Middle East contract awards: November 2023

19 December 2023

 

In November, there were $13.1bn of contract awards in the Middle East and North Africa region, in an almost two-thirds reduction on the record $39bn signed the previous month, according to regional projects tracker MEED Projects. The award value total was also below average when compared to the $20bn average monthly awards over the preceding 12 months and the $15bn long-term average for monthly contract awards.

The strong overall project award activity in 2023, particularly in October, nevertheless leaves the region still potentially on track to match, if not exceed, the record value for annual contract awards set in 2014.

As in previous months, November’s contract awards tally was led by multibillion-dollar awards by regional heavyweights Saudi Arabia and the UAE, along with Qatar. 

Saudi Arabia

Saudi Arabia recorded $5.5bn of contract awards in November, the biggest of which were a pair of $1.2bn awards by Saudi Power Procurement Company for the 1.2GW Rabigh combined-cycle power plant and the 1.1GW Al-Hinakiyah solar independent power producer plant. 

A $1.2bn, 1.1GW solar project at Al-Hinakiyah was awarded under round four of the kingdom’s National Renewable Energy Programme (NREP) along with the $440m, 400MW solar project at Tubarjal. The projects form part of Saudi Arabia’s plan to install 27.3GW of renewable energy capacity by 2024 and 58.7GW by 2030 through the NREP.

Saudi Arabia’s projects market is set for a further boost following the kingdom’s successful bid to host Expo 2030, with Riyadh stating that it plans to invest $7.8bn into related infrastructure. Activity on the kingdom'a gigaprojects also continues, with MEED estimating in late November that $60.6bn of deals had been inked from 2018 to date.

Qatar

Qatar saw $2.6bn of deals inked in November, with the largest a $1.2bn contract signed by North Oil Company with India’s Larsen & Toubro for the Al-Shaheen oil field development Ruya batch one project, which is part of the estimated $6bn project to increase the production potential of the field. The scope of work involves the installation of a large offshore platform and integration with existing facilities.

Download the Middle East contracts awarded for November 2023
UAE

The UAE recorded the third-largest value of deals signed in November, at $2.4bn. The biggest was a $1.2bn contract let by local developer Wasl to China State Construction Engineering Corporation for the MGM resort and the Bellagio and Aria hotels on The Island development in Dubai. According to MEED Projects, it is the largest construction deal to be signed in the emirate since local contractor Alec secured the $1.36bn contract to build One Zabeel from local developer Ithra in 2017. 

The UAE has also seen movement on other big-ticket projects, with Dubai approving the $4.9bn Blue Line extension to the Dubai Metro network on 24 November. Dubai’s construction market is set to make a pivotal shift next year as the emirate’s focus switches from real estate to public infrastructure projects.

North Africa

In North Africa, Algeria and Morocco both contributed to the November contract awards total, with $960m and $955m of deals signed, respectively. Algeria’s value came from a single award by state-owned Anesrif for a new mining railway between Tindouf and Bechar. The project is part of multibillion-dollar rail building programme by Anesrif that involves the development of a total 12,000 kilometres of railway lines.

In Morocco, the largest contract award was an $875m signing by the National Office of Electricity & Drinking Water (Onee) with a consortium led by Spain's Acciona to deliver the first phase of a major seawater reverse osmosis desalination plant in Grand Casablanca.

Egypt recorded $148m of deals signed in November, down from $776m in October. The biggest deal was signed by the National Authority for Tunnels for the signalling system on phase three of the 10th of Ramadan light rail transit project. 

Other GCC

Back in the GCC, several contracts were also signed in Oman, Kuwait and Bahrain in November, with work worth $200m, $117m and $63m being awarded, respectively.

Oman’s projects market is set for growth, with the sultanate reinitiating plans to build the long-stalled Blue City project. The design works are ongoing and are expected to be completed by mid-2024.

Iraq

Iraq rounded out the deals recorded in November, with a $139m contract for a cement plant awarded by the Northern Region Cement Company to Germany's KHD Humboldt Wedag and the Aviation Industry Corporation of China.

Related reads:

 

For more up-to-date information on the region’s largest projects, go to MEED Projects, which tracks trillions of dollars-worth of schemes.

MEED Projects is a subscriber-only service that provides comprehensive, up-to-date and accurate project information. It monitors industry and business development opportunities through market data tailored to your needs.

Be the first to know about new projects; we provide the data so you can win the business. If you would like to see a demo of MEED Projects, or just want to find out more, register your details online or call +971 (0) 4 818 0200.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11372287/main.gif
Sneha Abraham
Related Articles
  • Consultants submit bids for Saudi Arabia’s GCC rail link

    20 July 2026

     

    Consultants submitted proposals on 14 July for a contract to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.

    Saudi Arabia Railways (SAR) issued the tender on 7 May, MEED previously reported.

    The tender covers the concept, preliminary and issued for construction design stages. SAR requires the selected consultant to review, update and complete the existing preliminary design.

    The consultants who submitted bids include: 

    • Atkins with Khatib & Alami
    • DeutscheBahn with ARX
    • Egis with Sener
    • Idom with Dal al-Handasah
    • Systra

    Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Turkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have gained renewed momentum since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, Qatar’s cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to span about 2,186km in total.

    The route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220km/h and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705320/main.gif
    Yasir Iqbal
  • Chinese firm wins Dubai drainage contract

    20 July 2026

    China State Construction Engineering Corporation (CSCEC) has announced it has won a contract to deliver a stormwater drainage pipeline package under Dubai Municipality’s Tasreef programme.

    The contract is for the TF-15-C2 stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai. 

    MEED exclusively revealed in May that the contractor had been selected for the engineering, procurement and construction (EPC) contract. The project is estimated to cost $162m.

    The scope of work includes the construction of about 20 kilometres of new stormwater pipelines, together with associated inspection and intake manholes. The project is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    It is being delivered as part of Dubai’s Tasreef strategic plan, which supports the Dubai 2040 Urban Master Plan. Once completed, the new drainage infrastructure is expected to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.

    In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.

    These include a separate contract awarded to CSCEC for the TF-11-C1 stormwater drainage project in the Dubailand area.

    Also in February, Dubai Municipality invited consultants to qualify for a contract to supervise construction on the TF-15-C2 stormwater drainage projects along with two other projects (TF-13-C1 and TF-16-C1) under the Tasreef programme.

    According to a source, a consultant has yet to be appointed.

    TF-16-C1 involves upgrading and rehabilitating the stormwater system east of the Dubai Canal, while TF-13-C1 involves building a water pipeline stormwater drainage system at Al-Marmoum, Al-Qudra and Al-Yalayis 2 & 3.

    Bids are currently under evaluation for the EPC contracts for both projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705058/main.jpg
    Mark Dowdall
  • Dubai receives eight bids for Hassyan SWRO pipeline contract

    20 July 2026

    Register for MEED’s 14-day trial access 

    Eight contractors have made offers for a contract to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the Hassyan seawater reverse osmosis (SWRO) phase two network in Dubai.

    The contract relates to project one of the Hassyan pipeline network expansion being undertaken by state utility Dubai Electricity & Water Authority (Dewa).

    Local firm Binladin Contracting Group submitted the lowest offer of AED335.92m ($91.5m), according to results published by the utility.

    The other bids were:

    • Green Oasis General Contracting (UAE) – AED345.00m ($93.9m)
    • Al-Nasr Contracting (UAE) – AED391.54m ($106.6m)
    • Wade Adams Contracting (UAE) – AED393.80m ($107.2m)
    • RMB Contracting (UAE) – AED437.96m ($119.3m) 
    • Tristar Engineering & Construction (UAE) – AED441.55m ($120.2m)
    • Shapoorji Pallonji Mideast (UAE/India) – AED451.47m ($122.9m)
    • Gulf Petrochemical Services Trading (UAE) – AED495.20m ($134.8m)

    RMB also submitted a conditional discounted offer of AED427.02m ($116.3m). Three companies submitted regret notices, while one offer was rejected after no valid commercial offer was received. 

    In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.

    Dewa has two other contracts out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.

    Project two was tendered on 22 January and has a bid submission deadline of 21 July. Project three was tendered on 26 January and has a bid submission deadline of 29 July.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704940/main.jpg
    Mark Dowdall
  • Abu Dhabi launches E20 highway expansion project

    20 July 2026

    Abu Dhabi’s Department of Municipalities and Transport (DMT) has announced the E20 highway expansion project.

    The scheme covers widening the main carriageway from three to five lanes, constructing more than 10 kilometres (km) of new ramps and loops, and building four bridges.

    Works also include 1.5km of internal roads and the addition of eight signalised junctions across Khalifa City and the Zayed International airport precinct.

    The project includes utility works, comprising 62km of stormwater drainage, 37km of irrigation networks and the installation of 485 streetlights.

    The E20 expansion is one of the major infrastructure schemes being overseen by DMT in Abu Dhabi.

    Separately, DMT is evaluating bids for a design-and-build contract to construct two bridges serving Hudayriyat Island in Abu Dhabi.

    The scope includes a two-lane bridge connecting 32nd Street to Shakhbout Bin Sultan Street, and a single-lane bridge on 8th Street. It also includes upgrades to signalised intersections.

    Shakhbout Bin Sultan Street is a two-way road with three lanes in each direction, providing access to and from Hudayriyat Island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704696/main.jpg
    Yasir Iqbal
  • Firms given more time for Mid Island Parkway prequalifications

    20 July 2026

     

    Abu Dhabi’s Modon Infrastructure has extended the deadline to 31 July for firms to submit expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership (PPP).

    The previous deadline was 15 July. MEED understands the prequalification notice was issued in June, following Modon Infrastructure’s invitation in May for firms to register their interest.

    Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.

    Phase two of the MIPP involves the construction of about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.

    The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.

    Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704765/main.jpg
    Yasir Iqbal