Hitachi Energy rides HVDC boom

12 November 2024

The GCC region’s strong drive to decarbonise electricity generation, distribution and consumption has led to an increased demand for renewable energy and electric mobility, which in turn require strong, secure and reliable grids.

“The key issue [among stakeholders] is how to stabilise the grid and maintain its resilience to ensure safety and security of supply,” Bruno Melles, global managing director for the Transformers Business Unit at Zurich-headquartered Hitachi Energy, tells MEED.

Options to address this issue include offshore and onshore interconnections, particularly through high-voltage direct current (HVDC) networks, as well as the deployment of battery energy storage systems.

HVDCs are broadly considered more environment-friendly compared to their alternating current predecessors by allowing electricity transmission over long distances with minimal losses.

Several HVDC networks are under construction across the GCC states. The region’s first subsea power transmission network in Abu Dhabi replaces existing offshore gas turbine generators catering to Adnoc’s offshore operations with more sustainable power sources available in Abu Dhabi’s onshore power network.

The Saudi-Egypt interconnection is also underway. Once completed, it will enable the daily exchange of up to 3,000MW of electricity, opening up potential energy trade between the GCC and other countries in the GulfAfrica and Europe.

Saudi Arabia also recently awarded a $5.3bn contract to interconnect its western, central and southern regions through an on-land HVDC network.

In addition, in May this year, Hitachi Energy signed agreements with Enowa, the utility arm of Saudi gigaproject developer Neom, to supply three HVDC transmission systems with a total capacity to transmit up to 9,000MW of electricity.

Discussions are under way for more of these types of projects, notes Melles, who says these projects reflect the need to integrate and secure the grid, particularly as more countries consider cross-border links and connecting their existing grids to remote renewable energy plants.

As interconnection investments grow, the need for digitalisation will also grow as utilities and transmission system operators seek more precise ways to manage their electrical loads and avoid waste.

Large users

The presence of industries with high power demands such as refining has been a distinguishing feature of most GCC states' power systems.

Most recently, the drive to deploy AI-based applications has spurred a boom in data centre construction particularly in the UAE and Saudi Arabia.

“We’re seeing plans to build data centres with load capacities of up to 1,000MW,” explains Melles, who points out that these facilities are fast becoming a major power utilisation point similar to other large industries.

The International Energy Agency estimates that data centres represent roughly 2% of global power consumption in 2022 and this is expected to more than double to 5% to 6%,  according to various projections.

An increase in the large power user base, even as electrification increases, reinforces the need for more resilient grids that can deal with varying loads and distances and energy sources, according to Melles.

Meeting demand

Globally, transmission and distribution infrastructure buildout is expected to catch up with prolific investments to expand generation capacity as power and decarbonisation demands increase.

Across the GCC, an estimated 49,000MW of conventional and renewable energy power generation plants are under construction as of October this year. The project pipeline remains robust, with key jurisdictions such as Saudi Arabia and Abu Dhabi aiming for renewable sources to meet up to 50% of their electricity demand by the end of the decade.

The GCC region’s power transmission and distribution sector is also set to experience its best year in terms of the value of awarded contracts. 

According to data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.

This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.

To meet demand, Hitachi Energy, which supplies solutions ranging from large transformers, communication networks, cooling systems and cybersecurity to cable accessories, recently launched a $1.5bn programme to boost its transformer production capacity between 2024 and 2027.

“We need to scale up capacity and availability, and we are committing with our parts suppliers… to be able to supply [transformers] to the industry,” explains Melles.

Hitachi Energy is also, more crucially, investing in human resources as it expands its production capacity and presence globally. "We are investing in people across all skill levels in our company not just in our factories… because we believe resource constraints will be more serious than steel or copper constraints."  

The executive notes that in addition to driving power demand, AI is a key development that suppliers like Hitachi Energy are following closely due to its potential to transform industries over time.

Current AI applications enable predictive maintenance and reliability, where they can analyse data from sensors and maintenance records to predict when equipment may fail.

The next stage, which Melles expects will cause widespread disruption, is when AI is applied to industrial process and engineering optimisation, which experts say may lead to increased efficiency, reduced resources and improved product quality, among others.

“AI offers a great opportunity if used properly,” the executive concludes.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12898322/main.jpg
Jennifer Aguinaldo
Related Articles
  • Local firm wins contract for Kuwait power project

    19 November 2025

    Local firm Alghanim International has won a contract to provide engineering services at the Subiya power and water distillation plant.

    Kuwait’s Central Agency for Public Tenders approved the award following a request from the Ministry of Electricity, Water & Renewable Energy.

    The contract, valued at $286m, covers engineering, supply, installation, operation and maintenance services to convert the 250MW second phase of the plant’s open-cycle gas turbines to combined-cycle gas turbines.

    The upgrade is intended to increase efficiency and provide additional generation capacity during periods of high demand.

    In July, MEED reported that Alghanim had submitted the lowest bid for the tender ahead of local firms Al-Daw Engineering General Trading & Contracting and Al-Zain United General Trading & Contracting.

    In 2024, US-based GE Vernova completed separate upgrades of four GE Vernova 9F.03 class gas turbines at the 2GW Sabiya combined-cycle power plant. Alghanim International acted as GE’s local engineering partner for that work.

    The Subiya power and water distillation plant is the largest power and water plant in Kuwait, with a power generation capacity of 7,046.7MW, accounting for 35% of the country’s installed capacity.

    It has a water desalination capacity of 100 million imperial gallons a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15116135/main.jpg
    Mark Dowdall
  • UKEF issues $3.5bn interest letter for Al-Maktoum airport

    19 November 2025

    Register for MEED’s 14-day trial access 

    The UK’s export credit agency UK Export Finance (UKEF) has issued a $3.5bn expression of interest letter to support the participation of UK businesses in the $35bn expansion of Al-Maktoum International airport, which is also known as Dubai World Central (DWC).

    Chris Bryant, UK minister for trade, handed the letter to Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), and Paul Griffiths, CEO of Dubai Airports.

    Letters of interest from UKEF, although not binding commitments, help ensure that UK exporters are given every opportunity to bid for contracts on a project. This is typically achieved by providing financial solutions in exchange for an agreed level of UK content used on the project.  

    Previous letter

    It is not the first time UKEF has issued a letter of interest for the expansion of Al-Maktoum International airport. In 2014, it issued a $2bn letter of interest. In a statement at the time, UKEF said five prime UK-based contractors were being supported, along with UK suppliers across the supply chain.

    The five prime contractors were Carillion, Kier, Balfour Beatty, Laing O’Rourke and Interserve. Of those five companies, Carillion entered liquidation in 2018 and Interserve entered administration in 2019. Balfour Beatty sold its shareholding in Dubai-based Dutco Balfour Beatty in 2017.

    Although some progress was made on the project after the UKEF offer in 2014, the scheme stalled and was revived again in April 2024, when Dubai approved new designs for the airport.

    Project progress

    Since then, the project client, DAEP, has been awarding and tendering contracts for the first construction packages. It has awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works for the terminal building are being undertaken by Abu Dhabi-based Tristar E&C.

    DAEP is also close to formally awarding a contract for the substructure works for the West Terminal and Concourse One, Concourse Two and Concourse Three.

    Tendering is also ongoing for an automated people-mover (APM) system. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. Construction works on the project’s first phase are expected to be completed by 2032.

    The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Dubai has said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.


    This aviation package also includes:

    > Middle East invests in giant airports
    > Broader region upgrades its airports
    > Global air travel shifts east

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115788/main.jpg
    Colin Foreman
  • Riyadh gives Expo infrastructure bidders more time

    19 November 2025

     

    Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has extended the deadline for firms to submit commercial offers for the contract to undertake the initial infrastructure works at the site to 23 November.

    ERC had initially set deadlines of 26 October and 9 November for the submission of technical and commercial bids, respectively.

    The tender for the project’s initial infrastructure works was issued in September, as MEED reported.

    In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.

    The firms invited to bid include:

    • Shibh Al-Jazira Contracting (local)
    • Hassan Allam Construction (Egypt)
    • El-Seif Engineering Contracting (local)
    • Al-Ayuni Investment & Contracting (local)
    • Kolin Construction (Turkiye)
    • Al-Yamama Trading & Contracting Company (local)
    • Saudi Pan Kingdom (local)
    • Unimac (local)
    • Mapa Insaat (Turkiye)
    • Yuksel Insaat (Turkiye)
    • IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
    • Mota-Engil / Albawani (Portugal/local)
    • Almabani / FCC Construction (local/Spain)

    The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:

    • Lot 1 covers the main utilities corridor
    • Lot 2 includes the northern cluster of the nature corridor
    • Lot 3 comprises the southern cluster of the nature corridor

    MEED previously reported that ERC was expected to issue the tender for some of the infrastructure packages in September.

    In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.

    Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.

    The expo is forecast to attract more than 40 million visitors.

    The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.

    In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115697/main.jpg
    Yasir Iqbal
  • NHC and Turkish firm sign $266m investment deal

    19 November 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s National Housing Company (NHC) has signed an investment agreement worth over SR1bn ($266m) with Turkiye’s Emlak Konut to develop new residential communities within the Mecca Gate project in Mecca.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Emlak Konut will develop 1,000 residential villas spanning over 255,000 square metres (sq m).

    The latest agreement follows the NHC’s signing of deals worth over SR8.5bn ($2.2bn) for the development of two mixed-use and residential communities in Riyadh.

    The first agreement, worth over SR5.2bn ($1.4bn), was signed with local developer Retal Urban Development Company.

    The deal encompasses the development of 4,839 residential units in the Al-Fursan suburb of Riyadh.

    The other contract, worth over SR3.3bn ($880m), was signed with a joint venture of Egypt’s Hassan Allam Holding and local developer Tilal Real Estate for a mixed-use project in the Khozam district.

    The development will cover an area of over 228,000 sq m.

    It will be delivered through Grova Developments, the development arm of Hassan Allam Holding.

    In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.

    Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers. 

    MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.

    By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115626/main.png
    Yasir Iqbal
  • Egypt announces oil discovery in Western Desert

    19 November 2025

    Register for MEED’s 14-day trial access 

    A new gas discovery has been made in Egypt’s Western Desert region, according to a statement released by the Ministry of Petroleum & Mineral Resources.

    The discovery was made by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation (EGPC) and US-headquartered Apache Corporation.

    The field is expected to be brought online this week, according to the ministry.

    The reserves were discovered after drilling the exploratory well ‘Gomana-1’, the ministry said.

    It added that sensors confirmed the presence of gas reserves, and tests indicated that the well is expected to have a production rate of around 36 million standard cubic feet of gas a day.

    Further tests are ongoing, and the initial evaluation of the well’s reserves is currently being finalised.

    The ministry said that the discovery followed the introduction of new incentives designed to encourage additional gas investment within Khalda’s areas of operation.

    Earlier this month, Egypt started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.

    The country is currently pushing to increase domestic gas production in order to meet domestic demand and reduce its import bill.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15112551/main.png
    Wil Crisp