Contractors submit bids for five Aramco offshore tenders

20 March 2024

Register for MEED's guest programme 

Entities in Saudi Aramco’s Long-Term Agreement (LTA) pool of contractors have submitted bids for five new offshore oil and gas field upgrade tenders issued in recent weeks.

The tenders are Contracts Release and Purchase Order (CRPO) numbers 131, 132, 139, 142 and 143, according to sources.

LTA entities submitted bids for these CRPOs in mid-March, sources told MEED.

Bidders were previously set deadlines in early March for the submission of bids for these CRPOs, as MEED previously reported.

Bidding activity for these tenders is taking place against the backdrop of Aramco having shelved more than a dozen offshore oil field upgrade tenders that were issued to its LTA pool of offshore contractors last year. The decision followed a Saudi Energy Ministry directive on 30 January for Aramco to abandon its campaign to expand oil production spare capacity from 12 million barrels a day (b/d) to 13 million b/d by 2027.

Aramco cancelled the tendering process for at least 15 CRPO jobs involving the engineering, procurement, construction and installation of key structures at major offshore oil fields, MEED previously reported.

CRPOs under bidding

The scope of work on the five CRPOs for which contractors have submitted bids, and their submission deadlines, are as follows:

  • CRPO 131: 13 March
    Two jackets at the Arabiyah field
    One simultaneous operations-capable jacket at the Hasbah field
    One gas lift production deck module (PDM)
    A 16-inch subsea pipeline running 5 kilometres (km)
    13.8kV subsea cables covering 5km
     
  • CRPO 132: 13 March
    Two oil injection PDMs at the Marjan field
    One gas injection PDM at Marjan
     
  • CRPO 139: 13 March
    Installation of five PDMs at the Zuluf field development
    Installation of eight pipelines covering 29km, in 10-inch, 12-inch and 16-inch sizes
    Laying of 15kV-subsea power cables covering 35km:
    – (a) 16-inch power line from Zuluf-560/569 to Zuluf-480/489
    – (b) 16-inch power line from Zuluf-700/709 to ZTP-5
    – (c) 10-inch power line from Zuluf-903-1510/1519 to Zuluf-1410/1419
    – (d) 16-inch power line from Safaniya-4070/4079 to Zuluf-410/419
    – (e) 16-inch power line from Safaniya-4210/4219 to Zuluf-330/339
    Installation of four subsea valve skids
    Installation of three offshore jackets
     
  • CRPO 142: 13 March
    Replacement of 17km flank pipeline at the Abu Safah field
    Demolition work
     
  • CRPO 143: 13 March
    Replacement of Berri and Manifa lateral lines

Aramco’s LTA pool of offshore service providers comprises the following entities:

  • Saipem (Italy)
  • McDermott International (US)
  • Larsen & Toubro Hydrocarbon Engineering (India) / Subsea 7 (UK)
  • Dynamic Industries (US)
  • National Petroleum Construction Company (UAE)
  • Lamprell (UAE/Saudi Arabia)
  • Sapura Energy (Malaysia)
  • Technip Energies (France) / MMHE (Malaysia)
  • China Offshore Oil Engineering Company (China)
  • Hyundai Heavy Industries (South Korea)
ALSO READ: Aramco spending drawdown to jolt oil projects

https://image.digitalinsightresearch.in/uploads/NewsArticle/11612829/main1727.jpg
Indrajit Sen
Related Articles
  • Parsons wins role on Elon Musk-backed Dubai Loop project

    4 May 2026

    US-based Parsons Corporation has been appointed to deliver programme management services for the Dubai Loop transportation system.

    The contract was awarded by Elon Musk-backed firm The Boring Company, which signed a construction agreement with Dubai’s Roads & Transport Authority (RTA) in February.

    Parsons’ scope of work includes independent design verification, stakeholder management, permitting and no-objection certificate (NOC) support, and multidisciplinary design reviews for the project’s first phase.

    The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.

    Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.

    The first phase is expected to cost about AED565m ($154m) and to be delivered within one year after design work and other preparations are completed. Tunnelling is expected to begin in the second half of this year.

    Next phase

    The second phase will connect Dubai World Trade Centre and DIFC with Business Bay.

    The tunnels will extend up to 22km and include 19 stations.

    The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.

    The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.

    The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.

    The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.

    The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16672074/main.jpg
    Yasir Iqbal
  • Humain tenders infrastructure for 6GW data centre campus

    4 May 2026

    Saudi artificial intelligence (AI) infrastructure company Humain, owned by the Public Investment Fund (PIF), has issued a tender inviting firms to develop infrastructure for its planned 6GW hyperscale AI data centre campus in Riyadh.

    The project will be delivered on an early contractor involvement (ECI) basis. Under the ECI process, selected contractors are required to submit methodologies and design proposals, after which one team will be selected to deliver the construction works.

    Firms have until 8 May to submit proposals.

    The development will be built on a 24-square-kilometre site in the Al-Saad area in east Riyadh. It will be delivered in two phases across six plots, each with a capacity of 1GW.

    The scope of infrastructure work covers:

    • Construction of 380kV/132kV/33kV electrical distribution network, two substations with a capacity of 500MVA and 200MVA, bulk supply point (2,000MVA)
    • Water network and fire protection systems
    • Sewage treatment plant and wastewater network
    • Stormwater systems
    • Roads
    • Underground cable and fibre optic networks
    • Landscaping works

    The client is being supported by Canadian engineering firm Hatch, France’s Egis and US-based firm JLL.

    Humain was launched in May last year to operate and invest across the AI value chain.

    Humain is building full-stack AI capabilities across four core areas: next-generation data centres, hyper-performance infrastructure and cloud platforms, and advanced AI models, including Allam.

    Also in May 2025, Humain signed preliminary deals with US chipmakers AMD and Nvidia to build multibillion-dollar advanced digital infrastructure in the kingdom.

    AMD said it will invest up to $10bn to deploy 500MW of AI compute capacity in Saudi Arabia over the next five years.

    In October, PIF and Saudi Aramco signed a non-binding term sheet setting out key terms under which Aramco would acquire a minority stake in Humain, with PIF retaining majority ownership.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16671267/main.jpg
    Yasir Iqbal
  • Abu Dhabi selects consortium for 2.5GW Taweelah C IPP

    4 May 2026

     

    Register for MEED’s 14-day trial access 

    A consortium of Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore) has been selected to develop the Taweelah C independent power producer (IPP) project in Abu Dhabi.

    The consortium will sign a power purchase agreement (PPA) in mid-May, a source told MEED.

    The combined-cycle gas turbine (CCGT) plant will have a capacity of 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.

    It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction (EPC) contractor.

    Last September, MEED reported that state offtaker Emirates Water & Electricity Company (Ewec) had received three bids for the facility.

    The bidders included:

    • Al-Jomaih Energy & Water Company / Sembcorp Industries
    • Sumitomo Corporation (Japan) / Korea Overseas Infrastructure & Urban Development Corporation / Korean Midland Power
    • Korea Western Power Company / Etihad Water & Electricity (UAE) / Kyuden International (Japan)

    At the time, Mohamed Al-Marzooqi, chief asset development and management officer at Ewec, said the bids would make Taweelah C “one of the lowest tariff CCGT projects in the region”.

    The carbon-capture-ready facility had been scheduled to begin commercial operations in the fourth quarter of 2028.

    This was based on the initial timeline for a PPA to be signed in the fourth quarter of 2025.

    Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.

    Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared to 2019.

    Ewec is also expanding its low-carbon water desalination capacity, with the Taweelah reverse osmosis (RO) plant already operating as the world’s largest RO facility and additional projects, such as the Mirfa 2 RO and Shuweihat 4 RO, under way.

    By 2030, it expects 95% of Abu Dhabi’s installed water capacity to come from RO technology.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670622/main0858.jpg
    Mark Dowdall
  • Dubai launches Blue Line metro tunnelling works

    4 May 2026

    Dubai has announced the launch of tunnelling works for the Dubai Metro Blue Line extension project.

    In a post on X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President, Prime Minister and Ruler of Dubai, announced the start of operations of the tunnel boring machine (TBM), which the Roads & Transport Authority (RTA) has named ‘Al-Wugeisha’.

    The TBM is 163 metres long, weighs more than 2,000 tonnes and will operate around the clock. The post added that its average excavation rate ranges from 13 to 17 metres a day.

    The Blue Line will connect the existing Red and Green lines. It will be 30 kilometres (km) long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project to a consortium comprising Turkiye’s Limak Holding and Mapa Group, along with the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The consortium is responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, it will assist with maintenance and operations for an initial three-year period.

    According to an official statement, the Blue Line will have a capacity of 46,000 passengers an hour in both directions.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670584/main.jpeg
    Yasir Iqbal
  • Firms submit Jeddah distribution centre bids

    4 May 2026

     

    Contractors submitted bids on 26 April for an estimated SR140m ($37m) contract to build a distribution centre in Jeddah.

    Saudi Logistics Services Company (SAL) launched the tender on 11 March, as previously reported by MEED. The project will cover an area of about 37,000 square metres. Egyptian firm Cosmos-E Engineers & Consultants has been appointed as the project consultant.

    This tender follows the start of construction by Egyptian contractor Rowad Modern Engineering, a subsidiary of Elsewedy Electric Group, on the expansion of SAL’s facilities at King Khalid International airport in Riyadh. The scope of work includes rehabilitating and upgrading existing infrastructure, as well as constructing new supporting facilities and services.

    SAL also launched the tendering process in September last year for its SR4.2bn ($1bn) logistics zone in northern Riyadh, MEED previously reported. UAE-based Global Engineering Consultants is the consultant for that development.

    The logistics hub aims to meet demand for customised warehouses near King Khalid International airport and the Riyadh Metro. The project aligns with Vision 2030 and the National Transport & Logistics Strategy, which aims to strengthen the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670338/main.gif
    Yasir Iqbal