Stadiums can be contractor busters
3 April 2023

Large-scale sports stadiums may be iconic buildings, but like the sporting events they host, the construction can result in winners and losers if risks are not managed correctly.
Managing these risks was discussed at HKA’s “An Inside Look at the Sources of Stadia Disputes” event in Doha on 28 February.
“Stadiums can be contractor busters. Some well-known examples worldwide have brought down big construction firms,” says Kourosh Kayvani, partner at HKA (pictured).
Kayvani has played key roles in designing and delivering many vast, sophisticated sports stadia. He was a senior design engineer for the roof structures over a number of sports facilities for the Sydney 2000 Olympics, including the Sydney Showground Stadium, International Hockey Centre and International Aquatic Centre Olympic Extension and Legacy.
He was also involved in a number of stadia used for the Melbourne 2006 Commonwealth Games, including the Marvel Stadium, Melbourne Cricket Ground and Melbourne Sports and Aquatic Centre.
Kayvani was the lead designer and project leader of the iconic arch and roof of Wembley Stadium in London.
Several contributing factors make stadiums challenging construction projects. “Stadiums are large and complex. They are big capital expenditures, and a $1bn stadium is not extreme anymore,” says Kayvani.
“Then there is the sheer complexity of the buildings in terms of their function and what it needs to do, which requires several disciplines. You need all the specialist skills in a complex building, such as structures, MEP, civil works and façade.
“You also have other disciplines, such as sports lighting. With that, you need to think about outside broadcasting, Wi-Fi access and enabling people to interact with sporting events,” he adds.
Iconic designs
The structures themselves also create unique challenges. “As well as packages of interconnected works, the building is layered, which means you build from the bottom up. Unlike a typical multi-storey building that is repetitive, it varies as you go up.
“Added to that, some of the elements installed last are long lead items that need to be procured early, such as the big steelwork elements. They need to be temporarily supported while the rest of the facility is being built,” says Kayvani.
The complexities that make stadium projects challenging may only sometimes be realised by the people building them.
“There are risks associated with the construction of stadiums that might not be factored for during the bidding process, particularly if there are bidders that have not done a project like this before,” says Kayvani.
“They might be optimistic about their prospects and regard the project as another building. Not understanding the importance of the specialist expertise and going for the cheapest option will not give the best value in the long run.”
Timing is also essential, as many stadium projects are built to support specific events. “The timing and the need to meet a certain deadline is another major pressure if the stadium is needed for an event like a World Cup or an Olympics,” he says.
Project teams must plan and decide how projects will be delivered to prevent disputes. “You need to think about the delivery model. Build-only is not common nowadays; it is mostly design and construct (D&C). The owner wants to pass on all the risk to the D&C contractor, and the contractor passes on to all of its subcontractors and designers, and then designers have to manage risks that they are not fully in control of,” says Kayvani.
“Often contractors have bought too much risk without being able to manage it.”
Exclusive from Meed
-
UAE GDP projection corrects on conflict24 April 2026
-
April 2026: Data drives regional projects24 April 2026
-
Boutique Group tenders Tuwaiq Palace hotel in Riyadh24 April 2026
-
Firms announce 129MW Dubai data centre24 April 2026
-
Iraq signs upstream oil contract24 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
UAE GDP projection corrects on conflict24 April 2026

MEED’s May 2026 report on the UAE includes:
> COMMENT: Conflict tests UAE diversification
> GVT &: ECONOMY: UAE economy absorbs multi-sector shock
> BANKING: UAE banks ready to weather the storm
> ATTACKS: UAE counts energy infrastructure costs
> UPSTREAM: Adnoc builds long-term oil and gas production potential
> DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
> POWER: Large-scale IPPs drive UAE power market
> WATER: UAE water investment broadens beyond desalination
> CONSTRUCTION: War casts shadow over UAE construction boom
> TRANSPORT: UAE rail momentum grows as trade routes face strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16554417/main.gif -
April 2026: Data drives regional projects24 April 2026
Click here to download the PDF
Includes: Commodity tracker | Top 10 global contractors | Brent spot price | Construction output
MEED’s May 2026 report on the UAE includes:
> COMMENT: Conflict tests UAE diversification
> GVT &: ECONOMY: UAE economy absorbs multi-sector shock
> BANKING: UAE banks ready to weather the storm
> ATTACKS: UAE counts energy infrastructure costs
> UPSTREAM: Adnoc builds long-term oil and gas production potential
> DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
> POWER: Large-scale IPPs drive UAE power market
> WATER: UAE water investment broadens beyond desalination
> CONSTRUCTION: War casts shadow over UAE construction boom
> TRANSPORT: UAE rail momentum grows as trade routes face strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16553627/main.gif -
Boutique Group tenders Tuwaiq Palace hotel in Riyadh24 April 2026

Saudi Arabia’s Boutique Group, backed by the sovereign wealth vehicle Public Investment Fund (PIF), has retendered a contract to convert Tuwaiq Palace in Riyadh into a hotel.
Contractors have been given a deadline of 31 May to submit proposals.
The scheme comprises 40 hotel rooms and suites and 56 one- and two-bedroom villas.
According to regional projects tracker MEED Projects, the contract was first tendered in 2022.
In January of that year, Crown Prince Mohammed Bin Salman launched Boutique Group to manage and convert historic and cultural Saudi palaces into ultra-luxury hotels.
Boutique Group’s first phase covers three palaces, two of which are under construction. Al-Hamra Palace in Jeddah is being converted to include 33 suites and 44 villas. In July 2023, MEED reported that Jeddah-based Al-Redwan Contracting was appointed the main contractor for the Al-Hamra Palace conversion.
The other project is the Red Palace in Riyadh, which will feature 46 suites and 25 guest rooms. In 2023, local contractor Mobco won the contract to undertake the project.
In 1957, the Red Palace became the headquarters of the Council of Ministers for 30 years, and later served as the main office for the Board of Grievances until 2002.
Jordan-headquartered Dar Al-Omran is acting as supervision consultant on all three projects.
Photo credits: Omrania
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16549695/main.jpg -
Firms announce 129MW Dubai data centre24 April 2026
Dubai’s Integrated Economic Zones Authority (DIEZ) has signed a joint-venture agreement with Netherlands-headquartered data centre developer Volt to build a new artificial intelligence (AI)-ready data centre in the emirate.
Planned for Dubai Silicon Oasis, the development will take the form of a campus covering up to 60,000 square metres.
The project will be delivered in two phases, starting with 29MW of immediately available capacity, followed by a second phase adding a further 100MW of committed power.
Under the arrangement, DIEZ will supply the land and essential infrastructure, while Volt will finance and develop the project, lead construction, and manage the design, leasing, implementation and day-to-day operations.
French firm Schneider Electric, which has its regional headquarters in Dubai Silicon Oasis, will support the development by supplying advanced electrical systems, power distribution capabilities and smart data centre infrastructure.
The GCC currently has more than 174 active data centre projects, representing over $93bn in investment, led by international players such as AWS, Google and Huawei, alongside regional developers including Khazna and Moro, supported by government-led localisation strategies.
More than a dozen large-scale facilities valued at over $100m each are currently under tender, with further packages expected to reach the market over the next six to 12 months.
The UAE is one of the leading data centre markets, with hyperscale campuses, sovereign cloud initiatives and edge data centre deployments underway.
Data centre development is closely aligned with the UAE’s digital economy and AI roadmap, as well as the wider smart city programme.
Priorities include hyperscale and colocation facilities to support cloud service providers; edge data centres to reduce latency and enable 5G and IoT use cases; energy-efficient designs using advanced cooling, modular construction and renewables; and strategic partnerships between global hyperscalers, local developers and utilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16548972/main.JPG -
Iraq signs upstream oil contract24 April 2026
State-owned Iraqi Drilling Company (IDC) has signed a contract with China’s EBS Petroleum for a project to drill 17 horizontal wells in the southeastern portion of the East Baghdad field.
Mohamed Hantoush, the general manager of IDC, said the contract signing came after a “series of successful achievements” by the company at the field.
The achievements included the completion of a project to drill 27 horizontal wells and another project to drill 18 horizontal wells, according to a statement released by Iraq’s Ministry of Oil.
In January, Iraq’s Midland Oil Company (MOC), in collaboration with EBS Petroleum, completed the country’s longest horizontal oil well in the southern part of the East Baghdad field.
The well, which was called EBMK-8-1H, reached a total depth of 6,320 metres, and had a 3,535-metre horizontal section, making it the country’s largest horizontal well ever drilled.
Senior officials from the Iraqi Oil Ministry and representatives of EBS Petroleum attended the well’s completion ceremony.
EBS Petroleum is a subsidiary of China’s ZhenHua Oil, which is focused on Iraq.
ZhenHua Oil is the operator of the field and is working with Iraqi partners to oversee the field’s development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16543675/main4942.jpg