Jordan refinery project delay is major setback
20 June 2024
Vital oil and gas projects in Jordan are witnessing little to no progress in the absence of a stable and effective project finance structure required to support the sector’s growth.
Jordan imports more than 90% of its oil, gas and refined product needs and therefore has a strong economic case for developing projects to boost its domestic hydrocarbon infrastructure.
However, despite the government being willing to push through projects deemed essential for reducing reliance on energy imports, the lack of project financing options and inability to attract foreign investments into the energy industry has led to these projects stalling.
Delays to the fourth expansion phase of the Zarqa refinery complex, Jordan’s only oil refining asset, are a prime example of the sluggish environment in Jordan’s oil and gas sector.
Zarqa refinery expansion
Located in Zarqa governorate, roughly 35 kilometres east of the capital Amman, the refinery has a capacity of 60,000 barrels a day (b/d).
The refinery’s first expansion project was completed in 1970, when capacity was boosted to 2,100 tonnes a day. The second expansion was completed in 1973, and the third in 1982, when the refinery’s production was increased to 8,700 tonnes a day.
Jordan Petroleum Refinery Company (JPRC) aims to increase Zarqa’s refining potential by two and a half times to 150,000 b/d. The expansion is also planned to allow the Zarqa refinery to upgrade residual fuel oil into lighter products, in accordance with Euro 5 emission standards, to reduce reliance on imports.
JPRC has been working to double the Zarqa refinery’s production capacity since April 2017, when it signed two separate agreements with the US’ Honeywell UOP and KBR to facilitate the expansion project, but the project has been starting and stopping ever since.
Under the terms of the 2017 agreement, Honeywell UOP was to provide manager licensor services, technology licensing, front-end engineering and design (feed) consultancy services and basic engineering designs, as well as catalysts and process equipment, training and start-up services.
KBR was to license its proprietary slurry-phase hydrocracking technology for the project. KBR’s scope of work increased in November 2017 when it signed another agreement with JPRC for the basic engineering design of a residue hydroprocessor to be installed as part of the expansion.
In October 2017, Spain’s Tecnicas Reunidas was appointed feed consultant for the project. Feed work resumed in July 2018 after a temporary suspension, with KBR selected as the new process technology licensor. France-based Technip Energies is the project management consultant.
Prevailing situation
The situation around the Zarqa refinery’s fourth expansion turned positive last May when JPRC was reported to have selected contractors to execute engineering, procurement and construction (EPC) works on the project.
JPRC’s CEO, Abdul Karim Al-Alawin, told Jordan’s Arabic-language newspaper Alghad that the state-owned refiner had awarded the project’s main contract, but stopped short of revealing the winner.
MEED learned through sources that JPRC had selected a consortium of Italian contractor Tecnimont and China’s Sinopec Engineering to execute EPC works on the expansion project.
According to the sources, JPRC issued a notification in “early May” to all bidders competing for the project, informing them of the selection of Tecnimont/Sinopec Engineering for the project’s main contract.
However, the official EPC contract is yet to be awarded as JPRC continues to secure funding from international credit agencies and other lenders for the project, which is estimated to cost $2.64bn, according to Al-Alawin.
“There is no definite date for this. We are still in the negotiation process for funding. We cannot decide when these negotiations are completed,” the CEO told Alghad. As per the latest information gathered by MEED Projects, Tecnimont has pulled out of the project due to its uncertain future.
As one of Jordan’s most significant and vital projects, the Zarqa refinery is a bellwether for the health of the kingdom’s overall oil and gas sector – and based on how hamstrung this project has become, the prognosis is not good.
Exclusive from Meed
-
Firms seek to prequalify for Oman waste-to-energy project10 November 2025
-
WEBINAR: Saudi gigaprojects 2026 and beyond7 November 2025
-
Bahrain advances utility reform7 November 2025
-
Masdar and OMV sign 140MW green hydrogen plant deal7 November 2025
-
Syria signs deal for 5GW power projects7 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms seek to prequalify for Oman waste-to-energy project10 November 2025
Oman’s state offtaker Nama Power & Water Procurement (Nama PWP) has received 18 statements of qualification from international and local companies for the planned waste-to-energy (WTE) project in Barka, South Al-Batinah Governorate.
The project will be Oman’s first large-scale WTE facility, with a generation capacity of 95MW-100MW.
According to Nama PWP, the facility will be developed on a 190,000-square-metre site and is scheduled to reach commercial operation in the fourth quarter of 2030.
The project is expected to contribute 757 gigawatt-hours of renewable energy annually and reduce carbon dioxide emissions by about 302,000 tonnes a year.
It will process up to 3,000 tonnes of municipal solid waste a day using grate incineration technology.
The following companies submitted statements of qualifications:
- Acwa Power (Saudi Arabia)
- Al-Ramooz National (Oman)
- Al-Tasnim Enterprise (Oman)
- Aspec for Contracting & Environmental Consultancy (Oman)
- China Communications Construction (China)
- China Everbright Environment Group (China)
- China Tianying (China)
- Eco Vision (Oman)
- Emirates Waste to Energy (UAE)
- Eternal Industrial Investment (China)
- FCC Medioambiente Internacional (Spain)
- Future Vision Engineering Services (Oman)
- Horsol Switz Engineering Asia (Singapore)
- Hunan Junxin (China)
- Itochu Corporation (Japan)
- Kanadevia Inova (Switzerland)
- Keppel Seghers Engineering Co (Singapore)
- Mohammed Abdulmohsin Al-Kharafi & Sons (Kuwait)
- NV Besix (Belgium/UAE)
- Oman National Engineering & Investment (Oman)
- Paprec Group (France)
- Satarem America (US)
- Seven Seas Petroleum (Oman)
- Shanghai Environment Group (China)
- Shanghai SUS Environment (China)
- Shenzhen Energy Group (China)
- Sinoma Energy Conservation (China)
- Suez International SAS (France/Oman branch)
- Veolia Middle East (France)
- Urbaser (Spain)
In August, MEED reported that Oman had finally moved to the prequalification phase following attempts to start work on the project to develop a WTE facility for several years.
In 2019, when it was known as Oman Power & Water Procurement Company, Nama PWP is understood to have started the process to appoint consultants for the project, based on an independent power producer model.
It later put the project on hold, only to revive the prequalification and procurement process, along with Oman Environmental Services Holding Company (Beah), in 2023.
Beah will supply the waste feedstock for the project, which is part of a long-term plan to convert municipal waste into energy and reduce landfill dependency, supporting Oman’s net-zero emissions target for 2050.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15058075/main.jpg -
WEBINAR: Saudi gigaprojects 2026 and beyond7 November 2025
Webinar: Saudi Gigaprojects 2026 & Beyond
Tuesday 25 November 2025 | 11:00 GST | Register now
Agenda:
- Latest update to November 2025 on the gigaprojects programme and the Saudi projects market in general, with full data analysis for 2025 year-to-date
- Latest assessment on the reprioritisation of the programme and views on which of the gigaprojects are being prioritised
- Summary of key recent project developments and announcements
- Analysis of key contracts awarded this year to date
- Highlights of key contracts to be tendered and awarded over the next six months
- Key drivers and challenges going forward plus MEED’s outlook for the future short and long-term prospects of the gigaprojects programme
- In-depth look at the recently announced King Salman Gate gigaproject and other planned, but unannounced PIF developments
- Life beyond the gigaprojects – what other key project programmes are being implemented in the kingdom
- Q&A session
Hosted by: Edward James, head of content and analysis at MEED
A well-known and respected thought leader in Mena affairs, Edward James has been with MEED for more than 19 years, working as a researcher, consultant and content director. Today he heads up all content and research produced by the MEED group. His specific areas of expertise are construction, hydrocarbons, power and water, and the petrochemicals market. He is considered one of the world’s foremost experts on the Mena projects market. He is a regular guest commentator on Middle East issues for news channels such as the BBC, CNN and ABC News and is a regular speaker at events in the region. https://image.digitalinsightresearch.in/uploads/NewsArticle/15045990/main.gif -
Bahrain advances utility reform7 November 2025

In September, Bahrain’s government referred a draft law to parliament to restructure the kingdom’s electricity and water sector.
This proposes dissolving the Electricity & Water Authority (Ewa) and transferring its assets and functions to a newly established National Electricity & Water Company, which will operate under the oversight of the Electricity & Water Regulatory Authority.
The reform marks the first full structural overhaul of Bahrain’s utilities sector in nearly two decades and signals a shift towards a more commercially driven model.
Regulatory and operational roles would be separated for the first time, allowing private sector participation under transparent licensing and tariff systems, aligning Bahrain with utility reforms seen in Saudi Arabia, Oman and the UAE.
It comes amid a relatively subdued year for new contracts that broadly falls in line with 2024’s performance. Most significantly, Bahrain continues to move towards its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).
In August, a developer tender was issued for the main works package for the Sitra IWPP. This followed the prequalification of seven companies and consortiums, reflecting a wide range of international interest.
The planned Sitra IWPP replaces the previously planned Al-Dur 3 and will be the first IWPP project to be awarded since the 1,500MW Al-Dur 2 IWPP was completed in 2021.
The combined-cycle gas turbine (CCGT) plant is expected to have a production capacity of about 1,200MW of electricity, while the project’s seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. The main contract is expected to be awarded by the end of the year, with commercial operations set for 2029.
A developer tender was also recently launched for Bahrain’s first independent, standalone SWRO plant following a prequalification process that shortlisted nine companies and consortiums.
The Al-Hidd IWP is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028. It is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.
The imminent launch of the two projects boosts Bahrain’s projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic, carried by relatively small-scale projects.
Solar PV projects
The creation of the National Electricity & Water Company as Bahrain’s new operational entity could also support the rollout of future renewable energy schemes.
As a corporatised offtaker, the company will be able to enter long-term power purchase agreements (PPAs) with private developers under a more bankable framework. Currently, these are negotiated by Ewa on a case-by-case basis.
The government recently signed a 123MWp solar PPA with the UAE’s Yellow Door Energy, highlighting growing private sector interest in the market. The project includes the world’s largest single-site rooftop solar installation and will be developed at Foulath Holding’s industrial complex in Salman Industrial City.
Bahrain has already set a target to source 20% of its energy from renewables by 2035 and reach net-zero emissions by 2060.
In October, Ewa also issued a tender for the development of the Bilaj Al-Jazayer solar independent power project (IPP). The planned 100MW project will be developed on a build-own-operate basis with a 25-year contract term.
In parallel, Bahrain is broadening its long-term energy strategy beyond solar. In July, the kingdom signed a cooperation agreement with the US on the peaceful use of nuclear energy, aimed at advancing research and potential deployment of small modular reactor (SMR) technology.
For countries like Bahrain, which has limited land availability and high energy demand growth, SMRs could offer a way to produce low-carbon, reliable baseload power without requiring vast areas of land for solar or wind farms.
Officials have indicated that SMRs, along with floating solar solutions, are being studied as part of a broader push to diversify energy sources and expand renewable generation capacity.
Water and waste
Bids for four Ewa-owned projects are currently being evaluated. This includes the construction of a new SWRO desalination plant on Hawar Island and rehabilitation works for the Ras Abu Jarjur water treatment plant in Askar. Contracts for both projects are expected to be awarded this year.
Bahrain’s Ministry of Works (MoW) is the other client for the island-state’s power and water infrastructure-related projects. It has awarded three smaller sewage-related contracts this year.
It is also preparing to tender the construction of a $130m sewage treatment plant in Khalifa City, which will be developed in two phases. Meanwhile, the construction of MoW’s sewerage scheme phase 2 network in Bahrain remains in the early design stage with no further updates.
As Bahrain moves ahead with these projects, the new electricity and water law could define how future investments are structured, regulated and financed. This could reshape the kingdom’s utilities landscape for decades to come.
MEED's December special report on Bahrain also includes:
> ECONOMY: Bahrain’s cautious economic evolution
> BANKING: Mergers loom over Bahrain’s banking system
> OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
> CONSTRUCTION: Bahrain construction faces major slowdown
> TRANSPORT: Bahrain signs game-changer aviation deal with Air Asiahttps://image.digitalinsightresearch.in/uploads/NewsArticle/15044915/main.gif -
Masdar and OMV sign 140MW green hydrogen plant deal7 November 2025
Register for MEED’s 14-day trial access
Abu Dhabi Future Energy Company (Masdar) has signed a binding agreement with Austrian energy company OMV to develop and operate a major green hydrogen production plant in Austria.
The 140MW green hydrogen electrolyser plant will be Europe's fifth-largest hydrogen plant, according to Masdar chairman, Sultan Ahmed Al-Jaber.
It will be built in Bruck an der Leitha, about 40 kilometres southeast of Vienna.
The facility will be developed under a newly established joint venture, in which Masdar owns 49% and OMV holds the majority 51% stake.
The agreement was signed at the Abu Dhabi International Petroleum Exhibition and Conference (Adipec), in the presence of Al-Jaber; Austria’s Federal Minister of Economy, Energy and Tourism, Wolfgang Hattmannsdorfer; OMV CEO Alfred Stern; and Masdar CEO Mohamed Jameel Al-Ramahi.
It is expected that the project will reach financial close in early 2026, subject to final documentation, shareholder consent and regulatory approvals.
Construction began in September, with operations scheduled to start in 2027.
OMV, which already operates a 10MW electrolyser in Schwechat, will procure renewable electricity for hydrogen production and retain ownership of the output.
Several large-scale hydrogen facilities across Europe are currently under construction.
In 2024, Germany's Siemens Energy signed a deal with German utility EWE to build a 280MW green hydrogen electrolysis plant. This is expected to begin operations in 2027.
Masdar and OMV previously signed a letter of intent to cooperate on green hydrogen, synthetic sustainable aviation fuels (e-SAF) and synthetic chemicals in both the UAE and central and northern Europe.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15040802/main0933.jpg -
Syria signs deal for 5GW power projects7 November 2025
Register for MEED’s 14-day trial access
The Syrian Ministry of Energy has signed final concession agreements with an international consortium led by Qatar’s Urbacon (UCC) Holding to build and operate eight power plants with a total capacity of 5GW.
The consortium includes Urbacon Concessions Investment (a subsidiary of UCC Holding), Kalyon GIS Energy (Turkiye), Cengiz Energy (Turkiye) and Power International (US).
UCC Holding and Power International USA are both subsidiaries of Qatar’s Power International Holding. The US-based subsidiary was likely created to ease transactions and imports to Syria under the new General Licence 25 (GL 25) US sanctions exemptions for Syria.
The final contracts cover the construction and operation of the following four natural gas-fired combined-cycle plants:
- North Aleppo (1,200MW)
- Deir Ezzor (1,000MW)
- Zayzoun (1,000MW)
- Mehardeh (800MW)
It also includes four solar projects totalling 1,000MW across Widian Al-Rabee, Deir Ezzor, Aleppo and Homs.
The agreements were signed in Damascus by Energy Minister Mohammad Al-Bashir and UCC Holding president Ramez Al-Khayyat, in the presence of consortium representatives and senior Syrian energy officials.
The deal represents Syria’s first integrated public-private partnership model in the energy sector and marks the start of the implementation phase of Syria’s national energy rehabilitation programme.
The projects also form part of a wider Qatari investment package in Syria.
In May, the ministry signed a $7bn memorandum of understanding that set the framework for strategic energy cooperation.
Preparatory engineering and technical works, including site surveys and feasibility studies, have since been completed.
Completion is expected within three years for the gas plants and two years for the solar plants, with the projects doubling the country’s output.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15040717/main.jpg