Firms express interest in new Hail and Ghasha phase

22 May 2023

 

Register for MEED's guest programme 

Contractors have expressed interest in tendering for new engineering, procurement and construction (EPC) contracts for Abu Dhabi National Oil Company’s (Adnoc’s) multibillion-dollar Hail and Ghasha sour gas development.

Adnoc started a fresh EPC tendering round for the project on 29 April. Contractors were issued expression of interest (EoI) documents just days after the cancellation of the pre-construction services agreements (PCSAs) that had been awarded in January.

Firms were initially asked to express interest in the new EPC tendering round by 14 May. According to sources, the deadline was extended until 19 May and firms submitted EoIs by that date.

The new EoI document details Adnoc’s latest EPC execution strategy for the Hail and Ghasha development. Under these plans, the offshore and onshore scope of work has been divided into three packages:

  • Package one: Subsea pipelines, umbilicals, cables, risers and other offshore structures
  • Package two: Offshore drilling centre facilities, the Ghasha offshore processing plant and central living quarters
  • Package three: The Manayif onshore processing plant, including offsite export pipelines and tie-ins, utilities, the main control building and process buildings. Work on a Ruwais sulphur-handling terminal and other non-process buildings is an optional scope for this package.

An Adnoc spokesperson previously told MEED: “Adnoc and our international partners remain committed to delivering the gas mandated from the Ghasha concession. We do not comment on market speculation.”

PCSAs cancelled

The PCSAs signed in January with two consortiums, comprising three contractors each, marked the start of detailed engineering work and procurement of critical long-lead items for the offshore and onshore scope of work on the Hail and Ghasha development.

A consortium of France-headquartered Technip EnergiesSouth Korean contractor Samsung Engineering and Italy’s Tecnimont was awarded the PCSA for the onshore package. The contractors revealed the value of the contract to be approximately $80m.

Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) won the PCSA for the offshore package, worth $60m.

Previously, the onshore work on the Hail and Ghasha scheme involved the construction of a gas process plant, pipeline network and new gas gathering units.

The offshore PCSA covered installing offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.

The reason for these PCSAs being annulled is unclear, but sources previously said the cost estimates submitted for the project were higher than the client’s overall budget.

Protracted project timeline

The cancelled PCSAs were part of an early engagement process with contractors that Adnoc started following the termination of at least two earlier bidding rounds.

US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for four EPC packages issued soon after.

Following the submission of commercial bids in early 2021, Adnoc made revisions to the feed as part of an optimisation process started by Technip Energies in November 2021. The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.

The four original EPC packages were consolidated into two integrated offshore and onshore packages, thought to be worth as much as $5bn and $5.5bn, respectively, based on the previous version of the project.

MEED reported in September last year that early engagement contractors had submitted proposals for the detailed engineering work on the Hail and Ghasha development. The January PCSAs are understood to have been issued based on these proposals.

Hail and Ghasha fields

The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.

Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent, Germany’s Wintershall Dea with 10 per cent and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.

Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.

In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn to execute offshore and onshore EPC works on the Dalma project, respectively.

Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.

In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.

The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract to provide four island drilling units. Their duration is 10 years.

Adnoc also awarded a third contract, valued at $681m, to another subsidiary, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10872981/main2245.jpg
Indrajit Sen
Related Articles
  • UAE rides high on non-oil boom

    26 April 2024

    Commentary
    John Bambridge
    Analysis editor

    The UAE has demonstrated remarkable economic resilience in recent years, with its non-oil sector bouncing back relatively quickly from Covid-19 and emerging as the real driving force behind the country’s growth. 

    Despite slower oil activity due to the Opec+ oil production cuts and regional turmoil, the non-oil sector has continued to go from strength to strength and is enjoying a resurgent boom in its real estate sector, with levels of activity not seen since before the 2008 global financial crash.

    Among the other drivers of UAE non-oil growth are the country’s rapid expansion and rollout of free trade agreements, with it having signed comprehensive economic partnership deals with 12 countries to date. In the absence of much progress on GCC-wide trade agreements, Abu Dhabi is opening itself up to greater trade opportunities with other markets. 

    Another significant recent development was the UAE’s removal from the Financial Action Task Force’s ‘grey list’ in 2024, which has bolstered investor confidence and general business sentiment.

    On the projects side, there is a real estate and construction boom, with over $475bn-worth of private real estate developments and public building and housing programmes planned or under way. Transport schemes at the top of the agenda include the UAE-Oman rail scheme and a high-speed rail link connecting Abu Dhabi and Dubai.

    Also in the works is the $22bn Dubai Strategic Sewerage Tunnel project. Such a network would have served the city well in mid-April, when its infrastructure fared poorly against the hardest rainfall in 75 years.

    On the oil side of the economy, Abu Dhabi National Oil Company (Adnoc) remains committed to expanding its upstream operations and is expected to maintain robust spending on key projects in 2024. Close to $8bn-worth of combined midstream, downstream and petrochemicals contracts are also expected to be awarded this year.

    The conflict in Gaza poses an increasingly serious challenge to the region, however. The UAE has so far remained relatively quiescent on the conflict while concentrating on humanitarian operations. The country is clearly keen to retain the economic benefits that it has been enjoying since its normalisation of ties with Israel under the Abraham Accords.

    The newly kindled relationship is being tested, however, with the airstrike on the aid convoy of the World Central Kitchen drawing some of the harshest words from Abu Dhabi towards Tel Aviv to date. 

    The risk of rising escalation with Iran meanwhile could quickly quench the current exuberance of the UAE’s buoyant non-oil sector.

     


    MEED's April 2024 special report on the UAE includes:

    > GVT & ECONOMY: Non-oil activity underpins UAE economy
    > BANKING: UAE banks seize the moment
    > UPSTREAM: Adnoc oil and gas project spending sees steep uptick

    > DOWNSTREAM: UAE builds its downstream and chemicals potential
    > POWER: UAE marks successful power project deliveries
    > WATER: Dubai tunnels project dominates UAE pipeline
    > DUBAI CONSTRUCTION: Dubai real estate boosts construction sector

    > ABU DHABI CONSTRUCTION: Abu Dhabi makes major construction investments

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11705846/main.gif
    John Bambridge
  • Morocco seeks firms for 400MW wind schemes

    26 April 2024

    The Moroccan Agency for Sustainable Energy (Masen) has invited companies to prequalify for a contract to develop and operate new onshore wind farms.

    The 400MW Nassim Nord wind power programme includes two wind farms. The first is a 150MW extension to the existing Nassim Koudia Al Baida wind park, located in the Fahs Anjra and Mdiq-Fnideq provinces.

    The second scheme, called Nassim Dar Chaoui wind park, will be located in the provinces of Tangier and Tatouiane. It will have a capacity of approximately 250MW.

    According to an industry source, Masen expects to receive the prequalification submissions on 24 June.

    The project will be implemented under a 30-year power-purchase agreement between Masen and the project company that will include the successful bidder.

    Masen, either alone or with a Moroccan public entity, will take a 35% stake in both the project company and the operation and maintenance (O&M) company that will be formed for the project.

    Masen is expected to issue the request for proposals for the Nassim Nord wind projects in September.

    Owned by Masen and France's EDF Renewables, the Nassim Koudia Al Baida scheme is Morocco's first wind independent prower producer (IPP) project, which had an initial capacity of 50MW. In 2022, additional financing from the  European Bank for Reconstruction and Development (EBRD) and Climate Investment Fund (CTF) aimed to double the plant's capacity, 

    Noor Midelt 2 

    MEED reported on 25 April that Masen has invited prequalified developers and developer consortiums to bid for a contract to develop the second phase of its Noor Midelt solar independent power producer (IPP) programme.

    Located in central Morocco, the Noor Midelt 2 IPP consists of a 400MW solar photovoltaic (PV) power plant with battery storage of two hours.

    The client expects to receive bids for the contract by 8 July.

    2030 target

    Morocco has set a target for 52 per cent of its energy to be produced from clean energy sources by 2030, one of the most ambitious targets in the Middle East and North Africa region.

    Morocco aims to bring its renewable capacity to 10,000MW by 2030. Of the total, solar PV is expected to account for 4,500MW, wind for 4,200MW and hydroelectric for 1,300MW.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11717256/main.jpg
    Jennifer Aguinaldo
  • Jubail 4 and 6 bidders get more time

    26 April 2024

    Prequalified bidders received a two-month extension for the preparation of proposals for a contract to develop an independent water project (IWP) in Jubail, Saudi Arabia.

    Saudi Water Partnership Company (SWPC) issued the request for proposals (RFP) for the Jubail 4 and 6 IWP in January this year, four months after it qualified nine individual companies and consortiums that can bid for the contract.

    Located in Jubail in Saudi Arabia's eastern province, the plants will be able to treat 600,000 cubic metres a day (cm/d) of seawater using reverse osmosis technology.

    MEED understands the client now expects to receive bids for the contract by 30 June instead of 30 April.

    The following utility developers and investors qualified to bid for the contract: 

    • Abu Dhabi National Energy Company (Taqa)
    • Acciona (Spain)
    • Acwa Power (local)
    • Ajlan & Bros (local) / Rawafid Industrial Company (local)
    • Al-Jomaih Energy Water Company (local)  / Sogex Oman Company (local) 
    • GS Inima (Spain/South Korea)
    • International Power (Engie, France)
    • Marubeni Corporation (Japan)
    • Power & Water Utility Company for Jubail & Yanbu (Marafiq, local)

    Thirty-five companies, including 16 Saudi-based firms, previously expressed interest in the project. 

    The desalination plant will be located 18 kilometres south of Jubail Industrial City, adjacent to four existing desalination units – Jubail phase one, Jubail phase two, and the Jubail 3A and 3B IWP facilities.

    As with the previous seawater reverse osmosis (SWRO) IWP contracts already awarded in the kingdom, the successful bidder, through a project company, will develop the project and sell the entire capacity and output to SWPC under a 25-year water-purchase agreement (WPA).

    A credit support agreement from the government of Saudi Arabia backs SWPC’s obligations under the WPA.

    SWPC’s transaction advisory team for the project comprises Netherlands-headquartered KPMG Professional Services as lead and financial adviser, UK-based Eversheds Sutherland as legal adviser and Canada’s WSP as technical adviser.

    It also appointed UAE-based Future Water & Power Consulting to assist with the project tender and in finalising the site studies required for the bid.

    SWPC has awarded the contracts for six IWP projects in Saudi Arabia – Rabigh 3, Shuqaiq 3, Yanbu 4 (Ar-Rayis 1), Jubail 3A, Jubail 3B and Rabigh 4. A seventh contract for developing the Shuaibah 3 SWRO plan was also directly negotiated and awarded in 2022.

    The seven IWP schemes have a total combined capacity of 3.3 million cm/d.

    Ras Mohaisen

    SWPC recently received two bids for a contract to develop the Ras Mohaisen IWP scheme.

    The bidders are Spain’s Acciona and a team comprising the local firms Acwa Power, Haji Abdullah Alireza & Partners Company and AlKifah Holding.

    The Ras Mohaisen IWP will have the capacity to treat 300,000 cubic metres of seawater a day (cm/d) using reverse osmosis technology.

    It will also include storage tanks with a capacity of 600,000 cubic metres, equivalent to two operating days, and an electrical substation.

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11716872/main.gif
    Jennifer Aguinaldo
  • Amiral cogen eyes financial close

    26 April 2024

    The developer team for the cogeneration independent steam and power plant (ISPP) serving the Amiral petrochemicals complex in Jubail, Saudi Arabia is expected to reach financial close for the project before the end of the second quarter this year.

    Saudi Aramco Total Refining & Petrochemical Company (Satorp) signed a power and steam purchase agreement with a team that comprises the UAE's Abu Dhabi National Energy Company (Taqa) and Japan's Jera in March. 

    A special purpose entity owned by Taqa (51%) and Jera (49%) will develop the Amiral cogeneration plant on a 25-year build-own-operate basis, extendable by five years on mutual agreement.

    Taqa and Jera will also undertake the plant's operation and maintenance (O&M) through an O&M special purpose entity.

    "The target is to reach financial close by the end of May or June," a source familiar with the project tells MEED. 

    The planned facility is anticipated to have a design capacity of about 475MW of power generation and roughly 452 tonnes an hour of steam from advanced combined-cycle gas-fired technology.

    The firms said the plant is expected to be operational by 2027.

    "The Amiral cogeneration plant will include state-of-the-art power and steam generation systems, gas and water receiving systems, and gas insulated switchgear interconnections while at the same time meeting stringent efficiency standards imposed by the Saudi Energy Efficiency Centre," the firms said on 28 March.

    "The project also has provision for the future installation of a carbon dioxide capture plant and is capable of hydrogen cofiring."

    South Korean contracting company Samsung C&T will undertake the engineering, procurement and construction (EPC) contract for the Amiral cogeneration ISPP project.

    Steam cracker complex

    Integrated with the existing Satorp refinery in Jubail, the new complex aims to house one of the largest mixed-load steam crackers in the Gulf that can produce up to 1,650 kt/y of ethylene and other industrial gases.

    This expansion is expected to attract more than $4bn in additional investment in various industrial sectors, including carbon fibres, lubes, drilling fluids, detergents, food additives, automotive parts and tires. It is also expected to create about 7,000 local direct and indirect jobs.

    Satorp reached the final investment decision on Amiral in December 2022.

    Aramco owns 62.5% of shares in Satorp, while France's TotalEnergies has a 37.5% stake.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11716656/main.jpg
    Jennifer Aguinaldo
  • Acwa Power signs $356m Barka extension

    25 April 2024

    Barka Water and Power Company (BWPC), a subsidiary of Saudi utility developer Acwa Power, has received a letter of award from Nama Power and Water Procurement Company in Oman (PWP) for extending the power and water purchase agreement (PWPA) for the plant.

    The value of the contract extension is $356m, Acwa Power said in a bourse filing on 25 April.

    The award includes extending the operation of the power plant for eight years and 9 months with operations starting from 1 June 2024, and the water desalination plant for three years starting from 1 September 2024, with an extension option at PWP’s discretion for a further term of three years and another term of two years and nine 9 months for a total of 8 years and 9 months.

    BWPC is registered in Oman and listed in the Muscat Stock Exchange.

    The Barka independent water and power project (IWPP) is located 60 kilometres north of Muscat. It began commercial operations in June 2003, and a majority stake was acquired by Acwa Power in August 2010.

    At the time it started operations, the facility was contributing 6% of the electricity and 24% of the desalinated water in Oman.

    The gas-fired power plant has the capacity to generate 427MW of electricity using combine-cycle gas turbines, while the desalination plant that runs on multi-stage flash technology had an initial capacity of 91,000 cubic metres a day (cm/d).

    A succeeding independent water project entailed the development of a seawater reverse osmosis (SWRO) plant with a capacity of 45,000 cm/d, which became operational in 2014. A further expansion of the SWRO plant, with a capacity of 56,800 cm/d became operational two years later.

    Earlier this week, Acwa Power CEO, Marco Arcelli, said his company is in negotiations with long-term investors, such as pension funds, for the selective sale of assets.

    The report did not specify which assets are being considered for sale.  

    Last week, Arcelli told MEED that Acwa Power and Saudi sovereign wealth vehicle the Public Investment Fund (PIF) are discussing the fourth round of the renewable energy programme that PIF is implementing.

    However, he declined to comment on the outage of one of the company's concentrated solar power plants in Morocco, which is expected to result in $47m of lost revenue for the firm.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11713505/main.jpg
    Jennifer Aguinaldo