Mena pushes for nuclear future

2 August 2023

 

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.

The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.

Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.

In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.

Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.

Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.

Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.

Alternative base load

Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.

Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.

The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.

“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”

The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.

Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.

He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.

Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others. 

He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”

Saudi programme

Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.

The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.

In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.

Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications. 

Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.

The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.

Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.

Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.

The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.

The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.

Done deal

Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.

“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.

“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”

The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.

“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.

In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.

“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.

Russian conundrum

The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.

It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.

The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.

Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.

The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.

Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.

The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.

This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks

Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.

While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11013559/main.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait receives bids for Al-Khairan phase one IWPP

    2 June 2026

     

    Two developer consortiums have submitted bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, according to a source.

    Bids were received by the Kuwait Authority for Partnership Projects (Kapp) on 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The bidders include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The Al-Khairan IWPP is being procured by Kapp in partnership with the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate in the tender.

    Ernst & Young, BNP Paribas, AtkinsRealis and Addleshaw Goddard are financial advisers on the project. Chadbourne & Parke is acting as legal adviser.

    The winning bidder will sign a set of public-private partnership agreements covering financing, design, construction, operation and transfer of the project. The energy conversion and water-purchase agreement is expected to cover a 25-year supply period.

    Future phases

    The Al-Khairan IWPP project is expected to run on low-sulphur fuel oil as the primary fuel and to accommodate crude oil, gas oil and natural gas as backup fuels. Future phases will further expand capacity.

    It is understood that the estimated $750m second phase of the Al-Khairan IWPP project will add a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant.

    The project, first mooted over a decade ago, remains in the early development stages, with no plans currently to advance to procurement in 2026, a source said.

    According to the source, the immediate focus is on advancing plans for the 3,600MW Nuwaiseeb power and water desalination IWPP project.

    The Nuwaiseeb IWPP plant will have a desalination capacity of 75 million imperial gallons a day.

    Kapp plans to release a transaction advisory tender for the project by the end of the year.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072685/main.jpg
    Mark Dowdall
  • Doosan confirms Saudi Jafurah 2 cogen contract

    2 June 2026

    South Korea’s Doosan Enerbility has confirmed it has signed an engineering, procurement and construction (EPC) contract worth about $556m for the second phase of the Jafurah combined heat and power (CHP) plant in Saudi Arabia.

    The project is being developed by Korea Electric Power Corporation (Kepco) in partnership with Saudi Aramco.

    Doosan said the contract covers design, equipment supply, installation, construction and commissioning of the facility.

    The Jafurah CHP phase 2 project will be built near the Jafurah gas field, about 400 kilometres east of Riyadh. Once operational, it will generate 330MW of electricity and produce 465 tonnes of steam an hour for the nearby gas field.

    According to the firm, the project’s main steam turbine will be supplied by Doosan Skoda Power, a subsidiary of Doosan Enerbility.

    WSP is acting as the project management consultant for the project, which is scheduled for completion in 2029.

    The Jafurah gas development is part of Aramco’s $3.2bn unconventional resources programme, which aims to develop shale gas in three areas. Jafurah lies southeast of Ghawar, the world’s largest conventional oil field.

    The programme is part of Riyadh’s plans under Vision 20230 to ensure the kingdom remains self-sufficient in gas supply amid rising demand from the residential and industrial power sectors.

    Jafurah phase one

    In February 2025, MEED exclusively reported that talks were under way to expand the capacity of the $500m Jafurah cogeneration independent steam and power plant (ISPP).

    Construction works were completed on the facility last November.

    At the time of its procurement, the plant’s first phase was to have a power capacity of 270-320MW, and a low-pressure (LP) steam demand of 77-166 thousand pounds an hour (klb/hr) and high-pressure (HP) steam demand of 29-126 klb/hour by 2023.

    The LP and HP steam demand will increase to 283-373 klb/hr and 66-321 klb/hr by 2027, respectively.

    The oil giant issued the letter of award to Kepco for the contract to develop the Jafurah ISPP scheme in July 2022.

    Kepco subsequently awarded South Korea’s Doosan Heavy Industries & Construction the project’s EPC contract.

    US/India-based Synergy Consulting provided financial advisory services to Kepco on its bid.

    Sumitomo Mitsui Banking Corporation (SMBC) served as the client’s financial adviser for the project. Germany’s Fichtner Consulting Engineers is technical consultant, while the UK’s Wood Group is project management consultant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072199/main.jpg
    Mark Dowdall
  • Al-Mabanee submits lowest bids for Kuwait infrastructure

    2 June 2026

    Kuwait’s Public Authority for Housing Welfare (PAHW) has opened commercial bids for two major infrastructure and public buildings packages at South Al-Mutlaa Residential City.

    Local firm Al-Mabanee United Company has emerged as the lowest bidder for both contracts, submitting combined offers worth KD44m. Both packages entail the construction, completion and maintenance of services, infrastructure works and public buildings for different district centres within the city.

    The first contract covers the infrastructure and public buildings for the N3 District Centre. PAHW received proposals from eight bidders, with Al-Mabanee United Company submitting the lowest price at KD20.9m. The second-lowest offer was submitted by The Contractor General Trading & Contracting Company at KD22.4m, followed by Golden Engineering Group for General Trading & Contracting at KD22.7m, though Golden Engineering Group was flagged for not providing a bid bond.

    Al-Khonaini General Trading & Contracting Company, operating as Inshat Al-Khonaini, ranked fourth with a bid of KD22.7m, followed closely by Kuwait Industrial Centre Company at KD22.8m. Combined Group Contracting Company submitted a bid of KD23.8m, Al-Dar Engineering & Construction Company bid KD25.7m, and China’s Sichuan Road & Bridge Group Corporation submitted the highest active proposal at KD29m. 

    The second contract is for identical infrastructure and public building works at the N1 District Centre. Al-Mabanee United Company submitted the lowest bid of KD22.8m. Its closest competitor was The Contractor General Trading & Contracting Company, which submitted an offer of KD23.9m.

    Al-Khonaini General Trading & Contracting Company came in third with a bid of KD24.2m, followed by Kuwait Industrial Centre Company at KD24.4m and Golden Engineering Group for General Trading & Contracting at KD24.4m. Combined Group Contracting Company placed a bid of KD26m, Al-Dar Engineering & Construction Company bid KD26.5m, and United Construction Company, known as Al-Inshat Al-Muttahida, submitted an offer of KD 30.9m. Al-Ghanim International General Trading & Contracting filed the highest bid at KD344m and was also noted for lacking a bid bond.

    South Mutlaa Residential City is a large-scale planned development designed to accommodate around 400,000 residents in a modern, fully serviced urban environment. Once completed, it will offer contemporary housing alongside extensive logistical services and a wide range of public and commercial areas, including hospitals, schools and other social services.

    The project also includes major infrastructure works such as approximately 150 kilometres of roads and related structures, lighting and other public works, as well as integrated systems for water distribution, rainwater collection and sewage. In addition, it will provide the civil infrastructure needed for electricity distribution, telecommunications networks and traffic control to support a well-connected, functional city.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071938/main.gif
    Colin Foreman
  • Local developer secures finance for three Riyadh projects

    2 June 2026

    Qimam Noshoz for Real Estate Development Company, a subsidiary of Saudi Arabia’s Banan Real Estate Company, has signed a sharia-compliant credit facility agreement worth SR84m ($22.4m) with Riyad Bank to fund three commercial, hospitality and sports developments in the kingdom.

    The financing agreement is split into two distinct tranches to align with the projects’ development timelines. The first tranche consists of SR49m with a maturity duration of seven years, while the remaining SR35m has been secured for an eight-year term.

    Qimam Noshoz will utilise the capital to fund construction works for the Al-Rahmaniyah Gem and Al-Wadi District Gem projects. Both of these projects are already leased to the fitness operator Armah Sports Company. The other project is an independent hotel located within the Al-Wadi District.

    The Al-Wadi development is designed as an integrated commercial complex spanning approximately 7,818.5 square metres of land, with a built-up area of about 975 square metres. It includes a men’s gym, a women’s gym and a hotel building.

    The Al-Rahmaniyah project is an integrated commercial development combining fitness facilities with retail. The asset features men’s and women’s gyms operating alongside an independent commercial zone.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071628/main.jpg
    Colin Foreman
  • SLB wins $385m contract for Kuwait oil research centre

    2 June 2026

    Schlumberger Oilfield Eastern, a unit of the US-headquartered oilfield services company SLB, has been awarded a KD118m ($385m) contract to develop an oil and gas research centre in Kuwait.

    The contract was awarded by the state-owned upstream operator Kuwait Oil Company (KOC), according to a report by Kuwait’s Al-Rai newspaper.

    The Ahmadi Innovation Valley (AIV) project is planned as an advanced research and innovation hub equipped with specialised facilities and technical teams focused on applied research for Kuwait’s oil and gas sector.

    The contract was awarded after the Higher Purchase Committee (HPC) of Kuwait’s national oil and gas company Kuwait Petroleum Corporation (KPC) determined the bid to be compliant with the project’s technical and commercial requirements.

    In February 2025, KOC signed memorandums of understanding (MoUs) with five international oilfield service companies to support the development of the AIV initiative.

    These companies were:

    • SLB (US)
    • Baker Hughes (US)
    • Weatherford (US)
    • Halliburton (US)
    • National Energy Services Reunited (US)

    Under the preliminary agreements, each of the five companies agreed to establish a world-class research and development centre at the project site, focused on helping KOC meet challenges in the upstream sector.

    KOC’s CEO Ahmad Jaber Al-Eidan had said in February 2025 that the project will enable Kuwait to keep pace with global transformations while investing in advanced technologies to ensure the sector’s sustainability and achieve operational excellence.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17063475/main.gif
    Wil Crisp