Neom Green Hydrogen mulls next phase
23 November 2023

Neom Green Hydrogen Company (NGHC) received the first set of wind turbines for one of the two renewable energy plants that will power its integrated green hydrogen and ammonia production facility in early October.
The initial panels for the project’s solar power plant and hydrogen storage tanks are expected to arrive soon. The first air separation units, meanwhile, will be delivered in the first quarter of 2024.
“We are on track to meet our 2026 target commercial operation date, with the first ammonia production expected sometime between mid to late summer of 2026,” David Edmondson, CEO of NGHC (pictured), tells MEED.
Announced in the summer of 2020, the region’s first, and probably the world’s largest, green hydrogen and ammonia production facility reached financial close in May this year. The project required a final investment of $8.4bn.
“The decision to develop the project was made in 2019 in the strong belief that there would be a market for green hydrogen,” explains Edmondson.
“Having Air Products was certainly a major factor in that decision because of their hydrogen knowledge and experience. They already have an existing infrastructure for the production and distribution of hydrogen, including for mobility.”
The US-headquartered industrial gases firm, Saudi utility developer and investor Acwa Power and Public Investment Fund-backed Neom equally own NGHC.
The scale of the integrated project is unprecedented. It will require over 4GW of wind and solar power and 400MW of battery energy storage systems. A 190-kilometre electricity transmission grid will link these to a 2GW electrolysis plant in Neom’s Oxagon industrial city.
The plant will produce up to 600 tonnes of hydrogen daily, which will be converted into roughly 1.2 million tonnes of ammonia a year. Air Products will ship the ammonia to Europe to be cracked back to hydrogen for mobility applications.
Despite some pushback on the business model's efficiency and the feasibility of green hydrogen applications in transport and mobility, Edmondson assures MEED that years of due diligence and compliance with EU carbon intensity policies support the business case. Twenty-three banks are financing the project, he points out.
“The NGHC plant is designed to ensure that the carbon intensity of the end product will be beneath the required threshold in Europe,” he says.
Edmondson acknowledges the premium costs currently involved in a low-carbon-intensity supply chain. However, this is expected to change as companies implement their net-zero commitments and suppliers scale their production to meet rising demand.
Air Products’ key role
In addition to being the exclusive offtaker for over 30 years for the green ammonia produced at the plant, Air Products is also the project’s main engineering, procurement and construction (EPC) contractor.
The firm’s triple role as an equity investor, EPC contractor and offtaker ensures that “we keep the focus on lowest cost of green hydrogen or ammonia”, notes Edmondson.
“Despite being the EPC contractor and a major investor in NGHC, Air Products’ primary objective is to generate revenue out of selling the ammonia that they have agreed to offtake from NGHC, not through the EPC contract,” he adds.
Phase two
With construction well under way for the integrated Neom green hydrogen and ammonia project, NGHC and its shareholders are now looking at a potential second phase.
“The Neom green hydrogen project is not expected to be a single investment,” says Edmondson.
“With all the ammonia to be produced at the plant under construction already sold to Air Products, there remains an interest in looking at additional investments for both the export market as well as the local market requirements for green hydrogen.”
Neom, which aims to be carbon-free and 100 per cent powered by renewable energy, is considering alternative fuels such as green hydrogen to achieve that goal.
Potential applications include mobility, given the plan to develop a rail system and other modes of transport for Neom.
“There was no domestic demand for green hydrogen fuel when the project was originally conceived in 2019. The market is continuing to evolve and we now see a stronger business case for local supply of green hydrogen,” says Edmondson.
The next phase is envisaged to be another large-scale project addressing domestic and international demand for green hydrogen and green ammonia.
Edmondson says more serious discussions about the project’s next phase will be on the agenda in 2024.
Ongoing innovation
The groundwork for the more widespread adoption of green hydrogen in Neom and across Saudi Arabia is under way.
In 2024, Neom’s energy and water subsidiary Enowa will open the Hydrogen and Innovation Development Centre (HIDC), which aims to produce and adopt decarbonised and clean synthetic fuels in partnership with Saudi Aramco.
Initially, the NGHC project at the HIDC will gather operational data from the facility’s first 20MW electrolyser from Germany’s ThyssenKrupp Nucera, which will be used at the NGHC plant.
This will help advance Enowa’s plans with Air Products Qudra to test advanced hydrogen fuel cell-based mobility and logistics solutions at Neom.
Neom factor
As a trailblazing project, Edmondson recognises the many opportunities that Neom has provided.
“We have had excellent support from Neom on both our land and permitting requirements as we have developed the project,” he says.
“We have also benefitted from legislation that allowed the first private grid in the kingdom and were granted the first industrial licence in Saudi Arabia for a green hydrogen plant.
“Neom has certainly risen to the challenge of supporting investors to make the project a reality.”
Exclusive from Meed
-
Diriyah cancels construction contract for One Hotel20 November 2026
-
Bahrain keeps moving through a difficult year20 November 2026
-
Gulf needs $40bn of pipelines to bypass Hormuz20 November 2026
-
Riyadh gives bidders more time for aviation complex20 November 2026
-
Dar Global launches Trump project in Qatar20 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Diriyah cancels construction contract for One Hotel20 November 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Diriyah Company has cancelled the main construction works contract for the One Hotel project in the Diriyah Two area of its masterplan.
The contract was awarded to a joint venture of India’s Ashoka Buildcon for Contracting and BEC Arabia Contracting Company, as MEED reported in February.
In a filing to the Bombay Stock Exchange, Ashoka Buildcon said: “Diriyah Company has now notified the joint venture that the said project has been cancelled due to internal reasons attributable to the employer.”
Ashoka Buildcon holds a 49% stake in the joint venture.
The project comprises a four-storey hospitality building with approximately 325 guest rooms, on a 31,000-square-metre plot. French engineering firm Egis was the project consultant.
The development follows several recent tender cancellations, particularly in Saudi Arabia’s water sector. Earlier this month, MEED exclusively reported that Water Transmission Company (WTCO) had cancelled tenders for Package B and the combined Packages C1 and C3 of its New Water Pipeline to Feed Riyadh City 2 scheme.
The packages, with a combined estimated value of about $556m, cover a long-distance potable-water transmission system intended to reinforce supplies to Riyadh. Bidders were notified of the decision in November.
Before that, Saudi Water Authority (SWA) also cancelled the tender for a 300-million-litres-a-day seawater reverse osmosis desalination plant in Yanbu.
India’s VA Tech Wabag announced in July 2025 that it had received the estimated $272m main contract for the project. However, on November 14, it said SWA had subsequently cancelled the tender through the Etimad government procurement platform, citing internal reasons.
MEED’s October 2026 report on Saudi Arabia includes:
> COMMENT: Saudi projects hold steady
> GOVERNMENT: Riyadh looks to reset its regional defence outlook
> ECONOMY: Conflict bolsters case for Saudi economic diversification
> BANKING: Saudi lenders readjust to lower lending and deposit climate
> UPSTREAM: Aramco upstream spending gathers pace
> DOWNSTREAM: Sabic steps up Saudi petchems investment
> POWER: Saudi Arabia’s power award activity slows
> WATER: Saudi water sector hits sharp slowdown
> CONSTRUCTION: Saudi construction defies the headwinds
> TRANSPORT: Saudi infrastructure pushes forward amid conflict
> DATABANK: Saudi data indicates project spending shiftTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21612890/main.png -
Bahrain keeps moving through a difficult year20 November 2026
Commentary
Colin Foreman
EditorWhen Formula 1 cars took to the grid at Malaysia’s Sepang International Circuit on 4 October, they were racing in the Bahrain Grand Prix. The race, originally scheduled for April, was postponed because of the regional conflict. Rather than lose its place on the calendar, Bahrain backed a one-off arrangement to stage it in Southeast Asia as the Formula 1 Gulf Air Bahrain Grand Prix in Malaysia.
The episode captures Manama’s approach to 2026. With the Strait of Hormuz closed and the country’s airspace shut for 40 days, Bahrain has sought alternative routes to keep its economy moving.
Gulf Air relocated its hub to Saudi Arabia’s Dammam airport during the airspace closure, taking passengers by road across the King Fahd Causeway, and expects to report higher revenues this year than in 2025. Aluminium Bahrain (Alba) is running at about 80% of capacity, with 300-350 trucks a day delivering alumina using ports in Oman and Saudi Arabia. The company has also agreed the $2.2bn acquisition of the Aluminium Dunkerque smelter in France.
Project activity has continued. Gulf Petrochemical Industries Company has appointed Fluor and Honeywell for its planned Sitra aromatics complex. Bids for the $1.5bn Sitra independent water and power project are under evaluation.
Construction contract awards reached $737m by the end of October, already exceeding the total for 2025.
In early November, Manama went ahead with the fourth edition of the Gateway Gulf investment forum, which produced more than 110 announcements valued at over $20bn.
The cost of the regional conflict is nonetheless steep. The Washington-based IMF expects the economy to contract by 11.3% this year. Public debt reached BD20.3bn ($54bn) at the end of August, and foreign exchange reserves have been supported by a BD2bn ($5.3bn) currency swap line from the UAE.
Lasting recovery will depend on factors that lie largely beyond Bahrain’s control. The IMF is forecasting real GDP growth of 13.9% in 2027, but this is contingent on the reopening of Gulf trade routes and a return to normal levels of energy production.

MEED’s December 2026 report on Bahrain includes:
> GOVERNMENT: Bahrain creaks under the strain of war
> BANKING: Manama’s lenders hold out for better times
> OIL & GAS: GPIC’s expansion project lifts Bahrain’s energy sector
> POWER & WATER: Bahrain’s utility pipeline shows signs of progress
> CONSTRUCTION: Bahrain construction activity remains subduedTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21389640/main.gif -
Gulf needs $40bn of pipelines to bypass Hormuz20 November 2026
Register for MEED’s 14-day trial access
Gulf producers would need to spend about $40bn on new pipelines to route most of their oil exports around the Strait of Hormuz, according to the International Energy Agency (IEA).
The estimate, published in the agency's World Energy Outlook 2026, covers 6.8 million barrels a day (b/d) of export capacity that is either under construction or proposed in Saudi Arabia, the UAE and Iraq. The IEA calculates that the investment would add about $2 to the cost of each barrel exported from the Middle East.
The figure gives the clearest indication yet of the scale of the pipeline programme that could follow the 2026 crisis, which the IEA describes as the largest energy supply shock the world has faced. Oil volumes transiting the strait collapsed from 20 million b/d to an average of about 3 million b/d in March, April and May.
Project pipeline
The only scheme under construction in the IEA’s list is Abu Dhabi National Oil Company’s (Adnoc) West-East pipeline, which will add 1.8 million b/d of capacity. MEED has reported that the 520-kilometre line from Jebel Dhanna to Fujairah is being built in three sections. It is expected to double Adnoc’s crude export capacity through Fujairah when it is commissioned in 2027.
Separately, Adnoc expects to tender the main engineering, procurement and construction (EPC) contract for a new offshore line linking its Gulf processing islands to Jebel Dhanna, which will eventually connect to the West-East pipeline, by the end of the year.
The largest proposed project is a 3 million b/d expansion of Saudi Aramco’s East-West pipeline from Abqaiq to Yanbu on the Red Sea. Aramco president and CEO Amin Nasser has said engineering work began in the early days of the conflict. Saudi Energy Minister Prince Abdulaziz bin Salman said in October that the kingdom is looking to expand its crude export capacity by pipeline to as much as 10 million b/d.
In Iraq, the IEA counts two 1 million b/d lines from Haditha. One would run to Baniyas in Syria. The other would run to Fishkhabur, where it would link to the Iraq-Turkiye pipeline to Ceyhan. MEED has reported that a consortium led by Qatar’s UCC, including Chevron and TotalEnergies, is discussing terms for four interconnected pipeline packages worth about $5bn, with a contract expected to be signed before year-end. Iraq and Saudi Arabia are also considering reviving the 1,568km pipeline from Zubair to Yanbu, which was halted in 1990.
The agency says the new routes would not help all Gulf producers. Bahrain, Kuwait and Qatar would still depend on the strait for their exports.
Bypass flows
About 8 million b/d of bypass pipeline capacity is already available, according to the report. These lines carried about 2 million b/d in 2025 and ramped up to a peak of 6.8 million b/d during the crisis.
In the IEA’s Stated Policies Scenario (STEPS), only the Adnoc project is completed and bypass flows return to about 3 million b/d by 2035. If every existing, under-construction and proposed route were built and used to capacity, bypass flows could reach about 14.5 million b/d. Most Saudi and UAE exports, along with more than 60% of Iraq’s, would then avoid the strait.
The IEA’s new Low Hormuz Case adds higher output from producers outside the Gulf and demand cuts by importers. In that case, oil transit through the strait falls below 2 million b/d by 2035. Raising supply outside the strait would require about $200bn of additional upstream investment between 2025 and 2035.
Security caveats
The agency cautions that the pipelines would not remove the risk. Drone attacks temporarily shut the East-West pipeline in September, and any exports to the Red Sea must pass through the Bab Al-Mandab Strait. MEED has reported that Houthi attacks on Aramco’s Red Sea assets since July, including the Jizan refinery, have cost Riyadh that alternative route. Even in the Low Hormuz Case, the Middle East still exports nearly 15 million b/d in 2035, about 20% of global oil trade.
The IEA also notes that if the strait is at least partially open, Gulf producers would have few reasons not to use it. That could weaken the commercial case for the most expensive bypass schemes.
Execution risks are emerging in Iraq. MEED has reported that the Common Seawater Supply Project is behind schedule, largely because pipeline segments cannot easily be imported through the strait. The same problem could force contractors on new export lines to use more costly routes.
The IEA says there is no feasible bypass for liquefied natural gas (LNG). About 110 billion cubic metres of gas passed through the strait in 2025, most of it from Qatar. Adnoc is pursuing a 4 million tonne-a-year LNG export facility at Fujairah, fed by pipeline from Abu Dhabi. MEED has reported that it has selected three teams for front-end engineering and design work.
Cost pressures
The wider upstream picture is less encouraging for contractors. The IEA expects global upstream oil and gas investment to rise by about 1% to $550bn in 2026, with increases elsewhere largely offset by reductions in the Middle East. Its Upstream Capital Cost Index is forecast to rise by about 8% this year, which the agency says will raise the risk of overruns and delays.
The agency also warns that a resolution of the crisis could create a buyers’ market for oil and gas. Lower prices would test whether the security case for bypass pipelines survives once the strait reopens.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21612651/main.jpg -
Riyadh gives bidders more time for aviation complex20 November 2026

Contractors have been given an extension until 31 January to submit proposals for an estimated SR3bn ($817m) contract to build an aviation complex within the King Salman International airport master development in Riyadh.
Government-owned aviation organisation Saudi Royal Aviation (SRA) tendered the contract in August, with an initial bid submission deadline of 8 October, which was later extended to 19 November.
Phase one of the programme comprised the concept design stage, which the design consultant has completed.
SRA is now seeking to deliver the second phase, covering design development, detailed design, procurement, construction, testing, commissioning and close-out of the works.
The scope covers 30 landside buildings, including 16 screening areas and gates, plus 15 airside buildings, including four gates.
The assets include maintenance hangars, workshops, office and administrative buildings (including interior fit-out), warehouses, storage, security and catering facilities, aprons and access roads, and site utilities and civil works.
King Salman International airport will provide primary utilities to designated tie-in points, with the contractor taking responsibility from there.
Although the site is within King Salman International airport’s boundaries, it is classified as landside and is a greenfield development. The contractor must therefore meet airport security, safety and access requirements, in addition to SRA’s own clearance processes.
Project scale
The King Salman International airport project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.
The airport aims to accommodate up to 100 million passengers by 2030. The goal for cargo is to process 2 million tonnes a year by 2030.
Saudi Arabia plans to invest significantly in its aviation sector. The Saudi Aviation Strategy, announced by the General Authority of Civil Aviation, aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.
It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21611358/main.png -
Dar Global launches Trump project in Qatar20 November 2026
London-listed developer Dar Global and The Trump Organisation have launched the QR2.5bn ($686m) Trump International Simaisma development in Qatar.
The project combines beachfront residences, a golf course and lifestyle amenities, according to senior company officials speaking at a launch ceremony in Palm Beach, Florida.
The residential element, Trump Residences, will comprise a gated community of three-, four- and five-bedroom branded villas. Each villa will have beach access and views of the sea and golf course.
The development will also include the Trump International Golf Club, Simaisma, Qatar, anchored by an 18-hole championship golf course, a members-only clubhouse and a beach club.
A private community centre will provide sports, recreation and wellness facilities for residents.
The project forms part of Qatar’s wider Simaisma tourism development, launched by Qatar’s Ministry of Municipality in June 2024.
The Simaisma project covers eight square kilometres and extends along seven kilometres of beachfront on Qatar’s eastern coast, north of Doha. It includes 16 tourism zones available for private sector development, with planned resorts, a theme park, an 18-hole golf course, residential villas, a yacht marina, restaurants and retail facilities.
Qatari Diar Real Estate Investment Company is managing the wider development.
The integrated tourism project supports the objectives of Qatar’s Third National Development Strategy 2024-30, which aims to increase the contribution of non-oil sectors to the economy.
The launch extends the partnership between Dar Global and The Trump Organisation into Qatar.
Dar Global develops luxury residential and hospitality projects across Europe and the Middle East.
As of 30 June 2026, Dar Global’s portfolio had a total gross development value of $23bn, the company said.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21609076/main.jpeg