Rumah and Nairiyah tariffs set precedent

19 November 2024

Commentary
Jennifer Aguinaldo
Energy & technology editor

The levelised costs of electricity (LCOEs) for the four combined-cycle gas turbine independent power projects (IPPs) recently awarded in Saudi Arabia are expected to set a precedent for tariffs in upcoming thermal IPPs procured in the GCC region.

Two separate developer consortiums bid for and won the contracts to develop the Rumah 1 and 2 and Nairiyah 1 and 2 IPPs, which are located in Riyadh and the Eastern Province, respectively.

A consortium comprising Saudi Electricity Company (SEC), Riyadh-based utility developer Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contract to develop the Rumah 1 and Nairiyah 1 IPPs, each with a capacity of 1,800MW.

The team offered an LCOE of $cents 4.5859 a kilowatt-hour ($c/kWh) for Rumah 1, and $c4.6114/kWh for Nairiyah 1.

A consortium comprising the UAE-based Abu Dhabi National Energy Company (Taqa), Japan’s Jera Company and the local Albawani Company won the contract to develop and operate the Rumah 2 and Nairyiah 2 IPPs. 

The Taqa-Jera-Albawani consortium offered an LCOE of $c4.5613/kWh for Rumah 2, and $c4.4960/kWh for Nairiyah 2.

LCOEs represent an all-in tariff including capital and operating expenditures during the power-purchase agreement (PPA) period. In this case, the principal buyer, Saudi Power Procurement Company, agreed to buy the electricity from the project companies for 25 years.

The last comparable IPP procured by SEC in Saudi Arabia was Rabigh 2, for which Acwa Power proposed a tariff of $c1.9/kWh in 2012-13. Rabigh 2 is older than the Fadhili IPP, which was awarded in 2016, but the latter is a cogeneration plant, which was won by France's Engie.

Engineering, procurement and construction (EPC) contractors and original equipment manufacturers say that capital expenditure (capex) for building thermal plants has significantly increased compared to before the Covid-19 pandemic.

Estimates indicate that EPC costs have increased from about $500/kWh to $700-$800/kWh since around 2020.

Despite this, the latest thermal IPP tariffs in Saudi Arabia do not appear significantly higher compared to the tariff for the Fujairah F3 IPP in the UAE, which was procured in 2020.

Several factors underpin tariff trends, according to experts. LCOEs cover fuel capex recovery and operating expenses, where fuel can represent 70%-80%, depending on the prevailing fuel price during the proposals stage.

It should also be noted that the fuel prices and project ownership structures vary depending on jurisdiction, which directly affects the LCOE.

Scale, with the four Saudi plants being awarded together, is also an important factor, as is the technology, because more energy-efficient gas turbines could have contributed to keeping the Saudi tariffs lower than initially expected.

A transaction adviser also notes that the 2024 cost of debt outlook is lower, so swap rates are lower.

Crucially, MEED understands that the tariffs submitted for Rumah and Nairiyah do not yet include potential exit costs, assuming a carbon capture, utilisation and storage (CCUS) solution is not reached while the PPAs are in force.

According to an industry source, CCUS discussions for the Rumah and Nairyah IPPs are set to begin in the 2030s, and the tariffs agreed today will be adjusted based on the outcome of those discussions. 

All this suggests that interesting comparisons will be soon drawn between the Rumah and Nairiyah tariffs in Saudi Arabia and the tariffs that bidders plan to propose for the Taweelah C and Madinat Zayed schemes in Abu Dhabi.

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12941265/main.jpg
Jennifer Aguinaldo
Related Articles
  • Partners launch feed-to-EPC contest for Duqm petchems project

    27 April 2026

     

    Register for MEED’s 14-day trial access 

    Omani state energy conglomerate OQ Group and Kuwait Petroleum International (KPI), the overseas subsidiary of Kuwait Petroleum Corporation, have initiated a feed-to-EPC competition among contractors to develop a major petrochemicals complex at Duqm.

    Under a feed-to-EPC model, the project operator selects contractors to carry out front-end engineering and design (feed). It then awards the engineering, procurement and construction (EPC) contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.

    OQ8, the 50:50 joint venture of OQ and KPI, is understood to have issued the tender for the Duqm petrochemicals project’s feed-to-EPC competition in mid-March, with a deadline of 6 May for contractors to submit proposals, sources told MEED.

    Several local and international contractors based in Oman are believed to be participating in the competition, according to sources.

    OQ Group CEO Ashraf Bin Hamad Al-Maamari and KPI’s CEO Shafi Bin Taleb Al-Ajmi signed an agreement on 3 February, during the Kuwait Oil & Gas Show and Conference, to develop a major petrochemicals-producing complex in Oman’s Duqm. The parties did not disclose details at the time.

    ALSO READ: Duqm petrochemicals revival provides fillip to Gulf projects market

    The agreement represented a significant step forward in Oman and Kuwait’s long-held plans to jointly develop a petrochemicals complex next to the existing Duqm refinery, which will benefit from favourable feedstock access and strong cost competitiveness.

    The planned facility will also benefit from  in Al-Wusta governorate, along Oman’s Arabian Sea coastline.

    OQ8 had struggled to make meaningful progress on the Duqm petrochemicals project since the plan was conceived as early as 2018, for a variety of reasons.

    The original plan for the Duqm petrochemicals facility, estimated at $7bn, centred on a mixed-feed steam cracker with a capacity to produce 1.6 million tonnes a year (t/y) of ethylene. The project also included a polypropylene (PP) plant with a capacity of 280,000 t/y and a high-density polyethylene (HDPE) plant with a capacity of 480,000 t/y.

    The complex was also expected to include an aromatics plant, as well as storage facilities for naphtha and liquefied petroleum gas (LPG).

    The project’s prospects were temporarily boosted when Saudi Basic Industries Corporation (Sabic) expressed interest in investing by signing a non-binding memorandum of understanding with OQ in December 2021.

    Reuters reported in December that Sabic was withdrawing from the project, leaving OQ to look for other partners. The new agreement between OQ and KPI is understood to have followed the Saudi chemical giant’s departure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577785/main.jpg
    Indrajit Sen
  • Nakheel awards $953m Palm Jebel Ali villas deal

    27 April 2026

    Dubai-based real estate developer Nakheel, now part of Dubai Holding, has awarded two contracts worth AED3.5bn ($953m) to local firms for the construction of 544 villas at its Palm Jebel Ali project in Dubai.

    The first contract was awarded to Ginco General Contracting for the construction of 354 villas across fronds A to D.

    The second contract was awarded to United Engineering Construction Company (Unec) for the construction of 190 villas on fronds E and F.

    Construction is expected to begin in Q2 this year, with completion scheduled for 2028.

    Earlier phases

    In October 2024, Nakheel awarded three contracts worth AED5bn ($1.3bn) for the construction of 723 villas on fronds K to P. The contracts went to Ginco, Unec and the local Shapoorji Pallonji.

    Under these awards, Ginco is delivering 197 villas on fronds O and P, Shapoorji Pallonji is constructing 275 villas on fronds M and N, and Unec is building 251 villas on fronds K and L. Villa construction is expected to be completed by 2026.

    Infrastructure works

    This was followed by Nakheel awarding infrastructure contracts worth over AED750m ($204m) to local firm Dutco Construction for works on Palm Jebel Ali.

    The infrastructure work includes utility connections, excavation, backfilling, and the construction of roads and pavements across fronds A to G. It also covers 11-kilovolt power distribution and telecommunications-related utility works.

    Reclamation contract

    In August 2024, Nakheel awarded an AED810m ($220m) contract to complete the reclamation works for the project.

    The contract was awarded to Belgium’s Jan De Nul. Its scope includes dredging, land reclamation, beach profiling and sand placement to support the construction of villas across all fronds.

    Masterplan details

    Nakheel released details of the new masterplan for Palm Jebel Ali in June 2023. Twice the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature more than 80 hotels and resorts, along with a range of entertainment and leisure facilities.

    It includes seven connected islands that will cater to approximately 35,000 families. The development also emphasises sustainability, with 30% of public facilities expected to be powered by renewable energy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577782/main.jpg
    Yasir Iqbal
  • Iraq’s first LNG terminal to be completed in June

    27 April 2026

    Iraq’s first liquefied natural gas (LNG) import terminal is expected to be completed in early June, according to the country’s Ministry of Electricity.

    The terminal, which has an estimated investment value of $450m, is being developed at the Port of Khor Al-Zubair and will have a capacity of 750 million standard cubic feet a day (cf/d).

    Ministry spokesperson Ahmed Mousa told the Iraqi News Agency that “work is proceeding at an accelerated pace to complete the LNG platform”, noting that “the government has set 1 June as the date for finishing the project”.

    In October last year, US-based Excelerate Energy signed a commercial agreement with a subsidiary of Iraq’s Ministry of Electricity to develop the floating LNG terminal.

    The contract was signed at the office of Iraq’s Prime Minister Mohammed Shia Al-Sudani during a ceremony attended by senior officials from both countries, including the US deputy secretary of energy James Danly.

    The contract included a five-year agreement for regasification services and LNG supply with extension options, featuring a minimum contracted offtake of 250 million cf/d.

    Ahmed Mousa said that “under the contract, the company is responsible for completing the facility as well as securing the agreed gas quantities from any source, in line with the specified terms”.

    He added: “Work is continuing according to the planned timelines to complete the project on schedule, as part of the Ministry of Electricity’s plans to keep pace with peak summer loads.”

    Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.

    Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.

    Recently, Iraq’s oil and gas sector has been disrupted by fallout from the US and Israel’s attack on Iran on 28 February and the subsequent regional conflict.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% amid problems shipping crude through the Strait of Hormuz.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577746/main.jpg
    Wil Crisp
  • Iraqi LNG import terminal raises questions about energy strategy

    27 April 2026

    Commentary
    Wil Crisp
    Oil & gas reporter

    Iraq’s first LNG import terminal is set to come online in early June, at a time when global LNG prices are likely to remain close to their highest levels in more than three years.

    The disruption to global oil and gas exports in the wake of the US and Israel’s attack on Iran on 28 February led to LNG prices soaring, with natural gas prices in Asia and Europe rising to their highest levels since January 2023 during March.

    So far, there has been little progress towards a diplomatic or military solution to reopen the Strait of Hormuz, and most analysts do not forecast significant price declines in the near term.

    On 24 April, the International Energy Agency (IEA) said that the combined effect of short-term supply losses and slower capacity growth could result in a cumulative loss of around 120 billion cubic metres of LNG supply between 2026 and 2030.

    While the IEA expects new liquefaction projects in other regions to offset these losses over time, it still believes the crisis will lead to prolonged tight market conditions through 2026 and 2027.

    This means that Iraq will likely have to pay elevated prices for imported LNG for some time to come – if it can receive shipments at all.

    The port of Khor Al-Zubair is located in the Arabian Gulf, and LNG shipments from the US or Australia would need to pass through the Strait of Hormuz before reaching the terminal.

    This will only be possible if a solution is found to the ongoing blockade of the shipping route.

    Investment debate

    Iraq’s project to develop a floating LNG terminal is estimated to cost $450m, and many in Iraq may question whether this was the best use of these funds.

    While it may have been difficult for Iraqi policymakers to foresee the attack by the US and Israel on Iran and its impact on LNG markets, Iraq had several strong options to enhance domestic energy security rather than turning to LNG imports.

    The most obvious of these was investing in infrastructure to enable it to utilise its domestic gas reserves.

    According to the World Bank’s 2025 Global Gas Flaring Tracker Report, in 2024, Iraq burned off more unused gas than any other country, except Russia and Iran, which ranked first and second, respectively.

    That year, an estimated total of more than 18 billion cubic metres of natural gas was flared in Iraq due to a lack of infrastructure to properly capture and process it.

    It is highly likely that projects to gather and process this gas would have been more reliable and cost-effective than investing in a new floating LNG terminal, which increases the country’s exposure to global LNG price fluctuations and shipping disruptions.

    Other options could have included developing domestic gas fields or investing in solar and battery storage projects, which have become increasingly affordable in recent years.

    The cost of solar panels has fallen by more than 95% over the past decade.

    Power shortfall

    As things stand, Iraq is likely to face severe electricity shortages this summer.

    On 21 April, Iraq’s Ministry of Electricity said it plans to produce 30,000MW this summer, well short of the predicted peak demand of around 55,000MW.

    Ahmed Musa, a spokesperson for the Electricity Ministry, told the state-run Iraqi News Agency that the shortfall will result in planned outages across the country.

    He also said that even meeting the 30,000MW target is contingent on sufficient gas supplies.

    If Iraq experiences the same level of power outages as last year – or worse – many are likely to view the $450m spent on an LNG import terminal as a waste of money and an expensive symbol of poor planning.

    Power cuts this summer could stoke unrest at a time that is already politically precarious due to the ongoing regional conflict.

    In recent years, electricity shortages have repeatedly fuelled protests in Iraq during the summer months, particularly in Basra, where blackouts and poor public services have driven people to take to the streets.

    If the Strait of Hormuz does not reopen soon, Iraq’s economic crisis will deepen, and electricity shortages are likely to further undermine the country’s stability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577743/main.jpg
    Wil Crisp
  • Kuwait approves Doha desalination plant award

    27 April 2026

    Kuwait’s Central Agency for Public Tenders has approved the recommendation of the Ministry of Electricity & Water to award a KD114.28m ($371.5m) contract to supply, install, operate and maintain the second phase of the Doha seawater reverse osmosis (SWRO) desalination plant.

    A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag has been selected for the project, with the award understood to be pending final approval from the Audit Bureau.

    The project will deliver a production capacity of about 60 million imperial gallons a day (MIGD) and will include the desalination plant with full reverse osmosis trains, pre- and post-treatment systems, recarbonation equipment, booster pumps, and safety and filtration systems.

    The total project duration is 96 months. The Doha SWRO desalination plant is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.

    MEED previously reported that the Heisco/Wabag joint venture submitted the lowest bid. Bidders and prices included:

    • Heavy Engineering Industries & Shipbuilding / Wabag: $373.2m
    • Cox Water (Spain): $538.1m
    • Orascom Construction (Egypt): $568.4m

    In April 2025, MEED reported that Kuwait had retendered the contract for the facility after the ministry cancelled the initial tender in June 2024.

    The Ministry of Electricity & Water awarded South Korea’s Doosan Heavy Industries & Construction – now known as Doosan Enerbility – a $422m contract in May 2016 to build the 60 MIGD Doha 1 SWRO plant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577722/main.jpg
    Mark Dowdall