Region remains global project finance hotspot

25 October 2024

 


This package also includes: PPP activity eases back but remains strong


While the Middle East and North Africa (Mena) region has recently become the focus of global attentions for all the wrong reasons – amid surging conflict in the Levant – advisers continue to see the adjacent Gulf as a standout market for project finance.

“The Middle East market has been buoyant compared to the project finance market in many other parts of the world,” says Matthew Escritt, a partner at the UAE office of law firm Pinsent Masons, who has advised on large regional financings. 

“By far and away, the Middle East is the place to be if you want to do big-ticket project finance.”

Major deals such as the $6.1bn financing for Neom Green Hydrogen Company, which closed in 2023, affirm the region’s continued affinity with large and sometimes complex transactions that involve senior and mezzanine facilities and bring numerous financial institutions into the mix.

The use of project finance structures across a widening array of sectors – from hard and soft infrastructure, to newer asset classes such as green energy – suggests that the Middle East will remain a hotspot for funding activity.

Ratings agency S&P Global has forecast that alongside the energy sector, the region will see significant investments in transport and social infrastructure, as well as in digitalisation, with large outlays on connectivity and a doubling of data centre capacity as the region’s population continues to grow.

Regional reconfiguration

While the Mena region as a whole has seen an uptick in activity, the picture is not even.

“Activity in Saudi Arabia has seen something of a slowdown after it became clear that some of the kingdom’s more ambitious plans were being recalibrated,” says Escritt.

“Liquidity has become tighter and we’re finding that procurers are taking longer to announce their preferred bidder.”

Appetite among international banks has been weaker for some sectors, such as social infrastructure. 

Neom’s large green hydrogen financing of 2023 remains a standout rather than the norm, although local lenders appear ready to step into the breach when circumstances allow. For example, in April of this year, when Neom secured a $2.7bn revolving credit facility to cover short-term financing requirements, it was nine local banks that ended up providing the financing.  It was, according to Neom CEO Nadhim Al-Nasr, a “natural fit” within the company’s wider funding structure.

International banks’ interest remains fixed on energy sector and infrastructure projects. Outside of these, says Escritt, the project finance market is dominated by large local banks. This, he says, has contributed to a tighter liquidity environment as these financial institutions run up against exposure limits. “The key to unlocking that market’s undoubted potential is to create conditions that improve the appetite of foreign lenders for Saudi Arabian credits,” says Escritt.

International lenders’ comfort zones were once largely focused on massive financings such as the kingdom’s Sadara petrochemicals project, which in 2013 drew commitments of $12.5bn.  

“Frankly, the days of the Sadara blockbuster-type projects are over. But there’s still some substantial projects out there,” says John Dewar, a partner at international law firm Milbank, which specialises in energy and infrastructure financings.

Dewar points out that there are still a fair number of $2bn-$4bn projects in the region, but that it is more challenging to syndicate larger scales of debt. Even export credit agency (ECA) support is not a given in the Mena region.

“Even if they’ve got large export content in them, it’s still more difficult to get them mobilised into oil and gas financings, for example. The ECAs are pulling back from those types of deals,” says Dewar. “Petrochemicals is slightly easier, but nonetheless, over the next couple of years we will see fewer agency lenders involved in the petrochemicals sector than we have at the moment.”

The UAE – Abu Dhabi in particular – remains a bright spot in the region.  

 “Abu Dhabi has shown that it is very good at getting things done,” says Escritt, whose team helped bring the Khalifa University student accommodation public-private partnership project to financial close – another significant social infrastructure project in the UAE capital. 

“There’s a strong appetite among the major project finance players for Abu Dhabi risk – they like it. 

“You are also now seeing the larger local banks stepping into this space, with Abu Dhabi Commercial Bank and First Abu Dhabi Bank in particular showing appetite for these credits,” says Escritt.

The Qatari market has proved more sluggish, although the Al-Wakra and Wukair independent sewage treatment plant project – the country’s first – has seen progress this year with a $540m financing on a 75:25 debt-to-equity ratio basis, including a soft mini-perm structure.

Emergent energy markets

Energy has traditionally been a magnet for project financing in the Mena region and should support one of the emerging areas within that segment – carbon capture and storage (CCS), which is an area of focus for regional oil companies.

Saudi Aramco’s first phase of its Accelerated Carbon Capture and Sequestration project is expected to be the world’s largest CCS hub upon completion. Aramco aims to transport and capture 9 million tonnes a year of emissions by 2027 in its first phase.

Carbon-capture financing could prove an attractive opportunity for banks, swelling the liquidity that is already there for hydrogen schemes.

Lender appetite has increased for these new energy schemes. “[Saudi Arabia] had a large splash on solar power recently with Acwa Power financings, while Saudi Aramco will have relatively large financing requirements for its energy transition projects. The [kingdom is] now still very much focused on project finance transactions,” says Dewar.

With Oman pushing green hydrogen projects in Duqm and Dhofar, and Egypt backing an ambitious renewables programme under a structure that investors have found to be attractive and bankable, project financing should make more headway in the low-carbon space across the region. 

In renewables, there is more depth in the market and more lenders willing to participate, although as law firm AO Shearman has noted, there remains a deficiency in bankability and unpredictable development costs in green hydrogen schemes.

This piqued interest in non-fossil fuel project funding contrasts with the reduced appetite globally among banks for traditional hydrocarbons schemes. “If you’re looking at oil and gas financing, then it’s increasingly a struggle outside of some of the Chinese banks,” says Dewar. “That’s not to say that in the Middle East there aren’t still a number of local and regional banks that are happy to participate in the market.”

Government support will remain critical in getting centrepiece financings under way in areas such as green hydrogen. And, as AO Shearman notes, given the nature of the supply chain for green hydrogen projects, there is value in including ECA-supported debt in the financing mix. In particular, where Mena projects involve key equipment coming in from outside the region, ECAs have an important role to play in building confidence.

ECAs remain a mainstay in traditional Gulf downstream sectors such as petrochemicals. For example, South Korea’s Hyundai Engineering & Construction has tapped $1bn of project financing support from the Export-Import Bank of Korea for the Amiral petrochemicals project in Saudi Arabia. As the lone South Korean contractor deployed on the estimated $7bn scheme, it therefore enjoys sole access to this project financing facility.

Project sponsors will also be looking to capital market instruments, despite these losing favour in recent years as the global
interest-rate environment rendered proposed bond components in project financings less appealing to many.

With the US Federal Reserve in a gradual monetary easing cycle, however, the use of project-related bonds may begin to revive.

For example, Saudi Aramco has managed to complete some large gas pipeline financings using acquisition facilities that were refinanced in the bond and sukuk markets.

“As the interest-rate environment changes, that’s going to get more people thinking about bond refinancing activity. We’ll see a bit more in a year’s time, when interest rates have come down and investors readjust and start to look for more attractive yields,” says Dewar.

With a different interest-rate climate in place, and more lenders and project backers gaining experience in the new energy schemes that are emerging in the Gulf and the wider Mena region, the hope is that banks will be dipping back into the region with transactions that will maintain its status as the global project finance hotspot for a while longer.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12678172/main.gif
James Gavin
Related Articles
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal
  • Saudi Arabia gauges interest for Al-Ula wastewater expansion

    27 October 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.

    The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.

    RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.

    The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.

    The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.

    French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.

    RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.

    Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg
    Mark Dowdall
  • Qatari firm wins $147m Syria road deal

    27 October 2026

    Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.

    The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.

    The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.

    The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.

    The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.

    The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif
    Yasir Iqbal
  • Adnoc showcases $16.3bn local manufacturing potential

    27 October 2026

    Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.

    The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.

    The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.

    The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:

    • Rotating equipment and power
    • Electrical, control and automation systems
    • Drilling and completion equipment
    • Chemicals and catalysts
    • Piping, fabrication and heavy equipment
    • Spare parts and advanced manufacturing

    Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.

    Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.

    Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.

    ICV scheme expansion

    Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.

    Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.

    The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.

    A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.

    ALSO READ:
    Adnoc steps up crude oil capacity expansion
    Adnoc funnels billions into boosting gas processing

    “Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.

    “The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.

    “The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”

    Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.

    “The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”

    Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg
    Indrajit Sen