Warming erodes Kuwait’s power and water reserves

14 August 2023

More on Kuwait’s power and water sector: 

> IWPP: Firms respond to Kuwait independent utilities request
> POWERLocal firm wins 250MW Subiya package
> PRIVATISATIONKuwait thermal plant privatisation to go ahead


 

The temperature in Kuwait soared to 51 degrees Celsius on 1 August, sending its electricity load index up to 16,940MW. This breached its maximum expected load this year of 16,830MW by 0.7 per cent.

This year’s projected maximum load is already 4 per cent higher than the previous year's recorded maximum load. It leaves only roughly 8 per cent of reserve capacity against an available capacity understood to stand at 18,250MW.

Similarly, water consumption across the Gulf state on 2 August, when the temperature decreased to 50 degrees, exceeded production by 29 million gallons, prompting the state utility to access its strategic water reserve capacity to plug the shortfall.

The electricity consumption spike reportedly caused two feeders at the country’s main substation south of Surra in the capital to trip, which led to power outages in some parts of Zahra, a district in Kuwait’s Hawalli governorate.

Kuwait’s Electricity & Renewable Energy Ministry (MEWRE) assured the public that the maximum capacity available in the country’s electricity network during the current summer is 18,250MW, as earlier cited, and that it could safely provide up to 17,660MW.

Persistent delays

The following week MEWRE – through the Kuwait Authority for Partnership Projects (Kapp) – received prequalification applications for the contracts to develop Kuwait’s next two independent water and power producer (IWPP) projects.

The two schemes – Al-Zour North 2 & 3 and Al-Khiran 1 – will have a total combined power generation capacity of 4,500MW and a water desalination capacity of over 150 million imperial gallons a day (MIGD), which will go a long way to address Kuwait’s precarious electricity and water supply situation.

Ironically, these two schemes have been in the planning and early procurement stages since 2017 and have suffered significant delays in the intervening period.

It is the second time developers have submitted statements of qualification (SOQs) for the contracts over the preceding 11 months.

The delays have caused major frustration for some developers and contractors. One utility developer that submitted an SOQ in September last year told MEED they did not participate in the latest attempt to start the prequalification process for the IWPP schemes, without elaborating.

Others expect the country’s stakeholders to eventually approve and expedite the procurement process for the integrated power and desalination facilities.

“I’m not very optimistic, but we submitted an SOQ anyway,” another source tells MEED.

EPC projects motoring ahead

The ministry’s conventional power plant projects have been moving at a relatively faster pace. In June this year, the local company Heavy Engineering Industries & Shipbuilding (Heisco) won a contract for the phase 2 upgrade of the Subiya power plant complex in Kuwait.

Heisco saw off competition from two local companies, Alghanim International and Al-Zain United General Trading & Contracting, for the KD114.28m ($372m) contract.

The project aims to convert an existing 250MW simple-cycle plant into a combined-cycle gas-turbine plant.

In April, a consortium comprising Heisco and Japan’s Mitsubishi Power was also awarded a contract to retrofit the main thermal power generation plant at the power complex.

The contract is understood to be valued at KD90.9m. It entails the upgrade of eight steam turbines and electric generators at the Subiya power plant, which is expected to reach a capacity of 2,400MW once the project is complete.

The existing plant at the Subiya power complex was commissioned between 1998 and 2002. This implies that the steam turbines and generators in commercial operation for nearly 20 years require upgrades to continue operating and improve their performance.

Two steps forward

While the country has pledged to become carbon neutral by 2060, the state utility has yet to make any remarkable progress in procuring new renewable energy capacity.

The recent political deadlock has hampered the procurement of the next phases of the Shagaya Renewable Energy Programme (SREP), despite the award 12 months previously of the project’s transaction advisory contract to a team led by London-headquartered consultancy firm EY.

At the time, the advisory contract was understood to cover the Al-Dibdibah solar project, which will comprise SREP’s second phase, and a third phase expected to include a 720MW solar photovoltaic (PV) plant, a 1,150MW concentrated solar power (CSP) facility and a wind power farm.

Notably, two state-backed downstream operators – Kuwait National Petroleum Company and Kuwait Integrated Petroleum Industries Company (Kipic) – have launched a tender for a contract to undertake a pre-feasibility study identifying opportunities to use renewable energy in their operations.

Kuwait is also expected to make some progress on its first utility privatisation scheme, which forms part of the initiative to strengthen private sector participation in the sector.

In December last year, it was revealed that UK-headquartered Deloitte had submitted a low bid of KD1.2m ($3.9m) for the transaction advisory contract in line with the planned privatisation of the $1.26bn North Shuaiba power and water plant in Kuwait.

GCC grid

While working to boost its electricity reserves and make its electricity systems greener, Kuwait stands to benefit from the ongoing upgrade of the GCC electricity grid, through which other GCC states, such as the UAE, may decide to transmit excess clean energy.

The Al-Fadhili high-voltage direct current (HVDC) converter station upgrade in Saudi Arabia is expected to enable the exchange of 1,800MW of electricity between the six states once complete.

In October last year, the GCC Interconnection Authority (GCCIA) awarded India-based KEC International a contract for an overhead transmission line project linking the substations in Wafra in Kuwait and Fadhili in Saudi Arabia.

The estimated $120m project extends an existing double-circuit 400kV line from Al-Zour in Kuwait to Ghunan in Saudi Arabia. The line has an intermediate interconnection at Fadhili, with associated substations completed in 2009 as part of the first phase of the GCCIA network. The new project is expected to complete in 2025.


This month’s special report on Kuwait also includes: 

> ECONOMYStakeholders hope Kuwait can execute spending plans
> ENERGYKuwait’s $300bn energy target is a big test
> BANKINGKuwaiti banks enter bounce-back mode
> INTERVIEWKuwait’s Gulf Centre United sets course for expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/11069881/main.gif
Jennifer Aguinaldo
Related Articles
  • Chinese firm announces $1.9bn Abu Dhabi renewables contract

    23 March 2026

    China Power Construction Corporation (PowerChina) has announced details of a contract signed for the engineering, procurement and construction (EPC) works on part of Abu Dhabi’s $6bn round-the-clock solar and battery storage project.

    The independent power project (IPP) will combine 5.2GW of solar photovoltaic (PV) capacity with 19GWh of battery storage. Last October, Emirates Water & Electricity Company (Ewec) and Abu Dhabi Future Energy Company (Masdar) broke ground on what will be the world’s largest combined solar and battery energy storage system (bess), designed to supply 1GW of round-the-clock power.

    India’s Larsen & Toubro and Beijing-headquartered PowerChina were awarded the EPC contract for the project last year, with PwC Middle East advising Ewec on financial structuring.

    According to the Chinese firm, the full project has been divided into two blocks, north and south, indicating at least two major packages. 

    PowerChina’s contract, valued at about $1.9bn, covers the northern block of the project, which includes 2.1GW of DC-side PV installations and a 7.75GWh bess. The scope includes the design, procurement and construction of substations, PV facilities and battery energy storage systems.

    Located in the Mshayrif area of Abu Dhabi, the wider project is designed to supply steady delivery of power between April and October each year, the UAE’s peak electricity demand season due to cooling loads.

    This includes serving large energy users that require 24/7 clean electricity, such as fast-growing data centre operators and technology firms driving artificial intelligence deployment in the region.

    Ewec will act as the offtaker under a long-term power purchase agreement.

    MEED previously reported that China’s CATL (Contemporary Amperex Technology Co), Jinko Solar and JA Solar will supply the bess and PV modules, with Jinko and JA each providing 2.6GW of modules. 

    The project will avoid 5.7 million tonnes of CO₂ emissions annually and provide enough clean energy to power nearly half a million homes.

    Construction is expected to be completed in 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16083288/main.jpg
    Mark Dowdall
  • Kuwait tenders major infrastructure packages

    23 March 2026

     

    Kuwait’s Ministry of Public Works (MPW) has tendered several contracts for infrastructure works across various parts of the country.

    The first tender covers the construction of rainwater drainage systems in the Sabah Al-Ahmad South, Sabah Al-Ahmad, Al-Khairan and Al-Wafra residential areas.

    The second tender includes the construction of a treated water system in Kuwait’s southern region.

    The third tender covers the construction of a treated water system in Kuwait’s northern region.

    The final tender covers the construction of roads, bridges, stormwater drainage, sewage and other services for a section of the Kabd-Sulaibiya Road, as well as a section of the Kabd-Sulaibiya industrial road link.

    MPW issued all of these tenders on 22 March, with a bid submission deadline of 21 April.

    UK analytics firm GlobalData expects Kuwait’s construction industry to grow by 5.1% in 2026-29, supported by government investment in the oil and gas sector aimed at raising production, as well as investment in the infrastructure sector.

    In the short term, growth will be boosted by planned expenditure under the 2025-26 budget, which was approved in March 2025.

    The construction industry in Kuwait is expected to record an annual average growth rate of 4.9% in 2026-29, supported by investments in renewable energy, transport, and oil and gas projects.

    The commercial construction sector is expected to grow by 4.8% in 2026-29, supported by public and private sector investment in the construction of hotels, retail outlets and office buildings.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16083252/main.jpg
    Yasir Iqbal
  • Qiddiya tenders new infrastructure package

    23 March 2026

     

    Saudi Arabian gigaproject developer Qiddiya Investment Company (QIC) has tendered a contract inviting firms to bid for new infrastructure works in Qiddiya Entertainment City.

    The scope covers two infrastructure development packages in District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.

    The tender was issued on 11 March, with a bid submission deadline of 22 April.

    Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.

    QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company set a 16 April deadline for firms to submit prequalification statements for the Qiddiya high-speed rail project in Riyadh.

    Previously, MEED reported that QIC had received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.

    The project will cover an area of more than 105,000 square metres (sq m).

    Last month, QIC started the main construction works on its performing arts centre at Qiddiya Entertainment City.

    The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    In December last year, QIC officially opened the Six Flags theme park to the public.

    The theme park covers an area of 320,000 sq m and features 28 rides and attractions, 10 of which are thrill rides and 18 designed for families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    The kingdom’s tourism sector posted record-breaking numbers last year, with over 130 million domestic and international visitors entering the kingdom, representing a 6% increase over 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16083013/main.jpg
    Yasir Iqbal
  • Kuwait’s Mina Al-Ahmadi refinery attacked

    23 March 2026

    Register for MEED’s 14-day trial access 

    Several units were shut down at Kuwait’s largest oil refinery after it was hit by drones as Iran targeted energy infrastructure across the Gulf, according to a statement from state-owned Kuwait Petroleum Corporation (KPC).

    Fires broke out across multiple units at the Mina Al-Ahmadi refinery in the morning of 20 March 2026 following the attack.

    The refinery normally processes about 730,000 barrels of oil a day.

    There were no casualties as a result of the attack, according to KPC.

    Kuwait’s oil and gas sector has been severely disrupted by the ongoing regional conflict.

    On 10 March, MEED revealed that the state-owned upstream operator Kuwait Oil Company (KOC) was operating with just 30% of its total workforce in their normal workplaces.

    Earlier in the month, KPC also declared force majeure due to difficulties transporting oil and gas through the Strait of Hormuz caused by the conflict.

    Force majeure, a French term meaning “superior force”, is a clause included in many international commercial contracts. It allows companies to suspend contractual obligations when extraordinary events occur beyond their control.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16067425/main.gif
    Wil Crisp
  • Iraq declares force majeure on foreign-operated oil fields

    23 March 2026

    Register for MEED’s 14-day trial access 

    Iraq has declared force majeure on all oil fields developed by foreign oil companies as the US and Israel’s war with Iran disrupts navigation through the Strait of Hormuz.

    The initial attack and Iran’s response have slashed Iraq’s exports.

    Prior to the war starting on 28 February, Iraq was exporting between 3.3 and 3.5 million barrels a day of crude oil.

    Oil sales account for nearly 90% of Iraq’s government revenues.

    Earlier this month, two drone strikes hit infrastructure at Iraq’s Majnoon oil field, increasing security concerns in the country’s energy sector.

    One of the drones hit a communications tower, and the other hit the office of the US engineering company KBR.

    There were no casualties as a result of the attacks.

    Foreign workers were evacuated from the site days after the US and Israel’s war with Iran started, and only Iraqi staff are currently working at the site.

    Shortly before the war started, KBR announced that it had been awarded a “major contract” by Iraq’s state-owned Basra Oil Company to provide integrated field management services for the Majnoon oil field.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16067302/main.png
    Wil Crisp