Region remains global project finance hotspot

25 October 2024

 


This package also includes: PPP activity eases back but remains strong


While the Middle East and North Africa (Mena) region has recently become the focus of global attentions for all the wrong reasons – amid surging conflict in the Levant – advisers continue to see the adjacent Gulf as a standout market for project finance.

“The Middle East market has been buoyant compared to the project finance market in many other parts of the world,” says Matthew Escritt, a partner at the UAE office of law firm Pinsent Masons, who has advised on large regional financings. 

“By far and away, the Middle East is the place to be if you want to do big-ticket project finance.”

Major deals such as the $6.1bn financing for Neom Green Hydrogen Company, which closed in 2023, affirm the region’s continued affinity with large and sometimes complex transactions that involve senior and mezzanine facilities and bring numerous financial institutions into the mix.

The use of project finance structures across a widening array of sectors – from hard and soft infrastructure, to newer asset classes such as green energy – suggests that the Middle East will remain a hotspot for funding activity.

Ratings agency S&P Global has forecast that alongside the energy sector, the region will see significant investments in transport and social infrastructure, as well as in digitalisation, with large outlays on connectivity and a doubling of data centre capacity as the region’s population continues to grow.

Regional reconfiguration

While the Mena region as a whole has seen an uptick in activity, the picture is not even.

“Activity in Saudi Arabia has seen something of a slowdown after it became clear that some of the kingdom’s more ambitious plans were being recalibrated,” says Escritt.

“Liquidity has become tighter and we’re finding that procurers are taking longer to announce their preferred bidder.”

Appetite among international banks has been weaker for some sectors, such as social infrastructure. 

Neom’s large green hydrogen financing of 2023 remains a standout rather than the norm, although local lenders appear ready to step into the breach when circumstances allow. For example, in April of this year, when Neom secured a $2.7bn revolving credit facility to cover short-term financing requirements, it was nine local banks that ended up providing the financing.  It was, according to Neom CEO Nadhim Al-Nasr, a “natural fit” within the company’s wider funding structure.

International banks’ interest remains fixed on energy sector and infrastructure projects. Outside of these, says Escritt, the project finance market is dominated by large local banks. This, he says, has contributed to a tighter liquidity environment as these financial institutions run up against exposure limits. “The key to unlocking that market’s undoubted potential is to create conditions that improve the appetite of foreign lenders for Saudi Arabian credits,” says Escritt.

International lenders’ comfort zones were once largely focused on massive financings such as the kingdom’s Sadara petrochemicals project, which in 2013 drew commitments of $12.5bn.  

“Frankly, the days of the Sadara blockbuster-type projects are over. But there’s still some substantial projects out there,” says John Dewar, a partner at international law firm Milbank, which specialises in energy and infrastructure financings.

Dewar points out that there are still a fair number of $2bn-$4bn projects in the region, but that it is more challenging to syndicate larger scales of debt. Even export credit agency (ECA) support is not a given in the Mena region.

“Even if they’ve got large export content in them, it’s still more difficult to get them mobilised into oil and gas financings, for example. The ECAs are pulling back from those types of deals,” says Dewar. “Petrochemicals is slightly easier, but nonetheless, over the next couple of years we will see fewer agency lenders involved in the petrochemicals sector than we have at the moment.”

The UAE – Abu Dhabi in particular – remains a bright spot in the region.  

 “Abu Dhabi has shown that it is very good at getting things done,” says Escritt, whose team helped bring the Khalifa University student accommodation public-private partnership project to financial close – another significant social infrastructure project in the UAE capital. 

“There’s a strong appetite among the major project finance players for Abu Dhabi risk – they like it. 

“You are also now seeing the larger local banks stepping into this space, with Abu Dhabi Commercial Bank and First Abu Dhabi Bank in particular showing appetite for these credits,” says Escritt.

The Qatari market has proved more sluggish, although the Al-Wakra and Wukair independent sewage treatment plant project – the country’s first – has seen progress this year with a $540m financing on a 75:25 debt-to-equity ratio basis, including a soft mini-perm structure.

Emergent energy markets

Energy has traditionally been a magnet for project financing in the Mena region and should support one of the emerging areas within that segment – carbon capture and storage (CCS), which is an area of focus for regional oil companies.

Saudi Aramco’s first phase of its Accelerated Carbon Capture and Sequestration project is expected to be the world’s largest CCS hub upon completion. Aramco aims to transport and capture 9 million tonnes a year of emissions by 2027 in its first phase.

Carbon-capture financing could prove an attractive opportunity for banks, swelling the liquidity that is already there for hydrogen schemes.

Lender appetite has increased for these new energy schemes. “[Saudi Arabia] had a large splash on solar power recently with Acwa Power financings, while Saudi Aramco will have relatively large financing requirements for its energy transition projects. The [kingdom is] now still very much focused on project finance transactions,” says Dewar.

With Oman pushing green hydrogen projects in Duqm and Dhofar, and Egypt backing an ambitious renewables programme under a structure that investors have found to be attractive and bankable, project financing should make more headway in the low-carbon space across the region. 

In renewables, there is more depth in the market and more lenders willing to participate, although as law firm AO Shearman has noted, there remains a deficiency in bankability and unpredictable development costs in green hydrogen schemes.

This piqued interest in non-fossil fuel project funding contrasts with the reduced appetite globally among banks for traditional hydrocarbons schemes. “If you’re looking at oil and gas financing, then it’s increasingly a struggle outside of some of the Chinese banks,” says Dewar. “That’s not to say that in the Middle East there aren’t still a number of local and regional banks that are happy to participate in the market.”

Government support will remain critical in getting centrepiece financings under way in areas such as green hydrogen. And, as AO Shearman notes, given the nature of the supply chain for green hydrogen projects, there is value in including ECA-supported debt in the financing mix. In particular, where Mena projects involve key equipment coming in from outside the region, ECAs have an important role to play in building confidence.

ECAs remain a mainstay in traditional Gulf downstream sectors such as petrochemicals. For example, South Korea’s Hyundai Engineering & Construction has tapped $1bn of project financing support from the Export-Import Bank of Korea for the Amiral petrochemicals project in Saudi Arabia. As the lone South Korean contractor deployed on the estimated $7bn scheme, it therefore enjoys sole access to this project financing facility.

Project sponsors will also be looking to capital market instruments, despite these losing favour in recent years as the global
interest-rate environment rendered proposed bond components in project financings less appealing to many.

With the US Federal Reserve in a gradual monetary easing cycle, however, the use of project-related bonds may begin to revive.

For example, Saudi Aramco has managed to complete some large gas pipeline financings using acquisition facilities that were refinanced in the bond and sukuk markets.

“As the interest-rate environment changes, that’s going to get more people thinking about bond refinancing activity. We’ll see a bit more in a year’s time, when interest rates have come down and investors readjust and start to look for more attractive yields,” says Dewar.

With a different interest-rate climate in place, and more lenders and project backers gaining experience in the new energy schemes that are emerging in the Gulf and the wider Mena region, the hope is that banks will be dipping back into the region with transactions that will maintain its status as the global project finance hotspot for a while longer.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12678172/main.gif
James Gavin
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp