Mena pushes for nuclear future
2 August 2023

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.
The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.
Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.
In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.
Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.
Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.
Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.
Alternative base load
Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.
Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.
The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.
“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”
The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.
Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.
He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.
Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others.
He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”
Saudi programme
Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.
The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.
In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.
Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications.
Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.
The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.
Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.
Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.
The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.
The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.
Done deal
Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.
“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.
“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”
The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.
“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.
In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.
“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.
Russian conundrum
The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.
It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.
The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.
Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.
The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.
Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.
The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.
This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks
Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.
While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.
Exclusive from Meed
-
Local firm executing Yasref tail gas treatment project14 April 2026
-
Kuwait sets April deadline for $718m drainage tender14 April 2026
-
Local firm makes hydrocarbon discovery in Oman’s Block 714 April 2026
-
-
Saudi firm wins $64.2m steel pipe orders from Aramco14 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Local firm executing Yasref tail gas treatment project14 April 2026

Yanbu Aramco Sinopec Refining Company (Yasref) is overseeing progress on a key project to build a tail gas treatment unit (TGTU) at its crude refinery complex, located in Yanbu on the west coast of Saudi Arabia.
Yasref is a joint venture in which Saudi Aramco owns the majority 62.5% stake and China Petroleum & Chemical Corporation (Sinopec) owns the other 37.5%. The Yasref refinery was commissioned in 2015 and has a crude oil refining capacity of 400,000 barrels a day (b/d).
The aim of the project, which Yasref calls the tail gas synergy project, is to significantly reduce emissions of sulphur dioxide (SO₂) and hydrogen sulphide (H₂S) from its production complex. The 'synergy' comes from integrating primary treatment (such as the Claus process, which typically recovers about 95-97% of sulphur) with advanced secondary treatment in a TGTU, to achieve overall sulphur recovery of nearly 99.9%.
Yasref awarded the main contract for the tail gas synergy project to Jeddah-based contractor Carlo Gavazzi Arabia earlier this year, according to information obtained by MEED Projects, with the contract estimated at $80m.
The local branch of London-headquartered Berkeley Engineering Consultants is acting as the project’s main consultant, according to MEED Projects.
The scope of work on Yasref’s tail gas synergy project includes the following:
- Construction of downstream TGTU with catalytic hydrogenation reactor and amine absorber train
- Modification of existing sulphur recovery units
- Construction of acid gas removal units employing amine solvent systems
- Construction of desulphurisation units including carbonyl sulphide hydrolysis
- Construction of associated utilities and auxiliary infrastructure: thermal exchangers, power and steam supplies, flare knockout drums
- Installation of safety and security systems hydrogen sulphide detection, overpressure relief, firewater deluge, access control, safety instrumented systems
- Integration of emission monitoring and process control instrumentation.
In April last year, Aramco, Sinopec and Yasref signed a venture framework agreement for a potential petrochemicals expansion of the Yasref refinery complex into a major integrated petrochemicals facility. The project would include a large-scale mixed-feed steam cracker with a capacity of 1.8 million tonnes a year (t/y) and a 1.5 million-t/y aromatics complex, along with associated downstream derivatives.
MEED understands that the Yasref petrochemicals expansion project, which is also referred to as Yasref+, is part of Aramco’s $100bn liquids-to-chemicals programme.
The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million b/d of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.
ALSO READ: Saudi downstream projects market enters lean period
https://image.digitalinsightresearch.in/uploads/NewsArticle/16383830/main3043.jpg -
Kuwait sets April deadline for $718m drainage tender14 April 2026
Kuwait’s Ministry of Public Works has set a 21 April deadline for a major tender estimated to be worth about KD222m ($718m).
The tender scope covers the construction of rainwater drainage networks across the residential areas of Sabah Al-Ahmad, South Sabah Al-Ahmad, Al-Khairan and Al-Wafra.
The Ministry of Public Works floated the tender on 22 March.
According to regional projects tracker MEED Projects, the works include the construction of a major concrete sewer, three collection basins and extensive stormwater drainage basins.
Rainwater collection tanks will be connected through an independent network, with outlets to the sea via the Nuwaiseeb exit to manage overflow.
The infrastructure will also filter pollutants such as oils, minerals and sediments to protect water quality and support environmental sustainability.
The project aims to reduce surface runoff, prevent street and urban flooding, and improve groundwater recharge.
UK analytics firm GlobalData expects Kuwait’s construction industry to grow by 5.1% in 2026-29, supported by government investment in the oil and gas sector aimed at raising production, as well as investment in the infrastructure sector.
In the short term, growth will be boosted by planned expenditure under the 2025-26 budget, which was approved in March 2025.
The construction industry in Kuwait is expected to record an annual average growth rate of 4.9% in 2026-29, supported by investments in renewable energy, transport, and oil and gas projects.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16383203/main.jpg -
Local firm makes hydrocarbon discovery in Oman’s Block 714 April 2026
Omani oil and gas exploration and production company Masar Petroleum has announced a discovery in the Hasirah Ridge in the sultanate’s Block 7.
Masar Petroleum was the inaugural operator to appraise and produce hydrocarbons from the Hasirah reservoir in Block 7 in 2017.
Building on that experience, Masar Petroleum has now successfully drilled a new exploration well south of its existing discoveries, validating the concept of the Hasirah Ridge — a geological trend 5 kilometres wide and 30km long mapped across Block 7 using 2D seismic data.
This discovery represents the first step towards unlocking the Ridge’s prospective resource base of 100 million to 380 million barrels, Masar Petroleum said in a statement.
Following this discovery, a planned 3D seismic survey and exploration and appraisal programme is expected to advance the development of the new resources by the end of 2028.
First production from this field is expected to come on stream during the last quarter of this year.
Masar Petroleum plans to rapidly advance appraisal and development opportunities across Block 7.
“Masar is a proud Omani E&P company that has delivered significant value through a continuous and focused effort on unlocking our potential,” Abdulsattar AlMurshidi, CEO of Masar Petroleum, said.
ALSO READ: Oman offers five hydrocarbon exploration blocks in new bidding round
https://image.digitalinsightresearch.in/uploads/NewsArticle/16383075/main2121.jpg -
Bidders get more time for Saudi water transmission projects14 April 2026

Saudi Arabia’s Water Transmission Company (WTCO) has extended the bid submission deadlines for engineering, procurement and construction (EPC) contracts for two major independent water transmission system projects.
The Jubail-Buraidah and Ras Mohaisen-Baha-Mecca transmission projects were first tendered last September under the public-private partnership model.
The deadlines for qualified contractors to submit technical and financial bids had initially been extended to March.
The new bid submission deadline for the Jubail-Buraidah project is 30 April.
Scheduled to begin construction in 2027, the scheme comprises an approximately 348-kilometre-long greenfield water transmission system with a capacity of 840,650 cubic metres a day (cm/d), delivering water from the Ashmasiah reservoirs to cities and towns in Al-Qassim province.
The project is large by WTCO standards. The company’s second phase of the Khobar-Hofuf system, completed in 2024, was 140km in length, with a capacity exceeding 530,000 cm/d.
Ras Mohaisen-Baha-Mecca
For the Ras Mohaisen-Baha-Mecca water transmission system project, the new bid submission deadline is 7 May.
The project involves constructing an approximately 325km-long greenfield independent water transmission system with a capacity of 542,000 cm/d, delivering water from Ras Mohaisen to the Adham and Aradhiyah regions.
Prequalification for both projects closed on 15 January.
It is understood that local firms Alkhorayef Water & Power Technologies and Mutlaq Al-Ghowairi Contracting Company (MGC) are among those qualified to bid for the Ras Mohaisen contract.
MGC secured the EPC contract for an even larger independent water transmission pipeline project in June last year.
The project, also linking Jubail and Buraidah, spans 587km and carries 650,000 cm/d.
According to regional project tracker MEED Projects, construction works recently commenced on the project, which is estimated to cost about SR8.5bn ($2.2bn).
WTCO is also planning to tender a contract for phase two of the Ras Mohaisen water transmission system project. This includes laying water transmission pipelines 408km in length with a capacity of 400,000 cm/d. This project is estimated to cost around $600m.
It is understood that the main contract tender will be issued in 2027.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16383056/main.jpg -
Saudi firm wins $64.2m steel pipe orders from Aramco14 April 2026
Saudi Arabia-based Arabian Pipes Company has announced it has won orders from Saudi Aramco to supply steel pipes, totalling SR241m ($64.2m).
Under the terms of the contracts, Arabian Pipes Company will supply steel pipes over contract durations of nine months and 11 months, commencing from the date of signing.
“These contract awards reinforce Arabian Pipes Company’s strong position as a key supplier to the kingdom’s energy sector and highlight its continued commitment to supporting major oil and gas infrastructure projects in Saudi Arabia,” the company said in a filing with the Saudi Exchange (Tadawul), where its shares trade.
The company added that the orders will contribute positively to its financial performance over the contract period.
Arabian Pipes Company last secured a contract from Aramco in August 2024, when it won an eleven-month steel pipe supply order worth approximately $28.53m.
Prior to that, in July 2024, the company won a contract worth SR293m ($78.1m) to supply steel pipes for the second expansion phase of Aramco’s Jafurah unconventional gas development. That contract had a duration of 10 months.
The order was placed as a subcontract by Denys Arabia, the main contractor performing engineering, procurement and construction works on one of the Jafurah second expansion phase project packages.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16382513/main2830.jpg