Transport projects driven by key trends

24 December 2024

 

Two key trends are driving the region’s transport projects. The first is a longstanding competitive advantage based on the Middle East’s strategic location, while the second is a renewed drive for regional integration. 

Over the past 20 years, the Middle East’s aviation sector has been transformed. Dubai has established itself as the world’s busiest international airport, while other regional airports have become significant aviation hubs, albeit on a smaller scale. 

The logic is simple. The Gulf is within an eight-hour flight of most major destinations and two-thirds of the world’s population. It is also strategically located between established markets in Europe and North America and emerging markets in Africa and Asia. 

Over the past decade, major projects have been undertaken to upgrade capacity and harness more of the global aviation market. As these projects were completed, 2024 became a turning point and the focus pivoted to two new projects that will be the largest airports in the region by far.

Major airports

Riyadh’s King Salman International airport was launched at the end of 2022. The airport, which will be built to replace the existing King Khalid International airport, aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050.

In 2024, the project took several steps forward: it appointed UK-based Mace as a delivery partner; tendered contracts for delivery partner roles for the terminals, airside works and landside infrastructure; and began to approach contractors for construction work on the project. 

The region’s other major airport scheme is the $35bn expansion of Dubai’s Maktoum International airport. The project, which had been planned for over a decade, had new designs approved in April. It will have a passenger handling capacity of 260 million passengers annually – the world’s largest. 

Early infrastructure contracts have been awarded since the designs were approved, and contractors have been briefed on main construction packages that are expected to start in 2025. 

Building connections

The other key drive for the region’s transport projects is integration. Following the 2021 Al-Ula agreement, the GCC has been pressing to establish closer trade ties to accompany closer political links. At the same time, seaborne trade has been threatened by logistics bottlenecks and, more recently, by Houthi attacks in the Red Sea. These two factors combined have led to a push to build better overland transport links across the region.

The best demonstration of the renewed focus on overland transport links connecting the region came in April 2024, when Oman-Etihad Rail Company awarded contracts for the Hafeet Rail project connecting the UAE with Oman. 

The estimated AED5.5bn ($1.5bn) design-and-build contract for the civil works was secured by Abu Dhabi-based National Projects Construction, National Infrastructure Construction Company and Tristar Engineering & Construction with Oman’s Galfar Engineering & Contracting. A contract for the rolling stock systems and integration contracts went to German firm Siemens and Egyptian contractor Hassan Allam Construction. 

The speed at which the Hafeet Rail contracts were awarded was an anomaly, as other major rail projects have taken much longer to be awarded and move into construction. This has become a source of frustration for companies that invest considerable time and financial resources in tendering for contracts. 

One of the longest-running contract negotiations in the region is for the $7bn Saudi Landbridge project that will link the western Red Sea coast of the kingdom to the eastern Gulf coast through Riyadh. 

Saudi China Landbridge Consortium signed a memorandum of understanding to develop the project in October 2018. After six years of negotiations, there is now an expectation that construction will start in 2025, although there have been false dawns in the past.

The Mecca Metro project also has a long history. MEED reported in June 2024 that a feasibility study for the $8bn first phase of the scheme had restarted. Contracts for construction work were tendered and close to being awarded
in 2014. 

Another rail project that has been slow to progress is Bahrain’s planned metro scheme. Launched in 2021, Bahrain’s Transportation & Telecommunications Ministry prequalified seven groups for the contract to deliver the first phase of the network on a public-private partnership basis in early 2023. Since then, it is understood that the project has shifted back to the study phase as the government considers the best way to proceed with the scheme. 

Airport projects also take time. The construction contract for the substructure of Al-Maktoum International airport was close to being awarded in early 2020 before the Covid-19 pandemic. That tender then ceased to be a priority as the focus for Dubai’s aviation sector shifted to supporting airlines Emirates and Flydubai and airport operations during the lockdown period, enabling the sector to reopen more quickly than its competition. 

Now, expanding Dubai’s airport capacity is once again a strategic priority. Dubai International’s constrained site means it cannot add to its two existing runways, which means it is becoming vulnerable to being overtaken by other emerging hubs in the region.

At the tail end of the construction process, the completion of large-scale transportation projects is often delayed. The largest ongoing transport scheme in the region by value is Riyadh’s $23bn six-line metro network, for which construction contracts were awarded in 2013. It was rumoured in late 2024 that it would open by the end of the year, although no opening date has been confirmed. 

There are examples of rail projects being completed more quickly. The Doha Metro network was opened as planned before Qatar hosted football’s Fifa World Cup 2022. The second and third phases of the UAE’s Etihad Rail network were also completed promptly, which has allowed Etihad Rail to focus on other schemes such as the passenger rail service, the Hafeet Rail project and the proposed high-speed rail scheme. 

Like railways, there are examples of delayed airport schemes that ran over budget. The Midfield Terminal Complex at Abu Dhabi International airport was delayed for years, as was the opening of the first phase of Hamad International airport in Qatar and Muscat International airport in Oman. 

Although delays were a significant problem for the construction companies involved in the projects, it is worth
noting that once the projects were completed, they were broadly praised for their quality and step-change in passenger experience.

 

Future focus

Looking ahead to 2025, the region’s strategic location and competitive edge in aviation will remain, which will support the business case for airport projects. The more interesting challenge will be the region’s ability to fund projects as large as King Salman International airport and Al-Maktoum International airport. 

In Saudi Arabia, project spending is being more closely managed than it was in the past, and although people close to the King Salman International airport scheme insist that it remains a strategic priority, the same can be said of many other major projects in the kingdom. 

There are also funding questions to be answered for Al-Maktoum International airport. Dubai does not have the financial resources to match Saudi Arabia, and with other infrastructure spending commitments – such as the $5bn Blue Line extension to Dubai Metro and an $8bn stormwater drainage scheme – funding the $35bn airport project will be a challenging undertaking. 

High-level concerns are also present for transport links within the region. The warm relations that countries within the region enjoy today may change in the future, and should that happen, the impetus to complete regional rail links will quickly subside. 

On the operational level, securing contractors and resources from the supply chain will be an ongoing problem. The record levels of construction awards in recent years mean that construction companies can afford to be selective about the projects they work on, and when they do choose to bid, they no longer feel obliged to slash their prices.

According to regional projects tracker MEED Projects, there were $37.8bn of transport contract awards in 2023, up from the $36.8bn of awards recorded in 2022. 

By the end of October 2024, there had been $30.8bn of transport project contract awards. If extrapolated, this suggests a $37bn total for 2024, which is only slightly below the 2023 annual total. 

The ability of contractors to hold firm when bidding was evidenced in October 2024, when initial offers were submitted for Dubai Metro’s Blue Line extension. The lowest bids were about $1bn over the project’s official $5bn budget, and a subsequent round of revised prices did not reduce that gap significantly. 

Dubai Metro is just one of several major rail schemes due to be awarded soon. As well as the Saudi Landbridge, contractors are also competing for a contract to complete the extension to Riyadh Metro’s Line 2, which is at the bid evaluation stage. A contract to build an entirely new Line 7 was also tendered in September 2024 with a closing date in March 2025. 

While it is not entirely reliant on these metro projects and the airports in Riyadh and Dubai moving into construction, their progress will go a long way to determining whether 2025 is a good year or not for transport projects in the region. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13147137/main.gif
Colin Foreman
Related Articles
  • Qiddiya plans $7bn theme park hub near Paris

    25 August 2026

    Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.

    The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.

    The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.

    One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.

    The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.

    Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.

    The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.

    It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png
    Colin Foreman
  • Masdar shelves Abu Dhabi green hydrogen project

    25 August 2026

     

    Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.

    After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.

    However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.

    Contractors that submitted bids for the Masdar green hydrogen project included:

    • Envision (China)
    • Larsen & Toubro (India)
    • PowerChina (China)
    • Samsung E&A (South Korea)
    • Sinopec (China)

    Masdar did not respond to MEED’s request for comment on the information.

    In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.

    Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.

    Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.

    Contractors submitted bids by the end of the year, according to sources.

    The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.

    The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.

    It also included tie-ins to pre-defined interface points, including (but not limited to):

    • a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
    • a water supply connection to a nearby Taqa Distribution network

    Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.

    Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.

    The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.

    This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.

    “Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg
    Indrajit Sen
  • Oman invites bids for Musandam renewables study

    25 August 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.

    The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.

    The consultant will be required to determine which technologies are technically and economically justified for the governorate.

    The bid submission deadline is 24 September.

    The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.

    Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.

    Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.

    The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity. 

    Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.

    The bid submissions deadline is 10 September.

    The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.

    Bidding for this tender closes on 26 August.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg
    Mark Dowdall
  • US launches sanctions campaign against Iran

    25 August 2026

    The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.

    The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.

    The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.

    The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.

    Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.

    Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.

    Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.

    Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.

    The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg
    Colin Foreman
  • Kuwait tenders $3.3bn gas processing facility

    25 August 2026

     

    State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.

    The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.

    The tender was issued on 23 August.

    The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    In February, MEED reported that at least seven companies had shown interest in participating in the tender.

    Contractors that sent representatives to previous meetings to discuss the project include:

    • Samsung E&A (South Korea)
    • Larsen & Toubro (India)
    • Tecnicas Reunidas (Spain)
    • Saipem (Italy)
    • Hyundai Engineering & Construction (South Korea)
    • Hyundai Engineering Company (South Korea)
    • JGC (Japan)

    The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.

    Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.

    It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.

    Iran disputes ownership of the field, referring to it as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.

    The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.

    Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.

    KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.

    US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.

    A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.

    Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.

    MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.

    Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png
    Wil Crisp