Mena pushes for nuclear future

2 August 2023

 

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.

The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.

Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.

In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.

Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.

Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.

Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.

Alternative base load

Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.

Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.

The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.

“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”

The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.

Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.

He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.

Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others. 

He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”

Saudi programme

Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.

The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.

In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.

Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications. 

Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.

The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.

Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.

Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.

The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.

The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.

Done deal

Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.

“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.

“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”

The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.

“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.

In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.

“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.

Russian conundrum

The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.

It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.

The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.

Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.

The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.

Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.

The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.

This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks

Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.

While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11013559/main.gif
Jennifer Aguinaldo
Related Articles
  • Frontrunners emerge for Saudi Arabia’s seventh solar IPP round

    17 November 2026

     

    Register for MEED’s 14-day trial access 

    Four bidders are understood to be leading the race for contracts to develop four solar photovoltaic (PV) independent power projects (IPPs) under the seventh round of Saudi Arabia’s National Renewable Energy Programme (NREP).

    Round seven comprises the 1,400MW Tabjal 2, 600MW Mawqqaq, 600MW Tathleeth and 500MW South Al-Ula solar IPPs.

    Saudi Power Procurement Company (SPPC) is procuring the renewables programme, with the Energy Ministry supervising it.

    Developers submitted bids in September, as MEED reported exclusively.

    According to industry sources, the following bidders and bidding groups have emerged as frontrunners to win one project each:

    • Aljomaih (Saudi Arabia) / TotalEnergies (France)
    • EDF (France) / Saudi Energy
    • Etihad Water & Electricity (UAE) / Korea Electric Power Corporation (South Korea)
    • Wahajpeak (Saudi Arabia)

    An award for Wahajpeak would mark the company’s first major infrastructure award in the region since US-based infrastructure investment firm Stonepeak established it in 2025. 

    At least some solar contracts are expected to be finalised by year-end.

    In addition to the four solar plants, round seven comprises two wind IPPs with a total combined capacity of 5,300MW. 

    In October, MEED exclusively reported that consortiums had submitted bids for the two wind projects: the 1,300MW Bilgah and 900MW Shagra schemes.

    These include:

    • Abu Dhabi Future Energy (Masdar) / EDF (France) / Saudi Energy
    • EtihadWE (UAE) / Nesma Renewable Energy (Saudi Arabia) / Korea Electric Power Corporation (Kepco, South Korea)

    The request for proposals (RFPs) for both wind and solar were issued in January.

    As MEED reported, 16 developers qualified to bid as both managing and technical members of consortiums for the four solar PV projects. A further six companies qualified to bid as managing members only.

    For the wind IPPs, SPPC qualified 13 developers in the managing and technical members category and a further six companies in the managing members category only.

    Round eight

    SPPC will release the RFP notices in December for the eighth round of its renewable energy procurement programme, as exclusively reported by MEED.

    The round comprises three solar and wind projects with a combined capacity of 3.2GW.

    SPPC issued the request for qualifications (RFQ) notice on 11 November. Developers have until 22 November to submit qualification documents, as MEED reported last week.

    Round eight includes the following projects:

    • 900MW Tamir solar PV project in Riyadh
    • 1GW Sharq Al-Amwaj solar PV project in Asir
    • 1.3GW Al-Muzairah wind project in Mecca

    The NREP is designed to increase renewable generation capacity and reduce liquid-fuel use in power generation.

    Saudi Arabia aims for renewable energy and energy storage systems to account for about 50% of the kingdom’s electricity generation mix by 2030.

    Earlier rounds under the NREP have already deployed large capacities. In October 2025, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP. These were four solar PV IPPs and one wind IPP, with a total combined capacity of 4,500MW.

    The Aljomaih / TotalEnergies joint venture won the contract to develop the 400MW Al-Sufun solar IPP. Two of the three remaining solar IPPs in round six were awarded to Masdar, while the joint venture of EDF and Saudi Energy was selected to develop the 600MW Samtah solar IPP.

    A consortium of the UAE’s Etihad Water & Electricity, Saudi Arabia’s Nesma Renewable Energy and Korea Electric Power Corporation (South Korea) won the contract to develop the 1,500MW Dawadmi wind IPP, the only wind project in the round.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21466519/main.jpg
    Mark Dowdall
  • Al-Ula launches $6.8bn PPP project opportunities

    17 November 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for AlUla (RCU) has announced six public-private partnership (PPP) investment opportunities with a combined estimated value of SR25.4bn ($6.8bn).

    The schemes cover road infrastructure, water storage, wastewater treatment, solid waste management and the expansion of Al-Ula International airport.

    They are progressing under the National Centre for Privatisation’s approved privatisation plan, with requests for proposals (RFP) expected from the second quarter of 2027 through early 2028.

    The opportunities are:

    Secondary roads expansion: RCU plans to develop 18 secondary roads and utility corridors totalling about 1,400 kilometres (km). The SR17bn ($4.5bn) project includes new roads and networks for water supply, electricity, telecommunications, street lighting and stormwater drainage.

    The project covers 22 million square metres (sq m) and will be delivered using a design-build-finance-operate-maintain (DBFOM) model.

    The concession will run for about 20 years and will use availability-based payments. The private partner will operate and maintain the roads, while the utility infrastructure will be handed over to the relevant entities.

    The RFP process for the project packages is planned to start in early 2028, with phased completion targeted by 2033. Expressions of interest are due by 30 September 2027.

    Highways and primary roads expansion: The SR4bn ($1bn) opportunity covers the development and upgrade of five primary roads and associated utility networks, totalling 204km.

    The scope includes new roads, rehabilitation works, cycling paths and traffic-calming measures. It also includes water, electricity, telecommunications and stormwater-drainage infrastructure. The investment area is 3 million sq m.

    The scheme will be procured as a DBFOM project with availability-based payments and a 15-year concession. The concessionaire will operate and maintain the roads, while utilities will be handed over to the relevant entities.

    RCU expects to begin the RFP process in early 2028 and has set phased completion by 2032. Expressions of interest are due by 30 September 2027.

    Al-Ula International airport expansion: The SR2bn ($532m) airport project will include a 30,000 sq m passenger terminal with a capacity for up to 3 million passengers a year, a 5,000 sq m cargo terminal with equestrian facilities and a 10,000 sq m private aviation terminal.

    The scope also includes general aviation and helicopter facilities, a runway extension to 3,000 metres, roads, parking, maintenance facilities, utilities and fuel facilities.

    The project has a gross floor area of 45,000 sq m and covers a 7 million sq m site.

    About 1 million sq m of land will be available for associated commercial development, including logistics, retail, hospitality and aviation services.

    The project will use a build-transfer-operate model with a concession period of up to 35 years.

    RCU expects to launch the RFP in the third quarter of 2027 and is targeting completion by 2032. The interest submission deadline is 30 June 2027.

    Integrated solid waste management system: The SR1bn ($266m) project involves developing and operating an integrated solid waste management system over a 1.4 million sq m area.

    The scope includes a resource management park; a waste transfer station with a capacity of 76,000 tonnes a year; recycling facilities with a capacity of 45,000 tonnes a year; organic waste treatment facilities; and construction and demolition waste-processing facilities with a capacity of 220,000 tonnes a year.

    It also includes engineered landfill cells with a combined capacity of 5 million cubic metres and associated infrastructure.

    The project will be delivered through a DBFOM concession lasting 30 years, including three years of construction and 27 years of operations.

    Payments will comprise performance-based payments, waste gate fees and transfer fees.

    RCU expects to issue the RFP in the second quarter of 2027. The deadline for interest is 31 May 2027.

    Strategic water storage tanks: RCU plans to develop and operate five strategic potable-water storage tanks with a combined capacity of 295,000 cubic metres. The SR900m ($239m) scheme is intended to provide between three and four days of potable-water reserves.

    The project includes pumping stations, water connection networks and supporting infrastructure to serve urban districts, heritage sites, Al-Ula International airport and new development areas.

    The investment area covers 75,000 sq m.

    The project will be structured as a DBFOM concession lasting about 15 years, including two to three years of construction and 12 to 13 years of operations and maintenance.

    The availability-based payment mechanism will be linked to performance and water quality.

    RCU expects to issue the RFP in the fourth quarter of 2027, with phased completion targeted by 2031. Interested companies have until 30 November 2027 to submit their interest.

    Wastewater treatment plant enhancement and operation: The SR454m ($120m) wastewater scheme will rehabilitate Al-Ula’s existing wastewater treatment plant and expand its capacity using moving-bed biofilm reactor technology.

    The existing plant has a capacity of 8,000 cubic metres a day (cm/d). The first phase will add 18,000 cm/d, followed by a 36,000 cm/d second phase, increasing overall capacity to 62,000 cm/d.

    The 501,000 sq m project includes treated wastewater storage and pumping facilities, control systems and supporting infrastructure.

    The project will be delivered using a build-own-operate-transfer model with a 26-year concession. This comprises three years for construction and rehabilitation and 23 years of operations. The payment structure will include capacity, output and supplemental payments.

    RCU expects to launch the RFP in the second quarter of 2027. The deadline for interest is 31 May 2027.

    RCU was established in 2017 to develop and protect Al-Ula as a cultural, heritage, tourism and economic destination.

    The commission launched its masterplan in 2021, setting out a long-term development programme centred on the Hegra Historic City, Nabataean Horizon, Jabal Ikmah, Dadan and Al-Ula Old Town districts.

    The wider Al-Ula programme includes heritage conservation, hotels and resorts, cultural venues, residential projects, agricultural development, transport systems and enabling infrastructure.

    The latest opportunities form part of the infrastructure programme required to support the region’s planned tourism, residential and commercial development.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21465369/main.png
    Yasir Iqbal
  • Consortium closes financing on 900MW Egypt wind farm

    17 November 2026

    A developer consortium led by France’s Engie has announced financial close on a 900MW wind farm near Ras Shokeir in Egypt’s Gulf of Suez.

    Known as Gulf of Suez Wind Farm 3, the project is being developed on a build-own-operate basis under a 25-year power purchase agreement with Egyptian Electricity Transmission Company.

    The consortium comprises Engie (35%), Egypt’s Orascom Construction (25%) and Aeolus (40%), an African renewable energy independent power project platform of Toyota Tsusho Corporation.

    Construction began in June, and the project will connect to the grid in three phases. The first 300MW is forecast to enter commissioning in January 2028, while the full 900MW capacity is scheduled to be operational in summer 2028.

    The project is the consortium’s third wind farm in Egypt. Its two existing operational wind farms – Red Sea Wind Energy and Ras Ghareb – have a combined capacity of 912.5MW. Once the new facility is fully operational, the consortium’s wind power capacity in the country will reach 1.8GW.

    The facility will also become Engie’s largest onshore wind farm globally. Orascom Construction will execute all civil and electrical works for the balance of plant as well as supply certain local components.

    Financing for the project is being provided on a non-recourse basis by a group of development finance institutions and commercial lenders. These include the Japan Bank for International Cooperation, France’s Proparco, the Netherlands-based FMO, Societe Generale, Credit Agricole Corporate & Investment Bank and Germany’s KfW Ipex-Bank.

    Commercial lender financing is covered by Nippon Export & Investment Insurance (Nexi). HSBC Bank Egypt is acting as the working capital facility bank and onshore security agent. Equity bridge loans are being provided by KfW for Engie, Mizuho for Aeolus, and FMO and British International Investment for Orascom Construction.

    The project supports Egypt’s long-term energy strategy, including targets of more than 42% renewable energy by 2030 and 65% by 2040.

    Once operational, the wind farm is expected to generate enough electricity to supply more than 1.4 million Egyptian households and reduce carbon emissions by approximately 2 million tonnes a year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21464975/main.jpg
    Mark Dowdall
  • Emaar and Abu Dhabi firm plan $2bn projects

    17 November 2026

    Register for MEED’s 14-day trial access 

    UAE-based firms Al-Ain Asset Management and Emaar Hospitality Group have announced plans to develop five branded residential projects in Abu Dhabi with a combined investment value of AED8bn ($2.2bn).

    The developments will cover about 4.7 million square feet across prime waterfront locations in the emirate.

    The schemes will be operated under Emaar Hospitality Group’s Address, Palace and Vida brands, incorporating serviced residential units with hotel-style amenities.

    Specific plots, construction schedules and procurement packages for the five projects have not yet been disclosed.

    The initiative marks an expansion of the existing partnership between the two entities, which began in 2016 with the development of the Address Beach Resort in Dubai.

    The collaboration previously expanded into Abu Dhabi with the launch of Vida Residences Saadiyat Island.

    The recent announcement comes amid sustained momentum in the local market.

    According to GlobalData, the UAE construction industry will expand at an average annual rate of 3.9% between 2025 and 2027, driven by investments across infrastructure, energy, housing and tourism.

    The country’s residential construction sector is forecast to grow by an average of 2.7% annually between 2025 and 2028, supported by ongoing private development and government initiatives to meet population growth.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21461696/main.gif
    Yasir Iqbal
  • Libya considers tendering $1bn oil field development

    17 November 2026

    Libyan officials have discussed tendering a project to rehabilitate and develop Libya’s Dahra oil field, according to a statement from the country’s Audit Bureau.

    The head of the Audit Bureau, Khaled Shakshak, met with the head of Libya’s National Oil Corporation (NOC), Masoud Suleiman, on 15 November.

    During the meeting, they discussed options for tendering the Dahra oil field development project, which has previously been estimated at $1bn and is expected to significantly increase oil production from the field.

    The oil field in central Libya has suffered from years of poor maintenance and was sabotaged by Islamic State militants in 2015.

    Waha Oil Company announced in August 2022 that it had restarted test operations at the Al-Dhara oil field after a seven-year hiatus.

    Waha Oil Company is a joint venture of Libya’s NOC, US-based ConocoPhillips and France’s TotalEnergies.

    In August last year, MEED revealed that the field was producing 24,000 barrels a day (b/d) of oil and the US oilfield services provider Halliburton was working on the front-end engineering and design (feed) for the rehabilitation and development project.

    At the time, the project was expected to boost total production from the Al-Dhara field and neighbouring PL6 field to 130,000 b/d.

    The engineering, procurement and construction (EPC) scope of work on the project is understood to include:

    • Drilling of wells
    • Construction of platforms
    • Laying of pipelines
    • Construction of a condensate refinery
    • Installation of storage tanks
    • Installation of early production facilities
    • Installation of gas treatment units
    • Construction of a degassing station
    • Construction of other associated facilities

    Over 2026, there has been an uptick in interest in North African oil and gas assets amid continued disruption to shipping through the Strait of Hormuz, a key export route for some of the Middle East’s biggest oil and gas exporters.

    Flows through the Strait have been disrupted by a regional war that was triggered by US and Israeli attacks on Iran on 28 February.

    Countries negatively impacted by the disruption include Kuwait, Iraq, Saudi Arabia, the UAE and Qatar.

    Amid the ongoing disruption to oil and gas exports from these countries, some North African officials have promoted their oil and gas sectors as reliable alternative suppliers.

    In August, Libya’s Oil and Gas Minister Khalifa Abdel Sadig told a conference in Norway that Libya could be a “key player in providing energy security solutions” to the European Union.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21459109/main.png
    Wil Crisp