Mena pushes for nuclear future
2 August 2023

The Middle East and North Africa (Mena) region is set to register a rise of at least 30 per cent in power generation capacity by 2030 due to population growth and industrial expansion.
The rapid increase requires a strategy to advance energy security while reducing carbon emissions and fossil-fuel dependence, creating strong interest in nuclear power and renewable energy.
Iran has a 1GW nuclear plant in Bushehr and construction is under way for a second 300MW reactor in Khuzestan.
In the UAE, three of the four 1.4GW reactors at the GCC region’s first multi-unit nuclear power plant in Barakah, Abu Dhabi, are now connected to the electricity grid.
Egypt, in partnership with Russia’s Rosatom, is building its first nuclear power plant in El-Debaa.
Riyadh, meanwhile, tendered the contract to build its first large-scale power plant in Duwaiheen last year.
Beyond the GCC, Jordan has announced the production of 20 kilograms of yellowcake from 160 tonnes of uranium ore at a newly operational processing facility, while Morocco has completed a study supporting a plan to go nuclear.
Alternative base load
Apart from Saudi Arabia, these countries have significant renewable capacity as of 2023. All aim for renewables to account for up to half of installed capacity by the end of the decade.
Nuclear is seen as an alternative base load to thermal capacity to counter the intermittency of renewables in the absence of viable storage solutions. This has helped build the case for adding nuclear to the energy mix – although, in the UAE, the Barakah plant predated the renewable energy programme.
The decarbonisation potential of nuclear may be overstated, however, says a leading regional expert on utility projects.
“We should use all available clean-carbon solutions to decarbonise all industrial and human consumption and endeavour,” says Paddy Padmanathan, former CEO of Saudi utility Acwa Power. “Clearly we need to decarbonise as soon as possible.”
The rate at which the residual carbon budget is being consumed implies that even zero emissions by 2050 will not be sufficient, according to the executive. This begs the question: Which technologies will deliver solutions at scale to quickly achieve decarbonisation.
Nuclear power plants, which – with the exception of Abu Dhabi’s Barakah – have struggled to be delivered on time and within budget, may not be a viable solution, says Padmanathan, who now sits on the board of the UK energy startup Xlinks and green hydrogen firm Zhero.
He says nuclear power plants outside China have taken twice as long to build than planned and have typically cost more than twice their budget. Such capital expenditure and long construction times mean nuclear may only make sense if you have lots of spare cash, he adds.
Hence it is unwise to factor in nuclear to plans to decarbonise power generation by 2050, Padmanathan argues. “We already have much – if not all – the technologies to get the job done,” he notes, referring to renewable energy and battery storage solutions, among others.
He continues: “One cannot bank on such a rare outlier as Barakah, which got completed with only a marginal increase in cost and time, and rely on nuclear to deliver any meaningful level of flexible base load.”
Saudi programme
Budget availability and the urgency of decarbonisation aside, other factors complicate nuclear projects in the region, particularly in Saudi Arabia.
The kingdom’s nuclear energy programme dates back to 2010 with the creation of King Abdullah City for Atomic & Renewable Energy (KA-Care). In 2021, KA-Care invited consultancy bids for its first large-scale nuclear power project in Duwaiheen, close to the Qatar border. It awarded the financial, legal and technical advisory services contracts last year.
In October 2022, Riyadh issued the request for proposals for the main contract to Russian, South Korean, Chinese and French firms.
Earlier this year, it formed the Saudi Nuclear Energy Holding Company, which plans to develop nuclear power plants as early as 2027 to produce electricity and to desalinate seawater, as well as for thermal energy applications.
Most recently, the state offtaker Saudi Power Procurement Company floated a tender for advisers to help prepare and review project agreements related to the procurement of electricity from Saudi’s first nuclear power plant, raising further speculation about the nuclear project.
The Saudi programme, particularly the kingdom’s plans to mine uranium as part of its economic and industrial strategy, is a thorn in Washington’s side. It is understood to have been a key theme in discussions when US President Joe Biden visited Riyadh last year.
Washington is wary of the nuclear power plant contract being awarded to Chinese or Russian contractors, not only because this could drive Riyadh closer to geopolitical rivals of the US, but also because it weakens US demands for Riyadh to abandon its nuclear fuel cycle ambitions before signing any bilateral nuclear cooperation agreement (NCA), otherwise known in Washington as a 123 agreement.
Uranium has to be enriched to up to 5 per cent for use in nuclear power plants and to 90 per cent to become weapons-grade. According to an Energy Intelligence report, the stalemate between Washington and Riyadh centres around US demands for Saudi Arabia to commit to the NCA and not pursue a domestic uranium enrichment or reprocessing programme.
The US also wants the kingdom to sign and ratify the International Atomic Energy Agency’s (IAEA) Additional Protocol, allowing nuclear inspectors fuller access to Saudi Arabia’s nuclear programme.
The report alludes to the US supporting South Korean contractor Kepco’s bid to develop the nuclear plant because it provides Washington with a final lever for pressuring Riyadh to accept its conditions for the 123 agreement and IAEA protocol.
Done deal
Biden’s visit did not produce material results, although unconfirmed reports say he may have given his blessing to the project, while others argue Riyadh did not need it.
“I think, in the end, this is a done deal, meaning that Saudi Arabia will pursue a nuclear energy programme,” says Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US.
“They will pursue domestic uranium mining and likely enrichment, and we will see a more global ramp-up of nuclear energy use – and also, over time, possibly areas of proliferation in security uses not just in the Mena region, but across a wide geography.”
The US can either take solace from the fact that it takes time to develop a nuclear project, or it can – if it is not too late – revisit its relationship with Saudi Arabia, especially in the wake of a rapprochement between Tehran and Riyadh under a deal brokered by China.
“Moving into design and procurement phases … whether with Russian, Chinese or South Korean [firms] … heightens already sensitive notions of strategic competition in the Gulf, as the US understands it,” notes Young.
In hindsight, it appears the US government has under-appreciated the seriousness of the Saudi plan or the importance of localised industry and mining as a domestic economic and security interest.
“Saudi Arabia sees an opportunity to play the US against its other options, so this is a unique moment of bargaining in which the nuclear file can be traded against broader foreign policy priorities for the Saudi leadership,” Young says.
Russian conundrum
The Barakah nuclear process, which entailed Abu Dhabi signing a 123 agreement with Washington, is seen as a gold standard. Emirates Nuclear Energy Company (Enec) signed supply contracts with France’s Areva and Russia’s Tenex for the supply of uranium concentrates and for the provision of conversion and enrichment services.
It then contracted Uranium One, part of Russia’s Rosatom, and UK-headquartered Rio Tinto for the supply of natural uranium for the plant. US-based ConverDyn provided conversion services, while British firm Urenco provided enrichment services.
The enriched uranium was supplied to Kepco Nuclear Fuels to manufacture the fuel assemblies for use at the Barakah nuclear power plant.
Fuel supply, processing, removal and storage are now complicated by Russia’s conflict and its global reputation, notes Young. The reference to Russia is important, given that Iran has provided drones to the country for use in its war with Ukraine, in exchange for the sale of advanced military equipment and cyber warfare. This is seen as a direct threat to Opec ally Riyadh.
The Tehran-Riyadh rapprochement only makes sense from a viewpoint where a dead Iran nuclear deal could expedite the Islamic Republic’s plan to build a bomb, potentially leading to a nuclear arms raise in the region, which everyone – particularly the two countries’ biggest client, China – would rather avoid.
Despite these complexities, the regional and global push to build nuclear capacity following the invasion of Ukraine and the threat to global gas supplies does not appear to be slowing.
The UAE, for instance, has partnered with the US to mobilise $100bn to support clean energy projects at home and abroad, and has pledged $30bn for energy cooperation with South Korea. Both these commitments involve significant investments in renewable and civilian nuclear energy projects.
This suggests that nuclear as a clean energy option is here to stay, despite mounting costs and geopolitical risks
Unfortunately, however, in a region marked by perennial instability, there are few incentives for the involved countries to be more transparent about their programmes.
While the evolving rapprochement between countries that have previously considered each other existential threats might not eliminate the spectre of a nuclear arms race, it can defuse tensions in the interim while helping push decarbonisation agendas.
Exclusive from Meed
-
Jordan sets market briefing for Amman water PPP10 April 2026
-
-
Masdar’s move abroad will not be the last10 April 2026
-
Turkish firm launches Mecca villas project10 April 2026
-
Kuwait gives bidders more time for Al-Khairan IWPP10 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Jordan sets market briefing for Amman water PPP10 April 2026
Jordan’s Ministry of Investment, through its Public-Private Partnership Unit (PPPU), has announced a public information session for the South Amman non-revenue water (NRW) reduction PPP project.
The session will be held on 15 April and is being organised in collaboration with the Ministry of Water & Irrigation and Miyahuna, according to a notice published by the PPPU.
The project covers the southern and southeastern areas of Amman and aims to reduce water losses and improve the efficiency of the capital’s distribution network.
According to the ministry, the scheme will serve about 1.4 million people across 17 zones and forms part of Jordan’s wider National Water Strategy.
The planned market briefing is intended to provide early detail on the project’s PPP structure, procurement pathway and performance-based contracting model.
It is also expected to outline the project’s risk allocation and bankability framework to prospective investors, operators and infrastructure companies.
The Ministry of Investment opened prequalification for the scheme in March.
Qualified companies and consortiums have been invited to participate in a two-stage procurement process for the performance-based contract.
The project aims to reduce NRW levels to 25% by 2040, while modernising and expanding the existing network using smart technologies and advanced leak detection systems.
The original deadline was 23 April. That has since been extended to 12 May.
Jordan is among the most water-scarce countries in the world, and losses from distribution networks are estimated to account for about 45% of water supplied.
The country is also advancing its $6bn Aqaba-Amman water desalination and conveyance project that aims to meet about 40% of Jordan’s municipal water demand by 2040.
As MEED recently reported, the project is nearing financial close. Once complete, it will supply about 300 million cubic metres of potable water a year from the Red Sea to Amman and other regions.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16340931/main.jpg -
OQ allows more time for natural gas liquids project proposals10 April 2026

Omani state energy conglomerate OQ Group has allowed contractors more time to prepare proposals for a major project to build a natural gas liquids (NGL) facility in the sultanate.
The planned NGL facility will extract condensates in Saih Nihayda in central Oman and transport those volumes to Duqm, located along the sultanate’s Arabian Sea coastline, for fractionation and export, OQ Group has said.
OQ Group intends to deliver the project using a front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) competition model.
The state enterprise issued the main tender for the feed-to-EPC competition “earlier in March”, setting an initial deadline of 8 April for contractors to submit proposals, MEED previously reported. The deadline has now been extended to 6 May, according to sources.
MEED previously reported that OQ had started the prequalification process for the feed-to-EPC contest for the planned NGL project in November last year, with contractors submitting responses by 15 December.
The following contractors, among others, are understood to have been invited to participate in the feed-to-EPC contest for OQ’s planned NGL project, sources told MEED:
- Chiyoda (Japan) / CTCI (Taiwan)
- G S Engineering & Construction (South Korea)
- Hyundai Engineering & Construction (South Korea) / KBR (US)
- JGC Corporation (Japan)
- Kent (UAE)
- Petrofac (UK)
- Saipem (Italy)
- Samsung E&A (South Korea) / Larsen & Toubro Energy Hydrocarbon (India) / Wood (UAE)
- Technip Energies (France)
- Tecnicas Reunidas (Spain)
- Tecnimont (Italy)
The scope of work on the project covers the development, verification and integration of feed deliverables for the following facilities and systems:
- NGL extraction facility – Saih Nihayda:
- Verification and updating of the existing feed to enable dual-mode operation (ethane recovery and ethane rejection).
- Identification and implementation of required process, equipment, utilities, and control system modifications.
- NGL Pipeline – Saih Nihayda to Duqm:
Feed for a new approximately 230km NGL transmission pipeline, including routing, hydraulics, stations, pigging facilities, metering, corrosion protection, leak detection, and safety systems.
- Fractionation unit at Duqm:
- Feed for a new fractionation facility to process ethane and propane + NGL and recover propane, butane, condensate, and provision for future ethane recovery.
- Design accommodating licensed or open-art technology and future tie-in to a planned petrochemical project in Duqm.
- Product pipelines, storage and export facilities at Duqm jetty:
- Feed for product pipelines, cryogenic and atmospheric storage tanks, vapour recovery systems, marine loading arms, and export facilities.
- Integration with existing port and refinery infrastructure, where feasible.
- Supporting systems and studies:
Utilities, offsites, flare systems, safety and environmental studies, cost estimates (class 2+10%), project schedules, constructability assessments, and EPC tender documentation.
Natural gas liquids projects
Gulf national oil companies have been allocating significant capital expenditure to building or expanding NGL production facilities.
QatarEnergy, in September last year, awarded the main EPC contract for its project to add a fifth NGL train at its fractionation complex in Qatar’s Mesaieed Industrial City. The aim of the project, which is estimated to be worth $2.5bn, is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.
The main EPC contract for the QatarEnergy NGL-5 project was won by a consortium of India’s Larsen & Toubro Energy Hydrocarbons Onshore and Greece-headquartered Consolidated Contractors Group.
Separately, the gas processing business of Abu Dhabi National Oil Company (Adnoc Gas) has also selected the main contractor for a project to install a fifth NGL fractionation train at its Ruwais gas processing facility in Abu Dhabi.
The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day, or about 8 million tonnes a year.
The Ruwais NGL Train 5 project represents the second phase of Adnoc Gas’ ambitious Rich Gas Development (RGD) programme, and its budget value is estimated to be around $4bn, Peter Van Driel, Adnoc Gas’ chief financial officer, confirmed in February. The company expects to achieve final investment decision on the project within the first quarter of 2026, Van Driel said at the time.
ALSO READ: PDO awards Oman gas plant expansion project
https://image.digitalinsightresearch.in/uploads/NewsArticle/16340039/main5958.jpg -
Masdar’s move abroad will not be the last10 April 2026
Commentary
Mark Dowdall
Power & water editorMasdar’s new joint-venture agreement with France’s TotalEnergies will not be the last time we see regional energy investors use strong balance sheets and domestic growth to build larger positions overseas.
For Masdar in particular, the deal broadens its international exposure at a time when investors are asking questions about the Middle East’s geopolitical risk.
By combining portfolios, the two companies start with 3GW of operational capacity and another 6GW in advanced development.
The deal covers nine Asian countries, reflecting a prudent strategy that spreads capital across markets with different risk profiles and growth trajectories.
In Kazakhstan, which already includes 2.6GW of assets under development, there is clear logic behind this move.
The country is expected to see a significant increase in renewable generation over the next decade, supported by strong wind resources and the availability of large land areas for utility-scale developments.
There is also a practical advantage in partnering with TotalEnergies, which already has project delivery experience and an established presence in several of these markets.
The US-Iran ceasefire announced on 8 April has brought some respite to energy infrastructure stakeholders in the region.
For investors and developers, however, the long-term uncertainty remains. Until there is clear evidence of regime change, the removal of sanctions or lasting peace in the region, the outlook will be less clear.
With uncertainty one of the biggest killers of investor confidence, many will now be looking at this agreement and thinking whether they should also follow suit.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16340038/main.jpg -
Turkish firm launches Mecca villas project10 April 2026
Register for MEED’s 14-day trial access
Turkish real estate investment firm Emlak Konut has announced the launch of Hayat Makkah, its first development in Saudi Arabia.
The project is part of the National Housing Company’s (NHC) wider Mecca Gate masterplan.
According to the company, Hayat Makkah will feature 1,014 villas, with home sizes ranging from 150 to 5,000 square metres.
NHC and Emlak Konut signed an investment agreement worth over SR1bn ($266m) in November last year to develop the project.
The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.
Ertan Keles, chairman of Emlak Konut, said the firm is in talks with stakeholders about launching a second project, while a third development is also being lined up in Jeddah.
GlobalData expects the Saudi Arabian construction industry to grow by 3.6% in real terms in 2026, supported by an increase in foreign direct investment (FDI) and investments in the housing and manufacturing sectors.
The residential construction sector is expected to grow by 3.8% in real terms in 2026 and register an average annual growth rate of 4.7% between 2027 and 2030, supported by the country’s aim – under Saudi Vision 2030 – to increase homeownership from 65.4% in 2024 to 70% by 2030, including by building 600,000 homes by 2030.
According to the General Authority for Statistics, Saudi Arabia attracted a net FDI inflow of SR72.3bn ($19.3bn) in the first nine months of 2025, an increase of 32.7% year-on-year (YoY) compared to the same period in 2024.
Similarly, the total value of real estate loans from banks grew by 11.5% YoY in 2025, preceded by an annual growth of 13.3% in 2024, according to the Saudi Central Bank (Sama).
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16340004/main.png -
Kuwait gives bidders more time for Al-Khairan IWPP10 April 2026

Kuwait has extended bidding for the first phase of the Al-Khairan independent water and power producer (IWPP) project.
The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).
The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant.
The new deadline is 30 April. The original deadline was 31 March.
The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate.
These include:
- Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) / Jera (Japan)
- Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
- China Power / Malakoff International (Malaysia) / Abdul Aziz Al-Ajlan Sons (Saudi Arabia)
- Nebras Power (Qatar)
- Sumitomo Corporation (Japan)
The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).
The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.
The energy conversion and water purchase agreement is expected to cover a 25-year supply period.
Kapp extended another deadline recently for a contract to develop zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.
The PPP authority is procuring the 500MW solar photovoltaic independent power project (IPP) in partnership with the ministry.
The bid submission deadline was moved to the end of April, a source close to the project told MEED.
According to the MEWRE, the total generation capacity currently offered under partnership projects has reached 6,100MW, equivalent to about 30% of Kuwait’s existing power capacity.
The ministry and Kapp are also preparing to tender the main contract for the 3,600MW Nuwaiseeb power and water desalination plant after plans were approved by Kuwait’s Council of Ministers last November.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16339960/main.jpg

