QatarEnergy selects $10bn LNG project winner
12 May 2023

QatarEnergy has selected the winning contractor for the engineering, procurement and construction (EPC) of the two new liquefied natural gas (LNG) trains that constitute the main package of the North Field South project – the next development phase of Qatar’s LNG expansion programme.
The two LNG trains will have a capacity of 7.8 million tonnes a year (t/y) each and will increase QatarEnergy’s LNG production capacity to 126 million t/y when commissioned in 2028.
A consortium of France’s Technip Energies and Greece/Lebanon-based Consolidated Contractors Company (CCC) has been selected by QatarEnergy for the estimated $10bn EPC contract, according to sources.
The official contract award ceremony is set to take place in mid-May at QatarEnergy’s headquarters in Doha, sources told MEED.
A consortium of Taiwan’s CTCI, South Korean contractor Hyundai Engineering & Construction and Italian contractor Saipem was competing with Technip Energies/CCC for the North Field South LNG trains.
QatarEnergy did not respond to MEED’s request for comment on the selection of Technip Energies/CCC for the North Field South LNG trains, and the timing of the official contract award. Technip Energies previously declined to comment on the North Field South project.
North Field South LNG scheme
QatarEnergy issued the estimated $6bn tender for the EPC works on the North Field South LNG trains in April last year. Technip Energies has performed the front-end engineering and design (feed) work on the LNG trains package.
Contractors submitted technical bids for the package on 20 October, as MEED previously reported. QatarEnergy received commercial bids for the two LNG trains on 15 February this year.
Upon initial evaluation of commercial bids, QatarEnergy is understood to have reached out to bidders with requests to reduce their prices by up to 15 per cent. Bidders then submitted revised prices by 17 March.
Japan-headquartered Chiyoda Corporation, which had formed a consortium with Technip Energies to bid for the North Field South LNG trains, pulled out of the project “due to a combination of factors”, according to sources. Following Chiyoda’s withdrawal, Technip Energies tied up with CCC for the LNG trains package.
North Field East LNG scheme
EPC works are progressing on the four main packages of QatarEnergy’s North Field East LNG project, which will increase Qatar’s LNG output to 110 million t/y by 2025 from its existing capacity of 77.5 million t/y.
Launched in 2017, the North Field East project constitutes the first phase of QatarEnergy’s $28.75bn North Field LNG expansion project.
The EPC works on the North Field East project were divided into six packages – four onshore and two offshore.
ALSO READ: Qatar fires on all cylinders with gas strategy
QatarEnergy awarded a massive $13bn contract for North Field East package 1 to a consortium of Chiyoda and Technip Energies on 8 February 2021. The package covers the EPC of four LNG trains, with each train planned to have an output capacity of about 8 million t/y. In turn, the Chiyoda/Technip Energies consortium awarded CCC a $2.3bn sub-contract in July 2021 to execute a significant share of their work on the North Field East main package.
In March 2021, QatarEnergy awarded South Korea’s Samsung C&T Corporation a $2bn contract for executing EPC works on the second North Field East package. This will expand the LNG storage and loading facilities in Ras Laffan Industrial City (RLIC).
In August, QatarEnergy awarded the third North Field East package to Spanish contractor Tecnicas Reunidas. The scope of work on the package covers EPC works to expand the storage and loading facilities for condensates, propane and butane and increase the import facilities for mono-ethylene glycol within RLIC.
A 70:30 joint venture of Tecnicas Reunidas and China’s Wison Engineering won the $600m EPC contract for the fourth North Field East package in April this year, related to the building of sulphur handling, storage and loading facilities.
As well as an LNG output of some 32 million t/y, North Field East will produce 4,000 tonnes a day (t/d) of ethane as feedstock for future petrochemical developments, 260,000 barrels a day (b/d) of condensates, 11,000 t/d of liquefied petroleum gas (LPG) and 20 t/d of helium.
ALSO READ: Qatar scripts success story for LNG sector
Between June and July last year, QatarEnergy completed selecting stakeholders in the North Field East scheme.
The state enterprise has divested a total stake of 25 per cent in the North Field East programme, billed as the single largest project in the history of the LNG industry.
France’s TotalEnergies, Italian energy company Eni, US oil and gas producers ConocoPhillips and ExxonMobil, and UK/Netherlands-based Shell have collectively pooled over $7bn into the North Field East project.
QatarEnergy has also completed the selection process for international partners in the NFS LNG project. Out of the 25 per cent share available for foreign stakeholders, TotalEnergies and Shell have won 9.375 per cent stakes each, while ConocoPhillips has secured a 6.25 per cent stake.
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
