Contractors confirm Adnoc contracts for Hail and Ghasha
18 January 2023
Contractors have confirmed signing a pre-construction services agreement (PCSA) with Abu Dhabi National Oil Company (Adnoc) for the onshore scope of the Hail and Ghasha offshore sour gas field development.
France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont, which have formed a consortium for the Hail and Ghasha onshore package, have issued statements about being awarded the PCSA. The contractors revealed the value of the contract to be approximately $80m.
The onshore work on the Hail and Ghasha scheme involves the construction of a gas process plant, pipeline network and new gas gathering units.
As part of the PCSA, the contractors are required to perform initial detailed engineering and procurement services of critical long lead items.
“The PCSA scope of work also includes the preparation of an open book cost estimate for the project delivery of the onshore scope, which will be considered as part of the client’s [Adnoc] final investment decision making process,” they said in their statements.
Under the terms of the other PCSA, Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) will work together on the offshore package, which covers the installation of offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.
The offshore contractors have confirmed the value of their PCSA with Adnoc to be $60m.
Project progress
MEED in September last year reported on contractors submitting proposals for the detailed engineering work on the Hail and Ghasha megaproject as part of an early engagement process.
The PCSAs Adnoc has signed with the two consortiums are understood to be based on the proposals received last year.
The early engagement process with contractors is expected to precede the start of the full engineering, procurement and construction (EPC) execution phase of the strategic scheme.
US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for what were four EPC packages issued soon after.
However, following the submission of commercial bids in early 2021, Adnoc opted to make revisions to the feed as part of an optimisation process started by Technip Energies in November 2021.
The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.
As part of the optimisation process, the four original EPC packages were consolidated into two integrated offshore and onshore packages, which are now estimated to be as high as $5bn and $5.5bn, respectively, as per sources and based on the previous version of the project.
Following the award of the PCSAs, the consortiums will get to work on the detailed design aspect of their respective packages, with the aim of putting together a final offer for the main EPC work on Hail and Ghasha.
The timing of the award of the final EPC contracts is unknown at this point, but considering the fast-track execution schedule Adnoc is known to have planned for the Hail and Ghasha project, it could be expected to take place before the end of this year.
Hail and Ghasha fields
The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.
Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent; Germany’s Wintershall Dea with 10 per cent; and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.
Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.
In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn for executing offshore and onshore EPC works on the Dalma project, respectively.
Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.
In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.
The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract for the provision of four island drilling units. Their duration is 10 years.
Adnoc also awarded a third contract, valued at $681m, to another subsidiary company, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.
Exclusive from Meed
-
Egypt seeks consultant for major inland waterway study18 November 2025
-
Kuwait to make decision on four oil pipeline packages18 November 2025
-
Indian firm wins Oman chemicals project EPC contract17 November 2025
-
Egypt starts production from strategic gas field17 November 2025
-
Major Iraq refinery project stalls17 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt seeks consultant for major inland waterway study18 November 2025
Egypt’s Transport Ministry has issued an expressions of interest (EOI) request, through the River Transport Authority, to appoint a consultancy firm for a study on a proposed inland waterway linking Lake Victoria to the Mediterranean.
The consultant will carry out basin-wide data collection and prepare a strategic environmental and social assessment for the project.
The assignment includes hydrological, topographic, bathymetric and geotechnical surveys across the Nile Basin.
The consultancy is expected to run for about 15 months, starting in February or March 2026.
Firms must submit EOIs by 6 December.
The study forms part of the Vic-Med project, a multi-country plan to establish a continuous inland waterway from Lake Victoria to the Mediterranean Sea.
The masterplan project aims to reduce transport costs for landlocked countries and provide a lower-carbon alternative to road freight along the Nile corridor
The work is part of phase two, part one of the feasibility study, funded through a $2m grant from the New Partnership for Africa's Development – Infrastructure Project Preparation Facility (NEPAD–IPPF), the African Development Bank’s (AfDB) fund for early-stage project development.
The first phase, completed in July 2019 with $650,000 in AfDB funding, developed the project’s legal and institutional framework and launched two regional inland water transport programmes.
The second phase, valued at $11.7m, covers updated feasibility studies and expanded technical assessments supporting detailed engineering design and cost-benefit analysis in the next stage.
This phase also covers the establishment of a regional operating unit for the project in Cairo.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15108707/main.jpg -
Kuwait to make decision on four oil pipeline packages18 November 2025

Kuwait is evaluating bids on four packages for a major pipeline project after prices were submitted earlier this month, according to industry sources.
The four separate packages cover pipeline work in the north, south, east and west regions of the country, sources said.
Although the total of all bids submitted by Kuwait-based Alghanim International General Trading & Contracting is the lowest at KD419m ($1.4bn), the company submitted the lowest individual bid on only one package, located in northern Kuwait.
Its bid for the north Kuwait package was KD149.8m ($488.3m).
Mechanical Engineering & Construction Company submitted the lowest bids for pipeline work on two packages located in the south and east of the country.
Both of these bids were valued at KD97,868,394 ($319m).
Al-Dar Engineering & Construction Company is the low bidder on the fourth package, for pipe work in western Kuwait, submitting a bid of KD64,825,398 ($211.3m).
Together, all four contracts are expected to be worth about $1.4bn when awarded.
The scope of all four packages focuses on developing new flowlines and connecting pipelines for oil-producing wells and water wells.
In some cases, companies are also required to replace old flowlines.
The contracts are based on work orders, so when KOC needs to connect wells it will issue a request for work execution, industry sources said.
Kuwait is trying to boost project activity in its upstream sector.
The country’s national oil company, Kuwait Petroleum Corporation, is aiming to increase oil production capacity to 4 million barrels a day (b/d) by 2035.
In August, Kuwait announced that it was producing 3.2 million b/d.
Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15106496/main.png -
Indian firm wins Oman chemicals project EPC contract17 November 2025
Register for MEED’s 14-day trial access
Indian contractor Nuberg EPC has won a contract to perform engineering, procurement and construction (EPC) works on a project to build chlor alkali and calcium chloride plants in Oman for privately-owned Al-Ghaith Chemical Industries.
The project involves expanding Al-Ghaith’s existing chlor alkali plant in Sur Industrial City, by adding 120 tonnes a day (t/d) of capacity, taking the unit’s total output capacity to 190 t/d. The project also involves building a calcium chloride plant that will have a production capacity of 80 t/d.
Nuberg EPC said the contract is being executed on a lump sum turnkey basis, with its scope covering design, front-end engineering and design (feed), detailed engineering, procurement, fabrication, construction, commissioning and handover.
Project execution is already under way, with completion targeted within 19 months, Nuberg EPC said.
The project marks the second phase of Al-Ghaith’s integrated chemicals complex in Sur and represents a first-of-its-kind large-scale chlor alkali expansion in Oman.
Nuberg EPC also performed EPC works on the original chlor alkali plant, which has a capacity of 70 t/d.
In addition to the Oman project, Al-Ghaith has, in the previous decade, also brought on board Nuberg EPC for its chlor alkali and calcium chloride plants in Abu Dhabi. Those contracts covered the commissioning of a 60 t/d chlor alkali plant that was later expanded to 120 t/d, and the execution of a 125 t/d calcium chloride plant and a 50 t/d carbon dioxide plant.
Nuberg EPC has also executed the expansion of a 45 t/d chlor alkali plant and a greenfield 80 t/d calcium chloride plant for Oman Chlorine in Sohar, increasing the total chlor alkali output capacity to 75 t/d.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15104096/main5048.jpg -
Egypt starts production from strategic gas field17 November 2025
Egypt has started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid, according to a statement from the country’s Petroleum & Mineral Resources Ministry.
Productivity testing showed an output rate approaching 45 million cubic feet a day (cf/d).
Kareem Badawi, Egypt’s Petroleum & Mineral Resources Minister, said he intends to accelerate development of the field and confirmed that work is under way to connect two additional wells, with the aim of increasing production to 75 million cf/d in the coming months.
He added that the ministry aims to cut the county’s gas import bill by boosting domestic production.
The operator of the concession is Cheiron, an Egyptian independent exploration and production company.
Egypt’s oil ministry said in its statement that the West Burullus field development project represents a model for future integrated projects and investment plans.
It said that a range of domestic and foreign companies are involved in bringing the field into production.
In February, a banking consortium led by Banque du Caire, alongside Arab International Bank, Al-Baraka Bank Egypt and Saib Bank, arranged $75m in syndicated medium-term financing for Cheiron Egypt Delta, a subsidiary of the Cheiron Group.
This financing will help cover part of the investment costs for the gas field development project.
At the time, Cheiron said that the financing will provide up to 45.5% of the total $165m investment required for the project.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15102295/main3406.jpg -
Major Iraq refinery project stalls17 November 2025

Construction has yet to start on Iraq’s Al-Faw Investment Refinery project due to a range of problems, according to industry sources.
In May last year, a statement released by the Iraqi Prime Minister’s Office said that Iraq’s state-owned Southern Refineries Company and China National Chemical Engineering Company (CNCEC) had signed a contract to develop the project.
Iraq’s Oil Ministry previously said the project would be worth $7bn-$8bn.
One source said: “This project is failing to make progress despite the efforts of senior political figures in the country.”
A meeting was chaired by Iraqi Prime Minister Mohammed Shia Al-Sudani in August this year to discuss and try to resolve the problems that are stopping the commencement of construction, according to industry sources.
It is believed that financing remains a key obstacle for the project.
The Al-Faw project is part of the Iraqi government’s plan to increase Iraq’s refining capacities, attract foreign investment and increase the production of petroleum products domestically.
The refinery will have a capacity of 300,000 barrels a day and will produce oil derivatives for both domestic and international markets.
The project will be carried out in two stages.
The first phase will involve refining operations, while the second will involve constructing a petrochemicals complex with a capacity of 3 million tonnes a year.
The project also includes the construction of a 2,000MW power plant and the establishment of the Al-Faw Academy for Refinery Technology, to train 5,000 Iraqi workers that will eventually work at the facility.
Hualu, a subsidiary of CNCEC, signed a preliminary principles agreement for the project in December 2021.
At the time, Iraq’s Oil Ministry said that the project would have a value of $7bn-$8bn.
Due to material price inflation since December 2021, some insiders believe that the project value may now be significantly higher.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15102287/main.jpg

