Chinese firm confirms Aramco offshore contract awards

2 January 2025

Register for MEED's 14-day trial access 

China Offshore Oil Engineering Company (COOEC) has announced that Saudi Aramco has awarded it a pair of offshore engineering, procurement, construction and installation (EPCI) contracts.

The statement by COOEC confirms an earlier report by MEED that the Tianjin-headquartered contractor won Aramco’s Contracts Release and Purchase Order (CRPO) numbers 149 and 152.

CRPOs 149 and 152 are estimated to be valued at $30m and $250m-$300m, respectively. The scope of work on the two contracts covers the EPCI of structures at the Abu Safah and Arabiyah-Hasbah offshore field developments in Saudi Arabia.

The brief EPCI scope of work on the two CRPOs won by COOEC and their bid submission dates are as follows:

  • CRPO 149 – 29 September: 
    Installation of one offshore jacket at the Abu Safah field development
     
  • CRPO 152 – 24 September:
    Installation of structures at the Arabiyah and Hasbah offshore fields:
     Two jackets at the Arabiyah field
     One simultaneous operations-capable jacket at the Hasbah field
     One gas lift production deck module
     A 16-inch subsea pipeline running 5 kilometres (km)
     13.8kV subsea cables covering 5km

CRPOs 149 and 152 were among a batch of three offshore EPCI contracts that Aramco awarded in late November. The third contract – CRPO 153 – was won by Oslo-listed Subsea7.

The scope of work on CRPO 153, for which bids were submitted by Aramco’s Long-Term Agreement (LTA) pool of offshore contractors on 29 September, involves replacing a 17km flank pipeline at the Abu Safah field, related demolition work and modification of other units.

The value of the CRPO 153 contract is estimated to be $200m-$250m.

Robust offshore spending

In January last year, the Saudi Energy Ministry directed Aramco to abandon its campaign to expand its oil production spare capacity from 12 million barrels a day (b/d) to 13 million b/d by 2027. As a direct consequence of that government decision, Aramco cancelled the tendering process for at least 15 tenders involving the EPCI of structures at offshore oil and gas fields.

Since that decision, however, Aramco has gone the other way. The Saudi energy giant spent an estimated $5bn in 2024 on offshore EPCI contracts, which included CRPOs 149, 152 and 153.

Italian contractor Saipem was the biggest beneficiary of Aramco’s robust offshore spending, winning five of the eight CRPOs awarded last year.

In early May, Aramco awarded Saipem the contract for CRPO 143, which involves replacing an oil line between the Berri and Manifa oil fields in the kingdom’s Gulf waters.

Aramco then awarded Saipem the contract for CRPO 138, which involves laying a trunkline at the Abu Safah offshore field. The contract is estimated to be worth $500m.

The Milan-listed contractor then scooped three major CRPOs in August, starting with CRPOs 132 and 139, the combined value of which is estimated to be about $1bn. In early September, Saipem began work on the two contracts, which involve the EPCI of structures to upgrade the Marjan, Zuluf and Safaniya offshore field developments.

Just days after awarding CRPOs 132 and 139 to Saipem, Aramco awarded the Italian contractor CRPO 127, a $2bn contract that involves the EPCI of topsides and jackets for wellhead platforms, a tie-in platform jacket and topside, rigid flowlines, submarine composite cables and fibre optic cables at the Marjan oil and gas field.

Offshore jobs under bidding

Meanwhile, Aramco is evaluating technical and commercial bids it has received from LTA contractors for CRPO 150, which involves installing structures at its Northern Area Oil Operations.

Separately, contractors in Aramco’s LTA pool are preparing bids for eight more CRPOs.

MEED previously reported that Aramco has allowed its LTA contractors additional time to prepare bids for four tenders that will further expand the Zuluf offshore field development in Saudi Arabia.

The four tenders are CRPOs 145, 146, 147 and 148, and their total value is estimated to be about $4bn, sources previously said.

Aramco recently issued four more CRPOs to its LTA pool of contractors: CRPOs 157, 158, 159 and 160. Bids for CRPOs 158, 159 and 160 are due by 15 January, while 15 March has been set as the bid submission deadline for CRPO 157.

Aramco’s LTA pool of offshore service providers comprises the following entities:

  • Saipem (Italy)
  • McDermott International (US)
  • Larsen & Toubro Energy Hydrocarbon (India) / Subsea7 (UK)
  • Dynamic Industries (US)
  • NMDC Energy (UAE)
  • Lamprell (UAE/Saudi Arabia)
  • Sapura Energy (Malaysia)
  • Technip Energies (France) / MMHE (Malaysia)
  • China Offshore Oil Engineering Company (China)
  • Hyundai Heavy Industries (South Korea)
https://image.digitalinsightresearch.in/uploads/NewsArticle/13211769/main0927.jpg
Indrajit Sen
Related Articles
  • Adnoc plans new offshore-to-onshore oil transport pipeline

    20 August 2026

     

    Abu Dhabi National Oil Company is moving ahead with an ambitious plan to build an oil pipeline network that will transport oil from its main offshore oil processing islands in the Gulf to its onshore crude export terminal in Jebel Dhanna, Abu Dhabi.

    The planned pipeline network will source crude from Zirku Island and Das Island, where Adnoc gathers and treats oil produced at Abu Dhabi’s offshore fields, among other processing hubs, and transport those volumes across 300 kilometres inland to the Jebel Dhanna terminal.

    According to sources, the proposed pipelines will eventually connect to the West-East crude pipeline network currently being built from Abu Dhabi’s Jebel Dhanna to the emirate of Fujairah, and is expected to be commissioned in 2027.

    The Abu Dhabi energy giant has awarded a contract for concept studies and front-end engineering and design (feed) to Abu Dhabi-based NT Energies, a joint venture of Abu Dhabi-based contractor NMDC Energy and France’s Technip Energies, sources told MEED.

    NT Energies is expected to carry out the concept studies and feed on a “fast-track basis”, with the work anticipated to take seven months, sources said.

    A kick-off meeting between the client and the appointed consultant took place on 6 July, sources added.

    Additionally, Adnoc has appointed Australia-headquartered Worley to provide project management consultancy (PMC) services, sources further said.

    West-East oil pipeline

    In May, Adnoc said it was accelerating work on the West-East crude transport pipeline project from Jebel Dhanna to Fujairah, upon directions from its board.

    The West-East pipeline project involves constructing a cross-country pipeline to transport crude from Adnoc’s export terminal at Jebel Dhanna to the Fujairah terminal, covering a distance of about 520km.

    The pipeline will double Adnoc’s crude export capacity through Fujairah on the Indian Ocean coast and enable shipments to bypass the geopolitically volatile Strait of Hormuz.

    Crude will be sourced from Adnoc’s offshore processing centres at Das, Zakum and Umm Lulu islands before being stored at new storage facilities to be built at the Jebel Dhanna terminal.

    The pipeline will be segmented into three sections:

    • Jebel Dhanna to Habshan main pumping station (MPS) – 115km
    • Habshan MPS to Sweihan depot – 254km
    • Sweihan depot to Fujairah terminal – 153km

    Adnoc awarded Egyptian contractor Engineering for Petroleum & Process Industries (Enppi) an engineering, procurement and construction management (EPCm) contract for the project in February 2024.

    Adnoc’s total spend on EPCm works could be as high as $3bn, MEED previously reported.

    Sources have told MEED that Adnoc has, in turn, appointed state-owned China Petroleum Pipeline (CPP) and locally based Bin Asheer to carry out construction works on the three segments of the West-East pipeline network.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18887774/main0639.jpg
    Indrajit Sen
  • Contractors confirm Al-Maktoum airport people-mover award

    20 August 2026

    Register for MEED’s 14-day trial access 

    A team of Japan’s Mitsubishi Corporation and Indian contractor Larsen & Toubro (L&T) has confirmed that it has won a design-and-build contract for the automated people-mover (APM) system for phase one of Al-Maktoum International airport in Dubai.

    In a statement released earlier today, L&T classified the contract as large, a term the company uses to denote an order value of $261m-$523m.

    MEED exclusively reported in July that Dubai Aviation Engineering Projects (DAEP) had selected a contractor to deliver the APM system as part of the first phase of the $35bn expansion of the airport.

    The APM system will serve as a critical facility for operations at Al-Maktoum International. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations at the airport.

    The firms submitted the bids for the project in July last year, as MEED exclusively reported.

    The contract is the latest in a series of awards signed by DAEP recently. It has awarded contracts valued at about AED13bn ($3.5bn), with construction works currently under way on several airport packages.

    These include enabling works, the second runway and the initial structural foundations for passenger terminals and gates.

    Upcoming awards

    In June, DAEP said that it will award contracts worth over AED55bn ($15bn) by the end of this year for construction works at Al-Maktoum International airport.

    The projects slated for contract awards include the substructure works for the western passenger terminal, the fourth aircraft concourse building and the baggage handling system, in addition to the superstructure works for the western passenger terminal and the first, second and third aircraft concourses.

    The packages also encompass long-span structural frameworks for buildings covering about 1.5 million square metres (sq m), infrastructure works for the southern airfield area and power generation and district cooling plants supporting the construction programme.

    The award of the facade and roofing packages is also planned for this year.

    Construction progress

    In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal were awarded to Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    Construction of substructure works began in November last year, when DAEP formally selected a contractor to deliver the package.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000 sq m facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultant on the expansion of Al-Maktoum.

    The airport’s construction is planned to be undertaken in three phases. It will cover an area of 70 square kilometres south of Dubai and will have five parallel runways and 430 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18884056/main.png
    Yasir Iqbal
  • Saudi Arabia awards estimated $1bn phosphate rail deal

    20 August 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabian Railways (SAR) has awarded an estimated SR4bn-plus ($1.1bn) contract to add another track to the first section of the existing phosphate transport railway network in the kingdom’s Eastern Province.

    The contract was awarded to local firm Alomaier Trading & Contracting Company.

    The scope includes track doubling, alignment modifications, utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track.

    The scope also covers support for signalling and telecommunications systems.

    The existing railway line runs from the Waad Al-Shamal mines to Ras Al-Khair. The new project will cover about 100 kilometres (km), connecting the AZ1/Nariyah Yard to Ras Al-Khair.

    Switzerland-based engineering firm ARX is the project consultant.

    The project is the first of four packages for the phosphate railway line that SAR is expected to award imminently.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track on the North Train freight line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase cargo-carrying capacity on the network and facilitate growth in industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway-focused materials and equipment, including the construction of a cement sleeper manufacturing facility.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18876428/main.jpg
    Yasir Iqbal
  • Libya and Tunisia reschedule joint oil and gas licensing round

    19 August 2026

    The Libyan-Tunisian Joint Oil Exploration, Exploitation & Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.

    The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.

    Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.

    The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.

    Significant data is available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.

    The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.

    Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).

    LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.

    Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.

    The key dates from the new schedule for the licensing round are:

    • 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
    • 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
    • 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
    • 31 December 2026: Bid round closes
    • 8 January 2027: Bid submissions due
    • 26 February 2027: Winning bidders notified
    • 30 April 2027: Formal awards expected

    Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.

    Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.

    A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.

    Despite this, the field has remained undeveloped for over three decades.

    One of the key challenges to developing the reserve is its high carbon dioxide content.

    Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main0914.jpg
    Wil Crisp
  • UAE cuts trade and financial links with Iran

    19 August 2026

    Register for MEED’s 14-day trial access 

    The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.

    The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.

    The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.

    It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.

    The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.

    The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg
    Colin Foreman