Stadiums can be contractor busters

3 April 2023

 

Large-scale sports stadiums may be iconic buildings, but like the sporting events they host, the construction can result in winners and losers if risks are not managed correctly.

Managing these risks was discussed at HKA’s “An Inside Look at the Sources of Stadia Disputes” event in Doha on 28 February.

“Stadiums can be contractor busters. Some well-known examples worldwide have brought down big construction firms,” says Kourosh Kayvani, partner at HKA (pictured).

Kayvani has played key roles in designing and delivering many vast, sophisticated sports stadia. He was a senior design engineer for the roof structures over a number of sports facilities for the Sydney 2000 Olympics, including the Sydney Showground Stadium, International Hockey Centre and International Aquatic Centre Olympic Extension and Legacy.

He was also involved in a number of stadia used for the Melbourne 2006 Commonwealth Games, including the Marvel Stadium, Melbourne Cricket Ground and Melbourne Sports and Aquatic Centre.

Kayvani was the lead designer and project leader of the iconic arch and roof of Wembley Stadium in London.

Several contributing factors make stadiums challenging construction projects. “Stadiums are large and complex. They are big capital expenditures, and a $1bn stadium is not extreme anymore,” says Kayvani.

“Then there is the sheer complexity of the buildings in terms of their function and what it needs to do, which requires several disciplines. You need all the specialist skills in a complex building, such as structures, MEP, civil works and façade.

“You also have other disciplines, such as sports lighting. With that, you need to think about outside broadcasting, Wi-Fi access and enabling people to interact with sporting events,” he adds.

Iconic designs

The structures themselves also create unique challenges. “As well as packages of interconnected works, the building is layered, which means you build from the bottom up. Unlike a typical multi-storey building that is repetitive, it varies as you go up.

“Added to that, some of the elements installed last are long lead items that need to be procured early, such as the big steelwork elements. They need to be temporarily supported while the rest of the facility is being built,” says Kayvani.

The complexities that make stadium projects challenging may only sometimes be realised by the people building them.

“There are risks associated with the construction of stadiums that might not be factored for during the bidding process, particularly if there are bidders that have not done a project like this before,” says Kayvani.

“They might be optimistic about their prospects and regard the project as another building. Not understanding the importance of the specialist expertise and going for the cheapest option will not give the best value in the long run.”

Timing is also essential, as many stadium projects are built to support specific events. “The timing and the need to meet a certain deadline is another major pressure if the stadium is needed for an event like a World Cup or an Olympics,” he says.

Project teams must plan and decide how projects will be delivered to prevent disputes. “You need to think about the delivery model. Build-only is not common nowadays; it is mostly design and construct (D&C). The owner wants to pass on all the risk to the D&C contractor, and the contractor passes on to all of its subcontractors and designers, and then designers have to manage risks that they are not fully in control of,” says Kayvani.

“Often contractors have bought too much risk without being able to manage it.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/10727208/main.gif
Colin Foreman
Related Articles
  • Abu Dhabi announces $15bn infrastructure PPP projects

    12 May 2026

    The Abu Dhabi Investment Office and the Abu Dhabi Projects and Infrastructure Centre have launched a AED55bn ($15bn) public-private partnership (PPP) pipeline of 24 projects to be tendered in 2026 and 2027.

    The projects will be tendered across the transport, infrastructure and social sectors.

    According to a statement published by the Abu Dhabi Media Office, the transport sector accounts for 11 road projects, with AED35bn ($9.5bn) of construction capex, covering more than 300 kilometres of new and upgraded roads, tunnels, intersections and related network works.

    The infrastructure pipeline includes five projects budgeted at AED11bn ($3bn), covering dams, water storage, flood control, stormwater upgrades and urban landscaping.

    Social infrastructure includes eight projects budgeted at AED9bn ($2.5bn), covering sports facilities, specialist healthcare assets, schools and university campuses.

    The statement added that the pipeline forms part of Abu Dhabi’s infrastructure delivery plan and will be executed through PPP structures.

    It is also intended to support company establishment in the emirate, local content objectives, and supply-chain and industrial capacity.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16793904/main.jpg
    Yasir Iqbal
  • Saudi Arabia tenders GCC rail link from Kuwait to UAE border

    12 May 2026

     

    Saudi Arabia has begun the procurement process to deliver its portion of the GCC railway, which will connect all six member states.

    Saudi Arabia Railways (SAR) issued a tender for design consultancy services for the project on 7 May.

    The kingdom’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, at Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Türkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have been progressing with renewed impetus since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, the Qatari cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will span 2,186 kilometres, beginning in Kuwait, passing through Dammam in Saudi Arabia, reaching Bahrain via a planned causeway, and continuing from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman.

    The network’s route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but divided between its constituent parts.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16793841/main.jpg
    Yasir Iqbal
  • Kuwait tenders upstream oil project

    12 May 2026

    State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to develop power infrastructure to provide electricity to the country’s Bahra oil field.

    The project focuses on constructing an 11kV, 72MW main intake in the Bahra-A area.

    It also includes the development of 11kV, 20MW substations in the Bahra-A2 area, and the conversion of a substation in the Bahra-A1 area in northern Kuwait.

    An initial meeting for the project is scheduled for 7 June, and bids are due by 9 August.

    Kuwait’s oil and gas sector has been severely impacted by the blockade of the Strait of Hormuz, through which all of its crude exports are normally shipped.

    The country recorded zero crude oil exports in April for the first time since the end of the Gulf War in 1991, according to shipping monitor TankerTrackers.com.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792080/main.png
    Wil Crisp
  • Chinese company signs deal to develop Syria cement plant

    12 May 2026

    China’s Jiangsu Pengfei Group has signed a deal with Damascus-based Al-Hasan Holding Group (HHG) to develop a cement plant in Syria’s Raqa governorate.

    The “strategic agreement” was signed on 29 April, according to a statement from HHG.

    The clinker production line will have a capacity of 5,000 tonnes a day (t/d).

    Syria is seeking to expand cement production capacity to meet demand from the domestic construction sector.

    HHG is an integrated investment conglomerate headquartered in Damascus with a portfolio of companies across sectors including industry, trade, energy, construction, tourism and services.

    It was founded by the Syrian businessman Hassan Kamel Al-Hasan.

    Jiangsu Pengfei Group is a manufacturer of rotary kiln and grinding equipment.

    The company is involved in the design, manufacture and service of equipment in the fields of building materials, metallurgy and the chemical industry.

    It is also an engineering, procurement and construction service provider that has completed more than 100 cement production line projects.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792079/main.jpg
    Wil Crisp
  • Libya’s national oil company takes control of key refinery

    12 May 2026

    Libya’s state-owned National Oil Corporation (NOC) has signed an agreement to take full control of the country’s Ras Lanuf refinery.

    The agreement marks the end of a decade-long dispute with UAE-based Trasta Energy.

    NOC has signed a final agreement with Trasta to end their partnership in the Libyan Emirates Oil Refining Company (Lerco), giving the NOC full ownership of the Ras Lanuf refinery and petrochemical complex, according to a statement.

    In its statement, NOC said the deal was one of the most important developments in Libya’s oil sector since the 2011 uprising and closed one of the industry’s most complex disputes.

    NOC also said that the deal has paved the way for a new phase of rehabilitation, operation and development.

    Some analysts have linked tensions in the partnership to political divisions in Libya and the UAE’s support for eastern military commander Khalifa Haftar.

    Lerco was established as a joint venture to operate and develop the Ras Lanuf complex, but operations were disrupted after Libya’s civil war, which started in 2011 and overthrew Muammar Gaddafi.

    The Ras Lanuf complex is located about 600 kilometres east of Tripoli on Libya’s northeastern coast and has the capacity to refine about 220,000 barrels of oil a day (b/d), which would make it the country’s largest if it comes online.

    It includes a refinery, storage facilities, export terminals and petrochemical units.

    Under the agreement, all of Trasta’s shares will be transferred to the NOC, allowing the complex to operate under full Libyan management.

    Political instability and security problems have led to repeated problems in Libya’s downstream sector over the past decade.

    On 10 May, it was announced that the Zawiya refinery, which is the country’s largest functioning oil refinery, and the nearby oil port were resuming operations after military clashes forced the refinery to shut down for two days.

    Azzawiya Oil Refining Company, which operates the facility, said it had decided to lift the state of emergency, allowing work to resume at the site.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792076/main.jpg
    Wil Crisp