Lowest bidder changes again for Dubai Metro Blue Line
5 December 2024

Register for MEED's 14-day trial access
The lowest bidder for the Dubai Metro Blue Line project has changed again after contractors submitted revised offers on 3 December.
The lowest bidder is the consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC) with a price of AED20.5bn ($5.6bn).
The second-lowest bidder is the team of Beijing-based China State Construction Engineering Corporation (CSCEC) and France’s Alstom with a price of AED21.6bn.
The consortium of India’s Larsen & Toubro (L&T), China’s Powerchina, the local Wade Adams and Hitachi submitted an offer of AED21.7bn.
These prices were changed from the previous round of bids that were submitted on 21 November, when the project client, the Roads & Transport Authority (RTA), asked bidders to submit alternatives to reduce the price. Some of these alternatives have been accepted, while others have been rejected.
The China State/Alstom team was the lowest bidder with a price of AED19.8bn on 21 November, followed by L&T/Powerchina/Wade Adams/Hitachi with an offer of AED20.3bn, and Limak/Mapa/CRRC with a bid of AED20.6bn.
The RTA had received another round of updated offers on 14 November. That time the Limak/Mapa/CRRC team submitted the lowest bid with a price of AED21.7bn.
For the first round of revised offers on 7 November, the group of China Tiesiju Civil Engineering Group (CTCE), Egypt’s Arab Contractors, the local Binladin Contracting Group and Spain’s CAF submitted the lowest-priced revised base offer of AED22.2bn.
The CTCE/Arab Contractors/Binladin/CAF group submitted the lowest base offer when the bids were first submitted on 6 October.
The design-and-build contractor for the Blue Line will be responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, the contractor will assist with maintenance and operations for an initial three-year period.
The Blue Line will connect the existing Red and Green lines. It will have a total length of 30 kilometres (km), 15.5km underground and 14.5km above ground.
The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.
The scope of the contract also includes the supply of 28 driverless trains, the construction of a depot to accommodate up to 60 trains and the construction of all associated roads, facilities and utility diversion works.
The detailed scope of work for the project includes:
- Civil works, including detailed design and construction of architectural and structural components (including viaducts, tunnels and stations)
- Design and execution of electromechanical works
- Design, procurement and delivery of operation and control systems for rail, stations and facilities
- Design, manufacturing and supply of rolling stock
UAE Vice President, Prime Minister and Ruler of Dubai, Sheikh Mohammed Bin Rashid Al-Maktoum, approved the Blue Line extension project last year. In a post on social media network X, formerly Twitter, he said the project will cost AED18bn ($4.9bn) and will have a length of 30km, half of which will be underground.
He added that the extensions will transport 320,000 passengers a day and serve a population of about 1 million people living in areas such as Festival City, International City, Rashidiya, Warqa, Mirdif, Silicon Oasis and Academic City.
Exclusive from Meed
-
-
-
-
Qiddiya awards estimated $1bn racecourse deal1 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Contractor appointed for Abu Dhabi Riviera residences1 July 2026

Dubai-based real estate developer Mered has appointed Turkiye’s Sera Group as the main contractor for its Riviera Residences project on Al-Reem Island in Abu Dhabi.
The development will comprise more than 400 one- to three-bedroom apartments and 11 villas.
Lebanese engineering firm Dar Al-Handasah is the project consultant, while Switzerland’s Herzog & de Meuron is the architect.
The enabling works are being carried out by local contractor NSCC International.
Mered and Sera Group are also working together on the Iconic Tower project in Dubai Internet City, where the developer awarded the main contract in December 2024.
The 67-storey tower is being built on a site covering about 6,368 square metres.
Local firm Mirage is the project consultant, while Singapore-based Hirsch Bedner Associates is the project architect.
Dubai-based Chawla Architectural & Consulting Engineers is the architect of record, and Omnium International is the quantity surveyor.
The foundation works were carried out by local firm Dutch Foundations.
Mered’s latest contract awards in the UAE market come amid heightened real estate and construction activity, with schemes worth more than $323bn at the execution or planning stages, according to UK-based analytics firm GlobalData.
GlobalData forecasts that output from the UAE’s residential construction sector will grow by 3% in real terms in 2026-29, supported by infrastructure, energy and utilities developments, as well as residential construction projects.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17509888/main.jpg -
Aramco extends deadline for Ras Tanura refinery gas pipeline1 July 2026

Saudi Aramco has granted contractors more time to prepare bids for a tender to replace a pipeline in the Gas Line Abqaiq–Ras Tanura (GART) transmission network.
The GART grid transports associated gas and natural gas liquids (NGL) from the Abqaiq oil processing complex as feedstock, northwards to the Ras Tanura refinery in Saudi Arabia’s Eastern Province.
The aim of the project is to replace the GART-22 pipeline that connects the Juaymah export terminal on the Gulf coast in the Eastern Province to the Ras Tanura refinery, to ensure reliable fuel gas supply and meet ongoing demand.
The basic scope of work for the project is to install a new 24-inch pipeline system to replace the GART-22 line and the abandoned GART-24 line. It will cover a distance of 18 kilometres between Juaymah and the Ras Tanura terminal.
The scope also includes the installation of associated scraper trap facilities (launcher and receiver), pressure control valves, motor-operated valves and gas detection and sampling systems.
Aramco issued the tender for the project in May, setting an initial deadline of 30 June for contractors to submit proposals, MEED previously reported.
The Saudi energy giant has now extended that deadline until 10 July, according to sources.
The following contractors, among others, are understood to be bidding for the project:
- ACE Pipeline Arabia
- Combined Group Contracting Company
- Gas Arabian Services Company
- Max Streicher Saudi Arabia
- National Basics Company
- Saad Ali Alessa Group
- Sicim
- Sinopec Engineering Group Saudi
- Tecton Engineering & Construction
Ras Tanura refinery complex
The Ras Tanura refinery is the oldest, and one of the largest, crude oil refineries in Saudi Arabia. The complex has a refining capacity of 550,000 barrels a day (b/d).
The facility also has a 305,000 b/d NGL processing facility, a 960,000 b/d crude stabilisation facility, combined steam and gas turbine electrical power generation plants with a summer capacity of 145MW and a winter capacity of 158MW, and a combined 150-pound and 600-pound steam capacity of 6,217 million pounds an hour.
It has 75 crude oil and products storage tanks with a combined capacity of 5.8 million barrels.
The Ras Tanura refinery’s major facilities include a 325,000 b/d crude distillation unit, a 225,000 b/d gas condensate distillation unit, a 50,000 b/d hydrocracker and 107,000 b/d of catalytic reforming capacity.
The facility is Aramco’s only refinery to contain a Visbreaker processing unit, which has a 60,000 b/d capacity.
The Visbreaker reduces the quantity of residual oil produced in the distillation of crude oil and increases the yield of more valuable middle distillates, heating oil and diesel.
The refinery complex also produces 17,000 b/d of asphalt, more than any other refinery in Saudi Arabia.
Ras Tanura receives crude feedstock from the Abqaiq, Safaniya and Manifa oil field developments.
Crude is typically transferred to Ras Tanura through a pipeline and can also be supplied by ship.
Most of Ras Tanura’s production is transferred to the Dhahran bulk plant for domestic use, while some products are exported from the nearby Ras Tanura shipping terminal.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17508681/main4014.jpg -
Siemens Energy to supply turbines for Oman IPP projects1 July 2026
Germany’s Siemens Energy has announced it will supply power generation technology and long-term service agreements for the 2.6GW Misfah and Duqm independent power producer (IPP) projects in Oman.
The scope includes the supply of six F-class gas turbines, six generators and 20-year long-term service agreements for the equipment.
The combined-cycle gas-fired plants will add almost 20% to the sultanate’s electricity generation capacity. They are expected to provide electricity to more than two million people.
Oman’s Nama Power & Water Procurement (Nama PWP) signed power-purchase agreements (PPAs) for the development and operation of the plants in January.
The two combined-cycle gas turbine plants are being developed by a consortium comprising Korea Western Power (Kowepo), Qatar’s Nebras Power, the UAE’s Etihad Water & Electricity (EtihadWE) and Oman’s Bhawan Infrastructure Services.
The Misfah IPP will be led by Nebras Power and located in Wilayat Bousher in Muscat Governorate, with a planned capacity of 1,600MW.
The Duqm IPP will be led by Kowepo and located in Wilayat Duqm in Al-Wusta Governorate, with a capacity of 800MW.
In May, MEED exclusively reported that a consortium of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility had been appointed as the main contractor.
The gas turbines will have hydrogen co-firing capability, providing flexibility to increase hydrogen use over time, Siemens said in a statement.
The turbines will be manufactured at Siemens Energy’s facility in Berlin. The generators will be produced at the company’s plant in Muelheim, Germany.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17506190/main.jpg -
Qiddiya awards estimated $1bn racecourse deal1 July 2026

Register for MEED’s 14-day trial access
Saudi gigaproject developer Qiddiya Investment Company (QIC) has awarded an estimated SR4.3bn ($1.1bn) contract for the construction of a racecourse at Qiddiya entertainment city, on the outskirts of Riyadh.
The contract was awarded to Taj Dhabi, a local subsidiary of UAE-based Trojan Construction.
The racecourse venue will cover 1.3 million square metres and accommodate 70,000 spectators.
QIC issued the tender for the construction works in December last year, but formally announced the project only on 10 February. Contractors submitted their bids on 15 February, MEED previously reported.
According to a statement published on QIC’s website: “The venue will include the region’s first straight-mile turf course, alongside a 2.2 kilometre (km) main turf track and a 2.4km inner dirt track.
“A 21,000-seat grandstand will anchor the venue, with the ability to expand capacity to up to 70,000 guests through event overlays during major race days,” the statement added.
A centrepiece of the venue will be a 110-metre central parade ring, located in the middle of the racecourse.
The project also includes an equine hospital that will provide advanced veterinary services, including diagnostics, surgery, rehabilitation and emergency care for horses.
The Qiddiya City horse racing venue is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, the Prince Mohammed Bin Salman Stadium, a motorsports track, a performing arts centre, the Dragon Ball and Six Flags theme parks, and Aquarabia.
The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.
GCC presses ahead with tourism projects
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17506035/main.jpg -
NCP seeks firms for Saudi Arabia university hospital PPP1 July 2026
Saudi Arabia’s Umm Al-Qura University, in collaboration with the National Centre for Privatisation & PPP (NCP), has launched an expression of interest for the completion of the construction and operation of the Umm Al-Qura University Hospital in Mecca.
Issued to contractors on 30 June, the notice has a submission deadline of 21 July.
The scope includes completing the remaining construction works, as well as the subsequent operation of the hospital.
Upon completion, the hospital will have a capacity of 391 beds.
The project will be delivered as a public-private partnership (PPP) under a design, build, finance, operate and maintain model.
The contract duration is 30 years.
The project is the latest healthcare project to be procured on a PPP basis in the kingdom. In June, MEED reported that Saudi Arabia’s Ministry of Health and NCP had awarded a PPP contract for the operation and management of the Sabic Specialised Behavioural Healthcare Hospital in Riyadh.
That contract was awarded to SEH Healthcare, a consortium comprising local firms Specialised Medical Company (SMC Healthcare) and Health Gates Complex, and Germany’s Dr Ebel Fachkliniken.
In a filing with the Saudi Exchange (Tadawul), SMC Healthcare said the total estimated project value is about SR3.8bn ($1bn).
In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.
Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.
In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17506381/main.jpg
