Hitachi Energy rides HVDC boom

12 November 2024

The GCC region’s strong drive to decarbonise electricity generation, distribution and consumption has led to an increased demand for renewable energy and electric mobility, which in turn require strong, secure and reliable grids.

“The key issue [among stakeholders] is how to stabilise the grid and maintain its resilience to ensure safety and security of supply,” Bruno Melles, global managing director for the Transformers Business Unit at Zurich-headquartered Hitachi Energy, tells MEED.

Options to address this issue include offshore and onshore interconnections, particularly through high-voltage direct current (HVDC) networks, as well as the deployment of battery energy storage systems.

HVDCs are broadly considered more environment-friendly compared to their alternating current predecessors by allowing electricity transmission over long distances with minimal losses.

Several HVDC networks are under construction across the GCC states. The region’s first subsea power transmission network in Abu Dhabi replaces existing offshore gas turbine generators catering to Adnoc’s offshore operations with more sustainable power sources available in Abu Dhabi’s onshore power network.

The Saudi-Egypt interconnection is also underway. Once completed, it will enable the daily exchange of up to 3,000MW of electricity, opening up potential energy trade between the GCC and other countries in the GulfAfrica and Europe.

Saudi Arabia also recently awarded a $5.3bn contract to interconnect its western, central and southern regions through an on-land HVDC network.

In addition, in May this year, Hitachi Energy signed agreements with Enowa, the utility arm of Saudi gigaproject developer Neom, to supply three HVDC transmission systems with a total capacity to transmit up to 9,000MW of electricity.

Discussions are under way for more of these types of projects, notes Melles, who says these projects reflect the need to integrate and secure the grid, particularly as more countries consider cross-border links and connecting their existing grids to remote renewable energy plants.

As interconnection investments grow, the need for digitalisation will also grow as utilities and transmission system operators seek more precise ways to manage their electrical loads and avoid waste.

Large users

The presence of industries with high power demands such as refining has been a distinguishing feature of most GCC states' power systems.

Most recently, the drive to deploy AI-based applications has spurred a boom in data centre construction particularly in the UAE and Saudi Arabia.

“We’re seeing plans to build data centres with load capacities of up to 1,000MW,” explains Melles, who points out that these facilities are fast becoming a major power utilisation point similar to other large industries.

The International Energy Agency estimates that data centres represent roughly 2% of global power consumption in 2022 and this is expected to more than double to 5% to 6%,  according to various projections.

An increase in the large power user base, even as electrification increases, reinforces the need for more resilient grids that can deal with varying loads and distances and energy sources, according to Melles.

Meeting demand

Globally, transmission and distribution infrastructure buildout is expected to catch up with prolific investments to expand generation capacity as power and decarbonisation demands increase.

Across the GCC, an estimated 49,000MW of conventional and renewable energy power generation plants are under construction as of October this year. The project pipeline remains robust, with key jurisdictions such as Saudi Arabia and Abu Dhabi aiming for renewable sources to meet up to 50% of their electricity demand by the end of the decade.

The GCC region’s power transmission and distribution sector is also set to experience its best year in terms of the value of awarded contracts. 

According to data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.

This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.

To meet demand, Hitachi Energy, which supplies solutions ranging from large transformers, communication networks, cooling systems and cybersecurity to cable accessories, recently launched a $1.5bn programme to boost its transformer production capacity between 2024 and 2027.

“We need to scale up capacity and availability, and we are committing with our parts suppliers… to be able to supply [transformers] to the industry,” explains Melles.

Hitachi Energy is also, more crucially, investing in human resources as it expands its production capacity and presence globally. "We are investing in people across all skill levels in our company not just in our factories… because we believe resource constraints will be more serious than steel or copper constraints."  

The executive notes that in addition to driving power demand, AI is a key development that suppliers like Hitachi Energy are following closely due to its potential to transform industries over time.

Current AI applications enable predictive maintenance and reliability, where they can analyse data from sensors and maintenance records to predict when equipment may fail.

The next stage, which Melles expects will cause widespread disruption, is when AI is applied to industrial process and engineering optimisation, which experts say may lead to increased efficiency, reduced resources and improved product quality, among others.

“AI offers a great opportunity if used properly,” the executive concludes.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12898322/main.jpg
Jennifer Aguinaldo
Related Articles
  • Managing risk in the GCC construction market

    19 December 2025

     

    The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.

    Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.

    MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.

    The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.

    Systemic risk

    The regional market is characterised by several systemic issues that amplify risks for contractors. 

    The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.

    Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.

    Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:

    > Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.

    > Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.

    > Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.


    Supply-chain erosion

    The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly. 

    Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.

    The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.

    Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.

    The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is. 

    A 10-point checklist for contractors in 2026

    1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.

    2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.

    3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.

    4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.

    5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.

    6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.

    7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.

    8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.

    9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.

    10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need.  Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site.

    MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:

    Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com

    Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com

    Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com

    Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com

    IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com

    White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif
    Colin Foreman
  • Diriyah signs land lease deal with King Saud University

    19 December 2025

    Saudi Arabia gigaproject developer, Diriyah Company, has signed a long-term land lease agreement with Riyadh Valley Company, an investment arm of King Saud University.

    Diriyah Company will lease 552,000 square metres (sq m) of land from King Saud University for a period of 70 years. 

    The deal will enable the company to add the land bank to its second phase of the Diriyah Project, which is also known as DG2.

    The agreement was signed by Diriyah Company's Group CEO, Jerry Inzerillo, and the acting president of King Saud University and Riyadh Valley Company chairman, Ali Masmali.

    Diriyah Company is already developing the area adjacent to King Saud University. In April, it awarded an estimated SR4bn ($1.1bn) contract for a utilities relocation package for the King Saud University project located in the second phase of the Diriyah Gate development (DG2).

    The contract was awarded to the joint venture of Beijing-headquartered China Railway Construction Corporation and China Railway Construction Group Central Plain Construction Company.

    The scope of the contract covers the design, construction and relocation of KSU's utilities and administration offices, as well as the construction of a district cooling plant, water storage facilities, a sewage treatment plant, a natural gas plant, a diesel transfer pumping station, a utility tunnel, irrigation water storage tanks, office buildings, warehouses and maintenance workshops.

    In addition to KSU, DG2 will feature residential developments, hotels, an opera house, the Saudi Museum of Contemporary Art, six academies, an arena and a mosque.

    The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh’s city centre, it will cover 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287776/main.jpg
    Yasir Iqbal
  • Kuwait to sign Mubarak port agreement next week

    19 December 2025

    Kuwait and China are expected to sign the agreement to develop the subsequent phases of Kuwait’s Grand Mubarak Port next week.

    According to media reports, the announcement was made by Kuwait’s Public Works Minister ​Noura Al-Mashaan on Thursday.

    The contract value is estimated to be about KD1.2bn ($4bn).

    In May, Beijing-headquartered China Harbour Engineering Company, a subsidiary of China Communications Construction Company (CCCC), signed an early contractor involvement (ECI) agreement with Kuwait to develop the next phases of the project.

    The initial works include surveying, investigation, hydrological observation, geophysical exploration, testing, model testing, process simulation, design review, owner inspection, preliminary design of sand-retaining embankments, and on-site services and management.

    The project launch ceremony was held in mid-April. It was attended by several high-profile representatives from Kuwait and China, including Fu Xuyin, China’s vice-minister of the Ministry of Transport, Zhang Jianwei, the Chinese ambassador to Kuwait, and Nora Mohammad Al-Mashaan, Kuwait’s minister of public works.

    In January, MEED reported that Kuwait’s cabinet had approved a bid from China Communications Construction Company to implement all stages of its Mubarak Al-Kabeer Port project.

    The country ramped up its efforts on the project after meetings between Kuwaiti and Chinese officials in June last year.

    In 2023, the two countries signed a memorandum of understanding to develop port infrastructure.

    Phase one of the project cost $1.2bn and was completed in 2014.

    The project’s first phase included site levelling and the development of a marina, quay walls, berths, a navigational terminal and port buildings.

    The port is not operational because the phase one works did not include vital equipment such as cranes.

    It is understood that the completion of phase two will allow the port to start operations.

    The full scope for phase two of the project is expected to include:

    • Construction of loading and unloading facilities
    • Construction of quay walls and reclamation
    • Construction of the container yard and the back of the port
    • Infrastructure works
    • Construction of buildings
    • Construction of a container terminal
    • Construction of associated facilities
    • Installation of safety and security systems

    A third phase is also planned to further expand the port.

    The latest developments follow a series of agreements signed in September 2023 to deliver some of Kuwait’s immediate development goals for 2024-28. These agreements will position Chinese companies to play a leading role in the Fourth Kuwait Master Plan 2040.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287252/main.jpg
    Yasir Iqbal
  • Metito consortium wins Mecca sewage scheme

    19 December 2025

    A team comprising Metito (UAE), Etihad Water & Electricity Company (UAE) and SkyBridge Company (UK) has been awarded a contract to develop the Hadda independent sewage treatment plant (ISTP) project in Mecca Province, Saudi Arabia.

    The contract was awarded by Saudi Water Partnership Company (SWPC), the kingdom’s principal off-taker for water and wastewater public-private partnership (PPP) projects.

    The project will be developed on a build-own-operate-transfer basis and is expected to begin operations in 2028, followed by a 25-year operating term.

    The plant will provide an initial treatment capacity of 100,000 cubic metres a day and will feature a treated sewage effluent (TSE) reuse system with a storage tank and a 38-kilometre pipeline designed to handle 350,000 cubic metres a day.

    Earlier in December, MEED reported that the team had been named preferred bidder at a levelised tariff of SR2.354 ($0.63) a cubic metre.

    SWPC selected the Miahona-led consortium as the reserve bidder for this project with the second-lowest submitted bid of SR2.599($0.69) a cubic metre.

    According to SWPC, the TSE reuse system accounted for 31% of the preferred tariff for the Arana ISTP and 27% for the Hadda ISTP.

    In March last year, SWPC signed a 25-year water-purchase agreement with a team comprising the local Miahona Company and Belgium-based Besix for the contract to develop and operate the Al-Haer ISTP in Riyadh, as part of the third batch of the kingdom’s ISTP programme.

    Four months later, the Saudi-listed Power & Water Utility Company for Jubail & Yanbu (Marafiq) joined the developer consortium.

    The Miahona/Besix team offered to develop the project for SR1.9407 ($0.5173) a cubic metre, while the second-lowest bid, from a team comprising Spain’s Acciona and the local Tawzea, was SR2.2041($0.588) a cubic metre.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287185/main.jpg
    Yasir Iqbal
  • Morocco awards $1bn Casablanca airport terminal deal

    19 December 2025

    Morocco’s National Airports Office (ONDA) has awarded a MD12bn ($1.2bn) contract to build the new terminal at Casablanca’s Mohammed V International airport.

    The contract was awarded to the joint venture of local firms Societe Generale des Travaux du Maroc (SGTM) and Travaux Generaux de Construction de Casablanca (TGCC).

    Construction work on the Mohammed V International airport expansion is expected to begin immediately.

    The project is slated for completion in 2029.

    The expansion will cover more than 600,000 square metres (sq m) and increase the airport’s capacity to 30 million passengers a year.

    The project is designed by a consortium comprising the local branch of French engineering firm Egis Batiment International, Morocco’s Ala Concept and UK-based RSHP Architects.

    The scope of work covers preparatory works, structural works, waterproofing, steel structural works, building facades, electrical, mechanical and plumbing (MEP) works, data centre works, HVAC systems and other associated works.

    The tender also covers the construction of a 300-key airside hotel.

    The new terminal is expected to be ready in time for the 2030 Fifa World Cup, which Morocco is co-hosting alongside Portugal and Spain.

    ONDA tendered the project contract on 4 November, with a bid submission deadline of 16 December, as MEED reported.

    In July, ONDA began early works on the new terminal building, awarding an estimated MD294m ($29m) deal for enabling works to local firm Societe de Travaux Agricoles Marocaine.

    In January, Morocco’s Transport & Logistics Minister, Abdessamad Kayouh, said that the study to expand the airport’s capacity was nearing completion.

    The project is part of Morocco’s MD42bn ($4.3bn) plan to expand key airports in anticipation of increased passenger flow for the 2030 football World Cup.

    Morocco plans to upgrade several airports, including those in Tangier, Marrakech and Agadir, increasing their respective annual passenger capacities to 7 million, 16 million and 7 million.

    There are also plans to add a new terminal at Rabat-Sale airport, raising its capacity to 4 million passengers annually, and to increase Fez airport’s capacity to 5 million passengers annually. 

    The new terminal at Mohammed V International airport will be connected to a high-speed train network linking Kenitra to Marrakech.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15287093/main.jpg
    Yasir Iqbal