Iraq electricity sector makes slow progress

9 May 2024

Latest news from Iraq's power and water sectors:

> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
Siemens Energy and SLB sign Iraq flare gas-to-power deal
PowerChina in talks for Basra desalination plant
US seeks firms for Baghdad power plant package
Iraq plans green hydrogen project at refinery
Iraq approves long-term grid expansion


 

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.

The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.

The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.

The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.

The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.

Supply and demand mismatch

There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.

In recent years, the deficit has returned during the winter when heating requirements rise.

With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.

Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.

The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.

The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.

For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.

Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.

Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.

The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.

Awarded projects

As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.

For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.

Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.

According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.

The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.

In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.

In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.

CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.

In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.

Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.

In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.

Future projects

In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.

Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”. 

In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.

It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.

A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.

As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.  

Going nuclear 

Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.  

In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.

According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.

IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.

Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11745270/main.gif
Jennifer Aguinaldo
Related Articles
  • Dubai prequalifies developers for $22bn tunnels PPP

    6 February 2025

    Dubai Municipality has prequalified developers for the first four packages of the $22bn Dubai Strategic Sewerage Tunnels (DSST) project.

    According to industry sources, at least three companies have been prequalified as lead members of potential consortiums that can bid for the contracts.

    These include:

    • Etihad Water & Electricity subsidiary (local)
    • Itochu (Japan)
    • Vision Invest (Saudi Arabia)

    Other companies have been prequalified as technical members. 

    MEED reported in October that over a dozen companies were keen to prequalify as investors or sponsors of the planned public-private partnership (PPP) project.

    They included:

    • Abrdn Investcorp Infrastructure Investments Manager (UK)
    • Besix (Belgium)
    • China Railway Construction Corporation (CRCC)
    • China Railway Engineering Group (CREG)
    • China State Construction Engineering Corporation (China)
    • Itochu (Japan)
    • Nesma Company (Saudi Arabia)
    • Plenary (Australia)
    • Samsung C&T (South Korea)
    • Vision Invest (Saudi Arabia)
    • Webuild (Italy)

    The request for proposals for the project's first two packages is expected to be issued imminently.

    MEED previously reported that the bidders for the PPP packages will be prequalified consortiums comprised of sponsors or investors, EPC contractors, and operations and maintenance contractors.

    The overall project will require a capital expenditure of about AED30bn ($8bn), while the whole-life cost over the full concession terms of the entire project is estimated to reach AED80bn.

    The investor prequalification process for the scheme comes after the client prequalified EPC contractors that can partner with the developers or investors to bid for the contracts.

    MEED understands that packages J1 and W will be tendered together as separate contracts first, followed by J2 and J3, with the requests for proposals to be issued sequentially, staggered about six to 12 months apart.

    DSST packages

    Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered as PPP packages with concession periods lasting between 25 and 35 years.

    The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres (km), and the links will extend 10km. 

    The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.

    The third package, W for Warsan, comprises 16km of tunnels, TPS and 46km of links.

    J3, the fourth package, comprises 129km of links.

    J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (TLT) components of the overall project.

    J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.

    J3 will be procured under a design-build-finance model with a concession period of 25-35 years. Once completed, Dubai Municipality will operate J3, unlike the first three packages, which are planned to be operated and maintained by the winning PPP contractors.  

    The project’s remaining two packages entail expanding and upgrading the Jebel Ali and Warsan sewage treatment plants. MEED understands that these packages will be procured at a later stage.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13370610/main.jpg
    Jennifer Aguinaldo
  • Iraq and GE Vernova complete plants upgrade

    6 February 2025

    US-headquartered energy technology provider GE Vernova has completed the upgrades of “several key” power plants in Iraq.

    The firm and the Iraqi Ministry of Electricity (MoE) announced the upgrade’s completion on 5 February.

    The overall upgrade project, which GE Vernova previously announced, covers 46 gas turbines across 12 power plants, adding up to 500MW to Iraq’s national grid before the summer of 2025.

    They did not specify which power plants have completed upgrade works.  

    According to GE, some of the power plants included in this project already transitioned from heavy fuel oil (HFO) to natural gas, with a capacity increase of approximately 260MW. These plants include Ninawa, Al-Diwaniyah, Hilla, Karbala, Shat Al-Basra, Najibiya, Samawa, Dhiqar, Al-Khairat and Al-Haidariya.

    GE Vernova added: “The other plants are expected to be modernised within the summer of 2025, with an expected additional increase in capacity of approximately 250MW.

    “This modernisation is expected to improve operational flexibility and boost output, efficiency and availability of the power generation assets.”

    In addition, the firm announced the successful installation of its Advanced Gas Path (AGP) upgrades on several 9. E gas turbines powering the Al-Quds and Dhiqar power plants, and MXLII upgrades on 13E2 gas turbines powering the Al-Mansouriya power plant.

    According to GE Vernova, the expected output increases of up to 6% for each power plant will enable the MoE to generate more electricity using the same amount of fuel.

    In addition, as part of the services and upgrade agreement announced in 2024 with the MoE to enhance the availability of power plants across the country, GE Vernova completed comprehensive maintenance projects across several of these power plants, corresponding to a total capacity of 3.7GW.

    These power plants include Qayyarah, Diwaniyah, Al-Haydariyah and Baghdad South. 

    Iraq periodically suffers from power outages, especially during the summer months, when increased cooling requirements overwhelm its power plants and electricity grid.  


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13370380/main.jpg
    Jennifer Aguinaldo
  • Bankability remains hydrogen’s unbreakable challenge

    6 February 2025

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    There is some indication that green hydrogen as an industry has arrived at the valley of disillusionment if the Gartner hype cycle is anything to go by.

    This is evident with the dwindling number of attendees and absence of offtakers – global commodity trading companies that are expected to buy premium green hydrogen and derivative products – at previously well-attended green hydrogen summits in major cities in the Gulf.

    Following frenzied announcements of multibillion-dollar integrated green hydrogen and ammonia plants in the Middle East and North Africa region, particularly Egypt, Morocco, Oman and the UAE, between 2021 and 2023, it appears that key stakeholders have started coming to grips with reality.

    Of the close to 80 green hydrogen projects that MEED and MEED Projects track, only three have so far signed an offtake agreement, and only one has managed to reach financial close.

    The $8.4bn Neom green hydrogen project in Saudi Arabia reached financial close in March 2023, nearly two years after it was announced.

    The project, the largest of its kind requiring over 4GW of renewable energy and 2GW of electrolyser capacity, managed to reach financial close based on one of the three co-developers, the US’ Air Products, assuming the full offtake and construction risks for the project, note some experts.

    A project’s bankability ultimately relies on suitable stakeholders taking on the risks for every aspect of the project, from construction to operations.

    Currently, the risks or threats include evolving global regulations related to consumption and carbon emissions pricing; lack of technology maturity; supply and demand uncertainty; and the lack of mainstream demand, according to Wael Almazeedi, chief executive at Abu Dhabi-based International Renewable Energy Certification (I-rec) certified firm Avance Energy.

    Almazeedi said these risks “need to be mitigated to the satisfaction of project lenders” if the planned green hydrogen projects in the region are to secure financing and reach the construction phase.

    The challenges do not necessarily mean all projects will fail, however.

    Similar to predecessors such as solar and electrification technologies, the hope is for the planned green hydrogen projects to eventually emerge out of the realm of disillusionment and reach the so-called enlightenment slope and, ultimately, plateaus of productivity, using Gartner’s hype cycle model.

    Government support in terms of regulatory frameworks, inevitably including some form of subsidies to bridge the so-called green premium, as well as global certification standards, are at the top of suppliers’ agendas. 

    Across the key aspiring Mena clean hydrogen hubs, like the UAE in particular, clearer regulatory frameworks have started to emerge, which could encourage more cohesive cooperation and enable projects to get off the ground.

    Key EU countries also appear to remain committed to clean and green hydrogen imports as part of the green deal, while at least one power plant in Japan has completed a three-month trial of co-firing green ammonia with coal “with positive results”.  

    But until all these come together to ensure an unencumbered global supply chain, offtakers and project financing deals will likely remain elusive. 

    Related reads:


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13370135/main.gif
    Jennifer Aguinaldo
  • Morocco explores salt caverns for hydrogen storage

    6 February 2025

     

    A feasibility study is under way for a project to explore underground salt cavern sites for green hydrogen storage in Morocco.

    According to Samir Rachidi, director-general at Iresen, the underground salt caverns are located near the capital Casablanca.

    “There is already an existing cavity used to store natural gas,” Rachidi told MEED.

    It is understood the same process or principle will be used to store green hydrogen in salt caverns.

    The potential storage capacity of the salt caverns for green hydrogen can only be determined once the feasibility study is completed.  

    Photo credit: Shutterstock

    Underground salt caverns offer an option for the bulk storage of very large amounts of gaseous hydrogen.

    According to Ireland-headquartered chemicals firm Linde, which operates the world’s first commercial hydrogen high-purity cavern in Texas, the gas has to be purified and compressed before it can be injected into a cavern.

    It added that hydrogen-filled cavities can act as a backup for a pipeline network.

    First green ammonia project

    Rachidi also said that Moroccan phosphate specialist OCP is in the advanced stages of studying a project to produce 1 million tonnes of green ammonia annually by 2027.

    The planned facility, which will cater to export markets, will include a 200,000 tonne-a-year (t/y) green hydrogen production plant and 4,000MW of renewable energy plants.

    It will also include an electrolyser plant with a capacity of 2,000MW.

    At least seven other green hydrogen or ammonia projects are under study or in the pre-front-end engineering and design stage in the North African state.

    In April 2023, a team led by China Energy International Construction Group signed a memorandum of cooperation to develop a green hydrogen project in a coastal area in southern Morocco.

    A year earlier, Serbia-headquartered renewables developer and investor CWP Global appointed US firm Bechtel to support the development of large-scale green hydrogen and ammonia facilities in Morocco and Mauritania.

    The Amun green hydrogen project, which CWP Global plans to develop in Morocco, is understood to require 15GW of renewable energy and has an estimated budget of between $18bn and $20bn.

    Morocco established a National Hydrogen Commission in 2019 and published a green hydrogen roadmap in 2021. 

    The roadmap entails the production of green hydrogen for local ammonia production and export between 2020 and 2030; the production and export of green hydrogen, green ammonia and synthetic fuels between 2030 and 2040; and the global trade of these products between 2040 and 2050.   

    Main photo: For illustrative purposes only (Adnoc)


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13369568/main.jpg
    Jennifer Aguinaldo
  • Qatar maintains stable growth heading

    6 February 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13369431/main.gif
    MEED Editorial