Mena pushes for nuclear future

2 August 2023

 

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.

The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.

Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.

In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.

Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.

Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.

Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.

Alternative base load

Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.

Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.

The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.

“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”

The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.

Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.

He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.

Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others. 

He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”

Saudi programme

Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.

The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.

In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.

Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications. 

Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.

The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.

Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.

Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.

The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.

The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.

Done deal

Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.

“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.

“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”

The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.

“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.

In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.

“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.

Russian conundrum

The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.

It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.

The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.

Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.

The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.

Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.

The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.

This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks

Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.

While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11013559/main.gif
Jennifer Aguinaldo
Related Articles
  • Gulf LNG sector enters a new prolific phase

    24 October 2025

     

    Liquefied natural gas (LNG) has been produced in the GCC since the 1970s. However, it is only since the start of this decade that regional producers have begun committing tens of billions of dollars to significantly ramp up output, driven by soaring global demand for the super-chilled fuel.

    The GCC is projected to add at least 80 million tonnes a year (t/y) of LNG capacity by 2030, placing it firmly among the world’s top three producing regions. 

    Qatar leads the Gulf’s push for LNG dominance as the region’s largest – and one of its earliest – LNG producers.

    State enterprise QatarEnergy has been producing LNG from the giant North Field offshore gas reserve in the Gulf waters, which it shares with Iran, since the 1980s. QatarEnergy currently produces 77.5 million t/y of LNG from 15 processing trains, all located in a sprawling complex in Ras Laffan Industrial City.

    Top spot

    QatarEnergy is on course to nearly double its LNG production to 142 million t/y by the end of the decade through its $40bn North Field LNG expansion programme.

    The energy giant is understood to have spent nearly $30bn on the first two phases of its North Field expansion – North Field East and North Field South – which will raise LNG production capacity from 77.5 million t/y to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on both projects are progressing.

    QatarEnergy awarded the main EPC contracts for the North Field East project in 2021. The project aims to boost LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the engineering, procurement, construction and installation of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for the North Field South project to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company. 

    The contract includes two large LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases of the North Field expansion will add 48 million t/y of supply to the global LNG market.

    In February 2024, QatarEnergy announced the third phase of its North Field expansion – North Field West. The project will add 16 million t/y of LNG capacity through two processing trains of 8 million t/y each, following the model of earlier phases. It will source feedstock from the western zone of the offshore North Field reserve.

    Progress on the North Field West project has, however, been slow, and it has remained in the pre-front-end engineering and design (pre-feed) phase since its announcement.

    QatarEnergy is reportedly exploring options to fast-track it to the EPC stage.

    The first two phases of the North Field expansion will add 48 million t/y to the global LNG market

    Oman progress

    Oman has recently made significant progress in the global race to expand LNG production and exports. The Omani government made headlines in July last year, when it announced that majority state-owned Oman LNG would build a fourth train at its Qalhat LNG production complex in Sur.

    The new LNG train will have an output capacity of 3.8 million t/y, increasing Oman LNG’s total production capacity to 15.2 million t/y when it is commissioned in 2029.

    Oman LNG recently made key progress on its project to add a fourth processing train at the Sur LNG complex. The majority state-owned company has shortlisted a consortium of Chiyoda and South Korea’s Samsung C&T, Japanese contractor JGC Corporation and another consortium of Italian contractor Saipem and South Korea-based Daewoo Engineering & Construction to participate in the main tender for EPC works.

    Technical and commercial bids are due in February and March 2026, respectively.

    The EPC tender process began less than a year after Oman LNG awarded the feed contract to US-based consultancy KBR.

    Separately, France’s TotalEnergies is studying a potential expansion of its Marsa LNG bunkering and export terminal in Oman. The move is significant considering that the first phase of the project is currently under construction in the sultanate’s northern industrial city of Sohar, and will have an output capacity of 1 million t/y.

    TotalEnergies purportedly began an initial study on a potential second phase of the Marsa LNG facility earlier this year. The French energy major may consider doubling the output capacity of the LNG complex, although the plan is yet to be confirmed, according to sources.

    Earlier in the year, TotalEnergies appointed Technip Energies – already the main EPC contractor on the under- construction Marsa LNG terminal – as a consultant to perform concept and feasibility studies on the proposed second expansion phase.

    With Oman LNG advancing its fourth train and TotalEnergies mulling a potential doubling of LNG production in Oman, the sultanate is positioning itself as a key global LNG player by 2030.

    UAE plans

    Abu Dhabi National Oil Company (Adnoc) has historically been one of the GCC’s smaller LNG producers. Its subsidiary, Adnoc Gas, operates three large gas processing trains on Das Island. 

    The Das Island terminal has a liquefaction and export capacity of about 6 million t/y. The first two trains, commissioned in the 1970s, provide a combined 2.9 million t/y, while the third, added in the mid-1990s, contributes 3.2 million t/y.

    Adnoc Gas will significantly expand its LNG capacity with a new greenfield terminal in Ruwais, set to come online in 2028.  The terminal will add 9.6 million t/y of LNG capacity via two 4.8 million t/y trains.

    Adnoc awarded the $5.5bn EPC contract in June 2024 to a consortium of Technip Energies, JGC Corporation, and NMDC Energy, coinciding with its final investment decision.

    Along with the main processing trains, the Ruwais LNG complex will also feature process units, storage tanks and an export jetty for loading cargoes and LNG bunkering, as well as utilities, flare handling systems and associated buildings. The facility will ship LNG mainly to key Asian markets, such as Pakistan, India, China, South Korea and Japan. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14933998/main.gif
    Indrajit Sen
  • NHC signs Al-Fursan project deal with South Korean firm

    24 October 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s National Housing Company (NHC) has signed a memorandum of understanding (MoU) with South Korea’s GS Engineering & Construction to build a residential project in NHC’s Al‑Fursan suburb of Riyadh.

    The MoU was signed in Seoul earlier this week by Saudi Arabia’s Minister of Municipal and Rural Affairs and Housing, Majed Al‑Hogail, and NHC’s CEO, Mohammed Al‑Buty.

    In an official statement published by the Saudi Press Agency, NHC said: “The MoU extends the growing Saudi-Korean partnerships, strengthened by the signing of another MoU in November 2024 to develop the Balady Platform and implement digital twins and smart city applications, contributing to urban planning development and improved quality of life.”

    This is the second major project agreement NHC has signed for residential development within the Al‑Fursan district.

    In March last year, NHC and Egyptian real estate developer Talaat Moustafa Group signed an agreement to develop more than 27,000 residential units at NHC’s Banan City project in the Al‑Fursan suburb.

    The project will cover an area of 10 million square metres and include hospitals, schools, retail, sports facilities and other public amenities.

    In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.

    Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers. 

    For the district’s first phase, 18 real estate development agreements were signed with companies including Retal Urban Development Company and Sumou Real Estate Company.

    NHC also signed four consultancy contracts to manage projects and supervise implementation of phase one and the deployment of comprehensive infrastructure works.

    Other deals involved the development of facilities, including commercial and recreational areas, hospitals, health and sports centres, mosques and schools.

    MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.

    By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14934006/main.jpg
    Yasir Iqbal
  • October 2025: Data drives regional projects

    24 October 2025

    Click here to download the PDF

    Includes: Commodity tracker | Construction risk | Brent Spot Price | Construction output


    MEED’s November 2025 report on the UAE includes:

    > COMMENT: Investment shapes UAE growth story
    > GOVERNMENT: Public spending ties the UAE closer together

    > ECONOMY: UAE growth expansion beats expectations
    > BANKING: Stability is the watchword for UAE lenders
    > OIL & GAS: Adnoc strives to build long-term upstream potential
    > PETROCHEMICALS: Taziz fulfils Abu Dhabi’s chemical ambitions at pace
    > POWER: UAE power sector hits record $8.9bn in contracts
    > WATER: Tunnel projects set pace for UAE water sector
    > CONSTRUCTION: UAE construction faces delivery pressures
    > TRANSPORT: $70bn infrastructure schemes underpin UAE economic expansion

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14933968/main.gif
    MEED Editorial
  • Oman tenders industrial city infrastructure contracts

    24 October 2025

     

    Oman’s Public Establishment for Industrial Estates (Madayn) has issued two tenders for infrastructure development works at Al‑Suwaiq Industrial City in Al‑Batinah North Governorate and Madha Industrial City in Musandam Governorate.

    Madayn issued a tender on 21 October inviting companies to bid for a contract to develop the first phase of the infrastructure and utilities network at Al‑Suwaiq Industrial City.

    The scope covers construction of a building, greenhouses, roads, water network, electricity and sewage networks, and other associated facilities.

    The bid submission deadline is 30 November.

    The tender for construction of infrastructure works at Madha Industrial City was also issued on 21 October, with a submission deadline of 30 November. 

    In December 2023, Madayn inaugurated two projects at Al-Mazunah Free Zone valued at RO9.5m ($25m), including a facility building project and phase one package two and phases two and three at Al-Mazunah Free Zone.

    Madayn, OQ Refineries & Petrochemical Industries and the Industrial Innovation Academy signed an agreement in June 2022 to set up Ladayn Polymer Park in Sohar.

    At that time, Madayn also signed seven land‑usufruct agreements with an extendable duration of 33 years at reduced prices with the investors.

    According to a report from UK-based data analytics provider GlobalData, the output of the Omani construction industry is expected to register annual growth of 4.2% from 2025 to 2027, supported by investments in economic zones, renewable energy, manufacturing and tourism projects under Vision 2040.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14933905/main.jpg
    Yasir Iqbal
  • Petrofac submits lowest bid of $1.48bn for Kuwait oil project

    24 October 2025

    Register for MEED’s 14-day trial access 

    UK‑based Petrofac has submitted the lowest bid for a contract to install Water Injection Plant 4 (WIP‑4) in south Kuwait.

    Petrofac submitted a bid of KD453,736,367 ($1.48bn), which is 7% lower than the KD488,378,247 ($1.59bn) submitted by India’s Larsen & Toubro, the only other company to bid for the project.

    The project’s bid deadline was postponed at least 14 times before prices were ultimately submitted.

    The main contract tender was originally issued by Kuwait Oil Company (KOC) on 11 August 2024, with a bid submission deadline of 10 November 2024.

    The project includes:

    • Construction of a water injection plant called WIP-4
    • Installation of safety and security systems
    • Laying of pipelines
    • Installation of oil gathering systems
    • Installation of the new well pads
    • Construction of associated facilities

    When it was first tendered in August last year, nine companies were qualified to bid. They were:

    • Samsung Engineering & Construction (South Korea)
    • Sinopec Luoyand Engineering Company (China)
    • Hyundai Engineering & Construction Company (South Korea)
    • Sinopec Engineering Incorporation (China)
    • Larsen & Toubro (India)
    • Petrofac International (UK)
    • Saipem (Italy)
    • Daewoo Engineering & Construction (South Korea)
    • Tecnicas Reunidas (Spain)

    Kuwait is currently trying to boost project activity in its upstream sector.

    The country’s national oil company, Kuwait Petroleum Corporation (KPC), is aiming to increase oil production capacity to 4 million barrels a day by 2035.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14933876/main.jpg
    Wil Crisp