Stadiums can be contractor busters
3 April 2023

Large-scale sports stadiums may be iconic buildings, but like the sporting events they host, the construction can result in winners and losers if risks are not managed correctly.
Managing these risks was discussed at HKA’s “An Inside Look at the Sources of Stadia Disputes” event in Doha on 28 February.
“Stadiums can be contractor busters. Some well-known examples worldwide have brought down big construction firms,” says Kourosh Kayvani, partner at HKA (pictured).
Kayvani has played key roles in designing and delivering many vast, sophisticated sports stadia. He was a senior design engineer for the roof structures over a number of sports facilities for the Sydney 2000 Olympics, including the Sydney Showground Stadium, International Hockey Centre and International Aquatic Centre Olympic Extension and Legacy.
He was also involved in a number of stadia used for the Melbourne 2006 Commonwealth Games, including the Marvel Stadium, Melbourne Cricket Ground and Melbourne Sports and Aquatic Centre.
Kayvani was the lead designer and project leader of the iconic arch and roof of Wembley Stadium in London.
Several contributing factors make stadiums challenging construction projects. “Stadiums are large and complex. They are big capital expenditures, and a $1bn stadium is not extreme anymore,” says Kayvani.
“Then there is the sheer complexity of the buildings in terms of their function and what it needs to do, which requires several disciplines. You need all the specialist skills in a complex building, such as structures, MEP, civil works and façade.
“You also have other disciplines, such as sports lighting. With that, you need to think about outside broadcasting, Wi-Fi access and enabling people to interact with sporting events,” he adds.
Iconic designs
The structures themselves also create unique challenges. “As well as packages of interconnected works, the building is layered, which means you build from the bottom up. Unlike a typical multi-storey building that is repetitive, it varies as you go up.
“Added to that, some of the elements installed last are long lead items that need to be procured early, such as the big steelwork elements. They need to be temporarily supported while the rest of the facility is being built,” says Kayvani.
The complexities that make stadium projects challenging may only sometimes be realised by the people building them.
“There are risks associated with the construction of stadiums that might not be factored for during the bidding process, particularly if there are bidders that have not done a project like this before,” says Kayvani.
“They might be optimistic about their prospects and regard the project as another building. Not understanding the importance of the specialist expertise and going for the cheapest option will not give the best value in the long run.”
Timing is also essential, as many stadium projects are built to support specific events. “The timing and the need to meet a certain deadline is another major pressure if the stadium is needed for an event like a World Cup or an Olympics,” he says.
Project teams must plan and decide how projects will be delivered to prevent disputes. “You need to think about the delivery model. Build-only is not common nowadays; it is mostly design and construct (D&C). The owner wants to pass on all the risk to the D&C contractor, and the contractor passes on to all of its subcontractors and designers, and then designers have to manage risks that they are not fully in control of,” says Kayvani.
“Often contractors have bought too much risk without being able to manage it.”
Exclusive from Meed
-
Consultant wins Jeddah metro design22 May 2026
-
-
-
Eni makes oil and gas discovery in Egypt22 May 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Consultant wins Jeddah metro design22 May 2026

French engineering firm Egis has been appointed to undertake the preliminary design consultancy for the Jeddah Metro Blue Line project.
The project client, Jeddah Development Authority, issued the tender in early January, when MEED exclusively reported that Saudi Arabia had restarted plans to build the Jeddah Metro.
Engineering consulting firms submitted bids in April, as MEED reported.
The Blue Line will run from King Abdulaziz International airport and connect to the Haramain high-speed railway station.
The line will be 35 kilometres (km) long and will include 15 stations.
Project history
Plans for the Jeddah Metro were first publicly floated in the early 2010s and were formally packaged into a wider Jeddah public transport programme around 2013-14.
In 2014, French engineering firm Systra was appointed to complete preliminary engineering for the Jeddah Metro, as MEED reported at the time.
In the same year, US-based engineering firm Aecom was awarded a SR276m ($74m) contract to provide pre-programme management consultancy services.
Under its 18-month contract, Aecom was expected to provide staff to support preliminary planning and design work for various phases of the metro project.
This was followed by the appointment of UK-based architectural firm Foster + Partners in 2015 to design the metro stations.
The project then stalled as government spending priorities were reset and major capital programmes were reviewed following the fall in oil prices in 2015, with the metro’s scope, cost and delivery model coming under reassessment.
Early concept designs envisaged a multi-line network integrated with buses and, later, other city-wide mobility upgrades.
Route details
According to Jeddah Transport Company’s website, the scheme comprises 81 stations and 197 trains serving more than 161km. The network will have four lines:
- Orange Line: a 44.8km line running along Al-Madinah Road and Old Makkah Road, with 29 stops including one at Obhur Bridge
- Blue Line: a 35km line running from King Abdulaziz International airport to the Haramain high-speed railway station, with 15 stations
- Green Line: a 17km line running through the city centre, from the downtown area to the Haramain railway station, with nine stops
- Red Line: A 59.7km line running from King Abdullah Stadium north to Old Makkah Street through King Abdulaziz Road and King Abdullah Road, with 25 stops
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16949416/main.jpg -
Egypt signs gas deal with QatarEnergy and Exxon Mobil22 May 2026
Egypt’s Ministry of Petroleum & Mineral Resources has signed a preliminary gas agreement with state-owned QatarEnergy and US-based Exxon Mobil.
The memorandum of understanding (MoU) focuses on cooperation in the development of natural gas discoveries in Cyprus.
The plan involves transporting gas from offshore discoveries in Cypriot waters to Egypt via pipelines.
In a statement, Egypt’s Ministry of Petroleum & Mineral Resources said that the deal would strengthen the North African country’s status as a regional hub for natural gas trading.
The agreement was witnessed by Egypt’s Prime Minister Mustafa Madbouli.
It was signed by Muhammad Al-Bajouri, from the legal affairs department of the Ministry of Petroleum & Minerals, and Kanan Nariman, vice-president for the development of liquefied natural gas (LNG) at Exxon Mobil.
It was also signed by Ali Immunae, director of international exploration and production at QatarEnergy.
Commenting on the MoU signing, Saad Sherida Al-Kaabi, the minister of state for energy affairs, and president and chief executive of QatarEnergy, said: “This MoU represents an important step in advancing regional energy cooperation across the Eastern Mediterranean through unlocking the long-term commercial potential of natural gas resources across that region.”
Egypt’s Ministry of Petroleum & Mineral Resources said the agreement paved the way for QatarEnergy and Exxon to take advantage of existing Egyptian infrastructure in the gas sector, especially the country’s existing LNG export terminals.
Under the terms of the agreement, a study will be conducted to analyse the feasibility of linking the gas discoveries in Cyprus to Egypt’s gas facilities.
The signatories will also establish a commercial framework aimed at achieving “the maximum possible benefit from natural gas resources in both Egypt and Cyprus”.
Egypt’s Minister of Oil and Gas Karim Badawi said the ministry has been working with ExxonMobil to explore cooperation on the development of gas discoveries in Cyprus.
He said the partnership with Egypt would help QatarEnergy and Exxon reduce the cost of developing the discoveries while allowing Egypt to achieve an economic return.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16944918/main.jpg -
Kuwait’s Heisco working on active projects worth $3.5bn22 May 2026

Kuwait’s Heavy Engineering Industries & Shipbuilding Company (Heisco) is in a strong position to weather challenges in the country’s project market, with active projects worth $3.5bn, according to documents seen by MEED.
The company also has active maintenance and service contracts that are worth $843m.
Heisco’s projects span the oil, gas, power, water, construction, transport and industrial sectors.
The company’s biggest active project contract is the $576m project to upgrade Kuwait’s Doha West power station.
This contract was awarded to Heisco by Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) in July 2024.
The company’s second-biggest active project is focused on the construction of crude oil pipelines and associated works in North Kuwait.
This $565m contract was awarded to Heisco by Kuwait’s state-owned upstream operator Kuwait Oil Company (KOC) in February this year.
Other major project contracts include a $442m MEW contract for the rehabilitation of the Az-Zour South power and water distillation station and a $223m KOC contract for the construction of flowlines and associated works in the West Kuwait Area.
Heisco’s biggest active maintenance contract is worth $295m and is focused on providing mechanical maintenance services at Kuwait’s Mina Abdullah Refinery.
This contract was awarded by the state-owned downstream operator Kuwait National Petroleum Company (KNPC) in July 2023 and it officially started in September that year.
The contract is currently due to conclude in November 2028.
Heisco’s second-biggest active maintenance contract is worth $95m and was awarded by Wafra Joint Operations (WJO) for work in the Divided Zone, which is shared by Kuwait and Saudi Arabia.
WJO’s onshore operations cover an area of about 5,000 square kilometres in the Divided Zone.
Saudi Arabian Chevron and Kuwait Gulf Oil Company are equal shareholders in WJO.
Six major fields have been discovered in the WJO area to date: Wafra, South Fuwaris, South Umm-Gudair, Humma, Arq and North Wafra.
Heisco’s Wafra maintenance contract was awarded in October last year and officially started in November the same year.
The contract is expected to conclude in May 2031 and its scope is focused on the maintenance of tanks and vessels as well as the provision of welding services.
Market headwinds
Kuwait’s oil and gas sector has been severely impacted by the blockade of the Strait of Hormuz, through which all of its crude exports are normally shipped.
The country recorded zero crude oil exports in April for the first time since the end of the Gulf War in 1991, according to shipping monitor TankerTrackers.com.
While the closure of the Strait of Hormuz is expected to have a significant impact on Kuwait’s project sector for some time, Heisco’s strong project pipeline is likely to help it weather the challenging economic environment.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16792105/main.png -
Eni makes oil and gas discovery in Egypt22 May 2026
A joint venture of Italy’s Eni and state-owned Egyptian General Petroleum Corporation (EGPC) has made a major oil and gas discovery in Egypt’s Western Desert region.
The partnership, known as Agiba Petroleum Company, made the discovery with an exploratory well drilled in the Bustan South block.
Initial estimates indicate the presence of approximately 330 billion cubic feet of gas and 10 million barrels of condensate and crude oil.
Together, this is a total of 70 million barrels of oil equivalent (boe), making the discovery Agiba Petroleum Company’s biggest in 15 years.
The new discovery is located only 10 kilometres from existing facilities and infrastructure, which should enable rapid development and connection to production.
The well revealed several sandstone and limestone reservoirs, according to a statement from Egypt’s Ministry of Petroleum & Mineral Resources.
The ministry said: “This new discovery reflects the success of the Ministry of Petroleum & Mineral Resources’ efforts and the incentives it offered to partners to intensify exploration activities in areas adjacent to existing fields.
“This facilitates new discoveries near existing infrastructure and production facilities without the need for new infrastructure development.
“This contributes to reducing the cost of producing a barrel, accelerating the integration of discoveries into the production map, and encouraging partners to implement the latest data collection and analysis technologies to increase the chances of successful exploration.”
Egypt is seeing increased interest in its oil and gas resources due to disruptions to shipping through the Strait of Hormuz, which have significantly reduced oil and gas exports from the GCC and Iraq.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16944815/main.jpg -
King Salman airport selects three contractors for apron ECI21 May 2026

Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has selected three groups to deliver the Terminal 6 apron, taxiways and other airfield infrastructure at King Salman International airport (KSIA) in Riyadh.
KSIADC, which is backed by Saudi sovereign wealth vehicle the Public Investment Fund, will initially deliver the project on an early contractor involvement (ECI) basis.
The selected groups are:
- Nesma & Partners / Limak / Samsung C&T / Alayuni Investment & Contracting (local/Turkiye/South Korea/local)
- Shibh Al-Jazira Contracting Company / Top International Engineering Corporation (local/China)
- Al-Rashid Trading & Contracting Company / IC Ictas (local/Turkiye)
The ECI process requires selected contractors to submit methodologies for the project and a design proposal. One team will then be selected for the construction.
MEED understands that the total package could be worth upto $800m.
In March, MEED exclusively reported that KSIADC had selected three groups for the construction of Terminal 6 at KSIA in Riyadh.
In November last year, MEED exclusively reported that KSIADC was targeting mid-2026 to award the contract for the construction of Terminal 6.
MEED reported in May 2025 that US firm Bechtel Corporation had been appointed as the delivery partner for the terminals at KSIA.
According to local media reports, KSIADC’s acting CEO, Marco Mejia, said the project developer had completed the project’s masterplan.
The reports added that Terminal 6 will boost the airport’s capacity by 40 million passengers.
The project is expected to be delivered before the start of Expo 2030 Riyadh.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16937556/main.jpg