World’s largest piling project shifts to The Line’s marina
26 March 2023
Image: Work on module 43 of The Line has peaked at more than 60 piles a day

Neom is preparing to shift the focus of the world’s largest piling project to The Line modules at the marina as excavation work for the waterway reaches an advanced stage.
The structures that make up The Line comprise 135 modules that are 800 metres in length and 500 metres tall at sea level. In total, The Line is 170 kilometres long and extends from the Red Sea coast inland towards Tabuk.
Modules 45, 46 and 47 are at the marina, which is expected to be two times bigger than any other marina in the world and capable of hosting the largest cruise ships.

Module 45: Each module will contain eight buildings on large-diameter bored piles
The marina is located on the other side of The Line to the sea, so ships must pass through The Line buildings.
This is a major engineering challenge as it means creating a 165-metre-wide waterway passing through the 500-metre-tall buildings.
The largest cruise ship is the Wonder of the Seas, which is 67 metres wide and 72 metres tall, and requires a draught of nearly 10 metres.

The Line will be able to host Royal Caribbean's Wonder of the Seas, the world's biggest cruise ship, which made its debut in March 2022. Credit: Neom via Twitter
The water channel entering the marina will also have to pass over The Spine, a subterranean infrastructure corridor running the length of The Line, which includes the high-speed railway lines. There are railway stations at every third module along The Line.

Module 46: As piling work moves to modules 46 and 47, the level of activity will increase even further
The marina is also proposed to include a 45,000-seat sports stadium built 300 metres above ground in between The Line buildings.
The marina is the largest excavation project in the world, with about 1 million cubic metres of earth being moved every week.
Once the excavation work and dewatering for the marina reach an appropriate stage, piling works will start.
So far, the piling work for The Line has been concentrated on module 43, where more than 4,500 piles have been installed. Work has reached a peak of more than 60 piles a day, making it the largest piling project in the world.
As piling work shifts to modules 46 and 47, the activity level is expected to increase even further.

Module 47: Excavation of about 1 million cubic metres of earth is taking place each week at the marina
Nine contractors are working on the piling as part of a framework agreement. Six of these are onsite. They are the local Al-Osais, Germany’s Bauer, the UK’s Keller, UAE-based NSCC, Beijing-based PowerChina and Italy’s Trevi.
The other three firms that are part of the framework agreement are France’s Bachy Soletanche, the local Huta and Saudi Baytur.
Three firms are working with Neom as delivery partners for The Line. They are UK-based Atkins and two US firms, Jacobs and Parsons.
The Line is designed to ultimately house 9 million residents who will have access to the development’s facilities within a five-minute walk. A high-speed rail system will have an end-to-end journey time of 20 minutes.

The city, including the planned 45,000-seat, suspended stadium, will be built within the 500-metre-high walls. Credit: Neom via Twitter

Sindalah island, spanning 840,000 square metres, is the first of a group of islands to be developed at Neom. In March, Neom signed a deal with Marriott International to open three properties on the luxury island. Plans for Sindalah include building over 400 premium hotel rooms and 300 suites, as well as an 86-berth marina for yachts up to 75 metres and serviced offshore buoys for superyachts up to 180 metres.
MEED's April 2023 special report on Saudi Arabia includes:
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack
Exclusive from Meed
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iraq enters era of resilience, reform and rising risks11 May 2026

Iraq’s projects market is at an inflection point. The country has built a sizeable and increasingly diverse projects pipeline, backed by ambitious national plans and an improving reform narrative. But according to MEED’s newly updated Iraq Projects Market report, the near-term outlook is now being tested by renewed regional volatility and persistent structural constraints at home.
Iraq is the Middle East and North Africa’s fifth-largest economy by nominal GDP, yet it remains heavily exposed to the hydrocarbons cycle. Oil and gas generate about 90% of government revenues and more than 40% of GDP, a dependency that shapes annual capital spending and the bankability of public-private partnership (PPP) deals. Earlier this year, the IMF forecast GDP growth of 3%-4%. In light of the latest regional conflict dynamics involving the US and Israel with Iran, that growth outlook is expected to soften as investor risk perceptions rise and supply chains face renewed stress.
Even so, Iraq’s projects market is not starting from a blank slate. By the end of March 2026, almost $120bn of contracts were in execution, with a further $300.4bn in the broader pipeline. The scale of that opportunity is underpinned by enduring reconstruction requirements, urgent energy-sector needs and a policy push to translate oil wealth into long-lived productive assets.
Reconstruction needs
Nearly a decade after the official end of the Islamic State conflict, Iraq’s reconstruction gap remains substantial. Estimates put the shortfall at about $88bn, reflecting the long tail of damage to housing, utilities, public buildings and transport links. Southern and central regions dominate the live pipeline, largely because they sit close to Iraq’s oil heartlands. Basra, in particular, is pivotal, anchoring major upstream activity and vital export infrastructure.
At the policy level, Iraq Vision 2030 signals a long-term ambition to diversify into tourism, agriculture, industry and digital transformation. The government’s immediate delivery vehicle is the National Development Plan (NDP) 2024-28, which commits more than $17bn a year in capital expenditure and prioritises energy, transport, housing and water infrastructure. This shift is reinforced by Iraq’s Green Growth Framework (2026), indicating that future procurement may place greater weight on efficiency, emissions reduction and climate resilience.
Macro risk
Despite policy ambition, the most immediate determinant of Iraq’s fiscal room is the oil price. A $10-a-barrel drop can reduce government revenue by an estimated $7bn-$9bn annually. Such sensitivity matters because infrastructure spending is still largely funded by the public purse. Oil price swings affect project awards, payment cycles and the government’s willingness to assume up-front capex obligations.
Iraq’s execution environment continues to be defined by bureaucratic delays, unclear land titles and opaque procurement processes. These factors can add 12-24 months to average delivery timelines. Nevertheless, there are signs of adaptation. PPP legislation is advancing, and developer-led models are gaining traction in large housing programmes. Furthermore, there is a growing reliance on international project management consultancy (PMC) firms—such as Hill International, Worley, and AtkinsRealis—to bridge capacity gaps and improve governance, cost control and scheduling.
Hydrocarbon driver
Oil and gas upstream remains the single largest driver of capital expenditure. Major developments, including the Gas Growth Integrated Project (GGIP) and Mansouriya, sit alongside a push to reduce gas flaring and expand downstream processing. The objective is to sustain export revenues while improving domestic fuel availability.
The power sector is even more urgent. Iraq faces an estimated 8-10GW generation shortfall, which keeps electricity supply at the centre of political risk. This gap is driving rapid procurement of generation capacity and grid upgrade contracts. Beyond traditional infrastructure, Iraq is also moving on digital adoption. Smart city pilots and fibre rollouts are attracting regional technology investors, while AI-enabled data centre projects are beginning to emerge.
Investment targets
Foreign direct investment (FDI) remains below $3bn a year, a low figure relative to market size. The most active investors outside the oil sector include the UAE, Saudi Arabia and Kuwait. To convert interest into deals, the National Investment Commission (NIC) is pursuing streamlined licensing and investor-protection reforms. A “one-stop shop” approach has reportedly reduced registration timelines for foreign investors from months to weeks in key sectors.
Investor protection mechanisms, such as access to international arbitration, are being strengthened, though enforcement remains a concern. Iraq’s three free zones—Basra, Karbala and Nineveh—offer additional incentives including tax holidays and customs exemptions, provided they can be paired with reliable utilities and bankable arrangements.
Conflict premium
The latest escalation involving the US and Israel with Iran has increased Iraq’s security risk premium. This is inflating materials costs and disrupting supply chains near eastern border zones. Even where projects are far from conflict areas, contractors are pricing in higher contingency for logistics and insurance. Iraq must also balance deep economic ties with Iran—particularly in energy—with Western investor expectations and sanctions-related compliance.
With more than 60% of its population under 25, Iraq has a potential demographic dividend, but it also faces immediate employment pressure and a shortage of skilled technical labour. Iraq’s projects market outlook for 2026 is best described as cautiously constructive. The pipeline is deep and the need is undeniable, but delivery will hinge on whether Iraq can translate plans into predictable execution. If progress on procurement and contract enforcement continues, Iraq can sustain a broad-based market that extends beyond hydrocarbons.
Click here to learn more about MEED’s newly updated Iraq Projects Market report
https://image.digitalinsightresearch.in/uploads/NewsArticle/16782507/main.gif -
Qiddiya seeks firms for light rail transit system11 May 2026

Saudi gigaproject developer Qiddiya Investment Company (QIC) has requested contractors to express interest in a contract to design and build the first phase of the light rail transit system at Qiddiya Entertainment City.
The notice was issued on 5 May, with firms given until 20 June to submit expressions of interest.
The project, also known as the Primary Urban Axis, comprises a 22-kilometre automated, driverless rail line as part of its first phase.
The contract scope includes about 16 stations – 11 elevated and five underground – along with 8km of tunnels, viaducts and other associated structures. It covers all civil, architectural, and mechanical, electrical and plumbing works.
Stations will be located at Resort Core East Village, Grand Central Station, Anime Hub Integrated Station and Primary Urban Axis 1 & 2 Hub Station.
A subsequent phase will extend the railway network by a further 11km.
QIC is accelerating plans to develop additional assets at Qiddiya City.
Separately, QIC, the Royal Commission for Riyadh City and the National Centre for Privatisation & PPP received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh. This follows submission of prequalification statements for the engineering, procurement, construction and financing package on 16 April, as previously reported by MEED.
The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at up to 250 kilometres per hour, reaching Qiddiya in 30 minutes.
Contractors are also preparing bids for a 13 May deadline for a contract covering new infrastructure works at Qiddiya Entertainment City. The scope includes two infrastructure development packages for District 0, including the construction of four event park-and-ride facilities.
QIC’s other major projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC officially opened the Six Flags theme park to the public in December last year.
The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16779176/main.jpg -
Contractors submit bids for Saudi gas processing plant project8 May 2026

Contractors have submitted bids to Saudi Aramco subsidiary Aramco Gulf Operations Company (AGOC) for a project to build an onshore gas processing plant in Saudi Arabia’s Khafji that will draw and process gas from the Dorra offshore gas field, located in waters of the Saudi-Kuwait Neutral Zone.
MEED previously reported that AGOC had divided the engineering, procurement and construction (EPC) on the Khafji gas plant project into seven packages, and issued the main tenders for those last year.
Contractors were initially set deadlines of 24 October for technical bid submissions and 9 November for commercial bids. AGOC later extended the bid submission deadline to 22 December, and then until 22 April. A final deadline of 30 April was set, with contractors submitting bids by that date, according to sources.
The seven EPC packages cover works including open-art and licensed process facilities, pipelines, industrial support infrastructure, site preparation, overhead transmission lines, power supply systems and main operational and administrative buildings, with their breakdown as follows:
- Package 1 – Open-art facilities
- Package 2 – Licensed facilities
- Package 3 – Industrial support facilities
- Package 4 – Pipelines
- Package 5 – Site preparation
- Package 6 – Overhead transmission lines plus power supply (from Saudi Electricity Company)
- Package 7 – Headquarters complex
Saudi Arabia and Kuwait have been pressing ahead with their plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field.
The two countries have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, they have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.
Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.
The Khafji gas plant project is one of three multibillion-dollar projects launched by subsidiaries of Saudi Aramco and Kuwait Petroleum Corporation (KPC) to produce and process gas from the Dorra field that has advanced in recent months.
Dorra field facilities project
Al-Khafji Joint Operations (KJO), which is jointly owned by AGOC and KPC subsidiary Kuwait Gulf Oil Company (KGOC), has divided the scope of work on the Dorra field facilities project into four EPC packages – three offshore and one onshore.
India’s Larsen & Toubro Energy Hydrocarbon (L&TEH) won the contract for package one of the Dorra facilities project, which covers the EPC of seven offshore jackets and the laying of intra-field pipelines. The contract awarded by KJO to L&TEH is estimated to be valued at $140m-$150m, MEED reported in October.
Additionally, Italian, Indian and Spanish contractors have emerged as the lowest bidders for the other three EPC packages that form part of the Dorra facilities project.
A consortium of Italian contractor Saipem and L&TEH is understood to have submitted the lowest bid for offshore packages 2A and 2B, according to sources. The only other consortium understood to have submitted bids for packages 2A and 2B comprises Abu Dhabi-based NMDC Energy and South Korea’s Hyundai Heavy Industries.
The EPC scope of work for package 2A includes Dorra gas field wellhead topsides, flowlines and umbilicals. Package 2B involves the central gathering platform complex, export pipelines and cables.
Spanish contractor Tecnicas Reunidas is understood to have emerged as the lowest bidder for onshore package three, sources told MEED. Package three covers the EPC of onshore gas processing facilities.
KGOC onshore processing facilities
The third component of the overall Dorra gas field development programme is a planned onshore gas processing facility to be built in Kuwait, which has been undertaken by KGOC.
KGOC had been progressing with the front-end engineering and design (feed) work on the project, before the destabilising impact of the US-Israel conflict with Iran compelled the operator to put the project on hold, MEED reported in April.
The proposed facility, estimated to be worth $3.3bn, will receive gas from a pipeline from the Dorra offshore field, which is being separately developed by KJO. The complex will have the capacity to process up to 632 million cf/d of gas and 88.9 million barrels a day of condensates from the Dorra field.
The facility will be located near the Al-Zour refinery, owned by another KPC subsidiary, Kuwait Integrated Petroleum Industries Company.
A 700,000-square-metre plot has been allocated next to the Al-Zour refinery for the gas processing facility and discussions regarding survey work are ongoing. The site could require shoring, backfilling and dewatering.
The onshore gas processing plant will also supply surplus gas to KPC’s upstream business, Kuwait Oil Company, for possible injection into its oil fields.
Additionally, KGOC plans to award licensed technology contracts to US-based Honeywell UOP and Shell subsidiary Shell Catalysts & Technologies for the plant’s acid gas removal unit and sulphur recovery unit, respectively.
France-based Technip Energies has carried out a concept study and feed work on the entire Dorra gas field development programme.
Progress has been hampered by a dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.
In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.
Since that show of strength and unity, projects to produce and process gas from the Dorra field have gained momentum.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16734353/main5834.jpg -
Teams prepare bids for Riyadh East sewage treatment plant8 May 2026

At least six consortiums are preparing to submit bids for Saudi Arabia's Riyadh East independent sewage treatment plant (ISTP) project, according to sources.
The project will be developed under a build‑own‑operate‑transfer model with a 25‑year concession term.
The plant will have a treatment capacity of 200,000 cubic metres a day (cm/d) in its first phase, expanding to 500,000 cm/d in the second phase.
MEED understands that the following consortiums are in discussions to submit bids for the project, which has a recently extended bid submission deadline of 30 June:
- Suez (France) / Civil Works Company (Saudi Arabia) / Alwael (Saudi Arabia)
- Saur (France) / Samsung E&A (South Korea) / Al-Bawani (Saudi Arabia) / Nesma (Saudi Arabia)
- Alkhorayef (Saudi Arabia) / GS Inima (Spain)
- EtihadWE (UAE) / Metito (UAE)
- Veolia (France) / AlJomaih Energy & Water (Saudi Arabia)
- Miahona (Saudi Arabia) / Marafiq (Saudi Arabia)
In December 2025, a group comprising Metito, EtihadWE and SkyBridge was selected as the preferred bidder for the Hadda ISTP project. Miahona, Marafiq Company and Buhur for Investment was selected as the reserved bidder.
That same month, the Miahona-led consortium was selected as preferred bidder for the Arana ISTP and the Metito-led consortium was selected as the reserved bidder. Both projects have yet to reach financial close.
The Riyadh East, Hadda and Arana ISTPs are being undertaken by state water offtaker Sharakat, formerly Saudi Water Partnership Company, in collaboration with the National Centre for Privatisation & PPP.
In 2024, Sharakat prequalified 53 companies that could bid for the Riyadh East ISTP, part of seven planned ISTP projects it said it would procure between 2024 and 2026. The request for proposals was issued last October.
WSP is the technical adviser and KPMG Middle East is the lead and financial adviser on the project.
The targeted commercial operation date for the facility is 2029.
ISTP plans
According to Sharakat’s recent seven-year statement, it has identified six additional large ISTPs in the development pipeline.
These are:
- Kharj (75,000 cm/d)
- Abu Arish (50,000 cm/d)
- Hafar Al-Batin (100,000 cm/d)
- Riyadh North (TBD)
- Najran South (50,000 cm/d)
- Khamis Mushait (50,000 cm/d)
The company is also pursuing a nationwide small sewage treatment plant programme covering about 139 smaller ISTPs grouped into seven clusters.
These are designed to add about 521,450 cm/d of additional treatment capacity across the kingdom.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16734156/main.jpg -
Saudi Arabia tenders Jeddah-Mecca highway PPP8 May 2026

Saudi Arabia’s Roads General Authority (RGA) and the National Centre for Privatisation & PPP (NCP) have tendered the contract for the development of the Jeddah-Mecca highway project.
The tender was issued on 19 April, with a bid submission deadline of 19 August.
The scope of the tender is split into two sections: development of motor service areas (MSA) and highway services.
Under the MSA component, the company will develop, permit, finance, design, engineer, procure, construct, complete, test, commission, insure, operate and maintain three MSAs along the highway.
The contract term is 25 years, including two years of the construction period.
Each MSA plot will cover 34,500 square metres and will include facilities such as fuel stations, electric vehicle charging, truck services, tyre and oil change, car wash and repair, retail and food outlets, ATMs, restrooms, mosques, parking, landscaping and other associated utilities.
The highway services component will include insurance, operation and maintenance of highway assets for 10 years.
The 64-kilometre (km) Jeddah-Mecca highway has four lanes in each direction. The construction works on 51km are complete, while the rest is under construction and scheduled for completion in 2027.
In March, the RGA and NCP prequalified three bidders to develop the project. These were:
- Algihaz Holding / ICA Construction (local/Turkiye)
- Lamar Holding / Shaanxi Construction Engineering Group Corporation (Bahrain/China)
- Mada International Holding (local)
The expression of interest notice for the project was first issued in October 2024, as MEED reported.
The project is one of four planned highway schemes in the kingdom’s privatisation and public-private partnership (P&PPP) pipeline.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16731199/main.jpg
