Mena pushes for nuclear future

2 August 2023

 

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.

The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.

Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.

In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.

Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.

Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.

Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.

Alternative base load

Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.

Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.

The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.

“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”

The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.

Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.

He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.

Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others. 

He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”

Saudi programme

Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.

The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.

In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.

Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications. 

Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.

The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.

Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.

Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.

The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.

The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.

Done deal

Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.

“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.

“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”

The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.

“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.

In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.

“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.

Russian conundrum

The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.

It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.

The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.

Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.

The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.

Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.

The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.

This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks

Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.

While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11013559/main.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait schedules Terminal 2 operator price negotiations

    23 November 2026

    Kuwait's Central Agency for Public Tenders (Capt) has scheduled a price negotiation session for a contract to operate, manage and develop the new passenger Terminal 2 (T2) at Kuwait International airport.

    According to local media reports, Capt's board members have approved holding the session on 30 November.

    The decision responds to a request from the Public Authority for Civil Aviation (Paca) to establish suitable pricing agreements.

    The negotiations will involve two pre-qualified companies. 

    The contract covers the operation, management and service development of T2 and its associated aircraft aprons, as well as centralised operations and maintenance management across the airport.

    Lowest bidder

    Ireland's DAA International was the lowest bidder for the contract, submitting an offer of KD419m ($1.35bn), according to official price-opening records released by Capt on behalf of the Directorate General of Civil Aviation.

    Three international airport operators submitted commercial bids.

    DAA International's proposal undercut its nearest rival by about 45%. Turkiye's TAV Airports Holding submitted the second-lowest offer of KD764.15m ($2.46bn), while South Korea's Incheon International Airport Corporation bid KD959.48m ($3.1bn). All three proposals were marked as approved in the tender committee's price disclosure.

    The remit includes corporate management of centralised operations and maintenance across the wider Kuwait International airport complex, centralising operational procedures, systems integration and service delivery.

    Technical documents indicate that the winning operator will oversee facility management, terminal operational readiness, passenger processing systems, apron operations and staff development programmes before and after the terminal's commercial launch.

    The session forms part of Paca's efforts to take over the new terminal from the Ministry of Public Works, which is currently overseeing the project on the authority's behalf.

    Responsibility for management and operations will transfer to Paca once the project is complete.

    MEED reported in June 2023 that six airport operators had initially been invited to bid for the T2 operating concession.

    T2 is the centrepiece of Kuwait International airport's multibillion-dollar expansion, which aims to increase total handling capacity to 25 million passengers a year. Turkish contractor Limak Insaat is executing the main terminal building under an estimated $4.34bn contract awarded in 2016.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21716345/main.png
    Yasir Iqbal
  • Contractors express interest in Qiddiya wastewater projects

    23 November 2026

     

    Contractors have expressed interest with Qiddiya Investment Company (QIC) for two wastewater infrastructure packages at Qiddiya City, southwest of Riyadh.

    According to a source, expressions of interest (EoI) were submitted on 22 November, with at least eight contractors understood be interested in the project.

    The scope covers the design, construction, commissioning and operation of two wastewater treatment plants (WWTPs), as well as a centralised sludge treatment facility.

    The first package covers WWTP11 in District 24, with a treatment capacity of 60,000 cubic metres a day (cm/d), alongside a sludge treatment facility.

    The second package involves WWTP2 in District 18, with a capacity of 9,000 cm/d. It will also include a reverse osmosis facility to provide tertiary treatment and produce treated sewage effluent suitable for reuse.

    The following contractors have submitted EoIs for the project, industry sources told MEED:

    • AlFanar (Saudi Arabia)
    • AlKhorayef (Saudi Arabia)
    • Aqualia (Spain)
    • Cox (Spain)
    • Lantania (Spain)
    • Nesma (Saudi Arabia)
    • Tawzea (Saudi Arabia)
    • Wetico (Saudi Arabia)

    The deadline had initially been set for 8 November. It was extended to 18 November and then to 22 November to allow additional contractors to participate in the process, upon request.

    Included in the second wastwater package is a sludge treatment facility, which will have an initial processing capacity of approximately 415 cm/d of thickened sludge. Its scope comprises sludge stabilisation, dewatering, anaerobic digestion, biogas recovery and combined heat and power generation. The facility will also incorporate solar sludge drying, with a capacity of approximately 172 cm/d, to produce Class A biosolids.

    QIC has said it intends to procure the works under a design, build and operate model. The initial operations and maintenance period will be two years, with an option for QIC to extend this to five years.

    The two packages will be tendered under a single request for proposals (RFP). Contractors will be required to submit separate technical and commercial proposals for each package, as well as a combined proposal. QIC said it may award the packages separately or collectively.

    The release of the RFP had initially been scheduled for December, with contract awards targeted for June 2027. 

    The infrastructure package will cater to Saudi Arabia’s 360-square-kilometre Qiddiya entertainment city.

    QIC, which is owned by Saudi sovereign wealth vehicle the Public Investment Fund, is overseeing the development of Qiddiya City, including its supporting utilities infrastructure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21714953/main.jpg
    Mark Dowdall
  • OQEP and Petronas sign offshore block study deal

    23 November 2026

    Oman’s state-owned upstream firm OQ Exploration & Production (OQEP) and Malaysia’s state energy company Petronas have signed an agreement to jointly study hydrocarbons resources in offshore blocks 83 and 84.

    Blocks 83 and 84 cover 10,875 square kilometres (sq km) and 14,147 sq km, respectively, in waters of the Gulf of Oman, off the sultanate’s Qurayyat coast near Muscat.

    The joint study agreement between OQEP and Petronas covers geological and geophysical studies to evaluate the resource potential and commercial viability of the two blocks.

    After failing to discover hydrocarbons earlier in this decade in Oman’s first deepwater exploration well in Block 52, in which OQEP had been a minority stakeholder, the sultanate has been pushing hard in its campaign to find oil and gas reserves in its territorial waters.

    In February this year, OQEP acquired a 30% participating interest in offshore Block 18, following the Energy & Minerals Ministry’s award of exploration rights to a joint venture of OQEP subsidiary OQ Exploration & Production Al-Batinah Offshore and PC Oman Ventures, a wholly owned subsidiary of Petronas.

    Located off Oman’s northeastern coast, Block 18 covers more than 21,000 sq km in the Sea of Oman, with water depths of 50-3,000 metres. No confirmed discoveries have previously been reported in the block.

    ALSO READ: Oman and ExxonMobil partner for integrated gas and LNG project

    Under the concession agreement, Petronas holds a 70% participating interest and operatorship, while OQEP holds the remaining 30%.

    In June, the ministry signed an  with OQEP and state-owned Turkiye Petroller AO, granting the companies exclusive exploration, appraisal, development and production rights for offshore Block 80.

    The block covers approximately 5,737 sq km in the Gulf of Oman, near the Strait of Hormuz and off Musandam Governorate. It includes the producing Bukha and West Bukha oil and gas fields.

    The agreement stipulates a minimum exploration investment commitment of $90m over an initial eight-year exploration period. The work programme is divided into two phases to evaluate the block’s hydrocarbons potential.

    Separately, the ministry awarded OQEP exploration rights for three hydrocarbons blocks – 36, 43A and 66 – in the sultanate.

    Under the agreements, OQEP will conduct geological and geophysical surveys, analysis and modelling, and will drill exploratory wells at the three blocks, with the aim of developing recoverable reserves.

    Neither the ministry nor OQEP disclosed the blocks’ locations, areas or prospective reserves in their statement.

    OQEP portfolio

    Omani state energy group OQ Group holds the majority 75% stake in OQEP, with the remaining 25% shares trading on the Muscat Stock Exchange since October 2024, following an initial public offering from which OQ earned proceeds of $2bn.

    OQEP’s portfolio comprises 14 upstream oil and gas exploration and production assets in Oman, covering onshore and offshore operations and assets held under service contracts.

    Formerly known as Oman Oil Company Exploration & Production, OQEP’s flagship assets include Block 60, which contains the Abu Tubul and Bisat oil fields, and Block 48. The company also holds strategic interests in gas-producing blocks 9, 10 and 61.

    OQEP also expanded its producing portfolio in April this year through the acquisition of a 35% interest in onshore Block 27 from Japan's Mitsui E&P Middle East. The transaction was valued at RO28.8m ($75m).

    Block 27 is operated by US-based Occidental Petroleum, which holds a 65% participating interest under an exploration and production sharing agreement valid until 2035.

    ALSO READ: OQEP signs agreement with Indonesian state energy firm
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21714285/main5234.jpeg
    Indrajit Sen
  • Emirates NBD lends AED385m to Samana Developers

    23 November 2026

    Dubai-based Emirates NBD has signed a four-year, AED385m ($105m) bilateral financing facility with local real estate developer Samana Developers.

    The facility includes a term loan and a Real Estate Regulatory Agency (Rera) guarantee, the bank said in a statement on 23 November. It will fund land acquisition and the development of real estate projects across Dubai.

    The repayment structure allows the developer to use receivables from some of its existing projects.

    Emirates NBD said the deal builds on its existing relationship with the developer.

    Samana Developers was established in 2017. It says it was the fifth-largest off-plan developer in Dubai by sales activity in 2025.

    The company has a portfolio of 56 projects with a combined gross development value of about AED17.5bn ($4.8bn). Its schemes are concentrated in residential communities including Jumeirah Village Circle, Arjan, Dubai Sports City and Dubai Studio City.

    The developer says its development pipeline is worth more than AED12.5bn ($3.4bn).

    Emirates NBD said structured financing remains an important tool for established developers pursuing new opportunities, as investor interest in off-plan developments continues to support activity in Dubai's real estate market.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21714643/main3116.png
    Colin Foreman
  • Contractors submit final offers for Oxagon infrastructure

    23 November 2026

     

    Register for MEED’s 14-day trial access 

    Contractors have submitted their best and final offers for an infrastructure package at Oxagon, Saudi Arabia’s industrial and logistics city at Neom.

    The scope covers wet and dry infrastructure networks, civil works and limited earthworks. The wet infrastructure works include combined potable and firewater, irrigation, domestic wastewater, industrial wastewater and stormwater networks.

    The dry infrastructure works include optional 33kV medium-voltage power networks running from primary substation switchgear to defined asset interface points. The package also covers 230/400V low-voltage networks serving street and pedestrian lighting, control networks, radio systems, smart city systems, Saudi Electricity Company and ICT active components, pumping stations and other public-realm loads.

    The contractor will also install security systems, underground ICT pathways for transmission and distribution containment, security networks, service-provider networks and Interior Ministry fibre networks. The scope includes fibre-optic networks for Enowa power lines and wet-services instrumentation, control and automation packages.

    The civil infrastructure works comprise roads and pavements, road furniture, signage, wayfinding and landscaping within the right-of-way.

    Construction of the main Highway 55 and demolition of the existing highway are excluded, except for agreed under-Highway 55 crossings and defined tie-ins at approved interface points.

    Bulk earthworks and rough grading will be carried out by others. The appointed contractor will undertake local trimming, trenching, backfilling, compaction and preparation to achieve issued-for-construction finish levels.

    Tendering activity has intensified at Oxagon in recent months. Contractors have submitted best and final offers for a design-and-build contract to upgrade Highway 55 in the Oxagon region. The first phase includes 14 kilometres (km) of road with two lanes in each direction, one bridge and three interchanges, and is expected to take 22 months to complete.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia and is currently the only road providing north-south connectivity between Duba and the Neom region.

    Consultants also submitted bids on 31 October for a contract covering the concept design, feasibility study and route-alignment studies for a freight railway connecting the Port of Neom at Oxagon to Saudi Arabia Railways’ North-South Railway at the Al-Baseeta junction.

    The proposed rail line is expected to extend for more than 400km.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21712937/main.jpg
    Yasir Iqbal