Based on the plan, the private sector will be responsible for financing, designing and building the depots; financing and procuring the rolling stock or bus fleet and the ITS; and delivering the operations and maintenance for the BRT lines.
Representing the public sector, the MDA will execute and deliver the civil works on the project, including the bus lanes, tunnels, bridges and viaducts.
The MDA appointed a team of UK-based Deloitte, the US/Saudi HDR Middle East and the local Abdul Rahman Fahad Al-Khaili as transaction advisers for the project in 2021.
JOIN THE LEADERS BUILDING VISION 2030 AT THE 3RD EDITION OF MEED's SAUDI GIGAPROJECTS SUMMIT
12-14 May – Riyadh, Saudi Arabia
CLICK HERE TO REGISTER YOUR INTEREST
Exclusive from Meed
-
Emaar tenders Dubai Creek Harbour mall27 November 2026
-
Contractor wins Arabian Beauty Horses Village in Qatar27 November 2026
-
King Salman airport sets new infrastructure bid deadline27 November 2026
-
PIF secures inaugural A+ rating from S&P26 November 2026
-
Ras Al-Khaimah sewage PPP reaches financial close26 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Emaar tenders Dubai Creek Harbour mall27 November 2026

Dubai developer Emaar Properties has invited contractors to submit bids by 9 December for the main construction package of the Dubai Creek Harbour mall, known as Dubai Square.
The development covers a total retail, hospitality and commercial area of 2.6 million square metres, and is scheduled to open within three years.
Emaar unveiled Dubai Square in December 2025 as the anchor of its AED180bn ($49bn) Dubai Creek Harbour development.
The scheme has undergone several redesigns. MEED first reported on Emaar’s plans for a major retail centre at Dubai Creek Harbour in 2016. At the time, the project was envisioned to surpass Dubai Mall as the world’s largest retail destination, though its scale and layout have since evolved.
The mall will connect directly to the planned Dubai Creek Tower at the centre of the development.
UK-headquartered Brewer Smith Brewer Group is the project’s lead consultant, executive architect, architect of record and structural engineer. It is also the construction supervision consultant.
Dubai-based contractor Dutco Construction began mobilising last year for early site works.
In March last year, MEED reported that Emaar was preparing to relaunch development of both the tower and the mall. The developer had earmarked roughly AED14bn ($3.81bn) for the two assets as part of a wider AED65bn ($18bn), five-year capital expenditure programme.
Progress on the tower has been slower. First launched in 2015, it was promoted as the world’s tallest structure, designed to exceed the 828-metre Burj Khalifa. The original design was led by Spanish architect Santiago Calatrava and UK-based RMJM. The project stalled after concrete pile-cap works were completed in 2018.
In 2023, Emaar founder Mohamed Alabbar confirmed design works were continuing following an international design competition. In January 2026, Alabbar stated that a tender for the redesigned tower would be issued within three months. He later said the tender would be deferred until regional geopolitical tensions ease.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: UAE Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21892263/main.jpg -
Contractor wins Arabian Beauty Horses Village in Qatar27 November 2026

Qatar’s Culture Village Foundation (Katara) has awarded Qatar Trading & Contracting Group a QR574m ($158m) contract to build the Arabian Beauty Horses Village in Al-Uqdah Zone 74, in the Al-Khor area.
The project will include supporting infrastructure and public facilities designed for Arabian show horses and equestrian operations in the Al-Uqdah district.
Zone 74 is already an important centre for Qatar’s equestrian sector, anchored by the Al-Uqdah Equestrian Complex. The Qatar Racing & Equestrian Club began operating the complex in 2020 in coordination with Qatar’s Ministry of Culture and Sports.
The Arabian Beauty Horses Village is part of a broader, multistage state strategy to develop Al-Uqdah, on the outskirts of Al-Khor, as Qatar’s second major equestrian hub, alongside Al-Rayyan and Al-Shaqab in Doha.
According to UK analytics firm GlobalData, Qatar’s commercial construction sector is expected to grow at an average annual rate of 4.5% between 2025 and 2028, supported by investment in hotels, logistics facilities and data centres.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21890026/main.jpg -
King Salman airport sets new infrastructure bid deadline27 November 2026

Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has set a 10 January deadline for bids for the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.
The tender was issued on 26 October, with an initial bid-submission deadline of 6 December.
The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.
The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and part of Mohamed bin Faraj Road 5333, west of Junction 6.
It also includes new roads, ramps, service roads and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.
Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.
The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.
Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.
Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.
The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.
Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.
Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.
The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21887157/main.png -
PIF secures inaugural A+ rating from S&P26 November 2026
Saudi Arabia’s Public Investment Fund (PIF) has received an inaugural A+ long-term foreign and local currency issuer credit rating from S&P Global Ratings, with a stable outlook.
The fund’s existing A-1 short-term rating from S&P is unchanged. PIF said its ratings are in line with those of Saudi Arabia.
PIF said S&P’s assessment cited its diversified funding profile, moderate leverage and its focus on value realisation under its 2026-30 strategy. The agency also pointed to the fund’s role in driving the kingdom’s economic transformation.
“The inaugural A+ long-term rating from S&P marks an important milestone in the continued development of PIF’s credit profile and our long-term funding plan,” said Ziyad Alfawzan, head of capital finance strategy at PIF.
The new rating makes PIF one of a small number of sovereign wealth funds with long-term credit ratings from all three leading agencies.
Moody’s Ratings confirmed PIF’s Aa3 long-term issuer rating and aa3 baseline credit assessment in September after a periodic review, with a stable outlook. In October, Fitch Ratings affirmed the fund’s long-term foreign and local currency issuer default ratings at A+, also with a stable outlook.
The Moody’s rating is one notch higher than the A+ grades from S&P and Fitch.
Debt is an increasingly important source of funding for PIF as it pays for domestic investment programmes and gigaprojects.
The fund raised $2bn in January from a 10-year sukuk, its first debt sale of 2026. In May, it raised $7bn from a three-tranche bond, its first hard-currency public issuance since the Iran conflict disrupted regional capital markets.
A full set of long-term ratings is likely to widen PIF’s investor base for future bond and sukuk issuance. The fund also borrows through loans and other debt instruments as part of its funding mix.
PIF is entering what it calls the value realisation phase of its strategy, covering 2026 to 2030. Over this period, it aims to deliver sustainable financial returns while continuing to drive the diversification of the Saudi economy.
MEED’s latest report on Saudi Arabia includes:
> COMMENT: Saudi projects hold steady
> GOVERNMENT: Riyadh looks to reset its regional defence outlook
> ECONOMY: Conflict bolsters case for Saudi economic diversification
> BANKING: Saudi lenders readjust to lower lending and deposit climate
> UPSTREAM: Aramco upstream spending gathers pace
> DOWNSTREAM: Sabic steps up Saudi petchems investment
> POWER: Saudi Arabia’s power award activity slows
> WATER: Saudi water sector hits sharp slowdown
> CONSTRUCTION: Saudi construction defies the headwinds
> TRANSPORT: Saudi infrastructure pushes forward amid conflict
> DATABANK: Saudi data indicates project spending shiftTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21868102/main.gif -
Ras Al-Khaimah sewage PPP reaches financial close26 November 2026
A consortium led by Etihad Water & Electricity (EtihadWE) has reached financial close on the AED1.2bn ($326m) Rakwa independent sewage treatment plant (ISTP) in Ras Al-Khaimah.
EtihadWE’s partners are Abu Dhabi National Energy Company (Taqa) subsidiary Taqa Water Solutions and France’s Saur. Commercial operations are scheduled to start in early 2029. The announcement was made on 25 November at the RAK Energy Summit.
The project debt comes from a lender group of Emirates NBD, Emirates Islamic, Abu Dhabi Islamic Bank, Emirates Development Bank and HSBC. The financing follows the Green Loan Principles 2025 and qualifies as ‘blue’ infrastructure because of its focus on wastewater treatment and water reuse.
Ajman Bank, RAKBank and Dubai Islamic Bank are funding the equity bridge loans.
The plant will have an initial capacity of 60,000 cubic metres a day (cm/d), with design provisions to expand to 150,000 cm/d. In its first phase, it will serve a population equivalent of more than 300,000.
The scope also covers the Sector 6 pumping station, gravity sewer mains, a 30-kilometre treated sewage effluent de-transmission line and 20km of twin rising mains.
The plant will meet its electricity needs throughout its operating life from solar photovoltaic generation and battery energy storage. It will produce treated water for irrigation and recover sludge for reuse.
The scheme will serve residential, hospitality and commercial development in southern Ras Al-Khaimah, including Al-Hamra and Al-Marjan Island.
Saur International will commit capital, staff and expertise for the life of the concession.
Ras Al-Khaimah’s Public Services Department (PSD) and Investment & Development Office procured the contract. They prequalified 13 companies and consortiums to bid in September 2024.
The government, represented by the PSD, signed the long-term sewage treatment agreement with the consortium in January this year. The project is structured as a build-own-operate-transfer scheme. Synergy Consulting is the consortium’s financial adviser.
It is Ras Al-Khaimah’s first sewage treatment plant public-private partnership. EtihadWE is also preparing to procure another utility PPP in the emirate – an expansion of the seawater reverse osmosis plant in Ghalilah.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21867979/main.jpg
