Dubai extends $22bn tunnels EPC package deadline
27 February 2024
Dubai Municipality has extended the deadline for engineering, procurement and construction (EPC) companies to submit their statements of qualifications (SOQs) for the $22bn Dubai Strategic Sewerage Tunnels (DSST) public-private partnership (PPP) project.
Interested companies have until 28 March to submit their SOQs, according to a source close to the project. The new date is one month later than the initial planned submission deadline of 26 February.
This could imply that the announcement of prequalified EPC bidders, initially set for 11 March, will now be pushed to early April.
The client intends to start the prequalification process for the PPP consortiums that can bid for the project in the second quarter of this year.
In addition to its size, the project is gaining significant interest due to its unique procurement approach, whereby EPC contractors’ prequalification precedes developers’ prequalification.
“There is huge interest among EPC contractors,” notes an international contractor with regional headquarters in Dubai.
The bidders for each of the PPP requests for proposals (RFPs) will be prequalified consortiums comprised of sponsors, EPC contractors and operation and management (O&M) contractors.
MEED previously reported that the overall project will require a capital expenditure of roughly AED30bn ($8bn), while the whole life cost over the full concession terms of the entire project is estimated to reach AED80bn.
The project aims to convert Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.
Two major sewerage catchments currently serve Dubai. The first, located in Deira, is called Warsan, where the existing Warsan sewage treatment plant (STP) treats the flow.
The second catchment, called Jebel Ali, is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.
DSST-DLT packages
Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered separately as PPP packages with concession periods lasting between 25 and 35 years.
The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres, with the links extending 10km.
The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km, with a link stretching 46km.
W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.
J3, the fourth package, comprises 129km of links, which will be operated by Dubai Municipality once completed, unlike the first three packages, which are envisaged to be operated and maintained by the winning PPP contractors.
J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period between 25 and 35 years.
J3 will be procured under a design-build-finance model with a concession period of 25-35 years.
J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.
MEED understands the remaining two packages of the project, the expansion and upgrade of the Jebel Ali and Warsan STPs, will be procured in a process separate from the four DSST-DLT components of the project.
The RFPs for the four DSST-DLT packages will likely be issued in sequential order on a staggered basis around six to 12 months apart.
Dubai Municipality appointed advisers for the overall scheme last year. It selected Abu Dhabi-headquartered Tribe Infrastructure Group as lead and financial adviser, UK-based Ashurst as legal adviser and the US’ Parsons as technical adviser.
Exclusive from Meed
-
Hyundai E&C signs $725m Saudi high voltage deal
13 November 2024
-
Chinese-led consortium wins $262m Algeria rail deal
13 November 2024
-
Hatta hydropower plant heads for trial operation
13 November 2024
-
Bahrain invites independent water prequalifications
13 November 2024
-
Neom replaces CEO
12 November 2024
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Hyundai E&C signs $725m Saudi high voltage deal
13 November 2024
South Korea’s Hyundai Engineering & Construction (E&C) has won a KRW1tn ($725m) contract to build a high-voltage direct current (HVDC) network project in Saudi Arabia.
The contract forms part of a 1,089-kilometre (km), 500-kilovolt (kV) HVDC transmission line connecting Riyadh Power Plant 14 (PP14) to the Kudmi substation in southwest Saudi Arabia.
Related read: Interconnection vital to GCC energy future
The company signed the contract to build the transmission line's first package, which extends over 369km, with National Grid, the power transmission unit of state utility Saudi Electricity Company (SEC).
The lump sum turnkey project is expected to be completed by January 2027.
Hyundai E&C said the project will utilise a double bipole HVDC system with a power transmission capacity of 4,000MW.
Regarded as a next-generation electricity transmission technology, an HVDC transmission system is ideal for renewable energy such as solar or wind power. It uses direct current for electricity transmission, with voltages between 100kV and 800kV.
An HVDC system is often referred to as a 'power superhighway', transporting significantly more power over greater distances than the common high-voltage alternating current line, and incurs lower power losses.
The South Korean contractor said it has completed 35 transmission line projects in Saudi Arabia in the past 50 years.
Related read: Hitachi Energy rides HVDC boom
https://image.digitalinsightresearch.in/uploads/NewsArticle/12909551/main.jpg -
Chinese-led consortium wins $262m Algeria rail deal
13 November 2024
Algeria’s Anesrif has awarded a $262m construction contract to a consortium led by the China Road & Bridge Corporation (CRBC).
The CRBC-led consortium includes China Civil Engineering Construction Corporation and Algeria’s EPE SNTP.
The contract covers construction work for the Bouchegouf-Souk Ahras-Drea railway section, with a total length of 121 kilometres (km). It is scheduled to be completed in 32 months.
This contract is the latest example of Chinese companies undertaking major projects in Algeria.
MEED reported in January this year that Algeria had selected a team of Beijing-headquartered China Railway Construction Corporation and local contractor Cosider Travaux Publics for a contract to build a 575km railway line.
The line will connect the Gara Djebilet iron ore mine in Western Algeria’s Tindouf Province with the national rail network at Bechar.
The project will facilitate transporting materials from the Gara Djebilet iron ore mine to industrial centres and ports along Algeria’s national rail network.
https://image.digitalinsightresearch.in/uploads/NewsArticle/12908841/main5239.gif -
Hatta hydropower plant heads for trial operation
13 November 2024
Construction work on Dubai’s Hatta pumped-storage hydroelectric power plant is 94.15% complete, and generator installations are under way in preparation for a trial operation in the first quarter of 2025.
According to the state utility, Dubai Electricity & Water Authority (Dewa), the plant’s upper dam, which includes a 72-metre-high main wall and a 37-metre-high side dam, has also been filled.
The plant will have a production capacity of 250MW, a storage capacity of 1,500 megawatt-hours and a lifespan of up to 80 years.
The state utility awarded the contract to build the plant to a consortium of Austrian firms Strabag and Andritz and Turkey’s Ozkar in August 2019.
Dewa said on 12 November that the AED1.421bn ($387m) project is expected to be fully completed by the end of the second quarter of 2025.
The hydroelectric power plant is designed as an energy storage facility with a turnaround efficiency of 78.9%.
It uses the potential energy of water stored in the upper dam, converting it into kinetic energy as the water flows through a 1.2-kilometre subterranean tunnel.
This kinetic energy rotates the turbines, converting mechanical energy into electrical energy, which can be delivered to Dewa’s grid within 90 seconds to meet demand.
To store energy, clean power generated at the Mohammed Bin Rashid Al-Maktoum Solar Park will be used to pump water back to the upper dam, converting electrical power into kinetic energy during the process.
Dewa said the project is part of a comprehensive vision to develop Hatta and enhance its sustainable development, including the creation of job opportunities for Emiratis.
It added that the project “also supports the Dubai Clean Energy Strategy and the Dubai Net Zero Carbon Emissions Strategy 2050”.
Through the project, Dewa aims to diversify energy production from renewable and clean sources in Dubai. These include different available technologies, such as solar photovoltaic panels and concentrated solar power, as well as the use of renewable energy to produce green hydrogen.
https://image.digitalinsightresearch.in/uploads/NewsArticle/12908014/main.jpg -
Bahrain invites independent water prequalifications
13 November 2024
Bahrain’s Electricity & Water Authority (EWA) has invited interested firms to prequalify for a tender to develop the state’s first independent water project (IWP).
The Al-Hidd seawater reverse osmosis (SWRO) plant is expected to have a production capacity of about 60 million imperial gallons a day (MIGD) of potable water.
The client expects firms to submit their statements of qualifications (SOQs) by 18 December.
The facility will be developed on a brownfield site and is expected to be fully operational by the second quarter of 2028. It will help expand Bahrain’s water infrastructure to meet projected demand based on its 2030 master plan.
The Al-Hidd IWP will be developed using a build, own and operate (BOO) model for 20 to 25 years.
EWA has also issued the prequalification request for another BOO project, MEED reported on 11 November.
The Sitra independent water and power project (IWPP) is a combined-cycle gas turbine (CCGT) plant expected to have a production capacity of about 1,200MW of electricity. The project’s SWRO desalination facility will have a production capacity of 30MIGD of potable water.
The plant is Bahrain’s fourth IWPP, replacing the previously planned Al-Dur 3. The Sitra IWPP is expected to be fully operational by the second quarter of 2029.
Sixty representatives from utility developers and contracting firms attended a market-sounding event for the two separate utility BOO projects in Manama on 21 October.
The firms that sent representatives to the event included France’s Engie, Japan’s Mitsui, Saudi Arabia’s Acwa Power, AlJomaih Electricity & Water Company and Ajlan & Bros, and Kuwait’s Gulf Investment Corporation, among others, said sources.
EWA’s transaction advisory team for the two BOO projects comprises KPMG Fakhro as the financial consultant, WSP Parsons Brinckerhoff as the technical consultant and Trowers & Hamlins as the legal consultant.
MEED understands that EWA’s Sitra IWPP will likely be Bahrain’s last CCGT plant project. Solar power is expected to account for all future electricity generation capacity.
Bahrain aims to reach net-zero carbon emissions by 2060.
https://image.digitalinsightresearch.in/uploads/NewsArticle/12907891/main.gif -
Neom replaces CEO
12 November 2024
Register for MEED's 14-day trial access
Nadhmi Al-Nasr has left his role as Neom CEO and will be replaced by Aiman Al-Mudaifer as acting CEO of the company developing the $500bn project in northwestern Saudi Arabia, which includes The Line, Trojena and Oxagon.
In a statement published online, Neom said: “The Neom Board of Directors today announced the appointment of Eng. Aiman Al-Mudaifer as acting CEO of the company. Eng. Al-Mudaifer assumes leadership of Neom, following Nadhmi Al-Nasr’s departure.”
The statement added: “As Neom enters a new phase of delivery, this new leadership will ensure operational continuity, agility and efficiency to match the overall vision and objectives of the project.”
Al-Mudaifer has been head of the Public Investment Fund’s local real estate division since 2018, and the Neom statement says he has a deep and strategic understanding of Neom and its projects.
Neom has attracted significant criticism over the past year as it grapples with major programmes of construction work such as The Line. In a statement announcing the appointment of consultants for work on The Line on 11 November, Neom said it “is currently focused on the initial phases of infrastructure and enabling works for the new city”.
https://image.digitalinsightresearch.in/uploads/NewsArticle/12902059/main.jpg