Mena pushes for nuclear future
2 August 2023

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.
The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.
Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.
In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.
Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.
Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.
Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.
Alternative base load
Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.
Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.
The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.
“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”
The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.
Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.
He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.
Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others.
He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”
Saudi programme
Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.
The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.
In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.
Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications.
Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.
The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.
Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.
Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.
The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.
The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.
Done deal
Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.
“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.
“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”
The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.
“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.
In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.
“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.
Russian conundrum
The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.
It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.
The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.
Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.
The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.
Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.
The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.
This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks
Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.
While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.
Exclusive from Meed
-
Adnoc weighs early engagement for Umm Shaif expansion21 October 2026
-
QatarEnergy and local partner win seven Brazil offshore blocks20 October 2026
-
UAE firm wins Sphere Abu Dhabi LED display contract20 October 2026
-
Eni completes $1bn Libya gas project20 October 2026
-
Diriyah Company tenders East Wadi bridge20 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc weighs early engagement for Umm Shaif expansion21 October 2026

Adnoc Offshore, a subsidiary of Abu Dhabi National Oil Company (Adnoc Group), is considering an early engagement exercise with contractors for a major project covering the next expansion phase of the Umm Shaif oil and gas field offshore Abu Dhabi.
The early engagement round with contractors will precede Adnoc Offshore issuing the main tender for engineering, procurement and construction (EPC) works on the Umm Shaif long-term development plan 2.1 (LTDP-2.1) project, according to sources.
MEED previously reported that Adnoc Offshore completed the expression-of-interest exercise with contractors for the two main EPC packages of the Umm Shaif LTDP-2.1 project in June this year.
The project’s primary objective is to maintain Umm Shaif’s oil production capacity at approximately 390,000 barrels a day (b/d), while enabling peak output of up to 430,000 b/d.
The project includes the construction of a new combined artificial island at Umm Shaif, equipped with drilling, processing, utilities and supporting infrastructure. It also encompasses the installation of an optimised crude-stabilisation train at Adnoc’s existing Das Island facilities.
Located about 150 kilometres northwest of Abu Dhabi city, Umm Shaif is one of Adnoc’s oldest offshore oil-producing assets. In 2022, the company marked the 60th anniversary of the UAE’s first export of Umm Shaif crude, which took place in July 1962.
Umm Shaif sits within Abu Dhabi’s offshore Umm Shaif and Nasr hydrocarbons concession, which was previously operated by former Adnoc Group companies Adma-Opco and Zadco.
Between March and April 2018, Adnoc awarded a 10% stake in the Umm Shaif and Nasr offshore block to Italy’s Eni, 20% to France’s TotalEnergies and 10% to China National Petroleum Corporation. Adnoc retained the majority 60% interest.
The operators produce about 460,000 b/d of oil from the Umm Shaif and Nasr block.
Project scope of work
Adnoc Offshore has divided the EPC scope of work on the Umm Shaif LTDP-2.1 project into two packages.
The offshore package covers the construction of three water-injection wellhead towers, an electrical submersible pump wellhead tower, a riser platform, a manifold tower, two flare towers, offshore bridges and supporting bridge structures. Additional offshore works include the installation of well fluid flowlines, a main oil pipeline, water injection pipelines, gas export lines and subsea cable systems.
The onshore package covers the construction of facilities on Umm Shaif Island, including a three-phase separation system comprising two processing trains, each capable of handling 135,000 b/d. The facilities will also include two associated-gas compression trains and gas dehydration units, each rated at 275 million cubic feet a day. Supporting infrastructure includes produced-water treatment systems, water-injection facilities, utilities, process buildings and associated tie-in works.
Australia-headquartered Worley has performed front-end engineering and design (feed) work on the Umm Shaif LTDP-2.1 project.
Output expansion projects
In January 2022, Adnoc Offshore awarded a $946m contract to Abu Dhabi-based NMDC Energy (then known as National Petroleum Construction Company) to carry out EPC works on the first phase of the long-term development plan to sustain output from Umm Shaif, known as the Umm Shaif LTDP-1 project.
The main objectives of the Umm Shaif LTDP-1 project are to maintain Umm Shaif’s 275,000 b/d crude oil production capacity, increase efficiencies and enhance the field’s long-term output potential.
EPC works on the first phase of the Umm Shaif LTDP programme were completed in 2024, according to information obtained by regional projects tracker MEED Projects.
Adnoc Offshore then initiated work on the second expansion phase of the long-term development plan for the Umm Shaif offshore oil field in Abu Dhabi (Umm Shaif LTDP-2), awarding US-headquartered McDermott International the main EPC contract on the project in 2024.
The value of the contract for the Umm Shaif LTDP-2 project, which is also known as the Umm Shaif accelerated development, is understood to be $2bn. McDermott held a steel-cutting ceremony for the project on 25 May last year at its fabrication yard in Jebel Ali, Dubai.
The core objective of the project is to increase the Umm Shaif oil field’s output from about 275,000 b/d at present to 390,000 b/d by 2027, and to sustain that level of production until at least 2036.
ALSO READ: Adnoc announces FID on $6.2bn Umm Shaif gas cap project
https://image.digitalinsightresearch.in/uploads/NewsArticle/20779525/main4001.jpg -
QatarEnergy and local partner win seven Brazil offshore blocks20 October 2026
QatarEnergy, in a consortium with Brazil’s state energy producer, Petrobras, has won seven offshore exploration blocks in a concession licensing round organised by Brazil’s National Agency of Petroleum, Natural Gas and Biofuels (ANP).
The exploration blocks ANP awarded in the 6th concession open-acreage bid round are CE-M-471, CE-M-473, CE-M-475, CE-M-477, CE-M-537, CE-M-539 and CE-M-665. The blocks are located in the Ceara Basin along Brazil’s northeastern Equatorial Margin.
QatarEnergy will hold a 30% participating interest, with Petrobras holding the majority 70% stake.
The Equatorial Margin blocks cover about 4,700 square kilometres (sq km) and lie in water depths of about 2,000-3,600 metres.
“The concession contracts further strengthen and expand QatarEnergy’s upstream position in Brazil and are expected to be signed in the first half of 2027,” the state energy enterprise said in a statement.
QatarEnergy already holds working interests in producing fields and several exploration blocks in Brazil.
Prior to winning a stake in these seven offshore exploration blocks, QatarEnergy secured a 20% equity interest in the Agua-Marinha production-sharing contract (PSC) awarded by ANP, under Brazil’s 1st cycle permanent offer round in 2023.
Under the terms of the PSC and associated agreements, the remaining stakes in the Agua-Marinha concession are held by the operator Petrobras (30%), France’s TotalEnergies (30%) and the Brazilian subsidiary of Malaysia’s Petronas, Petroleo Brasil (20%).
The Agua-Marinha block covers 1,300 sq km. It is located in water depths of about 2,000 metres off the coast of Rio de Janeiro in the prolific Campos Basin.
In November 2022, QatarEnergy announced a discovery in Brazil’s Sepia offshore oil field, in which it holds a 21% interest. The announcement came less than a year after it acquired the stake.
ALSO READ: QatarEnergy acquires stakes in Angola offshore blocks
https://image.digitalinsightresearch.in/uploads/NewsArticle/20779233/main.jpg -
UAE firm wins Sphere Abu Dhabi LED display contract20 October 2026
UAE-based audiovisual and digital signage contractor Blue Rhine Industries (BRI) has been appointed to install and commission the external LED display for the Sphere Abu Dhabi project on Yas Island.
The firm was awarded the subcontract by the scheme’s main contractor, Alec Engineering & Contracting, a subsidiary of the UAE-based Alec Holdings.
The scope covers the installation of the external light-emitting diode (LED) display, known as the Exosphere, across the facade of the 112-metre-high building.
The award forms part of the main construction contract for the estimated $1.7bn entertainment venue, which is scheduled for completion in the third quarter of 2029.
In May, Alec Holdings confirmed that Alec Engineering & Contracting had received the letter of award for the main construction package.
MEED previously reported that Alec was the selected contractor and had carried out pre-construction work on the scheme.
The project is being developed by Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) in partnership with the US-based Sphere Entertainment. The parties finalised an agreement granting DCT Abu Dhabi the exclusive rights to build and operate the entertainment venue in the UAE capital, marking the first Sphere development outside the US.
The venue is located on a plot between Yas Mall and SeaWorld Abu Dhabi.
Designed to mirror the scale of the original Sphere in Las Vegas, the facility will have a capacity of up to 20,000 people and will host concerts, sporting events, and cultural exhibitions.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20776687/main.jpg -
Eni completes $1bn Libya gas project20 October 2026
Register for MEED’s 14-day trial access
Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).
In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.
The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.
The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.
In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.
It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.
The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.
The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.
Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.
“The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”
Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.
Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.
The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.
It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.
The first development phase, costing nearly $2bn, was completed in 1990.
This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg -
Diriyah Company tenders East Wadi bridge20 October 2026

Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.
The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.
The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.
The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.
The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.
Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png