Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Sumitomo team submits Facility E bid

    25 July 2024

    A team led by Japan's Sumitomo Corporation submitted a bid for the contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    Qatar state utility General Electricity & Water Corporation (Kahramaa) previously extended the tender closing date for the contract in response to developers’ requests, as MEED reported.

    Kahramaa received the single bid on 25 July.

    Sumitomo is understood to have submitted a proposal for the contract along with fellow Japanese utility developer Shikoku Electric, and Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation and Korea Southern Power Company.

    The developer consortium's engineering, procurement and consortium (EPC) partner is South Korea's Samsung C&T, according to sources close to the project.   

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day (MIGD).

    The contract to develop the Facility E IWPP was first tendered in 2019. The three teams that submitted bids for the contract in August 2020 were:   

    • Engie (France) / Mitsui (Japan) / Yonden (Shikoku Electric, Japan)
    • Sumitomo / Kansai Electric (Japan)
    • Marubeni / Kyushu Electric (Japan)

    The original plan was for Facility E IWPP to have a power generation capacity of about 2,300MW and a desalination component of 100MIGD once fully operational.

    However, Kahramaa revised the power plant’s design capacity to 2,600MW and sought alternative prices from bidders. 

    Kahramaa eventually cancelled and reissued the tender in September 2023. The current tender entails a power generation plant with the same capacity as initially tendered in 2019.

    MEED understands that the new target commercial operation date for the Facility E IWPP project has been moved to 2027. 

    The state utility’s transaction advisory team includes UK-headquartered PwC and Clyde & Co as financial and legal advisers, respectively, led by Belgrade-headquartered Energoprojekt as technical adviser.

    Facility E is Qatar’s fifth IWPP scheme. Completed and operational IWPPs include three projects in Ras Laffan – known as Facilities A, B and C – and Facility D in Umm Al-Houl.

    Awarded in 2015 and completed in 2018, Facility D was developed by a Japanese consortium of Mitsubishi Corporation and Tokyo Electric Power Company (Tepco). South Korea's Samsung C&T was the engineering, procurement and construction contractor.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12220438/main.gif
    Jennifer Aguinaldo
  • Iraq drives Gulf projects market growth

    25 July 2024

     

    The Gulf Projects Index rose by 0.7% from 7 June to 12 July, spurred by value gain in the Iraq projects market and, to a lesser extent, the UAE projects market, while the Saudi projects market experienced a slight contraction.

    The rise in the index represents the 16th consecutive month of upward trending value in the regional projects market, dating back to March 2023.

    Iraq rail plans

    The Iraqi projects market gained $26.3bn in value, or 7%, due to the reactivation of plans for a national network of high-speed rail connections across the country, from north to south as well as east to west. The costs of these Iraq rail schemes, which have been under study in various forms for several decades, are relatively indeterminate, but run into the tens of billions of dollars. The rail network is now in the design phase.

    In another major development for the country, the $27bn Gas Growth Integrated Project (GGIP) being undertaken by the National Oil Company and Basra Oil Company, in partnership with TotalEnergies and QatarEnergy, has also passed from study into front-end engineering and design.

    Elsewhere in the region, the UAE projects markets increased in value by $10.6bn, or 1.3%, while Saudi Arabia’s projects market shrank by a comparable $13.9bn, though lesser 0.7%, reducing its value to around about the value it held
    in mid-May.

    The other countries in the GCC and wider Gulf saw comparatively minor changes, with Qatar’s projects market adding $3.9bn or 1.7%, Bahrain’s projects market adding $2bn or 2.9%, Iran’s projects market adding $1.4bn or 0.5%, and Oman’s projects market adding a marginal $0.2bn or 0.1%. Kuwait’s project market value slipped by $0.7bn or 0.4%.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219885/main.gif
    John Bambridge
  • Abu Dhabi tenders 400MW battery storage contract

    25 July 2024

    State offtaker Emirates Water & Electricity Company (Ewec) has invited prequalified companies to submit their proposals for a contract to develop and operate an independent 400MW battery energy storage system (bess) power project in Abu Dhabi.

    Ewec expects to receive bids by the fourth quarter of 2024.

    The planned facility is expected to provide up to 800 megawatt-hours (MWh) of storage capacity.

    Called Bess 1, the project will closely follow the model of Ewec's independent power project (IPP) programme, in which developers enter into a long-term energy storage agreement (ESA) with Ewec as the sole procurer.

    The first plant will be in Al-Bihouth, approximately 45 kilometres (km) southwest of Abu Dhabi, and the second plant will be in Madinat Zayed, about 160km southwest of the city.  

    According to Ewec, the request for proposals is being issued to 27 prequalified companies and consortiums, out of the 93 companies that submitted an expression of interest to bid for the contract in April this year.

    It did not specify the prequalified companies.

     MEED previously reported that the companies that submitted SOQs to bid for the contract include:

    • Acwa Power (Saudi Arabia)
    • EDF (France)
    • GE (US)
    • Jera (Japan)
    • Korea Electric Power Corporation (Kepco, South Korea)
    • Marubeni Corporation (Japan)
    • Samsung C&T (South Korea)

    Sources also cited that "several Chinese Bess manufacturers and suppliers" have applied to prequalify as investors in the project.

    The ESA will be for 15 years, commencing on the project's commercial operation date, which falls in the third quarter of 2026. 

    According to Ewec, the Bess project will provide additional flexibility to the system and ancillary services such as frequency response and voltage regulation.

    "Ewec is deploying BESS to enhance the flexibility and stability of Abu Dhabi’s energy network, allowing for the effective management of peak demand and integration of increasing amounts of renewable energy," the utility said in a media statement on 25 July.

    It added: "BESS technology will also provide crucial ancillary services such as frequency response and voltage regulation, further reinforcing the security of supply and supporting Ewec to increase its solar photovoltaic (PV) capacity to 7.5 gigawatts (GW) by 2030.

    "This accelerated growth in renewables will significantly reduce the carbon dioxide intensity of Ewec's power supply, from 330 kilograms per megawatt hour (kg/MWh) in 2019 to an estimated 190 kg/MWh by 2030."

    Global BESS market

    The overall capacity of deployed Bess globally is expected to reach 127GW by 2027, up from an estimated cumulative deployment of 36.7GW at the end of 2023, according to a recent GlobalData report.

    The report cited Chinese companies BYD and CATL and South Korean companies LG Energy Solutions and Samsung SDI among the top battery technology providers globally.

    Related read: Abu Dhabi tenders 2.5GW Taweelah C contract

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219884/main.gif
    Jennifer Aguinaldo
  • Transforming Riyadh into a world-class city

    25 July 2024

     

    Riyadh is changing fast. As the Saudi capital, it is not only located in the country’s geographical centre, but also at the heart of Vision 2030 and the kingdom’s economic transformation, with a wide range of ambitious development projects.

    The city wants to be one of the best in the world. “The strategic vision for Riyadh focuses on transforming it into a world-class city that is sustainable, innovative and culturally rich,” says Fahad AlSolaie, deputy mayor for digital transformation and smart cities at Riyadh Region Municipality. 

    “The vision includes improving quality of life for residents, diversifying the economy away from oil dependence, and promoting green and smart urban development.”

    Riyadh’s ambitions are driven by population growth and people visiting the city for major global events. “Riyadh is expected to experience significant population growth in the coming years, driven by its economic expansion and global events hosted by the kingdom, such as Expo 2030 and major sports events,” says AlSolaie.

    “Additionally, the presence of large-scale unique projects like the King Abdullah Global Gardens, the development of Wadi Al-Sulay, King Salman Park and others contribute to the city’s attractiveness and livability, further boosting population growth. It is targeted for the population of Riyadh to reach 10 million residents, reflecting its rising prominence as a business and cultural hub. This growth will enhance Riyadh’s status as a dynamic urban centre, equipped to meet the evolving needs of its expanding population.”

    The vision includes improving quality of life, diversifying the economy, and promoting green and smart urban development
    Fahad AlSolaie, Riyadh Region Municipality

    Infrastructure projects

    Riyadh Region Municipality is playing a key role in the city’s development. “Riyadh municipality is responsible for a wide array of infrastructure projects that are crucial for the city’s development and sustainability. These include paving, asphalting and road stabilisation projects, which are essential for maintaining and improving the city’s road networks,” says AlSolaie.

    “The municipality develops public parks, ensuring that the necessary infrastructure is in place to provide recreational spaces. Bridge and tunnel construction and ongoing enhancements are also a significant focus, aimed at improving traffic flow and connectivity across the city. Furthermore, Riyadh is committed to extensive lighting projects and the maintenance of these systems, with the city one of the largest globally in terms of the number of streetlight poles.” 

    A key responsibility of the municipality is to maintain the city’s cleanliness and environmental health, adds AlSolaie. “This involves regular street cleaning, waste management and pollution control measures to keep the city clean and environmentally sustainable. These efforts are integral to quality of life, contributing to the vision of making Riyadh a more livable and accessible urban environment.”

    Signature schemes

    The municipality is also involved in the delivery of a series of signature projects in and around Riyadh. “The King Abdullah Global Gardens project aims to create a vast green space that combines natural landscapes with high-tech interactive exhibits, promoting environmental education and sustainability,” says AlSolaie. 

    The Wadi Al-Sulay development, meanwhile, is focused on transforming Wadi Al-Sulay into a recreational and cultural destination, featuring amenities that encourage outdoor activities and community gatherings.

    The municipality collaborates extensively with other government agencies and private sector partners to ensure cohesive and integrated development. This includes coordinating efforts on large-scale projects, urban planning and infrastructure improvements to support the city’s growth.

    “The municipality ensures alignment with master developers and major projects through regulatory frameworks, strategic planning sessions and collaborative platforms that facilitate integration of infrastructure projects and urban development efforts across the city,” says AlSolaie.

    With aspirations to become one of the world’s most advanced cities, digital transformation is helping Riyadh achieve its goals. “Digital transformation is vital for Riyadh Municipality for several compelling reasons. Firstly, it enhances service efficiency by adopting digital technologies, streamlining operations, reducing manual processes, minimising errors and speeding up response times. This not only improves service delivery, but also cuts operational costs, allowing for better resource allocation. 

    “Secondly, it improves citizen engagement through digital platforms that enable interactive and responsive communication. Citizens can easily access information, request services and provide feedback, enhancing transparency and building trust.

    “Thirdly, digital transformation fosters innovation in urban management using technologies such as the Internet of Things , artificial intelligence and big data analytics to optimise urban functionalities like smart waste monitor manholes and public safety. 

    “Additionally, it supports economic diversification by modernising infrastructure and services, thus attracting new businesses, especially in the technology sector, aligning with Saudi Arabia’s Vision 2030,” says AlSolaie.

    Online services

    Riyadh Region Municipality is moving its services online as part of the digital transformation. “Riyadh municipality is progressively digitising its services by offering e-services platforms where residents can access various municipal services such as mobile applications, geoportal web application and service requests online, thus increasing accessibility and convenience,” says AlSolaie. 

    The drive to digitise will enable Riyadh to become a smart city. “By implementing advanced technologies such as the Internet of Things, artificial intelligence and geographic information systems, Riyadh Municipality is optimising key city functions such as reducing and monitoring visual pollution, enhancing public safety and conducting environmental monitoring,” he says. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219710/main.gif
    Colin Foreman
  • WTTCO tenders water pipeline and reservoir packages

    25 July 2024

    State-owned Saudi water transmission and storage operator Water Transmission & Technologies Company (WTTCO) has issued two tenders involving a contract to build a water transmission pipeline in Dammam City and an engineering design services contract for water reservoir stations.

    The first contract is for the supply and installation of a water transmission system for the Second Industrial City in Dammam.

    WTTCO expects to receive proposals for this contract by 1 August.

    The second request for proposals involves a contract to provide engineering and design services for phases 2 and 3 of WTTCO’s strategic water reservoir station projects.

    The two phases cover reservoir stations in 150 locations and about 750 kilometres of water transmission pipeline.

    WTTCO expects to receive proposals from engineering consultancy firms for this contract by 4 August.

    The company has embarked on one of the world’s largest water conveyance and storage programmes as it seeks to increase potable water supply capacity across the kingdom.

    The expenditure programme, which WTTCO estimates is worth up to SR140bn ($38bn) by 2030, covers 396 individual projects, MEED reported in May.

    WTTCO’s objectives by 2027 are to have a total network size of 15,000km, 9.5 million cubic-metres-a-day transmission capacity, 118 pumping stations and more than 900 storage tanks.

    The capital expenditure programme was outlined in a WTTCO presentation at the Future Projects Forum in Riyadh on 20 May.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219515/main.jpg
    Jennifer Aguinaldo