Financing signed for $8.5bn Neom hydrogen project

1 March 2023

Neom Green Hydrogen Company (NGHC) has signed financing agreements with banks and lenders for the $8.5bn integrated green hydrogen project in Neom, Saudi Arabia.

According to a bourse filing by Saudi utility developer and investor Acwa Power, one of the three NGHC consortium companies, the total financing consists of $5.85bn of senior debt and $475m of mezzanine debt facilities.

Both are arranged on a non-recourse project finance basis, as follows:

  • $1.5bn from the National Development Fund on behalf of the National Infrastructure Fund
  • $1.25bn in the form of SR-denominated financing from the Saudi Industrial Development Fund

The balance is from a consortium of financiers, structured as a combination of long-term uncovered tranches and an Euler Hermes covered tranche, comprising:

  • First Abu Dhabi Bank
  • HSBC
  • Standard Chartered Bank
  • Mitsubishi UFJ Financial Group
  • BNP Paribas
  • Abu Dhabi Commercial Bank
  • Natixis
  • Saudi British Bank
  • Sumitomo Mitsui Banking Corporation
  • Saudi National Bank
  • KFW
  • Riyad Bank
  • Norinchukin Bank
  • Mizuho Bank
  • Banque Saudi Fransi
  • Alinma Bank
  • Apicorp
  • JP Morgan
  • DZ Bank
  • Korea Development Bank 
  • Credit Agricole

MEED previously reported that the project capital needs for the integrated Neom green hydrogen project have increased to $8.5bn, up 70 per cent from the original cost estimated at $5bn when the project was first announced in July 2020.

The project’s capital requirement had increased to $6.7bn during the intervening period, before reaching the current estimate.

The increases accounted for inflation since 2020 and the additional scope to make the project more self-sufficient and with lower operating costs.

The latest upward capital revision accounts for project financing costs, up-front fees, interest during construction, additional joint venture costs and land, among others.

Neom, Air Products and Acwa Power each have a 33.3 per cent stake in NGHC, the special project vehicle implementing the $8.5bn project.

Air Products is also the main engineering, procurement and construction (EPC) contractor and system integrator for the project and the exclusive offtaker of the green ammonia produced at the facility.

The integrated facility will produce hydrogen to be synthesised into carbon-free ammonia for export exclusively by Air Products to global markets.

Execution status

Air Products said the project’s engineering phase is 30 per cent complete, with all major subcontracts awarded. The land preparation is also complete.

Air Products signed a sub-contract agreement with India’s Larsen & Toubro (L&T) for the power grid and generation works for the Neom green hydrogen project, as MEED reported in January.

The contract covers the construction of a 2,930MW solar power generation plant, a 1,370MW wind power farm and a 400MW battery energy storage system, according to a source familiar with the plan.

The package also includes a power transmission network extending 190 kilometres.

The planned wind and solar power plants are located in northwest Saudi Arabia, close to the border with Jordan.

Notice to proceed

In April 2021, Acwa Power confirmed signing limited notice to proceed (LNTP) agreements for the overall EPC contract for the Neom green hydrogen project.

The agreements include an in-kingdom LNTP for the EPC contract between NGHC and Air Products Middle East Industrial Gases; and an out-of-kingdom LNTP for the EPC contract between NGHC and Air Products Equipment.

In addition to the renewable energy plants, battery storage and power transmission network, the Neom green hydrogen and ammonia project comprises 2,000MW of electrolysers to produce 650 tonnes of hydrogen a day and air separation units to produce nitrogen for the conversion of hydrogen into 1.2 million tonnes of ammonia a year.

In June 2021, US-headquartered Baker Hughes announced it would supply Air Products with advanced compression technology for the Neom facility’s electrolyser plant.

In December 2021, NGHC awarded Germany’s Thyssenkrupp Uhde Chlorine Engineers the contract to supply a more than 2GW electrolysis plant for the project.

Under this contract, Thyssenkrupp will engineer, procure and fabricate the plant based on the firm’s 20MW alkaline water electrolysis module.

In December, NGHC announced the signing of facility agreements with local, regional and international banks for the project.

It also announced the execution of a commitment letter with the Saudi Industrial Development Fund.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10639931/main.gif
Jennifer Aguinaldo
Related Articles
  • Arada completes Sokoon buildings construction

    26 March 2026

    Sharjah-based private real estate developer Arada has announced the completion of five additional buildings in the Naseej District of its Aljada development.

    Kuwaiti firm Mohammad Abdulmohsen Al-Kharafi & Sons secured the construction contract for the Sokoon buildings in 2023, replacing Airolink Building Contracting as the project’s main contractor.

    The first four Sokoon buildings were completed in December 2023.

    In April last year, Arada also announced the completion of all eight Tiraz buildings in the Naseej District. The Tiraz buildings comprise 920 homes, including studios, one-bedroom and two-bedroom apartments.

    With the completion of the five Sokoon buildings, Aljada’s total number of completed residential units has risen to more than 8,200.

    Spanning 2.2 square kilometres, Aljada features residential districts, retail spaces, educational institutions, healthcare services and other facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16141382/main.png
    Yasir Iqbal
  • Local contractor wins Medina substation contract

    26 March 2026

    Danway Saudi Arabia has won a contract with National Grid SA to construct a new 110/13.8kV substation in Medina.

    The contract is valued at more than SR100m ($26.7m) and covers the construction of the King Abdulaziz Road substation, including design, engineering, supply, installation, testing and commissioning.

    The project is expected to take approximately 23 months to complete.

    Key components include 110kV gas-insulated switchgear (GIS), 50/67MVA 110/13.8kV power transformers and 13.8kV switchgear.

    National Grid SA is a wholly owned subsidiary of Saudi Energy, formerly Saudi Electricity Company. It owns and operates the kingdom’s high-voltage transmission network and is responsible for grid planning, interconnection and system reliability.

    The operator recently appointed another local firm, Nesma Infrastructure & Technology, as the contractor for the construction of two 380kV double-circuit overhead transmission lines in Riyadh, connecting an existing substation to a wind power substation, referred to as Samha Wind BSP.

    As MEED understands, National Grid SA is also due to begin construction on the replacement of 132kV oil-filled underground cable circuits between several substations in the Central Operation Area in Murabba in Riyadh.

    Riyadh-based Keir International is the engineering, procurement and construction contractor for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16139578/main.jpg
    Mark Dowdall
  • Neom terminates $5bn Trojena dams contract with WeBuild

    26 March 2026

    Register for MEED’s 14-day trial access 

    Neom has terminated its contract with Italian contractor Webuild for the construction of three dams feeding a freshwater lake, as well as ‘The Bow’ architectural structure at Trojena in northwest Saudi Arabia.

    In a statement posted on its website, Webuild said: “The termination will become effective on 29 March. As of that date, the works are approximately 30% complete, with a remaining project backlog for Webuild of approximately €2.8bn ($3.2bn).”

    Neom awarded Webuild a SR20bn ($5bn) contract to build the dams in late 2023, which MEED exclusively reported at the time.

    The termination is the latest in a series of high-profile contract cancellations by Neom in recent weeks. Earlier this week, Neom terminated its contract with Malaysian contractor Eversendai Corporation for the steel structural works on the Ski Village project in Trojena.

    In a statement published on its website, Eversendai said it had received an official notice that the termination would take effect from 26 March.

    In January this year, Saudi Arabia confirmed the postponement of the 2029 Asian Winter Games, which were scheduled to be held at Trojena. Trojena was chosen to host the event in October 2022.

    Neom has also cancelled contracts for the construction of the tunnel sections of The Line in northwest Saudi Arabia.

    In a stock exchange filing dated 13 March, South Korean contractor Hyundai E&C said Neom cancelled its contract on 29 December last year.

    Hyundai E&C was executing the drill-and-blast section of The Line’s tunnels in a joint venture with Greece’s Archirodon and South Korean counterpart Samsung C&T.

    These developments follow a wider strategic review of Neom last year, as Saudi Arabia reassesses priorities under its Vision 2030 programme.

    With tighter liquidity at the sovereign wealth fund level, resources are being redirected towards projects linked to the Fifa World Cup 2034, Expo 2030, and essential housing, healthcare and education initiatives.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16140200/main.jpg
    Yasir Iqbal
  • Iraq gas field project disrupted by regional conflict

    26 March 2026

     

    Register for MEED’s 14-day trial access 

    Progress on Iraq’s project to develop the strategically important Akkas gas field has been disrupted by security issues related to the US and Israel’s ongoing war with Iran, according to industry sources.

    Work activity at the project site has been significantly reduced due to security concerns, and the project is now expected to take longer to complete.

    Iraq held a ceremony in January this year to mark the restart of drilling operations at the site as part of the field development project.

    In July last year, Iraq’s Oil Ministry announced signing a contract with the US-based oil field services provider SLB to develop production at Iraq’s Akkas gas field.

    Under the terms of the deal, SLB will drill wells at the Akkas field, aiming to initially raise production to 100 million cubic feet a day (cf/d).

    Many of SLB’s non-Iraqi employees have now been evacuated from the country.

    Over the long term, Iraq is targeting gas production of 400 million cf/d from the field.

    The contract with SLB replaces a previous deal with Ukraine-based Ukrzemresurs, which has been terminated.

    It also covers the construction of surface infrastructure and pipelines to connect Akkas to central processing units.

    The gas produced at Akkas will be used to fuel the Anbar combined-cycle power plant, which is under construction by the Electricity Ministry.

    Akkas gas field development

    The Akkas gas field, located in Anbar province in western Iraq, has 5.6 trillion cubic feet of proven reserves. The field was discovered in 1992 and began production in 1993.

    Since then, Iraq’s plans to develop the Akkas gas field to its full potential have experienced several setbacks.

    In April last year, the Iraqi Oil Ministry signed an agreement with Ukrzemresurs to develop the field.

    At the time, the Oil Ministry said that the partners were aiming to produce 100 million cf/d in the first two years, as per the agreement, with output targeted to increase to 400 million cf/d within four years.

    Prior to Ukrzemresurs, South Korean company Kogas was responsible for developing the field.

    Rights to the field were originally awarded to a consortium of Kogas and Kazakhstan’s state-owned oil company KazMunaiGas (KMG) in the third licensing round, which was launched in October 2011.

    KMG pulled out, leaving Kogas as the sole investor and operator on new contract terms.

    When the deal with Ukrzemresurs was originally announced last year, it was negatively received by some Iraqi politicians, with the Oil and Gas Committee in Iraq’s parliament rejecting the contract signing.

    At the time, Ali Al-Mashkour, a member of the Oil and Gas Committee, told Iraq’s Shafaq News Agency: “This contract involves a great waste of Iraq’s wealth, and there will be a waste of Iraq’s oil, and this confirms that Iraq is once again failing to choose reputable companies to work with in the most important economic field in the country.”

    He added: “We will work to uncover and expose the suspicions in this contract during the next stage, especially since this contract was made by some representatives for specific interests, which we will reveal soon with evidence.”

    Plans to sign the contract to develop the Akkas gas field with a Ukrainian company were first announced by the Oil Ministry in September 2023, but Ukrzemresurs was not named at the time.

    Iraq’s government is trying to transform the country into a gas-exporting nation. Currently, Iraq is reliant on Iran for gas imports.

    Both Saudi Arabia and the US, which are looking to contain Iranian influence in the region, have been supporting Iraq in developing its non-associated gas fields as this will reduce Iraq’s economic reliance on Iran.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16138892/main.png
    Wil Crisp
  • Dubai seeks contractors for Nadd Hessa stormwater project

    26 March 2026

    Dubai Municipality has invited contractors to prequalify for a contract to build a sewerage and stormwater system in the Nadd Hessa area.

    The project is being procured through the Sewerage and Recycled Water Projects Department.

    The submission deadline is 2 April.

    Nadd Hessa is an emerging development area, located between Dubai Silicon Oasis and Academic City along the E311 corridor.

    It has been earmarked for future residential expansion, with enabling infrastructure now being tendered to support planned housing and community developments in the area.

    The scheme, known as DS 328/1–C1, covers the construction of sewerage and stormwater infrastructure, including approximately 12.4 kilometres of sewerage lines with diameters of up to 400 millimetres.

    The scope also includes about 14km of stormwater lines with diameters of up to 1,000 millimetres.

    In addition, the project involves around 500 metres of microtunnelling works for both sewerage and stormwater networks.

    The municipality is currently prequalifying contractors for several upcoming water projects, including the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).

    Bid submissions for this project are also due by 2 April.

    In addition, the authority is planning a broader review of Dubai’s water and wastewater infrastructure to support future population growth, including identifying locations for future infrastructure. 

    Two separate consultancy tenders were issued in March.

    One involves a study to develop a sustainable urban drainage systems strategy across the emirate. The other covers a review of the emirate’s sewage treatment and recycled water distribution strategy. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16138660/main.jpg
    Mark Dowdall