Contractors confirm Adnoc contracts for Hail and Ghasha

18 January 2023

Contractors have confirmed signing a pre-construction services agreement (PCSA) with Abu Dhabi National Oil Company (Adnoc) for the onshore scope of the Hail and Ghasha offshore sour gas field development.

France-headquartered Technip Energies, South Korean contractor Samsung Engineering and Italy’s Tecnimont, which have formed a consortium for the Hail and Ghasha onshore package, have issued statements about being awarded the PCSA. The contractors revealed the value of the contract to be approximately $80m.

The onshore work on the Hail and Ghasha scheme involves the construction of a gas process plant, pipeline network and new gas gathering units.

As part of the PCSA, the contractors are required to perform initial detailed engineering and procurement services of critical long lead items.

“The PCSA scope of work also includes the preparation of an open book cost estimate for the project delivery of the onshore scope, which will be considered as part of the client’s [Adnoc] final investment decision making process,” they said in their statements.

Under the terms of the other PCSA, Italian contractor Saipem, Abu Dhabi’s National Petroleum Construction Company (NPCC) and state-owned China Petroleum Engineering & Construction Company (CPECC) will work together on the offshore package, which covers the installation of offshore platforms, gas compression facilities and more than 400 kilometres of subsea pipelines.

The offshore contractors have confirmed the value of their PCSA with Adnoc to be $60m.

Project progress

MEED in September last year reported on contractors submitting proposals for the detailed engineering work on the Hail and Ghasha megaproject as part of an early engagement process.

The PCSAs Adnoc has signed with the two consortiums are understood to be based on the proposals received last year.

The early engagement process with contractors is expected to precede the start of the full engineering, procurement and construction (EPC) execution phase of the strategic scheme.

US engineering firm Bechtel completed the project’s original front-end engineering and design (feed) in 2019, with tenders for what were four EPC packages issued soon after.

However, following the submission of commercial bids in early 2021, Adnoc opted to make revisions to the feed as part of an optimisation process started by Technip Energies in November 2021.

The revised feed aimed to reduce the scheme’s overall capital expenditure, which was previously estimated to be as high as $15bn.

As part of the optimisation process, the four original EPC packages were consolidated into two integrated offshore and onshore packages, which are now estimated to be as high as $5bn and $5.5bn, respectively, as per sources and based on the previous version of the project.

Following the award of the PCSAs, the consortiums will get to work on the detailed design aspect of their respective packages, with the aim of putting together a final offer for the main EPC work on Hail and Ghasha.

The timing of the award of the final EPC contracts is unknown at this point, but considering the fast-track execution schedule Adnoc is known to have planned for the Hail and Ghasha project, it could be expected to take place before the end of this year.

Hail and Ghasha fields

The Hail and Ghasha fields, along with the Hair Dalma, Satah, Bu Haseer, Nasr, Sarb, Shuwaihat and Mubarraz fields, are located in Abu Dhabi’s offshore Ghasha concession.

Adnoc holds the majority 55 per cent stake in the Ghasha concession. The other stakeholders are Italian energy major Eni with 25 per cent; Germany’s Wintershall Dea with 10 per cent; and Austria’s OMV and Russia’s Lukoil, each with 5 per cent.

Adnoc plans to produce more than 1.5 billion cubic feet a day of sour gas from the Ghasha concession by the middle of this decade. This target is aligned with the company’s broader goal of achieving gas self-sufficiency for the UAE by 2030.

In November 2021, Adnoc and its partners in the Ghasha concession awarded two EPC contracts for the Dalma offshore sour gas development project. Abu Dhabi’s NPCC and Spain-headquartered Tecnicas Reunidas won contracts worth $1.46bn for executing offshore and onshore EPC works on the Dalma project, respectively.

Four artificial islands have already been completed in the Ghasha concession, and development drilling is under way.

In addition, Adnoc awarded two contracts totalling $2bn to its subsidiary Adnoc Drilling in July last year for the Hail and Ghasha offshore sour gas field development project.

The awards comprise a $1.3bn contract for integrated drilling services and fluids, and a $711m contract for the provision of four island drilling units. Their duration is 10 years.

Adnoc also awarded a third contract, valued at $681m, to another subsidiary company, Adnoc Logistics & Services, to provide offshore logistics and marine support services for the planned Hail and Ghasha development.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10526349/main.jpg
Indrajit Sen
Related Articles
  • Public Investment Fund backs Neom

    16 April 2026

    Commentary
    Colin Foreman
    Editor

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has backed Neom by including it as one of six strategic ecosystems in its newly approved 2026-30 strategy.

    The future of the $500bn gigaproject had been thrown into doubt following the postponement of the 2029 Asian Winter Games at the Trojena mountain resort, the cancellation of construction contracts – such as the $5bn deal with Italian contractor Webuild for dam works at Trojena – and the slowdown of development at The Line, where tunnelling contracts were cancelled and staff left the project.

    The backing comes as Neom’s operational focus appears to be evolving in response to shifting regional dynamics and global economic conditions. For example, on 15 April Neom posted on its official X account about a new Europe-Egypt-Neom-GCC corridor, describing it as a faster route for time-sensitive goods. It said the corridor combines trucking and ferry services to move goods quickly into the Gulf, adding that importers from several European markets are already using it to reach the UAE, Kuwait, Iraq, Oman and beyond.

    Powered by Pan Marine, DFDS and regional RoPax services, the initiative is positioned as a way to add flexibility and resilience to regional supply chains. This emphasis on logistics and immediate trade utility suggests a shift away from the more speculative architectural announcements that characterised Neom’s early years, towards activity more directly tied to current market realities.

    PIF’s broader 2026-30 strategy places heavy emphasis on “delivering competitive domestic ecosystems to connect sectors, unlock the full potential of strategic assets, maximise long-term returns and continue to drive the economic transformation of Saudi Arabia”.

    The inclusion of Neom as a standalone ecosystem within the Vision Portfolio suggests that while the project remains part of the kingdom’s Vision 2030 goals, it will be subject to the fund's focus on working with the private sector.

    That means the long-term success of Neom will increasingly depend on its ability to attract external investment and function as a viable economic hub rather than just a state-funded construction site.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16417262/main.jpeg
    Colin Foreman
  • Kuwait gas project worth $3.3bn put on hold

    16 April 2026

     

    State-owned Kuwait Gulf Oil Company’s (KGOC’s) planned tender for the development of an onshore gas plant next to the Al-Zour refinery has been put on hold due to uncertainty created by the US and Israel’s war with Iran, according to industry sources.

    The project budget is estimated to be $3.3bn, and the last meeting with contractors to discuss the project took place in Kuwait on 10 February.

    Previously, it was expected to be tendered in late March, but the tendering process was delayed due to the regional conflict and disruption to shipping through the Strait of Hormuz.

    One source said: “This tender is now effectively on hold while KGOC waits for increased stability in the region before it invites companies to bid for the contract.”

    Under current plans, the plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    Ownership of the field is disputed by Iran, which refers to the field as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    It is believed that the Dorra field’s close proximity to Iran will make development difficult due to the current security environment.

    The offshore elements of the project are expected to be especially difficult to protect from attacks from Iran.

    In July last year, MEED reported that KGOC had initiated the project by launching an early engagement process with contractors for the main engineering, procurement and construction tender.

    France-based Technip Energies completed the contract for the front-end engineering and design.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413221/main.png
    Wil Crisp
  • Iraq pushes to revive oil pipeline through Saudi Arabia

    16 April 2026

    Iraq is pushing to revive an oil pipeline that passes through Saudi Arabia, allowing it to diversify export routes.

    Saheb Bazoun, a spokesman for Iraq’s Oil Ministry, said the pipeline would help to insulate Iraq from any future blockades of the Strait of Hormuz, which has been largely closed since 28 February.

    The original pipeline through Saudi Arabia has not been used for more than 30 years and would need work to be done in order to bring it online.

    It is 1,568km long, extending from the city of Zubair in Iraq to the Saudi port of Yanbu on the Red Sea.

    The pipeline was built in two phases during the 1980s. The first phase stretches between Zubair and Khurais, while the second extends to Yanbu. The pipeline’s operating capacity reached over 1.6 million barrels a day (b/d).

    Following the Gulf War, the pipeline was shut down in August 1990. It has remained out of operation for decades, despite Iraq’s several attempts to restart it.

    The original pipeline project cost over $2.6bn, including storage tanks and loading terminals.

    In the wake of the US and Israel attacking Iran on 28 February, global markets have lost 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413290/main.jpg
    Wil Crisp
  • Algeria opens bidding for water treatment plant

    15 April 2026

     

    State-owned Cosider Pipelines, part of Algeria’s public infrastructure group Cosider, has issued a tender for the construction of a demineralisation plant in In Salah in Algeria.

    The contract covers the design, supply, installation, testing and commissioning of a plant with a treatment capacity of 62,000 cubic metres a day (cm/d).

    The tender is open to local and international companies specialising in the design and construction of demineralisation and reverse osmosis desalination plants.

    The bid submission deadline is 26 April.

    The project will be located at In Salah, a key industrial area in southern Algeria, where treated water supply is important for both municipal and industrial use.

    Cosider said that individual bidders must demonstrate that they have completed at least one reverse osmosis demineralisation or desalination plant with a capacity of 20,000 cubic metres a day or more.

    They must also show an average annual turnover of at least AD1bn ($7.7m) for their five best years over the past decade.

    For consortium bids, all partners must share full responsibility for the contract, while the lead company must meet the technical and financial requirements.

    Recent projects

    In 2023, MEED reported that Riyadh-based water utility developer Wetico had won two contracts to develop water desalination plants in Algeria.

    Societe Algerienne de Realisation de Projects Industriels (Sarpi) awarded the contract for the El-Tarf desalination plant, while Entreprise Nationale de Canalisations (Enac) is the client for the Bejaja facility.

    Both plants were commissioned in 2025, each with a production capacity of 300,000 cm/d.

    Separately, Wetico was the main contractor on a third plant commissioned last year. The Cap Dijinet 2 seawater desalination plant in Boumerdes province covers 18 hectares and also has a capacity of 300,000 cm/d.

    Like many countries, Algeria is facing pressure on resources due to longer and more frequent droughts. Seawater desalination is seen as a key driver of the government’s strategy to guarantee drinking water supply.

    According to previous reports, the government is planning to build up to six additional plants by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16404325/main.jpg
    Mark Dowdall
  • WEBINAR: UAE Projects Market 2026

    15 April 2026

    Webinar: UAE Projects Market 2026
    Tuesday, 28 April 2026 | 11:00 GST  |  Register now


    Agenda:

    • Overview of the UAE projects market landscape
    • 2025 projects market performance
    • Value of work awarded 2026 YTD
    • Impact of the Iran conflict on the projects market and real estate, assessing supply chain disruptions, material cost inflation and war risk premiums
    • Key drivers, challenges and opportunities
    • Size of future pipeline by sector and status
    • Ranking of the top contractors and clients
    • Summary of key current and future projects
    • Short and long-term market outlook
    • Audience Q&A

    Hosted by: Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16401868/main.gif
    Colin Foreman