World’s largest piling project shifts to The Line’s marina
26 March 2023
Image: Work on module 43 of The Line has peaked at more than 60 piles a day

Neom is preparing to shift the focus of the world’s largest piling project to The Line modules at the marina as excavation work for the waterway reaches an advanced stage.
The structures that make up The Line comprise 135 modules that are 800 metres in length and 500 metres tall at sea level. In total, The Line is 170 kilometres long and extends from the Red Sea coast inland towards Tabuk.
Modules 45, 46 and 47 are at the marina, which is expected to be two times bigger than any other marina in the world and capable of hosting the largest cruise ships.

Module 45: Each module will contain eight buildings on large-diameter bored piles
The marina is located on the other side of The Line to the sea, so ships must pass through The Line buildings.
This is a major engineering challenge as it means creating a 165-metre-wide waterway passing through the 500-metre-tall buildings.
The largest cruise ship is the Wonder of the Seas, which is 67 metres wide and 72 metres tall, and requires a draught of nearly 10 metres.

The Line will be able to host Royal Caribbean's Wonder of the Seas, the world's biggest cruise ship, which made its debut in March 2022. Credit: Neom via Twitter
The water channel entering the marina will also have to pass over The Spine, a subterranean infrastructure corridor running the length of The Line, which includes the high-speed railway lines. There are railway stations at every third module along The Line.

Module 46: As piling work moves to modules 46 and 47, the level of activity will increase even further
The marina is also proposed to include a 45,000-seat sports stadium built 300 metres above ground in between The Line buildings.
The marina is the largest excavation project in the world, with about 1 million cubic metres of earth being moved every week.
Once the excavation work and dewatering for the marina reach an appropriate stage, piling works will start.
So far, the piling work for The Line has been concentrated on module 43, where more than 4,500 piles have been installed. Work has reached a peak of more than 60 piles a day, making it the largest piling project in the world.
As piling work shifts to modules 46 and 47, the activity level is expected to increase even further.

Module 47: Excavation of about 1 million cubic metres of earth is taking place each week at the marina
Nine contractors are working on the piling as part of a framework agreement. Six of these are onsite. They are the local Al-Osais, Germany’s Bauer, the UK’s Keller, UAE-based NSCC, Beijing-based PowerChina and Italy’s Trevi.
The other three firms that are part of the framework agreement are France’s Bachy Soletanche, the local Huta and Saudi Baytur.
Three firms are working with Neom as delivery partners for The Line. They are UK-based Atkins and two US firms, Jacobs and Parsons.
The Line is designed to ultimately house 9 million residents who will have access to the development’s facilities within a five-minute walk. A high-speed rail system will have an end-to-end journey time of 20 minutes.

The city, including the planned 45,000-seat, suspended stadium, will be built within the 500-metre-high walls. Credit: Neom via Twitter

Sindalah island, spanning 840,000 square metres, is the first of a group of islands to be developed at Neom. In March, Neom signed a deal with Marriott International to open three properties on the luxury island. Plans for Sindalah include building over 400 premium hotel rooms and 300 suites, as well as an 86-berth marina for yachts up to 75 metres and serviced offshore buoys for superyachts up to 180 metres.
MEED's April 2023 special report on Saudi Arabia includes:
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack
Exclusive from Meed
-
Projects market holds firm18 November 2026
-
OMV to drill Libya oil and gas exploration well18 November 2026
-
Indonesian contractor wins Algerian gas project deal18 November 2026
-
Frontrunners emerge for Saudi Arabia’s seventh solar IPP round17 November 2026
-
Al-Ula launches $6.8bn PPP project opportunities17 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Projects market holds firm18 November 2026
Commentary
Colin Foreman
EditorAfter eight months of conflict in the Gulf, the region’s economies are sustaining heavy damage. The IMF’s October World Economic Outlook forecasts contraction in every GCC state except Oman in 2026. Kuwait’s economy is projected to shrink by 16.7% and Qatar’s by 15.6% as disruption in the Strait of Hormuz cuts energy exports.
The projects market has held up far better. Data from MEED Projects shows the UAE leading the region for a second consecutive year, with contract awards 6.1% higher than in the same period of 2025. Abu Dhabi has been the standout, with awards up 35% on the back of a sharp rise in public capital spending. Saudi Arabia has awarded $68.8bn of contracts so far this year, 13% less than in 2025.Two key drivers are shaping the market in 2026. First, private developers, faced with declining off-plan sales, are focusing on project completion to unlock cash from investors who have already purchased property. Second, government and state-related entities have accelerated activity, pushing ahead with large-scale public infrastructure schemes alongside more commercially oriented developments.
Abu Dhabi has been the standout, with awards up 35% on last year
Warning signs remain beneath the headline totals. Tendering has slowed since hostilities resumed after the April ceasefire, and Dubai’s residential market has weakened, marked by a steep year-on-year drop in Q3 transactions. The effect on contract awards is likely to become clearer in the coming months.
The conflict is also generating new demand. Saudi Arabia and the UAE are prioritising ports, pipelines and transport links that bypass Hormuz, and reconstruction and repair work will follow once the fighting ends.
The central question for the final quarter is whether the Q3 slowdown marks a temporary pause or the start of a sustained decline.
Much will depend on when the strait reopens.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21514495/main.gif -
OMV to drill Libya oil and gas exploration well18 November 2026
Austrian oil and gas company OMV is planning to start drilling an exploration well in Libya’s Marwa concession before the end of this month, according to a statement from the North African country’s National Oil Corporation (NOC).
In its statement, NOC said that it held an “extensive technical meeting” with officials from OMV to discuss the company’s plans and contractual obligations.
The meeting reviewed activities carried out throughout 2026 alongside programmes scheduled for 2027.
NOC said: “Officials also addressed ways to overcome challenges hindering the completion of remaining work, including seismic surveys and exploration well drilling.”
During the meeting, OMV confirmed that preparations are under way to drill its first exploration well at the Marwa concession in Contract Area 103/3 (NC74B) by the end of November, targeting a depth of approximately 6,500 feet.
NOC’s Exploration Department said that intensifying oil and gas exploration is a key strategic priority for the organisation.
In June, NOC announced a capacity target of 2 million barrels of oil a day by 2030.
Earlier this month, Libya’s Audit Bureau said it had held a meeting with NOC to discuss tendering a project to rehabilitate and develop Libya’s Dahra oil field.
The head of the Audit Bureau, Khaled Shakshak, met with NOC head Masoud Suleiman on 15 November.
During the meeting, they discussed options for tendering the Dahra oil field development project, previously estimated at $1bn and expected to significantly increase the field’s oil production.
The oil field in central Libya has suffered from years of poor maintenance and was sabotaged by Islamic State militants in 2015.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21479617/main.jpg -
Indonesian contractor wins Algerian gas project deal18 November 2026
Indonesia’s Synergy Engineering has been officially awarded a design contract for a planned gas project in Algeria, according to a statement published in the country’s official energy and mining procurement bulletin.
The official contract award follows a provisional award that was announced on 29 July.
The front-end engineering and design (feed) contract has been awarded by Pertamina Algeria Eksplorasi Produksi (PAEP), which is a subsidiary of Indonesia’s state-owned energy company.
PAEP awarded the contract in association with Algeria’s national oil and gas company Sonatrach and Spain’s Repsol.
Sonatrach, Pertamina and Repsol are partners in Block 405a of the Menzel Ledjmet Nord (MLN) field.
The feed contract covers the development of a liquefied petroleum gas plant and a water injection facility at the MLN field as part of the field’s fifth development phase.
The contract has a 24-month term, according to the official statement.
Block 405a is situated onshore in the Illizi-Ghadames Basin in eastern Algeria. It comprises eight oil and gas fields split over three onstream development areas.
Algeria is home to Africa’s second-largest proven natural gas reserves after Nigeria. It is also Africa’s largest natural gas producer.
Amid ongoing issues exporting oil and gas from the GCC due to disruptions to shipping through the Strait of Hormuz, Algeria is seeking to increase its oil and gas exports to meet European demand.
In July, Algerian President Abdelmadjid Tebboune oversaw the signing of dozens of bilateral agreements as part of a wider push to bolster political and economic ties between Germany and Algeria.
The agreements included several focused on oil, gas and energy.
On 2 July, Sonatrach delivered its first shipment of liquefied natural gas (LNG) directly to Germany’s Wilhelmshaven 1 floating LNG import terminal.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21479337/main.gif -
Frontrunners emerge for Saudi Arabia’s seventh solar IPP round17 November 2026

Register for MEED’s 14-day trial access
Four bidders are understood to be leading the race for contracts to develop four solar photovoltaic (PV) independent power projects (IPPs) under the seventh round of Saudi Arabia’s National Renewable Energy Programme (NREP).
Round seven comprises the 1,400MW Tabjal 2, 600MW Mawqqaq, 600MW Tathleeth and 500MW South Al-Ula solar IPPs.
Saudi Power Procurement Company (SPPC) is procuring the renewables programme, with the Energy Ministry supervising it.
Developers submitted bids in September, as MEED reported exclusively.
According to industry sources, the following bidders and bidding groups have emerged as frontrunners to win one project each:
- Aljomaih (Saudi Arabia) / TotalEnergies (France)
- EDF (France) / Saudi Energy
- Etihad Water & Electricity (UAE) / Korea Electric Power Corporation (South Korea)
- Wahajpeak (Saudi Arabia)
An award for Wahajpeak would mark the company’s first major infrastructure award in the region since US-based infrastructure investment firm Stonepeak established it in 2025.
At least some solar contracts are expected to be finalised by year-end.
In addition to the four solar plants, round seven comprises two wind IPPs with a total combined capacity of 5,300MW.
In October, MEED exclusively reported that consortiums had submitted bids for the two wind projects: the 1,300MW Bilgah and 900MW Shagra schemes.
These include:
- Abu Dhabi Future Energy (Masdar) / EDF (France) / Saudi Energy
- EtihadWE (UAE) / Nesma Renewable Energy (Saudi Arabia) / Korea Electric Power Corporation (Kepco, South Korea)
The request for proposals (RFPs) for both wind and solar were issued in January.
As MEED reported, 16 developers qualified to bid as both managing and technical members of consortiums for the four solar PV projects. A further six companies qualified to bid as managing members only.
For the wind IPPs, SPPC qualified 13 developers in the managing and technical members category and a further six companies in the managing members category only.
Round eight
SPPC will release the RFP notices in December for the eighth round of its renewable energy procurement programme, as exclusively reported by MEED.
The round comprises three solar and wind projects with a combined capacity of 3.2GW.
SPPC issued the request for qualifications (RFQ) notice on 11 November. Developers have until 22 November to submit qualification documents, as MEED reported last week.
Round eight includes the following projects:
- 900MW Tamir solar PV project in Riyadh
- 1GW Sharq Al-Amwaj solar PV project in Asir
- 1.3GW Al-Muzairah wind project in Mecca
The NREP is designed to increase renewable generation capacity and reduce liquid-fuel use in power generation.
Saudi Arabia aims for renewable energy and energy storage systems to account for about 50% of the kingdom’s electricity generation mix by 2030.
Earlier rounds under the NREP have already deployed large capacities. In October 2025, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP. These were four solar PV IPPs and one wind IPP, with a total combined capacity of 4,500MW.
The Aljomaih / TotalEnergies joint venture won the contract to develop the 400MW Al-Sufun solar IPP. Two of the three remaining solar IPPs in round six were awarded to Masdar, while the joint venture of EDF and Saudi Energy was selected to develop the 600MW Samtah solar IPP.
A consortium of the UAE’s Etihad Water & Electricity, Saudi Arabia’s Nesma Renewable Energy and Korea Electric Power Corporation (South Korea) won the contract to develop the 1,500MW Dawadmi wind IPP, the only wind project in the round.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21466519/main.jpg -
Al-Ula launches $6.8bn PPP project opportunities17 November 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Royal Commission for AlUla (RCU) has announced six public-private partnership (PPP) investment opportunities with a combined estimated value of SR25.4bn ($6.8bn).
The schemes cover road infrastructure, water storage, wastewater treatment, solid waste management and the expansion of Al-Ula International airport.
They are progressing under the National Centre for Privatisation’s approved privatisation plan, with requests for proposals (RFP) expected from the second quarter of 2027 through early 2028.
The opportunities are:
Secondary roads expansion: RCU plans to develop 18 secondary roads and utility corridors totalling about 1,400 kilometres (km). The SR17bn ($4.5bn) project includes new roads and networks for water supply, electricity, telecommunications, street lighting and stormwater drainage.
The project covers 22 million square metres (sq m) and will be delivered using a design-build-finance-operate-maintain (DBFOM) model.
The concession will run for about 20 years and will use availability-based payments. The private partner will operate and maintain the roads, while the utility infrastructure will be handed over to the relevant entities.
The RFP process for the project packages is planned to start in early 2028, with phased completion targeted by 2033. Expressions of interest are due by 30 September 2027.
Highways and primary roads expansion: The SR4bn ($1bn) opportunity covers the development and upgrade of five primary roads and associated utility networks, totalling 204km.
The scope includes new roads, rehabilitation works, cycling paths and traffic-calming measures. It also includes water, electricity, telecommunications and stormwater-drainage infrastructure. The investment area is 3 million sq m.
The scheme will be procured as a DBFOM project with availability-based payments and a 15-year concession. The concessionaire will operate and maintain the roads, while utilities will be handed over to the relevant entities.
RCU expects to begin the RFP process in early 2028 and has set phased completion by 2032. Expressions of interest are due by 30 September 2027.
Al-Ula International airport expansion: The SR2bn ($532m) airport project will include a 30,000 sq m passenger terminal with a capacity for up to 3 million passengers a year, a 5,000 sq m cargo terminal with equestrian facilities and a 10,000 sq m private aviation terminal.
The scope also includes general aviation and helicopter facilities, a runway extension to 3,000 metres, roads, parking, maintenance facilities, utilities and fuel facilities.
The project has a gross floor area of 45,000 sq m and covers a 7 million sq m site.
About 1 million sq m of land will be available for associated commercial development, including logistics, retail, hospitality and aviation services.
The project will use a build-transfer-operate model with a concession period of up to 35 years.
RCU expects to launch the RFP in the third quarter of 2027 and is targeting completion by 2032. The interest submission deadline is 30 June 2027.
Integrated solid waste management system: The SR1bn ($266m) project involves developing and operating an integrated solid waste management system over a 1.4 million sq m area.
The scope includes a resource management park; a waste transfer station with a capacity of 76,000 tonnes a year; recycling facilities with a capacity of 45,000 tonnes a year; organic waste treatment facilities; and construction and demolition waste-processing facilities with a capacity of 220,000 tonnes a year.
It also includes engineered landfill cells with a combined capacity of 5 million cubic metres and associated infrastructure.
The project will be delivered through a DBFOM concession lasting 30 years, including three years of construction and 27 years of operations.
Payments will comprise performance-based payments, waste gate fees and transfer fees.
RCU expects to issue the RFP in the second quarter of 2027. The deadline for interest is 31 May 2027.
Strategic water storage tanks: RCU plans to develop and operate five strategic potable-water storage tanks with a combined capacity of 295,000 cubic metres. The SR900m ($239m) scheme is intended to provide between three and four days of potable-water reserves.
The project includes pumping stations, water connection networks and supporting infrastructure to serve urban districts, heritage sites, Al-Ula International airport and new development areas.
The investment area covers 75,000 sq m.
The project will be structured as a DBFOM concession lasting about 15 years, including two to three years of construction and 12 to 13 years of operations and maintenance.
The availability-based payment mechanism will be linked to performance and water quality.
RCU expects to issue the RFP in the fourth quarter of 2027, with phased completion targeted by 2031. Interested companies have until 30 November 2027 to submit their interest.
Wastewater treatment plant enhancement and operation: The SR454m ($120m) wastewater scheme will rehabilitate Al-Ula’s existing wastewater treatment plant and expand its capacity using moving-bed biofilm reactor technology.
The existing plant has a capacity of 8,000 cubic metres a day (cm/d). The first phase will add 18,000 cm/d, followed by a 36,000 cm/d second phase, increasing overall capacity to 62,000 cm/d.
The 501,000 sq m project includes treated wastewater storage and pumping facilities, control systems and supporting infrastructure.
The project will be delivered using a build-own-operate-transfer model with a 26-year concession. This comprises three years for construction and rehabilitation and 23 years of operations. The payment structure will include capacity, output and supplemental payments.
RCU expects to launch the RFP in the second quarter of 2027. The deadline for interest is 31 May 2027.
RCU was established in 2017 to develop and protect Al-Ula as a cultural, heritage, tourism and economic destination.
The commission launched its masterplan in 2021, setting out a long-term development programme centred on the Hegra Historic City, Nabataean Horizon, Jabal Ikmah, Dadan and Al-Ula Old Town districts.
The wider Al-Ula programme includes heritage conservation, hotels and resorts, cultural venues, residential projects, agricultural development, transport systems and enabling infrastructure.
The latest opportunities form part of the infrastructure programme required to support the region’s planned tourism, residential and commercial development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21465369/main.png