Contractors confirm Adnoc contracts for Hail and Ghasha
18 January 2023
Contractors have confirmed signing a pre-construction services agreement (PCSA) with Abu Dhabi National Oil Company (Adnoc) for the onshore scope of the Hail and Ghasha offshore sour gas field development.
France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont, which have formed a consortium for the Hail and Ghasha onshore package, have issued statements about being awarded the PCSA. The contractors revealed the value of the contract to be approximately $80m.
The onshore work on the Hail and Ghasha scheme involves the construction of a gas process plant, pipeline network and new gas gathering units.
As part of the PCSA, the contractors are required to perform initial detailed engineering and procurement services of critical long lead items.
“The PCSA scope of work also includes the preparation of an open book cost estimate for the project delivery of the onshore scope, which will be considered as part of the client’s [Adnoc] final investment decision making process,” they said in their statements.
Under the terms of the other PCSA, Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) will work together on the offshore package, which covers the installation of offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.
The offshore contractors have confirmed the value of their PCSA with Adnoc to be $60m.
Project progress
MEED in September last year reported on contractors submitting proposals for the detailed engineering work on the Hail and Ghasha megaproject as part of an early engagement process.
The PCSAs Adnoc has signed with the two consortiums are understood to be based on the proposals received last year.
The early engagement process with contractors is expected to precede the start of the full engineering, procurement and construction (EPC) execution phase of the strategic scheme.
US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for what were four EPC packages issued soon after.
However, following the submission of commercial bids in early 2021, Adnoc opted to make revisions to the feed as part of an optimisation process started by Technip Energies in November 2021.
The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.
As part of the optimisation process, the four original EPC packages were consolidated into two integrated offshore and onshore packages, which are now estimated to be as high as $5bn and $5.5bn, respectively, as per sources and based on the previous version of the project.
Following the award of the PCSAs, the consortiums will get to work on the detailed design aspect of their respective packages, with the aim of putting together a final offer for the main EPC work on Hail and Ghasha.
The timing of the award of the final EPC contracts is unknown at this point, but considering the fast-track execution schedule Adnoc is known to have planned for the Hail and Ghasha project, it could be expected to take place before the end of this year.
Hail and Ghasha fields
The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.
Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent; Germany’s Wintershall Dea with 10 per cent; and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.
Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.
In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn for executing offshore and onshore EPC works on the Dalma project, respectively.
Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.
In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.
The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract for the provision of four island drilling units. Their duration is 10 years.
Adnoc also awarded a third contract, valued at $681m, to another subsidiary company, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.
Exclusive from Meed
-
Firms submit Mid Island Parkway prequalifications18 August 2026
-
Adnoc selects contractors for new LNG project in the UAE18 August 2026
-
Saudi Arabia extends bid deadline for Round 7 solar projects18 August 2026
-
Construction begins on phase two of Cairo Metro Line 418 August 2026
-
RTA opens bridge connecting DWTC to Al-Mustaqbal Street18 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms submit Mid Island Parkway prequalifications18 August 2026

Abu Dhabi’s Modon Infrastructure has received expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership.
Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.
Phase two of the MIPP involves constructing about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.
The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.
The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.
Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.
Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.
Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.
It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18830452/main.png -
Adnoc selects contractors for new LNG project in the UAE18 August 2026

Abu Dhabi National Oil Company (Adnoc) has selected contractors for a design competition it is overseeing for a major project to build a new liquefied natural gas (LNG) export facility along the UAE’s eastern coast.
The proposed onshore LNG liquefaction facility – whose precise location Adnoc has yet to reveal – will have a nameplate output capacity of 4 million tonnes a year (t/y) and will mainly serve export purposes, MEED reported in June. The facility will receive sales-gas-quality feedstock via pipelines from Adnoc’s gas processing facilities in Abu Dhabi and will export LNG via a loading jetty.
MEED previously reported on Adnoc’s intention to execute work on the project through a design competition or front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) contest.
Under this model, the project operator selects contractors to carry out feed work. The operator then awards the EPC contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.
The Abu Dhabi energy giant has selected the following three entities to undertake feed work on the planned onshore LNG liquefaction facility, according to sources:
- Saipem (Italy) / Larsen & Toubro Energy Hydrocarbon (India)
- Technip Energies (France) / JGC Corporation (Japan)
- Tecnimont (Italy)
Adnoc issued draft letters of award to the selected contractors between 11 and 12 August, the sources added.
In addition to the contractors picked by Adnoc, MEED previously reported that the following contractors were shortlisted for the feed-to-EPC contest:
- McDermott (US)
- Samsung E&A (South Korea)
- Wison (China)
MEED reported that Adnoc issued the expression of interest (EoI) document for the planned LNG facility project on 2 June, with contractors submitting responses by 5 June.
Given the strategic importance of the project, Adnoc is understood to be fast-tracking the tendering exercise, issuing the main tender for the feed-to-EPC contest within days of the EoI submission. The company sought proposals from participating contractors by 1 July, sources said.
In its EoI document, Adnoc said it intends to award the main EPC contract in the third quarter of this year.
Adnoc has yet to specify where it plans to build the LNG complex, stating only in the EoI document that it will be located at a coastal site in the UAE.
MEED understands Adnoc may be considering a site near one of the UAE’s eastern port facilities in the emirate of Fujairah. The blockade of the Strait of Hormuz in recent months has increased interest in prioritising exports and maritime trade through ports on the Gulf of Oman.
The scope of work on the planned LNG facility covers the following units:
LNG facilities:
- An onshore LNG liquefaction facility in a coastal location, with a nominal output capacity of 4 million t/y;
- Process units necessary to bring sales feed to a liquefaction-quality feed gas (i.e. carbon dioxide removal, dehydration, mercury removal and total sulphur reduction);
- Common facilities including inlet receiving facilities, refrigerant storage and flares;
- Utilities to support the facility, allowing it to be self-sufficient, including but not limited to local power generation and any necessary tie-ins;
- LNG export facilities, including a jetty and berth;
- Structures including control buildings, amenities, a laboratory, a warehouse, workshops and administration buildings, to fully support the plant operation.
LNG storage facilities:
- LNG storage tanks, handling of boil-off gases (BOG) and potentially a BOG reliquefaction unit to facilitate major shutdown operations for bidders opting to compete with a single liquefaction train option.
Feed gas supply:
- Supplying and installing an additional identical gas compressor to be located at an existing compression station near Adnoc Gas’ Habshan complex in Abu Dhabi, to provide additional capacity in an existing gas pipeline system;
- A new feed gas pipeline, approximately 160 kilometres long, to route sales gas quality feed gas from an existing pipeline network to the LNG facility.
Modifications to upstream facilities (alternative scope):
- Installation of sulphur removal beds in Habshan to bring feed gas to required LNG quality at the upstream gas conditioning facility, rather than at the LNG facility. This may be selected by bidders to avoid additional investment for processing the regeneration gas.
Construction facilities:
- Temporary construction facilities, laydown area and material offloading facility, to support EPC execution requirements;
- Construction labour accommodation camp.
Adnoc LNG output capacity
Adnoc has an LNG liquefaction capacity of 6 million t/y, which is set to more than double to 15 million t/y when its under-construction LNG terminal complex in Abu Dhabi’s Ruwais enters operations in 2028.
The upcoming LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.
Adnoc awarded the full EPC contract and reached the final investment decision for the Ruwais LNG terminal project in June 2024. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy – a subsidiary of NMDC Group – was awarded the $5.5bn EPC contract. In March of that year, Adnoc issued a limited notice to proceed to the consortium of contractors led by Technip Energies for early EPC works on the Ruwais LNG terminal project.
The complex will feature process units, storage tanks and an export jetty for loading cargoes and LNG bunkering, as well as utilities, flare handling systems and associated buildings.
The planned LNG facility will run on electric-powered rotary equipment and compressors instead of gas-fired units. Adnoc awarded a $400m contract in October 2023 to US-based Baker Hughes for the supply of all-electric compression systems for the project. The LNG trains will run on energy-efficient Baker Hughes technology, including compressors driven by 75MW electric motors.
Adnoc has also signed agreements with international energy companies to divest a total stake of 40% in the Ruwais LNG project. UK energy producer BP, Mitsui & Co, Shell and French energy producer TotalEnergies will each hold 10% stakes in the Ruwais LNG terminal project, with Adnoc retaining the majority 60% stake in the facility.
Adnoc Group subsidiary Adnoc Gas will acquire its parent company’s 60% stake in the Ruwais LNG facility at cost in the second half of 2028, when first production from the complex is due.
To date, Adnoc has secured offtake agreements totalling 8 million t/y, representing approximately 90% of the Ruwais LNG project’s output capacity.
Photo for illustration only
https://image.digitalinsightresearch.in/uploads/NewsArticle/18829520/main.jpg -
Saudi Arabia extends bid deadline for Round 7 solar projects18 August 2026

Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), has extended the deadline for developers bidding for four solar projects under the seventh round of the National Renewable Energy Programme (NREP).
Round seven of the NREP comprises solar photovoltaic (PV) and wind independent power producer (IPP) projects with a combined capacity of 5,300MW. The renewables programme is being led and supervised by the Ministry of Energy.
The four solar PV projects comprise:
- 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf province)
- 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail province)
- 600MW Tathleeth solar PV IPP (Tathleeth, Aseer province)
- 500MW South Al-Ula solar PV IPP (Al-Ula, Medina province)
The projects were tendered in January, with submissions previously expected by 30 August. The new deadline is 13 September.
The programme also includes the 1,300MW Bilgah and 900MW Shagra wind IPPs. The bid submission deadline for these projects is 14 September.
As previously reported by MEED, procurement for the seventh round of the NREP opened in August 2025 when SPPC issued a request for qualification.
In January, MEED reported that 16 developers qualified to bid as both managing and technical members for the four solar PV projects. A further six companies qualified to bid as a managing member only.
For the wind IPPs, SPPC qualified 13 developers in the managing and technical members category, and a further six companies in the managing member category only. The request for proposals for both wind and solar IPPs was issued that same month.
The renewable energy programme aims to supply 50% of the kingdom’s electricity from renewable energy by 2030.
Earlier rounds under the NREP have already put in place large capacities. Last October, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP.
These comprise four solar PV IPP projects and one wind IPP project with a total combined capacity of 4,500MW.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18828963/main.jpg -
Construction begins on phase two of Cairo Metro Line 418 August 2026
Egypt’s National Authority for Tunnels (NAT) has begun implementing the second phase of Cairo Metro’s Line 4, spanning about 27 kilometres.
The main construction works contract was awarded to a joint venture of local firms, including Arab Contractors, Hassan Allam, Petrojet and Concord Engineering & Contracting.
Cairo Metro Line 4 will stretch from Fustat station to Zahraa Nasr City station in New Cairo. The line will comprise 21 stations, 15 underground and six elevated.
According to data from regional projects tracker MEED Projects, the scope also covers:
- Construction of a tunnel route starting from Al-Fustat station, following Salah Salem Road, and intersecting with the sixth metro line at Sayeda Aisha station
- An extension along Hafez Ibrahim Street, intersecting the Shinzo Abe Axis and linking Ahmed Al-Zomor and Al-Mithaq streets
- A section running via Nasr Road and Nasr City to Anwar Al-Mufti Street, with an interchange with the East Nile Monorail at Aviation station
- Construction of a depot at the Omra El-Gasima site
- Integration of interchange stations with existing lines, including Line 1 and Line 2
- Construction of structures over and under major roadways, including the Ring Road and Cairo-Suez Road
- Earthworks and site preparation, including elevated foundations and underground excavations
- Construction of all other associated infrastructure
Local media reports said construction work on the first phase of Line 4 is expected to be completed in 2028.
The joint venture of Arab Contractors, Hassan Allam, Petrojet and Concord Engineering & Contracting is also undertaking the main works on the first phase.
The Japan International Cooperation Agency (Jica) provided half of the $4bn funding required for Line 4’s first phase.
The media reports added that NAT is currently studying the third and fourth phases of Line 4.
The third phase aims to connect the Ashgar Gardens and Al-Hosary areas via a rail line spanning more than 16km.
The fourth phase will be more than 38km long and will connect the Al-Rehab area with the capital’s international airport east of Cairo.
Once completed across all phases, Line 4 will link 6th of October City with southern and eastern Cairo, the New Administrative Capital and Capital International airport, making it one of the longest transport networks in the country.
In April last year, MEED reported on Egypt’s future rail project plans, which include eight key projects spanning metro, high-speed rail and light rail transit.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18825481/main.jpg -
RTA opens bridge connecting DWTC to Al-Mustaqbal Street18 August 2026
Dubai’s Roads & Transport Authority (RTA) has opened a new 500-metre, two-lane bridge connecting traffic from Dubai World Trade Centre (DWTC) and One Central to Al-Mustaqbal Street.
The bridge will reduce travel time from DWTC to Al-Mustaqbal Street from around 10 minutes to about two minutes during major events.
The bridge is part of the $172m Al-Mustaqbal Street Development Project. The wider scheme includes around 2,000 metres of bridges and tunnels, along with a pedestrian bridge on Al-Sukook Street, and runs from Zaabeel Palace Street to Financial Centre Street.
As part of the project, Al-Mustaqbal Street will be widened from three to four lanes in each direction, increasing overall capacity by 33% to 8,800 vehicles per hour in both directions.
The RTA added that this is expected to cut end-to-end travel time along the corridor from 13 minutes to six minutes.
Three tunnels, totalling 1,500 metres, at the intersection of Al-Mustaqbal Street and Trade Centre Street are scheduled to open in February 2027.
These include a three-lane tunnel towards Deira with a capacity of 4,500 vehicles per hour, a two-lane tunnel for left-turn movements between the two streets, and a one-lane tunnel serving One Central.
The RTA said that the overall project completion rate has reached 85%.
In February last year, MEED exclusively reported that the RTA had selected local firm Wade Adams to undertake improvement works on Al-Mustaqbal Street.
Planning for growth
The Dubai 2040 Urban Master Plan was launched in March 2021. Its launch referenced studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.
In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan.
In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.
The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18822891/main.jpg
