Offshore oil and gas sees steady capex

6 March 2025

 

This package also includes: Saudi Arabia to retain upstream dominance


With nearly half of the Middle East and North Africa’s (Mena) hydrocarbons reserves located in offshore basins, regional oil and gas producers spend significantly on maintaining and ramping up production levels. Offshore projects are predominantly geared at raising drilling capabilities, expanding subsea infrastructure and building floating production systems.

In addition to boosting production capacity, producers also invest in offshore projects to improve technological innovation, safety and environmental sustainability. 

Capital expenditure (capex) on offshore projects in the region has remained steady in the past 10 years, with 2024 being one of the best years on record, witnessing total project spending of $23.5bn.

Qatar’s offshore goals

Qatar accounted for the largest capex on offshore oil and gas projects in Mena last year, according to data from regional projects tracker MEED Projects. The country invested more than $12bn in projects to produce incremental volumes of gas from its North Field reserve, as well to sustain its crude output.

In January 2024, North Oil Company awarded $6bn-worth of engineering, procurement and construction (EPC) contracts for a third capacity expansion project at the Al-Shaheen offshore field, to boost oil production by about 100,000 barrels a day (b/d).

North Oil Company – a joint venture of state enterprise QatarEnergy (70%) and France’s TotalEnergies (30%) – has been operating the Al-Shaheen field since July 2017. Situated 80 kilometres (km) north of Ras Laffan, at a water depth of 60 metres, Al-Shaheen holds one of the biggest oil reserves in the world and is Qatar’s largest field. It has a production potential of 300,000 b/d and accounts for about 45% of the country’s total oil production.

Meanwhile, Qatar’s North Field liquefied natural gas (LNG) expansion requires state enterprise QatarEnergy to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the $30bn-plus programme. QatarEnergy has invested billions of dollars in EPC works on the two phases of the North Field Production Sustainability (NFPS) project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.

QatarEnergy LNG, a subsidiary of QatarEnergy, awarded Italy’s Saipem an order valued at $4bn for combined packages Comp3A and Comp3B of the NFPS Offshore Compression Programme’s second phase in September last year. The scope of work on the packages encompasses the engineering, procurement, construction and installation (EPCI) of six platforms, approximately 100km of 28-inch- and 24-inch-diameter corrosion-resistant alloy rigid subsea pipelines, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

The job for combined packages Comp3A and Comp3B is Saipem’s latest contract award as part of the NFPS scheme. The Italian contractor has secured work totalling almost $6bn on the two phases of the project.

UAE pushes offshore

With Abu Dhabi National Oil Company (Adnoc Group) striving to attain an oil production capacity of 5 million b/d by 2027 and become self-sufficient in gas production by the end of this decade, offshore oil and gas projects have received a significant boost. Adnoc was the second-highest spender on offshore projects in the region last year, as well as in the past 10 years. 

In 2024, Adnoc Group subsidiary Adnoc Offshore spent about $6bn on major programmes to potentially increase oil production, such as the two phases of a project to raise output from the Upper Zakum offshore concession in Abu Dhabi to 1.2 million b/d.

In April last year, Adnoc Offshore awarded the project’s main EPC contract – known as UZ 1.2MMBD EPC-1 and worth $825m – to UAE-based Target Engineering Construction Company. In November, Target also won the contract for the project’s next phase, known as UZ 1.2MMBD EPC-2, which is understood to be valued at $500m.

Also last year, Adnoc Offshore awarded a contract, estimated to be worth $2bn, for a project to increase production from the Umm Shaif offshore oil field in Abu Dhabi. 

US-based oil and gas contractor McDermott International won the main contract for the Umm Shaif Accelerated Development project, which aims to increase the Umm Shaif oil field’s output from about 275,000 b/d to 390,000 b/d by 2027, and to sustain that level of production until at least 2036.

Aramco maintains capex

In January 2024, the Saudi Energy Ministry directed Saudi Aramco to abandon its campaign to expand its oil production spare capacity from 12 million b/d to 13 million b/d by 2027. As a consequence of that government decision, Aramco cancelled the tendering process for at least 15 schemes involving the EPCI of structures at offshore oil and gas fields. 

Aramco has since changed tack, spending an estimated $5bn in 2024 on offshore EPCI contracts and earning third place in the league table of highest offshore spenders in the Mena region last year. 

Saipem was the biggest beneficiary of Aramco’s offshore spending, winning five of the eight Contracts Release and Purchase Orders (CRPOs) awarded last year.

In May, Aramco awarded Saipem the contract for CRPO 143, which involves replacing an oil line between the Berri and Manifa oil fields in the kingdom’s Gulf waters.

Aramco then awarded Saipem the contract for CRPO 138, which involves laying a trunkline at the Abu Safah offshore field. The contract is estimated to be worth $500m.

The Milan-listed contractor then scooped three CRPOs in August, starting with CRPOs 132 and 139, the combined value of which is estimated to be about $1bn. In September, Saipem began work on the two contracts, which involve the EPCI of structures to upgrade the Marjan, Zuluf and Safaniya offshore field developments.

Just days after the award of CRPOs 132 and 139, Aramco awarded Saipem CRPO 127, a $2bn contract that involves the EPCI of topsides and jackets for wellhead platforms, a tie-in platform jacket and topside, rigid flowlines, submarine composite cables and fibre optic cables at the Marjan oil and gas field.

In late November, Aramco awarded three further CRPOs worth more than $500m. China Offshore Oil Engineering Company won CRPOs 149 and 152, which are estimated to be valued at $30m and $250m-$300m, respectively. UK-based Subsea7 secured CRPO 153, which is understood to be valued at $200m-$250m.

Positive outlook

Regional national oil companies, particularly those in the Gulf, will seek to maintain a steady stream of investment in offshore projects this year, capitalising on the favourable oil price environment in pursuit of their goal of ramping up output potential in the mid to long term.

Their international counterparts are also likely to press ahead with projects to derive maximum value out of their offshore hydrocarbons assets in the Mena region, a large portion of which are located in prolific, shallow-water formations, making the production of oil and gas more cost-effective than in other regions.

Capex on offshore oil and gas projects this year may well match the level seen in 2024, according to MEED Projects data. In the first two months of 2025, offshore EPC contract awards reached $7.5bn.

Adnoc Offshore accounts for that entire spend through its Lower Zakum Long-Term Development Plan (LTDP-1) project. The company’s long-term objective is to raise output capacity at the Lower Zakum offshore hydrocarbons concession in Abu Dhabi to 520,000 b/d by 2027 and maintain that level until 2034.

Spanish contractor Tecnicas Reunidas and Abu Dhabi-based contractors NMDC Energy and Target Engineering Construction Company have been selceted by Adnoc Offshore to execute EPC works on the three main packages of the Lower Zakum LTDP-1 project.

Separately, Aramco is in the bid evaluation and tendering stages with a total of 12 more CRPOs. The biggest of these offshore tenders are a set of four CRPOs – numbers 145, 146, 147 and 148 – that are part of a project to further expand the Zuluf offshore field development.

These four CRPOs, estimated to be worth about $5.8bn, involve the EPCI of several structures at the Zuluf field, to maintain and raise its long-term oil and gas production potential.

In addition to CRPOs 145, 146, 147 and 148, entities in Saudi Aramco’s Long-Term Agreement (LTA) pool of offshore contractors submitted bids last year for CRPO 150 – an estimated $50m tender that involves the installation of structures at Aramco’s Northern Area Oil Operations.

In December, Aramco issued seven more CRPOs – 154, 155, 156, 157, 158, 159 and 160 – for which its LTA contractors are in the process of preparing bids. Work on these tenders relates to EPCI on structures at several offshore oil and gas fields in Saudi Arabia.

Aramco has been the biggest spender on offshore oil and gas projects in the region in the past 10 years, with capex exceeding $48.5bn. The world’s largest company is predicted to spend significantly on offshore EPC projects in 2025, too.

Saudi Arabia to retain upstream dominance

https://image.digitalinsightresearch.in/uploads/NewsArticle/13451668/main.gif
Indrajit Sen
Related Articles
  • Managing risk in the GCC construction market

    19 December 2025

     

    The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.

    Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.

    MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.

    The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.

    Systemic risk

    The regional market is characterised by several systemic issues that amplify risks for contractors. 

    The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.

    Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.

    Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:

    > Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.

    > Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.

    > Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.


    Supply-chain erosion

    The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly. 

    Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.

    The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.

    Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.

    The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is. 

    A 10-point checklist for contractors in 2026

    1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.

    2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.

    3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.

    4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.

    5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.

    6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.

    7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.

    8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.

    9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.

    10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need.  Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site.

    MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:

    Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com

    Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com

    Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com

    Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com

    IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com

    White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif
    Colin Foreman
  • Diriyah signs land lease deal with King Saud University

    19 December 2025

    Saudi Arabia gigaproject developer, Diriyah Company, has signed a long-term land lease agreement with Riyadh Valley Company, an investment arm of King Saud University.

    Diriyah Company will lease 552,000 square metres (sq m) of land from King Saud University for a period of 70 years. 

    The deal will enable the company to add the land bank to its second phase of the Diriyah Project, which is also known as DG2.

    The agreement was signed by Diriyah Company's Group CEO, Jerry Inzerillo, and the acting president of King Saud University and Riyadh Valley Company chairman, Ali Masmali.

    Diriyah Company is already developing the area adjacent to King Saud University. In April, it awarded an estimated SR4bn ($1.1bn) contract for a utilities relocation package for the King Saud University project located in the second phase of the Diriyah Gate development (DG2).

    The contract was awarded to the joint venture of Beijing-headquartered China Railway Construction Corporation and China Railway Construction Group Central Plain Construction Company.

    The scope of the contract covers the design, construction and relocation of KSU's utilities and administration offices, as well as the construction of a district cooling plant, water storage facilities, a sewage treatment plant, a natural gas plant, a diesel transfer pumping station, a utility tunnel, irrigation water storage tanks, office buildings, warehouses and maintenance workshops.

    In addition to KSU, DG2 will feature residential developments, hotels, an opera house, the Saudi Museum of Contemporary Art, six academies, an arena and a mosque.

    The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh’s city centre, it will cover 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287776/main.jpg
    Yasir Iqbal
  • Kuwait to sign Mubarak port agreement next week

    19 December 2025

    Kuwait and China are expected to sign the agreement to develop the subsequent phases of Kuwait’s Grand Mubarak Port next week.

    According to media reports, the announcement was made by Kuwait’s Public Works Minister ​Noura Al-Mashaan on Thursday.

    The contract value is estimated to be about KD1.2bn ($4bn).

    In May, Beijing-headquartered China Harbour Engineering Company, a subsidiary of China Communications Construction Company (CCCC), signed an early contractor involvement (ECI) agreement with Kuwait to develop the next phases of the project.

    The initial works include surveying, investigation, hydrological observation, geophysical exploration, testing, model testing, process simulation, design review, owner inspection, preliminary design of sand-retaining embankments, and on-site services and management.

    The project launch ceremony was held in mid-April. It was attended by several high-profile representatives from Kuwait and China, including Fu Xuyin, China’s vice-minister of the Ministry of Transport, Zhang Jianwei, the Chinese ambassador to Kuwait, and Nora Mohammad Al-Mashaan, Kuwait’s minister of public works.

    In January, MEED reported that Kuwait’s cabinet had approved a bid from China Communications Construction Company to implement all stages of its Mubarak Al-Kabeer Port project.

    The country ramped up its efforts on the project after meetings between Kuwaiti and Chinese officials in June last year.

    In 2023, the two countries signed a memorandum of understanding to develop port infrastructure.

    Phase one of the project cost $1.2bn and was completed in 2014.

    The project’s first phase included site levelling and the development of a marina, quay walls, berths, a navigational terminal and port buildings.

    The port is not operational because the phase one works did not include vital equipment such as cranes.

    It is understood that the completion of phase two will allow the port to start operations.

    The full scope for phase two of the project is expected to include:

    • Construction of loading and unloading facilities
    • Construction of quay walls and reclamation
    • Construction of the container yard and the back of the port
    • Infrastructure works
    • Construction of buildings
    • Construction of a container terminal
    • Construction of associated facilities
    • Installation of safety and security systems

    A third phase is also planned to further expand the port.

    The latest developments follow a series of agreements signed in September 2023 to deliver some of Kuwait’s immediate development goals for 2024-28. These agreements will position Chinese companies to play a leading role in the Fourth Kuwait Master Plan 2040.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287252/main.jpg
    Yasir Iqbal
  • Metito consortium wins Mecca sewage scheme

    19 December 2025

    A team comprising Metito (UAE), Etihad Water & Electricity Company (UAE) and SkyBridge Company (UK) has been awarded a contract to develop the Hadda independent sewage treatment plant (ISTP) project in Mecca Province, Saudi Arabia.

    The contract was awarded by Saudi Water Partnership Company (SWPC), the kingdom’s principal off-taker for water and wastewater public-private partnership (PPP) projects.

    The project will be developed on a build-own-operate-transfer basis and is expected to begin operations in 2028, followed by a 25-year operating term.

    The plant will provide an initial treatment capacity of 100,000 cubic metres a day and will feature a treated sewage effluent (TSE) reuse system with a storage tank and a 38-kilometre pipeline designed to handle 350,000 cubic metres a day.

    Earlier in December, MEED reported that the team had been named preferred bidder at a levelised tariff of SR2.354 ($0.63) a cubic metre.

    SWPC selected the Miahona-led consortium as the reserve bidder for this project with the second-lowest submitted bid of SR2.599($0.69) a cubic metre.

    According to SWPC, the TSE reuse system accounted for 31% of the preferred tariff for the Arana ISTP and 27% for the Hadda ISTP.

    In March last year, SWPC signed a 25-year water-purchase agreement with a team comprising the local Miahona Company and Belgium-based Besix for the contract to develop and operate the Al-Haer ISTP in Riyadh, as part of the third batch of the kingdom’s ISTP programme.

    Four months later, the Saudi-listed Power & Water Utility Company for Jubail & Yanbu (Marafiq) joined the developer consortium.

    The Miahona/Besix team offered to develop the project for SR1.9407 ($0.5173) a cubic metre, while the second-lowest bid, from a team comprising Spain’s Acciona and the local Tawzea, was SR2.2041($0.588) a cubic metre.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287185/main.jpg
    Yasir Iqbal
  • Morocco awards $1bn Casablanca airport terminal deal

    19 December 2025

    Morocco’s National Airports Office (ONDA) has awarded a MD12bn ($1.2bn) contract to build the new terminal at Casablanca’s Mohammed V International airport.

    The contract was awarded to the joint venture of local firms Societe Generale des Travaux du Maroc (SGTM) and Travaux Generaux de Construction de Casablanca (TGCC).

    Construction work on the Mohammed V International airport expansion is expected to begin immediately.

    The project is slated for completion in 2029.

    The expansion will cover more than 600,000 square metres (sq m) and increase the airport’s capacity to 30 million passengers a year.

    The project is designed by a consortium comprising the local branch of French engineering firm Egis Batiment International, Morocco’s Ala Concept and UK-based RSHP Architects.

    The scope of work covers preparatory works, structural works, waterproofing, steel structural works, building facades, electrical, mechanical and plumbing (MEP) works, data centre works, HVAC systems and other associated works.

    The tender also covers the construction of a 300-key airside hotel.

    The new terminal is expected to be ready in time for the 2030 Fifa World Cup, which Morocco is co-hosting alongside Portugal and Spain.

    ONDA tendered the project contract on 4 November, with a bid submission deadline of 16 December, as MEED reported.

    In July, ONDA began early works on the new terminal building, awarding an estimated MD294m ($29m) deal for enabling works to local firm Societe de Travaux Agricoles Marocaine.

    In January, Morocco’s Transport & Logistics Minister, Abdessamad Kayouh, said that the study to expand the airport’s capacity was nearing completion.

    The project is part of Morocco’s MD42bn ($4.3bn) plan to expand key airports in anticipation of increased passenger flow for the 2030 football World Cup.

    Morocco plans to upgrade several airports, including those in Tangier, Marrakech and Agadir, increasing their respective annual passenger capacities to 7 million, 16 million and 7 million.

    There are also plans to add a new terminal at Rabat-Sale airport, raising its capacity to 4 million passengers annually, and to increase Fez airport’s capacity to 5 million passengers annually. 

    The new terminal at Mohammed V International airport will be connected to a high-speed train network linking Kenitra to Marrakech.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287093/main.jpg
    Yasir Iqbal