Legacy building at Diriyah
1 August 2024
It is impossible to talk about Saudi Arabia’s history without referencing Diriyah. Founded in 1446 in the Wadi Hanifa valley on the western outskirts of Riyadh, the historic town was the first capital of the Al-Saud dynasty and the launchpad for the kingdom’s unification campaign at the turn of the 20th century. In recognition, its central Turaif district was inscribed as a Unesco World Heritage site in 2010.
Today, the mud-brick settlement, built in the distinctive Najdi architectural style, has lent its name to one of the world’s most ambitious transformative developments. Sensitively conserving and building on its historical importance, it has created a unique cultural, educational, residential and tourism hub in the capital.
With an official budget of some $63bn, Diriyah is one of Saudi Arabia’s five official gigaprojects. It has held this label since early 2023, when responsibility for its development was handed to Diriyah Company, a project company formed as a Public Investment Fund (PIF) subsidiary a year earlier.
Covering an area of 14 square kilometres, Diriyah is targeting a population of 100,000 by its stated completion date of 2030. With more than 40 hotels, nine museums, 400 luxury boutiques, 100-plus restaurants and multiple educational institutions, it hopes to draw in more than 50 million annual visits.
Progress since ground was first broken four years ago has been rapid. As of May 2024, more than SR53bn ($14.1bn)-worth of construction contracts had been awarded. Today, visitors to the area can see hundreds of mobile cranes, plant and piling equipment rising over the boundary wall.
“We are in a good place,” says Mohammed Saad, Diriyah Company’s chief development officer. “We’ve finished our essential underground infrastructure and civil works, the super basement and all the tunnels that connect the basements together.”
But the real work has only just begun. Saad says a further SR30bn-35bn is scheduled to be awarded by the end of 2024, rising to SR40bn-45bn in 2025. By the end of this year, the public can expect to see substantial above-ground construction, particularly on the western side of the gigaproject, providing more tangible evidence of its advancement, which until now has been primarily below ground.
This is not to say that any vertical assets will be particularly tall. Because of the district's traditional low-rise nature, any building must be no higher than the historic structures. It should also emulate the Najdi style. For the same reason, most of the essential infrastructure, utilities and roads are hidden below ground.
Major project scopes
A significant step was made in early July when Diriyah Company awarded an estimated $2bn contract to a joint venture of El-Seif Engineering & Contracting and China State to build the North Cultural District. The deal, the largest let on the gigaproject to date, covers multiple assets, including hotels, the King Salman Foundation Library, King Salman University and the House of Saud Museum.
The work was originally planned as multiple construction packages until Diriyah Company took the commercial decision last year to bundle them into one contract. The decision to adopt super packages was driven by a dynamic market in which contractors have been almost overwhelmed with the volume of tenders from various gigaprojects and where cost inflation is taking hold.
“You will not get the attention of the big contractors if you offer small contracts,” Saad explains. By consolidating projects, contractors can focus their resources more effectively and efficiently and provide more competitive pricing.
“We have a hotel, we have an office building, we have a museum, and when we tendered them as one super package, there was a very solid response and interest from the big players because they could focus their resources and pricing and more efficiently engage their supply chains and subcontractors.”
The approach appears to be working. In late July, another estimated $2bn super package was awarded to a joint venture of local contractor Albawani and Qatar’s Urbacon to construct assets in the Wadi Safar district of the gigaproject. Featuring a mix of residential, residential farm plots, hotels, branded hotel villas, a golf course, an equestrian and polo club, and other leisure and entertainment facilities, including Aman, Chedi, Faena and Six Senses-branded hotels, Wadi Safar is positioned as the most upscale and exclusive development in Riyadh and indeed the kingdom as a whole.
The consolidated contract packages strategy reflects the supercharged nature of the Saudi projects market. With various clients, including the gigaprojects, all competing for a limited amount of contracting, material and labour resources, more innovative procurement strategies need to be adopted.
This is particularly critical for Diriyah and its enormous material requirements. For example, it has previously said that it will ultimately need some 350,000 doors, 1.5 million square metres of tiles, 1.2 million tonnes of rebar and 140,000 HVAC units.
Supply-side obstacles
Despite the progress, the project faces challenges related to contracting, engineering and material supply. The high demand for key materials, coupled with global supply chain disruptions, poses a significant conundrum. However, the delivery team has proactively secured and signed framework agreements with manufacturers to ensure a steady flow of required materials.
Transparent demand signalling is a core component of this. “We’ve analysed our material needs up to 2030 and prepared comprehensive requests for proposals for all key items,” says Saad. “We went out to the manufacturers and the supply chain in general to let them see the pipeline is tangible and secure. We are listening to vendors in order to speed things up and to lock down prices.”
Saad lists specific materials not naturally available in Saudi Arabia, such as finishing stones, as items that may be in short supply, in addition to some specialised MEP equipment that is only manufactured abroad. Overall, he is optimistic about the market’s ability to adapt. “The market will adjust itself,” he states. “Of course, there are challenges, but there are also opportunities for manufacturers to up their game.”
Likewise, contractors are being brought into discussions at earlier stages of contract planning. Diriyah is adopting strategies such as early contractor involvement in the design process to help better understand and manage construction risk. “We’re engaging with contractors and delivery partners as early as the concept design stages to get their feedback on the project’s constructability,” says Saad. “Later, these contractors can be invited to bid for the contract, which makes it easier for them and so they can be aware of any issues.”
Financial constraints
Another increasingly evident challenge is financing. As the gigaprojects programme steps up a gear, there have been growing strains on funding the huge costs associated with it, expenditure which in some cases is considerably higher than when first estimated during the initial master planning stages due to cost inflation and disruptions in the supply chain.
As with the other gigaprojects, Diriyah’s initial work has been fully funded by its PIF parent, but later phases will likely require other financing mechanisms. While some of this will come from the $100m in revenues it expects to make over the next year, the client company has been actively tapping into the capital markets, following in the footsteps of other gigaprojects such as Neom and Red Sea Global, which have concluded sizeable borrowing deals in the past two years.
This includes all options up to and including an initial public offering (IPO). The market consensus is that eventually all the PIF project company subsidiaries will go public when the time is right, and Diriyah is unlikely to be an exception.
For the same reason, the client is also exploring public-private partnerships (PPPs) to enable the private sector to take on some of the financial burden. For instance, City Cool Cooling Company recently won a $186m 25-year build-own-operate (BOO) concession to develop a 72,000-refrigeration-tonne district cooling plant. Future opportunities may include expansion of cooling capacity, other utilities and car parking operations.
“PPPs are a key component of our strategy,” says Saad. They provide a platform for private investors to participate in Diriyah's growth while leveraging the expertise and resources of the public sector. We realise we cannot build 10 million square metres alone. We need the private sector to participate and partner with us and give them an opportunity to be part of this journey.”
Another funding source will be off-plan property sales once its real estate offering comes to market. Based on the development plans, this is expected to be significant. With a mix of some 30,000 villas, apartments and townhouses, the ambition is to attract both local and expatriate residents, if or when the kingdom opens its property market to non-nationals.
Investment pathway
Eventually, third parties will also need to invest in the various real estate elements of the gigaproject. Diriyah Company, as a master developer, is actively seeking to attract other developers, family offices and financial institutions to develop land parcels for mixed-use, residential, hospitality, commercial, education and healthcare assets.
“We are already opening up to investors and meeting developers who are interested in partnering with us or buying land,” notes Saad. “It’s a good problem to have – there’s more interest than we can handle right now, which speaks volumes about the project's attractiveness.”
This is just as well. One criticism of the gigaprojects programme has been the shortfall in both local and international investment to date. A lack of understanding of what the gigaprojects are and will be, demand uncertainty, timeframe ambiguities and general market hesitancy have been identified as the stumbling blocks.
Diriyah is determined to change this situation. It is focusing on increasing public and investor awareness of the potential opportunity through initiatives such as its two-day Bashayer event last November, which showcased the masterplan and construction progress to selected key stakeholders. There has also been a push for greater transparency and publishing more specific details about the overall development to make it stand out from the crowded market.
The giant gigaproject is not being developed in isolation. Experience from successful developments worldwide highlights that connectivity and coordination with other government stakeholders are key. Diriyah is planned to be connected to an extension of Riyadh Metro’s Line 2 and a planned Line 7 linking it with King Khalid International airport and another gigaproject, Qiddiya. In total, four metro stations are planned for the development.
At the same time, talks are under way for Diriyah to be one of the main stations on the planned Q-Express high-speed rail link between the airport and Qiddiya, which will complement the metro network. For those arriving by car, there will be the opportunity to use the three-level, 1 million square-metre underground ‘super basement’ car park, which, with a capacity for 10,500 vehicles, will be the fifth-largest parking facility in the world, and by far the biggest in the region.
As Diriyah’s construction accelerates, it is already starting to define its identity more clearly. Building on the kingdom’s historical roots, it is set to create a new legacy for future generations.
Exclusive from Meed
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
-
What actually slows a gigaproject down9 September 2026
-
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026
-
Jordan tenders advisory for wastewater treatment plant9 September 2026
-
Consultants bid for Abu Dhabi light rail project management9 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
Register for MEED’s 14-day trial access
Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.
Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.
The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.
Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.
At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.
US strikes on Iranian tankers
US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.
The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.
Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.
The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.
Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.
Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.
The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.
Houthi attacks raise supply concerns
The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.
On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.
Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.
The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.
Riyadh condemns attacks
Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.
In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.
Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg -
What actually slows a gigaproject down9 September 2026

Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.
“None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.
For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.
“The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.
The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.
“Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”
Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.
Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.
Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.
“The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”
Integration needs to be well understood
“Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.
Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.
Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.
“The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”
That shared view, he argues, will be what the next phase of Gulf delivery is judged on.
Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.
“This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.
From reporting progress to managing risk before it lands
Digital tools have a role here, Caldwell says, but not as a headline in themselves.
Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.
“The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."
None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”
Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.
With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.
“The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.
What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.
“The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif -
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026

Register for MEED’s 14-day trial access
Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.
The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.
The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.
Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.
US-based architect Populous is the project consultant.
The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg -
Jordan tenders advisory for wastewater treatment plant9 September 2026
The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.
The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).
The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.
The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.
The submission deadline is 21 September.
The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.
The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.
The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.
WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.
The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.
The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg -
Consultants bid for Abu Dhabi light rail project management9 September 2026

Register for MEED’s 14-day trial access
Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.
The notice was issued on 7 September, with a submission deadline of 9 November.
The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.
The key sections of the tram are:
AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.
This section covers 13km and includes 13 at-grade stations and one underground station.
Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.
Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.
The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.
The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.
Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.
Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.
Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.
The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg