Sepco 3 to undertake Al-Zour North 2 & 3 EPC
6 May 2025

A utility developer team comprising Saudi Arabia's Acwa Power and the local Gulf Investment Company (GIC) is understood to have partnered with China-headquartered Shandong Tiejun Electric Power Company (Sepco 3) in its bid to develop Kuwait's second independent water and power project (IWPP).
The Al-Zour North 2 & 3 IWPP will have a power generation capacity of 2,700MW and a desalination capacity of 120 million imperial gallons a day (MIGD).
On 5 May, Kuwait's Ministry of Electricity, Water & Renewable Energy (MEWRE), through the Kuwait Authority for Partnership Projects (Kapp), opened the financial envelopes submitted for the contract by the lone bidder, the Acwa Power-GIC team.
The procurement authority said it opened the financial envelopes in the presence of qualified investors that had previously obtained the project's proposal request.
MEED understands that the financial envelopes contain the annual equivalent payment (AEP) value offer and the share price (SHP) offer.
Based on an uploaded picture on the Kapp website, the AEP value is about KD522.38m ($1.7bn).
The signing of the power and water purchase agreement by the Acwa Power team and MEWRE is expected to take place at a later date, an industry source said.
The project company will sign a 25-year energy conversion and water purchase agreement with MEWRE starting from the project’s commercial operation date.
The Al-Zour North 2 & 3 IWPP will use liquefied natural gas and high-pressure natural gas, with gas oil as a backup fuel, and will connect to the national grid via a 400-kilovolt transmission substation.
According to industry sources, Sepco 3 will be undertaking the project's engineering, procurement and construction (EPC) contract.
Unlike in most GCC states, where bidders submit separate levelised electricity and water costs – expressed in $cents a kilowatt-hour and per cubic metre – for IWPP tenders, Kuwait has two bid evaluation parameters.
The AEP value is a combination of average power and water costs within a year, while the SHP, or equivalent share price, is the amount of equity divided by the number of shares.
Separate tariffs for the power and water desalination plants may have been submitted but will not likely be disclosed publicly, one of the sources said.
Located about 100 kilometres south of Kuwait City, the Al-Zour North 2 & 3 IWPP will be adjacent to the western border of the first Al-Zour North facility for electric power generation and water desalination, which is currently in operation, and on the northern border of the Al-Zour South station.
The project struggled to take off partly due to stakeholder indecision, with the government undergoing several changes and transitions in the past few years.
The plan to develop Kuwait's second IWPP was first announced in 2016-17, following the commissioning of its first IWPP, Al-Zour North 1, in late 2016.
Following a series of delays and scope changes, Kapp finally tendered the contract to develop the Al-Zour North 2 & 3 IWPP in March last year. The tender was issued three years after Kapp had selected a team comprising three UK-headquartered firms – EY, Atkins and Addleshaw Goddard – as transaction advisers for this project, along with another planned IWPP in Al-Khiran, in April 2021.
First IWPP
Kuwait's erstwhile Partnerships Technical Bureau selected the winning consortium of UK/French company GDF Suez, now Engie; Japan's Sumitomo; and Kuwait's AH Sagar & Brothers Group as the preferred bidder for the Al-Zour North 1 IWPP in February 2012.
According to MEED archives, the successful consortium submitted the lowest bid to build the project, with an AEP value of KD127.1m ($453m) at the time.
The project company, Shamal Az-Zour Al-Oula, awarded South Korea’s Hyundai Heavy Industries and France’s Sidem the EPC contract to build the plant.
The combined-cycle power plant produces 1,539.2MW in net contracted power capacity from five General Electric GTG 9F-3 turbines generating 225.8MW each, and two General Electric STG D1 turbines generating 251MW each.
The integrated facility has a multiple-effect distillation unit capable of producing 107 MIGD, the equivalent of 486,400 cubic metres a day of desalinated water.
Public trading of shares
In line with Kuwait's Public-Private Partnership Law, Shamal Az-Zour Al-Oula began trading shares on the Kuwait stock exchange in 2020, after Kapp distributed 50% of its total shares to individual Kuwaiti investors in the last quarter of 2019.
Several public and private entities own the remaining 50% of the company's shares. They are:
- Azour North One Holding Company, owned by a consortium comprising Engie, Sumitomo Corporation and Abdullah Hama Al-Sagar & Brothers (40%);
- Kuwait Investment Authority (5%);
- Public Institution for Social Security (5%).
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg