Firms submit King Salman airport terminal prequalification
11 February 2025

Register for MEED’s 14-day trial access
King Salman International Airport Development Company (KSIADC), which is backed by Saudi Arabia’s Public Investment Fund, received prequalification statements from firms on 28 January for a contract to develop the first phase of Terminal 6 and the Iconic Terminal of King Salman International airport (KSIA) in Riyadh.
The client plans to deliver the package on an early contractor involvement (ECI) basis.
The ECI process requires selected contractors to submit methodologies for the project and a design proposal.
The client prequalified firms in September 2024 for the main engineering, procurement and construction (EPC) packages; early and enabling works; specialist systems and integration; specialist systems, materials and equipment; engineering and design; professional services; health, safety, security, environment and wellbeing services; modular installation and prefabrication; local content; environmental, social and governance (ESG); and other services.
The entire scheme is divided into eight assets. These include:
- Iconic Terminal
- Terminal 6
- Private aviation terminal
- Central runway and temporary apron
- Hangars
- Landside transport
- Cargo buildings
- Real estate
In August last year, KSIADC confirmed that it had signed up several architectural and design firms for the various elements of the project.
KSIADC said that UK-based Foster + Partners will design the airport’s masterplan, including the terminals, six runways and a multi-asset real estate area.
US-based engineering firm Jacobs will provide specialist consultancy services for the masterplan and the design of the new runways.
The client also confirmed the appointment of UK-based engineering firm Mace for the delivery partner role on the project.
The airspace design consultancy contract was awarded to local firm Nera.
Project scale
The project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.
If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity, according to GlobalData.
The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. The goal for cargo is to process 3.5 million tonnes a year by 2050.
Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation (Gaca), envisages tripling Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.
It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.
READ THE FEBRUARY MEED BUSINESS REVIEW
Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.
Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:
|
> AGENDA 1: Trump 2.0 targets technology
> AGENDA 2: Trump’s new trial in the Middle East
> AGENDA 3: Unlocking AI’s carbon conundrum
> GAZA: Gaza ceasefire goes into effect
> LEBANON: New Lebanese PM raises political hopes
> WATER DEVELOPERS: Acwa Power improves lead as IWP contract awards slow
> WATER & WASTEWATER: Water projects require innovation
> INTERVIEW: Omran’s tourism strategies help deliver Oman 2040
> PROJECTS RECORD: 2024 breaks all project records
> REAL ESTATE: Ras Al-Khaimah’s robust real estate boom continues
> QATAR: Doha works to reclaim spotlight
> GULF PROJECTS INDEX: Gulf projects market enters 2025 in state of growth
> CONTRACT AWARDS: Monthly haul cements record-breaking total for 2024
> ECONOMIC DATA: Data drives regional projects
> OPINION: Between the extremes as spring approaches
|
Exclusive from Meed
-
-
Aldar launches Yas Island community park project30 June 2026
-
-
Eni increases gas production in Libya30 June 2026
-
Jordan faces fresh round of challenges29 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese firm wins Qiddiya Janadriyah cultural district hotels30 June 2026

Beijing-headquartered China State Construction Engineering Corporation (CSCEC) has won a contract to deliver the Janadriyah cultural district at Qiddiya entertainment city on the outskirts of Riyadh.
The contract was awarded by gigaproject developer Qiddiya Investment Company (QIC).
The scope covers the construction of six structures, including a heritage building, a gateway hotel, a wadi hotel, a creative hub, a community centre and an open-air market.
QIC tendered the contract in December last year, as MEED exclusively reported.
The award is CSCEC’s second major win at Qiddiya in recent weeks.
Earlier this week, MEED exclusively reported that QIC had awarded CSCEC a contract to build a new transport hub at Qiddiya entertainment city.
The project is located within the resort core zone of the development.
MEED understands the scope includes construction of a parking structure for up to 2,000 vehicles; a transport hub comprising a passenger flow system and ticketing and transit-related facilities; retail, food and beverage and hospitality facilities; mechanical, electrical and plumbing (MEP) systems; and soft and hard landscaping works.
QIC is accelerating plans to develop additional assets at Qiddiya City.
Last week, MEED reported that QIC had invited contractors to prequalify for a contract to build an indoor sports arena within its Qiddiya entertainment city project.
The multipurpose arena is designed to International Olympic Committee standards.
It will be located in District 18, in the Uptown South area of Qiddiya.
Once completed, the indoor arena will be capable of hosting a wide range of sports, cultural and entertainment events.
The arena will feature numerous sports courts for basketball, handball, futsal, volleyball, tennis, boxing and gymnastics.
It will have a seating capacity of 18,000 spectators.
QIC’s other major projects include an e-sports arena, the National Tennis Centre, Prince Mohammed Bin Salman Stadium, a motorsports track, a racecourse, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC opened the Six Flags theme park to the public in December last year.
The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17489285/main.jpg -
Aldar launches Yas Island community park project30 June 2026
Abu Dhabi-based real estate developer Aldar, in partnership with the Abu Dhabi Department of Community Development (DCD), has announced the launch of Yas Community Park on Yas Island.
A key feature of the park is Nabdh Yas, a community hub developed in collaboration with DCD.
Once open, Nabdh Yas will serve as a central gathering space and host a range of community-led programmes.
In a statement, Aldar said: “Nabdh Yas will be delivered on a public-private partnership (PPP) basis, marking the first time private sector investment has been directed towards this type of community infrastructure.
“With DCD overseeing the hub’s development and long-term management, the initiative reflects Abu Dhabi’s focus on innovative approaches that generate lasting social value and enhance community wellbeing,” the statement added.
A memorandum of understanding was signed between Aldar and DCD.
The agreement establishes a framework to expand the Nabdh Community Hub model across Aldar developments in Abu Dhabi, Al-Ain and Al-Dhafra.
Last month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).
Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.
UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.
The group attributed its performance to revenue from its development backlog and steady income from its investment properties.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17489270/main.jpeg -
Dubai sets August deadline for Airport Express metro bids30 June 2026

Dubai’s Roads & Transport Authority (RTA) has given consultants until 10 August to submit proposals for a contract to study and design the Airport Express Line, which will extend from Dubai International airport (DXB) in the Al-Garhoud area to Al-Maktoum International Airport (DWC) in the Jebel Ali area.
The previous deadline was 8 July.
The proposed line will stretch about 55 kilometres and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.
The RTA issued the tender in April, with an initial deadline of June, as MEED reported.
The new line will run from the Red Line metro station at DXB through Al Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing to DWC.
There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch towards Business Bay, where another station will be built.
The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is under construction and due to be completed by 2030.
The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Earlier this month, MEED exclusively reported that the RTA had issued the request for qualification notice for a contract to build the new Gold Line, as part of its expansion of the Dubai Metro network.
Tendering activity is also ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.
MEED exclusively reported in April that consultants had submitted bids for the project.
The extension to the line will run for about 3km and will feature two stations.
The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17489266/main.jpg -
Eni increases gas production in Libya30 June 2026
The Italian oil and gas company Eni has announced the startup of offshore gas production enabled by the Sabratha compression project in Libya.
The client on the project was Mellitah Oil & Gas (MOG), a joint venture of Eni and Libya’s state-owned National Oil Corporation (NOC).
The Sabratha compression project was designed to increase gas output from the Bahr Essalam gas field, located approximately 100 kilometres off Libya’s coast.
The scope of the project included the installation of a new 1,600-tonne compression module on the Sabratha platform, equipped with new compression trains, providing an overall compression capacity of about 440 million cubic feet a day.
In a statement, Eni said: “The new module enables production under low-pressure conditions, offsetting the natural decline of the Bahr Essalam field and maximising gas recovery, ensuring increased volumes of gas of about 800 million cubic metres per year and associated condensate.
“This additional production will play a critical role in sustaining national power generation, reinforcing Libya’s energy security, and supporting export to Italy via the Greenstream pipeline.”
The company also said that the project strengthened the resilience of Libya’s gas infrastructure and represented “a tangible contribution to the stability and growth of the country’s energy sector”.
MOG also has two other projects in Libya that are currently under execution.
The first is the Bouri gas utilisation project, whose tie-in and commissioning activities are under way following the recent installation of the Bouri gas recovery module.
The other project, known as ‘Structures A&E’, will develop two offshore gas fields.
Eni has been present in Libya since 1959 and last year had average equity production in the country of approximately 162,000 barrels of oil equivalent a day.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17489032/main3444.jpg -
Jordan faces fresh round of challenges29 June 2026

MEED’s July 2026 report on the Levant includes:
> COMMENT: Levant recovers in three speeds
> GOVERNMENT: Jordan consolidates as deeper reforms lag
> BANKING: Caution governs Jordanian bank lending
> POWER & WATER: Record investment drives Jordan’s utilities market
> ECONOMY: Gulf liquidity outpaces Syria’s financial revival
> PROJECTS: Momentum builds for Syrian projects
> OIL & GAS: Activity ramps up in Syria’s oil and gas sector
> CONSTRUCTION: Prospects improve for Levant construction
> OIL & GAS: Lebanon taps foreign players to assess resourcesTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17479483/main.gif