Egypt’s desalination projects inch forward
8 February 2024
This package on Egypt’s water sector also includes:
> Egypt expects desalination tender in May
> Egypt nears 6 October City wastewater tender
> Egypt invites Helwan wastewater prequalification
> Team wins Fayoum wastewater retrofit deal

Data shows Egypt’s per capita annual renewable water supply dwindled from 1,426 cubic metres in 1977 to about 558 cubic metres in 2022. This puts the North African state well below the water scarcity threshold of 1,000 cubic metres a year per capita.
Climate change, inefficiency and the potential impact of the Grand Ethiopian Renaissance Dam (GERD) on water flows into the Nile River, which supplies up to 95 per cent of the country’s water requirements, will only exacerbate the water scarcity issue.
With a population of 113 million and one baby born every 19 seconds, Egypt must implement immediate measures and projects in line with its long-term water strategy to keep up with demand and avert a full-blown crisis, which would have a major impact on agriculture and economic output.
Government agencies have responded to the challenge by drawing up plans to modernise agricultural techniques to minimise water waste or develop unconventional water sources through the treatment of wastewater and seawater.
Currently, the country is understood to have over 60 water desalination plants with a total combined capacity of around 800,000 cubic metres a day (cm/d).
The government aims to grow this capacity 10-fold to 8.8 million cm/d by 2050 and has initiated an ambitious capacity procurement programme to reach this target.
In March last year, the London-based European Bank for Reconstruction & Development (EBRD) and Washington-headquartered International Finance Corporation signed an advisory deal with The Sovereign Fund of Egypt (TSFE) and the Egyptian government to support them in preparing and procuring the programme’s first four seawater desalination plants.
EBRD said the desalination project will help “to ensure Egypt’s water security, improve its resilience, mitigate the impact of climate change-induced freshwater scarcity and boost sustainable economic growth”.
The bank also stressed that the electricity used to power the desalination plants will be procured from renewable energy sources.
Two months later, in May 2023, TSFE prequalified 17 teams and companies that can bid for the contracts to develop up to 8.85 cm/d of renewable energy-powered desalination capacity in Egypt.
These companies and consortiums include the largest international and regional water utility developers and investors, as well as engineering, procurement and construction (EPC) contractors.
The entire programme will be procured in batches, with prequalified bidders split into four bands that will determine the capacity or size of the projects they can bid on.
In January 2024, Atter Ezzat Hannoura, public-private partnership (PPP) central unit director at Egypt’s Finance Ministry, said the target date for issuing the request for proposals for the first batch of water desalination plants is in May this year.
He also said the first batch of projects will comprise eight or nine seawater reverse osmosis (SWRO) plants, with a combined total capacity of up to 900,000 cm/d. This is significantly higher than the previously proposed four desalination plants with a capacity of under 500,000 cm/d.
Concerned authorities and ministries are still undertaking final discussions before the request for proposals can be released, according to Hannoura. One of these issues is how and where to source renewable power for the desalination plants.
The discussions are understood to revolve around two available options – drawing renewable power from the electricity grid or integrating solar farms into the desalination plants to minimise or eliminate their dependence on the grid.
Crucially, discussions are also focusing on the project structure to make them bankable.
As one expert points out, the planned water desalination PPP projects in Egypt, similar to its power generation capacity expansion plans, face multiple issues, not the least the creation of a more favourable business investment climate.
“We are monitoring the projects closely,” says a Dubai-based executive with a multinational bank. “We want to understand how they intend to manage the fiscal risks as well as the long-term nature of these projects, and how we might be able to play a role.”
Wastewater
Treating wastewater for reuse is another key element in Egypt’s water scarcity response. Some $2.1bn-worth of water treatment plant schemes are in the pre-execution phase in Egypt, according to the latest available data from regional projects tracker MEED Projects.
Egypt’s Construction Authority for Potable Water & Wastewater is undertaking the prequalification process for the contracts to design and build the next phases of the Gabal Al Asfar, Helwan and Alexandria West wastewater treatment plants.
Through Egypt’s PPP Central Unit, the New Urban Communities Authority (Nuca) has also initiated the procurement of an independent wastewater treatment plant (IWTP) in 6 October City, which is anticipated to have a design capacity of 150,000 cm/d.
The procuring authority is expected to issue the tender for the contract to develop and operate the project in the first quarter of 2024.
Under the current plan, the sewage treatment charge in the financial bids Nuca expects to receive will be split, with 70% in Egyptian pounds (£E) and 30% based on the US dollar, paid in £E at the prevailing US dollar/£E exchange rate on the day of payment.
Nuca is planning another IWTP facility in New Damietta along the Mediterranean coast, which will have a capacity of 50,000 cm/d.
MEED’s March 2024 special report on Egypt also includes:
> Cairo beset by regional geopolitical storm
> More pain for more gain for Egypt
> Familiar realities threaten Egypt’s energy ambitions

Exclusive from Meed
-
SLB passes evaluation for Kuwait upstream project12 December 2025
-
Dana Gas makes onshore discovery in Egypt12 December 2025
-
SAR to tender new phosphate rail track section in January12 December 2025
-
Dar Global to develop $4.2bn Oman mixed-use project10 December 2025
-
Contract award nears for Saudi Defence Ministry headquarters10 December 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
SLB passes evaluation for Kuwait upstream project12 December 2025
The US-based oilfield services company SLB, formerly Schlumberger, has passed the technical bid evaluation for a major project to develop Kuwait’s Mutriba oil field.
The Houston-headquartered company was the only bidder to pass the technical evaluation for the Mutriba integrated project management (IPM) contract.
The minimum passing technical evaluation score was 75%.
The full list of bidders was:
- SLB (US): 97%
- Halliburton (US): 72%
- Weatherford (US): 61.5%
The decision was finalised at a meeting of the Higher Purchase Committee (HPC) of state-owned Kuwait Petroleum Corporation (KPC) on 20 November 2025.
According to a document published earlier this year by KOC, the IPM tender for the Mutriba field aims to “accelerate production through a comprehensive study that includes economic feasibility evaluation, well planning and long-term sustainability strategies”.
The field was originally discovered in 2009.
Commercial production from the Mutriba field started earlier this year, on 15 June, after several wells were connected to production facilities.
The field is located in a relatively undeveloped area in northwest Kuwait and spans more than 230 square kilometres.
The oil at the Mutriba field has unusually high hydrogen sulfide content, which can be as much as 40%.
This presents operational challenges requiring specialised technologies and safety measures.
In order to start producing oil at the field, KOC deployed multiphase pumps to increase hydrocarbon pressure and enable transportation to the nearest Jurassic production facilities in north Kuwait.
The company also built long-distance pipelines stretching 50 to 70 kilometres, using high-grade corrosion-resistant materials engineered to withstand the high hydrogen sulfide levels and ensure long-term reliability.
KOC also commissioned the Mutriba long-term testing facility in northwest Kuwait, with a nameplate capacity of around 5,000 barrels of oil a day (b/d) and 5 million standard cubic feet of gas a day (mmscf/d).
Once this facility was commissioned, production stabilised at 5,000 b/d and 7 mmscf/d.
In documents published earlier this year, KOC said that starting production from the field had “laid a solid foundation” for the IPM contract by generating essential reservoir and surface data that will guide future development.
Future output from the field is expected to range between 80,000 and 120,000 b/d, in addition to approximately 150 mmscf/d of gas.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15235579/main.png -
Dana Gas makes onshore discovery in Egypt12 December 2025
Register for MEED’s 14-day trial access
UAE-based Dana Gas has made an onshore gas discovery in Egypt’s Nile Delta area, according to a statement from the company.
The discovery was made by the drilling of the North El-Basant 1 exploratory well, and initial well results indicate estimated reserves of 15-25 billion cubic feet of gas.
Production from the reserve is expected to exceed 8 million cubic feet a day (cf/d) once the well is connected to the national network.
The North El-Basant 1 exploratory well was the fourth well in a campaign of 11 development and exploration wells.
The campaign is being executed as part of the company’s $100m investment programme to support domestic gas production, increase reserves and meet growing energy demand.
Earlier this year, Dana Gas completed the drilling of three wells, adding 10 million cf/d.
The programme is expected to increase long-term production and add approximately 80 billion cubic feet of recoverable gas reserves, according to Dana Gas.
Dana Gas expects to start drilling the fifth well in the programme, the Daffodil exploration well, in the first week of January 2026.
Richard Hall, the chief executive of Dana Gas, said: “The latest drilling success reinforces the value of our investment programme in Egypt and highlights the significant remaining potential within the Nile Delta.”
He added: “By increasing local gas production, the programme will help reduce Egypt’s reliance on imported liquefied natural gas (LNG) and fuel oil and is expected to generate more than $1bn in savings for the national economy over time.”
Previously, Dana Gas signed an agreement with state-owned Egyptian Natural Gas Holding Company (EGas) to secure additional acreage under improved fiscal terms, and to accelerate drilling activity.
Hall said: “We appreciate the strong cooperation from EGas and the ministry, and we remain committed to delivering the majority of our planned programme next year.
“Regular and timely payments from our partners are crucial to sustaining our investment programme in Egypt."
In November, a new gas discovery was made in Egypt’s Western Desert region by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation and US-headquartered Apache Corporation.
Egypt also started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.
The country is currently pushing to increase gas production in order to meet domestic demand and reduce its import bill.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15235552/main.png -
SAR to tender new phosphate rail track section in January12 December 2025

Register for MEED’s 14-day trial access
Saudi Arabian Railways (SAR) is expected to float another multibillion-riyal tender to double the tracks on the existing phosphate railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the Eastern Province.
MEED understands that the new tender – covering the second section of the track-doubling works, spanning more than 150 kilometres (km) – will be issued in January.
The new tender follows SAR’s issuance of the tender for the project's first phase in November, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.
The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track.
The scope also covers support for signalling and telecommunications systems.
The tender notice was issued in late November, with a bid submission deadline of 20 January 2026.
Switzerland-based engineering firm ARX is the project consultant.
MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line.
The other packages expected to be tendered shortly include the depot and the systems package.
In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.
Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.
Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.
State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15229624/main.jpg -
Dar Global to develop $4.2bn Oman mixed-use project10 December 2025
Register for MEED’s 14-day trial access
Saudi Arabia-headquartered real estate developer Dar Global has announced that it will develop a mixed-use project in Muscat at an estimated investment of RO1.6bn ($4.2bn).
Dar Global will co-develop the Muscat Marine, Art & Digital District project with Oman's Art District Real Estate Development Company.
The project will cover an area of over 1.5 million square metres (sq m) and will be developed in several phases over 12 years.
The development will comprise a mix of residential communities, cultural venues, marinas, retail spaces, finance and business parks and hotels.
Dar Global, a subsidiary of Dar Al-Arkan, was one of the first Saudi brands to list on the London Stock Exchange.
Dar Al-Arkan established Dar Global in 2017 to focus on developing projects in the Middle East and Europe, including in Dubai, Qatar, Oman, London and the Costa del Sol in southern Spain.
Dar Global has $12bn-worth of projects under development in six countries: the UAE, Oman, Qatar, Saudi Arabia, the UK and Spain.
It completed three developments – the Urban Oasis and Da Vinci towers in Dubai and the Sidra gated community in Bosnia – in 2023.
The company collaborates with global brands including Missoni, W Hotels, Versace, Elie Saab, Automobili Pagani and Automobili Lamborghini.
In Oman, Dar Global is also developing the Aida project. In May, it awarded a contract to develop the villas and apartments as part of the project.
According to an official statement, the construction works are expected to start immediately and the project is slated for completion in 2026.
The main contract was awarded to local firm Al-Adrak Trading & Contracting.
The latest announcement follows the awarding of contracts in June last year for the development of the first phase of the Aida project.
The Aida project is being developed as a joint venture with Omran Group and the first phase is expected to be completed in 2027.
UK analytics firm GlobalData forecasts that the Omani construction industry will expand at an annual average growth rate of 4.2% in 2025-28. Growth in the country will be supported by rising government investments in renewable energy, the transport infrastructure and the housing sector, all as part of Oman's Vision 2040 strategy.
Growth during the forecast period will also be supported by increasing hospitality sector investments, with the government planning to invest RO11.9bn ($31bn) in tourism development projects by 2040 and supporting the construction of several hospitality projects.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15222694/main.jpg -
Contract award nears for Saudi Defence Ministry headquarters10 December 2025

Saudi Arabia’s Defence Ministry (MoD) is preparing to award the contract to build a new headquarters building, as part of its P-563 programme in Riyadh.
MEED understands that bid evaluation has reached advanced stages and the contract award is imminent.
The MoD issued the tender in April. The commercial bids were submitted in September, as MEED reported.
Located to the northwest of Riyadh, the P-563 programme includes the development of facilities and infrastructure to support the MoD’s broader initiatives under the kingdom’s Vision 2030 strategy.
It covers the construction of:
- A new military city featuring the MoD headquarters, support and logistics facilities, a residential and commercial community and space for future command centres
- A National Defence University with a library, conference centre and academic buildings
- A self-sustaining Joint Forces Command compound located approximately 50 kilometres from the military city
The budget for the entire programme is expected to be $10bn-$12bn.
In September 2023, MEED reported that Spain-headquartered Typsa had won two contracts for the project.
The first contract, worth $11.4m, included data management, geographic information systems management, geotechnical reporting and the preparation of the phase one final traffic report. The contract duration was 270 days from the notice to proceed.
The second contract, valued at $10.8m, involved preparing four conceptual masterplans for the P-563 site. It was set to last 255 days from the notice to proceed.
These followed a $290m consultancy contract awarded to Typsa in March of the same year. The single-award task order covered a three-year base period, with an optional two-year extension.
Typsa’s scope of work included programme management planning, communications, change and quality management and cost and schedule tracking.
It also included design requirements, codes, standards and submission requirements, programme guidance, study integration, risk analysis and management, design reviews and a programme-of-work breakdown plan.
READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFProspects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges
Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:
> AGENDA 1: Regional rail construction surges ahead> INDUSTRY REPORT 1: Larsen & Toubro climbs EPC contractor ranking> INDUSTRY REPORT 2: Chinese firms expand oil and gas presence> CONSTRUCTION: Aramco Stadium races towards completion> RENEWABLES: UAE moves ahead with $6bn solar and storage project> INTERVIEW: Engie pivots towards renewables projects> BAHRAIN MARKET FOCUS: Manama pursues reform amid strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15222401/main.gif