Legacy building at Diriyah

1 August 2024

It is impossible to talk about Saudi Arabia’s history without referencing Diriyah. Founded in 1446 in the Wadi Hanifa valley on the western outskirts of Riyadh, the historic town was the first capital of the Al-Saud dynasty and the launchpad for the kingdom’s unification campaign at the turn of the 20th century. In recognition, its central Turaif district was inscribed as a Unesco World Heritage site in 2010.

Today, the mud-brick settlement, built in the distinctive Najdi architectural style, has lent its name to one of the world’s most ambitious transformative developments. Sensitively conserving and building on its historical importance, it has created a unique cultural, educational, residential and tourism hub in the capital.

With an official budget of some $63bn, Diriyah is one of Saudi Arabia’s five official gigaprojects. It has held this label since early 2023, when responsibility for its development was handed to Diriyah Company, a project company formed as a Public Investment Fund (PIF) subsidiary a year earlier.

Covering an area of 14 square kilometres, Diriyah is targeting a population of 100,000 by its stated completion date of 2030. With more than 40 hotels, nine museums, 400 luxury boutiques, 100-plus restaurants and multiple educational institutions, it hopes to draw in more than 50 million annual visits.

Progress since ground was first broken four years ago has been rapid. As of May 2024, more than SR53bn ($14.1bn)-worth of construction contracts had been awarded. Today, visitors to the area can see hundreds of mobile cranes, plant and piling equipment rising over the boundary wall.

“We are in a good place,” says Mohammed Saad, Diriyah Company’s chief development officer. “We’ve finished our essential underground infrastructure and civil works, the super basement and all the tunnels that connect the basements together.”

But the real work has only just begun. Saad says a further SR30bn-35bn is scheduled to be awarded by the end of 2024, rising to SR40bn-45bn in 2025. By the end of this year, the public can expect to see substantial above-ground construction, particularly on the western side of the gigaproject, providing more tangible evidence of its advancement, which until now has been primarily below ground.

This is not to say that any vertical assets will be particularly tall. Because of the district's traditional low-rise nature, any building must be no higher than the historic structures. It should also emulate the Najdi style. For the same reason, most of the essential infrastructure, utilities and roads are hidden below ground.

Major project scopes

A significant step was made in early July when Diriyah Company awarded an estimated $2bn contract to a joint venture of El-Seif Engineering & Contracting and China State to build the North Cultural District. The deal, the largest let on the gigaproject to date, covers multiple assets, including hotels, the King Salman Foundation Library, King Salman University and the House of Saud Museum.

The work was originally planned as multiple construction packages until Diriyah Company took the commercial decision last year to bundle them into one contract. The decision to adopt super packages was driven by a dynamic market in which contractors have been almost overwhelmed with the volume of tenders from various gigaprojects and where cost inflation is taking hold.

“You will not get the attention of the big contractors if you offer small contracts,” Saad explains. By consolidating projects, contractors can focus their resources more effectively and efficiently and provide more competitive pricing.

“We have a hotel, we have an office building, we have a museum, and when we tendered them as one super package, there was a very solid response and interest from the big players because they could focus their resources and pricing and more efficiently engage their supply chains and subcontractors.”

The approach appears to be working. In late July, another estimated $2bn super package was awarded to a joint venture of local contractor Albawani and Qatar’s Urbacon to construct assets in the Wadi Safar district of the gigaproject. Featuring a mix of residential, residential farm plots, hotels, branded hotel villas, a golf course, an equestrian and polo club, and other leisure and entertainment facilities, including Aman, Chedi, Faena and Six Senses-branded hotels, Wadi Safar is positioned as the most upscale and exclusive development in Riyadh and indeed the kingdom as a whole.

The consolidated contract packages strategy reflects the supercharged nature of the Saudi projects market. With various clients, including the gigaprojects, all competing for a limited amount of contracting, material and labour resources, more innovative procurement strategies need to be adopted.

This is particularly critical for Diriyah and its enormous material requirements. For example, it has previously said that it will ultimately need some 350,000 doors, 1.5 million square metres of tiles, 1.2 million tonnes of rebar and 140,000 HVAC units.

Supply-side obstacles

Despite the progress, the project faces challenges related to contracting, engineering and material supply. The high demand for key materials, coupled with global supply chain disruptions, poses a significant conundrum. However, the delivery team has proactively secured and signed framework agreements with manufacturers to ensure a steady flow of required materials.

Transparent demand signalling is a core component of this. “We’ve analysed our material needs up to 2030 and prepared comprehensive requests for proposals for all key items,” says Saad. “We went out to the manufacturers and the supply chain in general to let them see the pipeline is tangible and secure. We are listening to vendors in order to speed things up and to lock down prices.”

Saad lists specific materials not naturally available in Saudi Arabia, such as finishing stones, as items that may be in short supply, in addition to some specialised MEP equipment that is only manufactured abroad. Overall, he is optimistic about the market’s ability to adapt. “The market will adjust itself,” he states. “Of course, there are challenges, but there are also opportunities for manufacturers to up their game.”

Likewise, contractors are being brought into discussions at earlier stages of contract planning. Diriyah is adopting strategies such as early contractor involvement in the design process to help better understand and manage construction risk. “We’re engaging with contractors and delivery partners as early as the concept design stages to get their feedback on the project’s constructability,” says Saad. “Later, these contractors can be invited to bid for the contract, which makes it easier for them and so they can be aware of any issues.”

Financial constraints

Another increasingly evident challenge is financing. As the gigaprojects programme steps up a gear, there have been growing strains on funding the huge costs associated with it, expenditure which in some cases is considerably higher than when first estimated during the initial master planning stages due to cost inflation and disruptions in the supply chain.

As with the other gigaprojects, Diriyah’s initial work has been fully funded by its PIF parent, but later phases will likely require other financing mechanisms. While some of this will come from the $100m in revenues it expects to make over the next year, the client company has been actively tapping into the capital markets, following in the footsteps of other gigaprojects such as Neom and Red Sea Global, which have concluded sizeable borrowing deals in the past two years.

This includes all options up to and including an initial public offering (IPO). The market consensus is that eventually all the PIF project company subsidiaries will go public when the time is right, and Diriyah is unlikely to be an exception.

For the same reason, the client is also exploring public-private partnerships (PPPs) to enable the private sector to take on some of the financial burden. For instance, City Cool Cooling Company recently won a $186m 25-year build-own-operate (BOO) concession to develop a 72,000-refrigeration-tonne district cooling plant. Future opportunities may include expansion of cooling capacity, other utilities and car parking operations.

“PPPs are a key component of our strategy,” says Saad. They provide a platform for private investors to participate in Diriyah's growth while leveraging the expertise and resources of the public sector. We realise we cannot build 10 million square metres alone. We need the private sector to participate and partner with us and give them an opportunity to be part of this journey.”

Another funding source will be off-plan property sales once its real estate offering comes to market. Based on the development plans, this is expected to be significant. With a mix of some 30,000 villas, apartments and townhouses, the ambition is to attract both local and expatriate residents, if or when the kingdom opens its property market to non-nationals.

Investment pathway

Eventually, third parties will also need to invest in the various real estate elements of the gigaproject. Diriyah Company, as a master developer, is actively seeking to attract other developers, family offices and financial institutions to develop land parcels for mixed-use, residential, hospitality, commercial, education and healthcare assets.

“We are already opening up to investors and meeting developers who are interested in partnering with us or buying land,” notes Saad. “It’s a good problem to have – there’s more interest than we can handle right now, which speaks volumes about the project's attractiveness.”

This is just as well. One criticism of the gigaprojects programme has been the shortfall in both local and international investment to date. A lack of understanding of what the gigaprojects are and will be, demand uncertainty, timeframe ambiguities and general market hesitancy have been identified as the stumbling blocks.

Diriyah is determined to change this situation. It is focusing on increasing public and investor awareness of the potential opportunity through initiatives such as its two-day Bashayer event last November, which showcased the masterplan and construction progress to selected key stakeholders. There has also been a push for greater transparency and publishing more specific details about the overall development to make it stand out from the crowded market.

The giant gigaproject is not being developed in isolation. Experience from successful developments worldwide highlights that connectivity and coordination with other government stakeholders are key. Diriyah is planned to be connected to an extension of Riyadh Metro’s Line 2 and a planned Line 7 linking it with King Khalid International airport and another gigaproject, Qiddiya. In total, four metro stations are planned for the development.

At the same time, talks are under way for Diriyah to be one of the main stations on the planned Q-Express high-speed rail link between the airport and Qiddiya, which will complement the metro network. For those arriving by car, there will be the opportunity to use the three-level, 1 million square-metre underground ‘super basement’ car park, which, with a capacity for 10,500 vehicles, will be the fifth-largest parking facility in the world, and by far the biggest in the region.

As Diriyah’s construction accelerates, it is already starting to define its identity more clearly. Building on the kingdom’s historical roots, it is set to create a new legacy for future generations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12260371/main.gif
Edward James
Related Articles
  • Saudi Arabia seeks firms for food testing labs PPP project

    2 April 2026

    Saudi Arabia’s Ministry of Municipalities & Housing, in collaboration with the National Centre for Privatisation & PPP (NCP), has issued an expression of interest (EOI) notice for a contract to develop and operate municipal food safety laboratories under a public-private partnership (PPP) framework.

    The project will be delivered on an equip, operate, maintain and transfer basis, with a contract duration of five years.

    The EOI was issued on 1 April, with a submission deadline of 15 April.

    The project scope covers the equipping, operation and maintenance of municipal food safety laboratories across five municipalities: Hafr Al-Batin, Northern Borders, Tabuk, Qassim and Al-Ahsa.

    Key objectives include upgrading laboratory equipment, expanding chemical and microbiological testing capacity for food and water products, and enhancing testing accuracy to support laboratory compliance across the value chain. The project also aims to ensure effective knowledge transfer and a structured handover to the relevant municipalities at the end of the contract term.

    NCP said in a statement: “The project is intended to strengthen public health and safety standards for citizens and residents of the kingdom in alignment with Saudi Vision 2030, while developing the municipal monitoring ecosystem, optimising food and water testing services, and enabling private sector participation in accordance with global best practices.”

    In October last year, NCP highlighted the scale and diversity of opportunities in the kingdom’s PPP pipeline.

    “At the moment, we have around 200 projects in the pipeline with a total value of roughly $190bn,” said Salman Badr, executive vice president – infrastructure advisory, NCP, during a MEED webinar.

    The projects are spread across 17 sectors. “We have a very sizable programme, and it reflects the breadth of the kingdom’s transformation agenda,” he said.

    NCP was established in 2017. It serves as the central authority and catalyst for designing and implementing privatisation and PPP projects across the kingdom.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16236864/main.gif
    Yasir Iqbal
  • Parsons to project manage Al-Ittihad Sports Village in Jeddah

    2 April 2026

    US-based engineering firm Parsons Corporation has been awarded a contract by Saudi Arabia’s Al-Ittihad Club Company to act as project management consultant for the Al-Ittihad Sports Village in Jeddah.

    Under the contract, Parsons will support the project during the design stage.

    The sports village will be developed near King Abdullah Sports City and will include Al-Ittihad’s headquarters, academy training pitches and supporting facilities, performance development centres, administrative offices and a range of commercial components.

    The development is being designed in line with Fifa requirements and international best practices, with the aim of strengthening high-performance sports infrastructure in Saudi Arabia.

    The latest award follows Parsons’ recent appointment to a 60-month contract by the Public Investment Fund-backed New Murabba Development Company to provide design and construction technical support.

    As part of that role, Parsons will support the development of the project’s downtown area, which will span 14 million square metres of residential, workplace and entertainment space.

    In October last year, Parsons announced it had secured a SR210m ($56m) contract from Diriyah Company. Its scope includes the design and construction supervision of infrastructure works in phase two of the Diriyah project, covering streets, footpaths, open spaces, and civic buildings and facilities.

    In May last year, Parsons also confirmed its appointment as delivery partner for the airside and landside packages at King Salman International airport in Riyadh.

    In a statement, Parsons said it had signed two contracts with King Salman International Airport Development Company. The first covers airfield assets, including runways, taxiways, aircraft parking areas and air traffic control towers.

    The second contract relates to landside infrastructure, including roads, utilities, tunnels, bridges, rail networks and landscaping.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16233673/main.jpg
    Yasir Iqbal
  • Read the April 2026 MEED Business Review

    2 April 2026

    Download / Subscribe / 14-day trial access

    When the first missiles and drones were fired at the GCC on 28 February, the region’s economic story pivoted abruptly, from long-term vision-building to near-term resilience.

    The conflict is now the Gulf’s most consequential economic stress test in a generation. It is challenging the safe haven premium that underpins capital inflows, while disrupting the physical networks that keep the region’s economies running, from energy exports and shipping lanes to airports and tourism.

    MEED editor Colin Foreman asks whether the GCC can sustain investor confidence as energy assets, trade routes, airports and banks absorb the shock. Read more here.

    April’s market focus is on Saudi Arabia, where the Iran war is compounding the logic behind the kingdom’s strategic pivot in its investment plans.

    This edition also includes MEED’s 2026 GCC contractor ranking, in which Chinese firms have surged to the top as Saudi spending cuts and geopolitical risks weigh on GCC construction activity.

    In the latest issue, we explore the region’s evolving arbitration landscape; present exclusive leadership insight from Jacobs on the future of passenger rail in the Middle East; and talk to Leyla Abdimomunova, head of real estate and construction at the Public Investment Fund’s National Development Division, about remaking Saudi construction.

    We hope our valued subscribers enjoy the April 2026 issue of MEED Business Review

     

    Must-read sections in the April 2026 issue of MEED Business Review include:

    AGENDA: Gulf economies under fire

    INDUSTRY REPORT:
    GCC contractor ranking
    Construction guard undergoes a shift

    > LEGAL: Redefining the region’s arbitration landscape

    > QATAR LNG: Qatar’s new $8bn investment heats up global LNG race  

    > INTERVIEW: Leyla Abdimomunova, National Development Division, PIF

    > LEADERSHIP: Shaping the future of passenger rail in the Middle East 

    > SAUDI MARKET FOCUS
    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    MEED COMMENTS: 
    Iran war erodes LNG’s image of reliability

    Dubai's real estate faces a hard test
    Energy resilience matters as much as capacity
    Drawn-out conflict may shift planning priorities

    > GULF PROJECTS INDEX: Gulf index rises amid tensions

    > FEBRUARY 2025 CONTRACTS: Middle East contract awards

    > ECONOMIC DATA: Data drives regional projects

    > OPINIONThe end of the republic and the end of times

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16222272/main.gif
    MEED Editorial
  • Consultants submit bids for Al-Maktoum airport metro link

    2 April 2026

     

    French firm Egis has emerged as the lowest bidder for the design contract for the Route 2020 extension, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Egis submitted the lowest bid, priced at AED232.6m ($63.3m).

    The other bidders are:

    • Halcrow International (UK): $66.4m
    • Parsons (US): $71.3m
    • Aecom (US): $82.6m
    • Surbana Jurong (Singapore): $106m

    The extension to the line will run for about 3 kilometres (km) and will feature two stations.

    MEED understands that the invitation to bid was issued in January with a submission deadline of mid-March.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The Roads & Transport Authority (RTA) awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    Dubai’s plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to Al-Maktoum International airport. There are long-term plans for further extensions.

    Other metro projects

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The other metro lines in the pipeline are the Purple Line and the Pink Line, both of which are in the early stages of development.

    Firms are also bidding to update the emirate’s rail masterplan. In October 2025, MEED reported that 10 firms had submitted offers to undertake the project.

    The rail masterplan study will update and modify the RTA’s rail network, which includes the Dubai Metro and Dubai Tram. These plans will support Dubai’s 2040 urban masterplan, which aims for all residents to be within a 30-minute metro or light-rail trip to their place of work. 

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services as well as a high-speed rail connection.

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Al-Jaddaf, Al-Rashidiya and International City 1, as well as a station in Dubai Creek Harbour. By 2040, daily ridership on the Blue Line is projected to reach 320,000 passengers. It will be the first Dubai Metro line to cross Dubai Creek, doing so on a 1,300-metre viaduct.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16233295/main.jpg
    Yasir Iqbal
  • Chevron to drill two gas wells in Egypt before 2027

    2 April 2026

    Chevron is planning to drill two new gas wells this year, one in the Narges field and another in the Western Mediterranean, according to Clay Neff, the president of exploration operations at the company.

    The well in the Western Mediterranean area is due to be drilled in partnership with the London-headquartered oil and gas company Shell.

    Egypt and the broader East Mediterranean region will be core pillars of Chevron’s investment roadmap over the coming years, Neff said.

    He also said that the investments in Egypt reflected the Eastern Mediterranean’s growing strategic importance within Chevron’s global portfolio

    According to Neff, Chevron is aiming to increase its operational production capacity in the region by as much as 50% over the next five years, something that is expected to strengthen cash generation and enhance profitability from its regional operations.

    Chevron’s presence in Egypt dates back nearly nine decades, beginning in 1937 with the distribution of petroleum products before expanding into exploration and production activities in recent years.

    The company currently produces more than 2 billion cubic feet of gas a day across the Eastern Mediterranean.

    Chevron is advancing broader expansion initiatives in the Eastern Mediterranean region that include modernising existing facilities and increasing production capacity, alongside ongoing engineering and design work on the Aphrodite gas field in Cyprus.

    A recently signed government agreement enables the construction of a subsea pipeline connecting Cyprus directly to Egypt.

    Neff said the company is targeting an early final investment decision on the project next year, expressing confidence that close cooperation between Cairo and Nicosia will support timely progress.

    He emphasised that meeting domestic and regional energy demand remains the company’s top priority before directing additional supplies toward export markets in Europe or elsewhere.

    Neff said that Egypt’s well-developed energy infrastructure, particularly its pipeline network and liquefaction plants, provided a strategic edge, adding that new discoveries and capacity expansions will gradually support higher export volumes while safeguarding local supply needs.

    The comments from Neff come shortly after it was announced that the UK oil and gas company BP was making progress with its campaign to drill five wells in Egypt’s portion of the Mediterranean.

    BP’s Fayoum 4 well is scheduled to start production in July, with an estimated output of around 100 million cubic feet of gas a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16226687/main.jpg
    Wil Crisp