World’s largest piling project shifts to The Line’s marina

26 March 2023

Image: Work on module 43 of The Line has peaked at more than 60 piles a day


 

Neom is preparing to shift the focus of the world’s largest piling project to The Line modules at the marina as excavation work for the waterway reaches an advanced stage. 

The structures that make up The Line comprise 135 modules that are 800 metres in length and 500 metres tall at sea level. In total, The Line is 170 kilometres long and extends from the Red Sea coast inland towards Tabuk. 

Modules 45, 46 and 47 are at the marina, which is expected to be two times bigger than any other marina in the world and capable of hosting the largest cruise ships.



Module 45: Each module will contain eight buildings on large-diameter bored piles


The marina is located on the other side of The Line to the sea, so ships must pass through The Line buildings.

This is a major engineering challenge as it means creating a 165-metre-wide waterway passing through the 500-metre-tall buildings.

The largest cruise ship is the Wonder of the Seas, which is 67 metres wide and 72 metres tall, and requires a draught of nearly 10 metres. 



The Line will be able to host Royal Caribbean's Wonder of the Seas, the world's biggest cruise ship, which made its debut in March 2022. Credit: Neom via Twitter


The water channel entering the marina will also have to pass over The Spine, a subterranean infrastructure corridor running the length of The Line, which includes the high-speed railway lines. There are railway stations at every third module along The Line.



Module 46: As piling work moves to modules 46 and 47, the level of activity will increase even further


The marina is also proposed to include a 45,000-seat sports stadium built 300 metres above ground in between The Line buildings. 

The marina is the largest excavation project in the world, with about 1 million cubic metres of earth being moved every week. 

Once the excavation work and dewatering for the marina reach an appropriate stage, piling works will start.

So far, the piling work for The Line has been concentrated on module 43, where more than 4,500 piles have been installed. Work has reached a peak of more than 60 piles a day, making it the largest piling project in the world.

As piling work shifts to modules 46 and 47, the activity level is expected to increase even further. 



Module 47: Excavation of about 1 million cubic metres of earth is taking place each week at the marina


Nine contractors are working on the piling as part of a framework agreement. Six of these are onsite. They are the local Al-Osais, Germany’s Bauer, the UK’s Keller, UAE-based NSCC, Beijing-based PowerChina and Italy’s Trevi. 

The other three firms that are part of the framework agreement are France’s Bachy Soletanche, the local Huta and Saudi Baytur. 

Three firms are working with Neom as delivery partners for The Line. They are UK-based Atkins and two US firms, Jacobs and Parsons.  

The Line is designed to ultimately house 9 million residents who will have access to the development’s facilities within a five-minute walk. A high-speed rail system will have an end-to-end journey time of 20 minutes.



The city, including the planned 45,000-seat, suspended stadium, will be built within the 500-metre-high walls. Credit: Neom via Twitter 


 

Sindalah island, spanning 840,000 square metres, is the first of a group of islands to be developed at Neom. In March, Neom signed a deal with Marriott International to open three properties on the luxury island. Plans for Sindalah include building over 400 premium hotel rooms and 300 suites, as well as an 86-berth marina for yachts up to 75 metres and serviced offshore buoys for superyachts up to 180 metres.


MEED's April 2023 special report on Saudi Arabia includes:

> ECONOMY: Riyadh steps up the Vision 2030 tempo

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> WATER: Saudi water begins next growth phase

> BANKING: Saudi banks bid to keep ahead of the pack

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/10701442/main.gif
Colin Foreman
Related Articles
  • Neom’s industrial pivot gathers pace

    1 October 2026

    Commentary
    Colin Foreman
    Editor

    Reprioritisation has been the buzzword in Saudi Arabia over the past two years and nowhere has that been more evident than at Neom. 

    The slowdown of development at The Line and the postponement of the 2029 Asian Winter Games at Trojena have dominated international headlines. As these projects scale back, Oxagon’s industrial and logistics base has become the $500bn gigaproject’s flagship development. There are tangible results: in August, the $8.5bn Neom Green Hydrogen project was commissioned, marking Neom’s most significant completion to date. 

    Construction activity elsewhere at Oxagon supports this trend. The AI data-centre campus being developed by Humain and DataVolt has broken ground on its first 100MW phase, backed by $5bn of investment and targeted for service in 2028. Neom has issued an expression of interest for a rail line linking the Port of Neom to Saudi Arabia Railways’ North-South network, tenders are out for an industrial wastewater plant and the upgrade of Highway 55, and the port itself is advancing towards a 2030 capacity target of 1.5 million TEUs. 

    The regional conflict that began in February has strengthened the business case by giving Oxagon’s Red Sea port added strategic weight as a second maritime gateway outside the Strait of Hormuz, at a time when Riyadh has committed to directing about 80% of the Public Investment Fund’s portfolio into domestic investment.

    These developments reflect a kingdom recalibrating rather than retreating

    Elsewhere, Saudi Arabia’s wider projects market is holding steady despite conflict-related disruption, with contract awards reaching $68bn so far this year. The regional power market is also diversifying, with Aljomaih, EDF and Kepco all more than tripling net capacity in recent years as Acwa retains its lead.

    These developments reflect a kingdom recalibrating rather than retreating, with priority given to projects capable of delivering commercial returns.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20178338/main.gif
    Colin Foreman
  • Contractor wins Dammam airport water infrastructure deal

    1 October 2026

    Saudi Arabia-based Alkhorayef Water & Power Technologies has won an SR80m ($21.3m) contract to rehabilitate water and wastewater infrastructure at King Fahd International airport in Dammam in the kingdom’s Eastern Province.

    The contract was awarded by Dammam Airports Company (DACO), and work is scheduled to be completed within 18 months, the firm said in a disclosure to the Saudi Exchange (Tadawul) on 29 September.

    The scope covers the design, construction, supply, installation, replacement, rehabilitation and integration of water and wastewater infrastructure.

    It includes pumps, storage tanks and reservoirs, reverse osmosis facilities, piping and tie-ins, as well as electrical and instrumentation works.

    The award comes as DACO advances a wider programme of investment at King Fahd International airport.

    DACO signed more than SR1.2bn ($320m) in agreements in June covering airport infrastructure, including a new power station, a medium-voltage distribution network and upgrades to the existing electrical grid. 

    In September, it also appointed WSP Middle East, the regional arm of Canadian engineering firm WSP, to develop the airport’s expansion under its masterplan.

    The expansion is intended to increase annual passenger capacity to more than 19.3 million by 2030, with a longer-term target of 32 million passengers. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20169118/main.jpg
    Mark Dowdall
  • Kuwait tenders LNG project

    1 October 2026

     

    State-owned Kuwait Integrated Petroleum Industries Company (Kipic) has tendered a project to develop a reliquefaction unit at the Al-Zour liquefied natural gas (LNG) import terminal.

    The project focuses on developing a boil-off gas (BOG) unit at the terminal, with bids due on 22 December.

    A meeting for contractors to discuss the project is scheduled for 18 October.

    The project scope includes engineering, procurement and construction works, along with pre-commissioning, commissioning and performance testing services.

    The list of prequalified companies is:

    • Fluor (US)
    • GS Engineering & Construction (South Korea)
    • Tecnicas Reunidas (Spain)
    • Larsen & Toubro (India)
    • Hyundai Engineering (South Korea)
    • CTCI Corporation (Taiwan)
    • Daewoo Engineering & Construction (South Korea)
    • Hyundai Engineering & Construction (South Korea)
    • Saipem (Italy)
    • Samsung Engineering (South Korea)
    • Sinopec Engineering (China)
    • JGC Holdings (Japan)
    • KBR (US)
    • China National Petroleum Corporation (China)
    • Technip (France)

    A BOG unit at an LNG facility captures, compresses and processes natural gas vapours that evaporate from cryogenic storage tanks, enabling the gas to be recycled back into the system rather than flared.

    In April, MEED revealed that contractors expected the project to be worth about $200m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20168625/main2005.jpg
    Wil Crisp
  • Riyadh approaches contractors for 2km tower

    1 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has reached out to contractors as part of a market-sounding exercise for the construction of the proposed 2-kilometre megatall tower project.

    MEED understands that a PIF subsidiary, the Tower District Real Estate Development Company, is undertaking the process.

    It is understood that several experienced international contractors, as well as some prominent local contractors, have been approached.

    The latest development follows PIF receiving offers in June last year from firms seeking a contract to provide project management consultancy (PMC) services for a new central business district (CBD) on the outskirts of Riyadh, which includes the proposed 2km tower.

    The PMC role covers both the tower and the surrounding district.

    Firms understood to have been invited to bid include US-based Aecom, Jacobs, Parsons and Turner, as well as the UK’s Mace.

    UK-based Foster & Partners is working as the architect for the tower after winning a design competition launched in late 2022.

    Record breaker

    The proposed tower would be more than double the height of the world’s tallest building, Dubai’s Burj Khalifa, which stands 828 metres tall. It is expected to be at least several hundred metres taller than the 1,000-metre-plus tower under construction in Jeddah.

    Contractors that have priced megatall towers in the region say a 2km-tall structure could cost about $5bn to construct, depending on the final design.

    The 2km tower and the surrounding CBD – known as Project Rise – sit within a larger masterplanned development to the north of Riyadh called the North Pole.


    MEED’s October 2026 report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20156496/main.jpg
    Yasir Iqbal
  • Singapore’s Temasek plans Middle East expansion

    1 October 2026

    Singapore’s Temasek plans to open offices in Riyadh and Abu Dhabi early next year as it targets investment and partnership opportunities in Saudi Arabia, the UAE, Qatar and the wider region.

    The state-owned investor had a net portfolio value of S$518bn ($401bn) as of 31 March 2026.

    It said the new offices will serve as regional hubs for Temasek and its portfolio companies, with some businesses expected to co-locate to work more closely with partners and pursue deals alongside the group. The openings are subject to regulatory approvals.

    Temasek said it will also step up engagement with institutions in Qatar, although it has not announced plans to establish an office there.

    The company said the expansion reflects its confidence in the region’s long-term fundamentals and the economic transformation being driven by national diversification programmes.

    It added that a presence in Riyadh and Abu Dhabi will also support investment activity beyond the region by improving access to opportunities across the wider Middle East, Central Asia and Africa.

    Several Temasek-owned or Temasek-backed companies are already active in the GCC, providing a platform for the group’s planned expansion.

    These include Singapore-headquartered engineering and consultancy firm Surbana Jurong, which has been involved in masterplanning and advisory work on major regional developments, alongside other portfolio companies with interests spanning infrastructure, logistics, financial services and technology.

    According to data from regional project tracker MEED Projects, Surbana Jurong is involved in several major projects in Saudi Arabia, including King Abdulaziz International airport (KAIA) in Jeddah, Jeddah Islamic Port, Red Sea Global’s Amaala masterplan, the Trojena dams scheme, Oxagon, King Salman International airport and Saudi Arabia Railway’s North-South Phosphate Railway 3.

    The firm has also worked on projects in the wider region, including the West Link project, Urban Loop, Musaffah Innovation District masterplan, Etihad Rail’s high-speed rail programme and Abu Dhabi airport’s Midfield Terminal.

    Surbana Jurong has also secured masterplanning contracts from Abu Dhabi’s Department of Municipalities & Transport and Abu Dhabi Ports.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20157511/main.jpg
    Yasir Iqbal