Mena pushes for nuclear future

2 August 2023

 

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.

The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.

Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.

In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.

Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.

Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.

Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.

Alternative base load

Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.

Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.

The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.

“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”

The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.

Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.

He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.

Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others. 

He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”

Saudi programme

Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.

The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.

In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.

Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications. 

Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.

The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.

Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.

Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.

The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.

The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.

Done deal

Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.

“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.

“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”

The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.

“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.

In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.

“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.

Russian conundrum

The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.

It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.

The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.

Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.

The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.

Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.

The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.

This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks

Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.

While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11013559/main.gif
Jennifer Aguinaldo
Related Articles
  • Qiddiya plans $7bn theme park hub near Paris

    25 August 2026

    Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.

    The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.

    The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.

    One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.

    The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.

    Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.

    The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.

    It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png
    Colin Foreman
  • Masdar shelves Abu Dhabi green hydrogen project

    25 August 2026

     

    Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.

    After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.

    However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.

    Contractors that submitted bids for the Masdar green hydrogen project included:

    • Envision (China)
    • Larsen & Toubro (India)
    • PowerChina (China)
    • Samsung E&A (South Korea)
    • Sinopec (China)

    Masdar did not respond to MEED’s request for comment on the information.

    In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.

    Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.

    Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.

    Contractors submitted bids by the end of the year, according to sources.

    The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.

    The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.

    It also included tie-ins to pre-defined interface points, including (but not limited to):

    • a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
    • a water supply connection to a nearby Taqa Distribution network

    Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.

    Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.

    The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.

    This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.

    “Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg
    Indrajit Sen
  • Oman invites bids for Musandam renewables study

    25 August 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.

    The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.

    The consultant will be required to determine which technologies are technically and economically justified for the governorate.

    The bid submission deadline is 24 September.

    The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.

    Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.

    Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.

    The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity. 

    Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.

    The bid submissions deadline is 10 September.

    The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.

    Bidding for this tender closes on 26 August.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg
    Mark Dowdall
  • US launches sanctions campaign against Iran

    25 August 2026

    The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.

    The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.

    The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.

    The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.

    Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.

    Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.

    Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.

    Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.

    The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg
    Colin Foreman
  • Kuwait tenders $3.3bn gas processing facility

    25 August 2026

     

    State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.

    The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.

    The tender was issued on 23 August.

    The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    In February, MEED reported that at least seven companies had shown interest in participating in the tender.

    Contractors that sent representatives to previous meetings to discuss the project include:

    • Samsung E&A (South Korea)
    • Larsen & Toubro (India)
    • Tecnicas Reunidas (Spain)
    • Saipem (Italy)
    • Hyundai Engineering & Construction (South Korea)
    • Hyundai Engineering Company (South Korea)
    • JGC (Japan)

    The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.

    Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.

    It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.

    Iran disputes ownership of the field, referring to it as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.

    The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.

    Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.

    KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.

    US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.

    A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.

    Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.

    MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.

    Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png
    Wil Crisp