Hitachi Energy rides HVDC boom
12 November 2024
The GCC region’s strong drive to decarbonise electricity generation, distribution and consumption has led to an increased demand for renewable energy and electric mobility, which in turn require strong, secure and reliable grids.
“The key issue [among stakeholders] is how to stabilise the grid and maintain its resilience to ensure safety and security of supply,” Bruno Melles, global managing director for the Transformers Business Unit at Zurich-headquartered Hitachi Energy, tells MEED.
Options to address this issue include offshore and onshore interconnections, particularly through high-voltage direct current (HVDC) networks, as well as the deployment of battery energy storage systems.
HVDCs are broadly considered more environment-friendly compared to their alternating current predecessors by allowing electricity transmission over long distances with minimal losses.
Several HVDC networks are under construction across the GCC states. The region’s first subsea power transmission network in Abu Dhabi replaces existing offshore gas turbine generators catering to Adnoc’s offshore operations with more sustainable power sources available in Abu Dhabi’s onshore power network.
The Saudi-Egypt interconnection is also underway. Once completed, it will enable the daily exchange of up to 3,000MW of electricity, opening up potential energy trade between the GCC and other countries in the Gulf, Africa and Europe.
Saudi Arabia also recently awarded a $5.3bn contract to interconnect its western, central and southern regions through an on-land HVDC network.
In addition, in May this year, Hitachi Energy signed agreements with Enowa, the utility arm of Saudi gigaproject developer Neom, to supply three HVDC transmission systems with a total capacity to transmit up to 9,000MW of electricity.
Discussions are under way for more of these types of projects, notes Melles, who says these projects reflect the need to integrate and secure the grid, particularly as more countries consider cross-border links and connecting their existing grids to remote renewable energy plants.
As interconnection investments grow, the need for digitalisation will also grow as utilities and transmission system operators seek more precise ways to manage their electrical loads and avoid waste.
Large users
The presence of industries with high power demands such as refining has been a distinguishing feature of most GCC states' power systems.
Most recently, the drive to deploy AI-based applications has spurred a boom in data centre construction particularly in the UAE and Saudi Arabia.
“We’re seeing plans to build data centres with load capacities of up to 1,000MW,” explains Melles, who points out that these facilities are fast becoming a major power utilisation point similar to other large industries.
The International Energy Agency estimates that data centres represent roughly 2% of global power consumption in 2022 and this is expected to more than double to 5% to 6%, according to various projections.
An increase in the large power user base, even as electrification increases, reinforces the need for more resilient grids that can deal with varying loads and distances and energy sources, according to Melles.
Meeting demand
Globally, transmission and distribution infrastructure buildout is expected to catch up with prolific investments to expand generation capacity as power and decarbonisation demands increase.
Across the GCC, an estimated 49,000MW of conventional and renewable energy power generation plants are under construction as of October this year. The project pipeline remains robust, with key jurisdictions such as Saudi Arabia and Abu Dhabi aiming for renewable sources to meet up to 50% of their electricity demand by the end of the decade.
The GCC region’s power transmission and distribution sector is also set to experience its best year in terms of the value of awarded contracts.
According to data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.
This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.
To meet demand, Hitachi Energy, which supplies solutions ranging from large transformers, communication networks, cooling systems and cybersecurity to cable accessories, recently launched a $1.5bn programme to boost its transformer production capacity between 2024 and 2027.
“We need to scale up capacity and availability, and we are committing with our parts suppliers… to be able to supply [transformers] to the industry,” explains Melles.
Hitachi Energy is also, more crucially, investing in human resources as it expands its production capacity and presence globally. "We are investing in people across all skill levels in our company not just in our factories… because we believe resource constraints will be more serious than steel or copper constraints."
The executive notes that in addition to driving power demand, AI is a key development that suppliers like Hitachi Energy are following closely due to its potential to transform industries over time.
Current AI applications enable predictive maintenance and reliability, where they can analyse data from sensors and maintenance records to predict when equipment may fail.
The next stage, which Melles expects will cause widespread disruption, is when AI is applied to industrial process and engineering optimisation, which experts say may lead to increased efficiency, reduced resources and improved product quality, among others.
“AI offers a great opportunity if used properly,” the executive concludes.
Exclusive from Meed
-
-
-
-
-
Firms submit Jeddah distribution centre bids4 May 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Parsons wins role on Elon Musk-backed Dubai Loop project4 May 2026
US-based Parsons Corporation has been appointed to deliver programme management services for the Dubai Loop transportation system.
The contract was awarded by Elon Musk-backed firm The Boring Company, which signed a construction agreement with Dubai’s Roads & Transport Authority (RTA) in February.
Parsons’ scope of work includes independent design verification, stakeholder management, permitting and no-objection certificate (NOC) support, and multidisciplinary design reviews for the project’s first phase.
The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.
Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.
The first phase is expected to cost about AED565m ($154m) and to be delivered within one year after design work and other preparations are completed. Tunnelling is expected to begin in the second half of this year.
Next phase
The second phase will connect Dubai World Trade Centre and DIFC with Business Bay.
The tunnels will extend up to 22km and include 19 stations.
The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.
The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.
The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.
The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.
The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16672074/main.jpg -
Humain tenders infrastructure for 6GW data centre campus4 May 2026
Saudi artificial intelligence (AI) infrastructure company Humain, owned by the Public Investment Fund (PIF), has issued a tender inviting firms to develop infrastructure for its planned 6GW hyperscale AI data centre campus in Riyadh.
The project will be delivered on an early contractor involvement (ECI) basis. Under the ECI process, selected contractors are required to submit methodologies and design proposals, after which one team will be selected to deliver the construction works.
Firms have until 8 May to submit proposals.
The development will be built on a 24-square-kilometre site in the Al-Saad area in east Riyadh. It will be delivered in two phases across six plots, each with a capacity of 1GW.
The scope of infrastructure work covers:
- Construction of 380kV/132kV/33kV electrical distribution network, two substations with a capacity of 500MVA and 200MVA, bulk supply point (2,000MVA)
- Water network and fire protection systems
- Sewage treatment plant and wastewater network
- Stormwater systems
- Roads
- Underground cable and fibre optic networks
- Landscaping works
The client is being supported by Canadian engineering firm Hatch, France’s Egis and US-based firm JLL.
Humain was launched in May last year to operate and invest across the AI value chain.
Humain is building full-stack AI capabilities across four core areas: next-generation data centres, hyper-performance infrastructure and cloud platforms, and advanced AI models, including Allam.
Also in May 2025, Humain signed preliminary deals with US chipmakers AMD and Nvidia to build multibillion-dollar advanced digital infrastructure in the kingdom.
AMD said it will invest up to $10bn to deploy 500MW of AI compute capacity in Saudi Arabia over the next five years.
In October, PIF and Saudi Aramco signed a non-binding term sheet setting out key terms under which Aramco would acquire a minority stake in Humain, with PIF retaining majority ownership.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16671267/main.jpg -
Abu Dhabi selects consortium for 2.5GW Taweelah C IPP4 May 2026

Register for MEED’s 14-day trial access
A consortium of Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore) has been selected to develop the Taweelah C independent power producer (IPP) project in Abu Dhabi.
The consortium will sign a power purchase agreement (PPA) in mid-May, a source told MEED.
The combined-cycle gas turbine (CCGT) plant will have a capacity of 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.
It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction (EPC) contractor.
Last September, MEED reported that state offtaker Emirates Water & Electricity Company (Ewec) had received three bids for the facility.
The bidders included:
- Al-Jomaih Energy & Water Company / Sembcorp Industries
- Sumitomo Corporation (Japan) / Korea Overseas Infrastructure & Urban Development Corporation / Korean Midland Power
- Korea Western Power Company / Etihad Water & Electricity (UAE) / Kyuden International (Japan)
At the time, Mohamed Al-Marzooqi, chief asset development and management officer at Ewec, said the bids would make Taweelah C “one of the lowest tariff CCGT projects in the region”.
The carbon-capture-ready facility had been scheduled to begin commercial operations in the fourth quarter of 2028.
This was based on the initial timeline for a PPA to be signed in the fourth quarter of 2025.
Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.
Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared to 2019.
Ewec is also expanding its low-carbon water desalination capacity, with the Taweelah reverse osmosis (RO) plant already operating as the world’s largest RO facility and additional projects, such as the Mirfa 2 RO and Shuweihat 4 RO, under way.
By 2030, it expects 95% of Abu Dhabi’s installed water capacity to come from RO technology.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16670622/main0858.jpg -
Dubai launches Blue Line metro tunnelling works4 May 2026
Dubai has announced the launch of tunnelling works for the Dubai Metro Blue Line extension project.
In a post on X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President, Prime Minister and Ruler of Dubai, announced the start of operations of the tunnel boring machine (TBM), which the Roads & Transport Authority (RTA) has named ‘Al-Wugeisha’.
The TBM is 163 metres long, weighs more than 2,000 tonnes and will operate around the clock. The post added that its average excavation rate ranges from 13 to 17 metres a day.
The Blue Line will connect the existing Red and Green lines. It will be 30 kilometres (km) long, with 15.5km underground and 14.5km above ground.
The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.
In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project to a consortium comprising Turkiye’s Limak Holding and Mapa Group, along with the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).
The consortium is responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, it will assist with maintenance and operations for an initial three-year period.
According to an official statement, the Blue Line will have a capacity of 46,000 passengers an hour in both directions.
The project is scheduled for completion in September 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16670584/main.jpeg -
Firms submit Jeddah distribution centre bids4 May 2026

Contractors submitted bids on 26 April for an estimated SR140m ($37m) contract to build a distribution centre in Jeddah.
Saudi Logistics Services Company (SAL) launched the tender on 11 March, as previously reported by MEED. The project will cover an area of about 37,000 square metres. Egyptian firm Cosmos-E Engineers & Consultants has been appointed as the project consultant.
This tender follows the start of construction by Egyptian contractor Rowad Modern Engineering, a subsidiary of Elsewedy Electric Group, on the expansion of SAL’s facilities at King Khalid International airport in Riyadh. The scope of work includes rehabilitating and upgrading existing infrastructure, as well as constructing new supporting facilities and services.
SAL also launched the tendering process in September last year for its SR4.2bn ($1bn) logistics zone in northern Riyadh, MEED previously reported. UAE-based Global Engineering Consultants is the consultant for that development.
The logistics hub aims to meet demand for customised warehouses near King Khalid International airport and the Riyadh Metro. The project aligns with Vision 2030 and the National Transport & Logistics Strategy, which aims to strengthen the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16670338/main.gif
.gif)
