China Energy wins Ghazlan power plant expansion contract

21 April 2025

Saudi Electricity Company (SEC) is understood to have formally awarded China Energy International Group, a subsidiary of Beijing-headquartered China Energy Engineering Corporation, a contract to build a gas-fired power plant in Ghazlan.

The Ghazlan power plant is located on the Gulf coast, 20 kilometres northeast of Ras Tanura and 80 kilometres north of Dammam in Saudi Arabia's Eastern Province.

As part of the contract, China Energy will expand the existing power plant by adding approximately 1,600MW on an engineering, procurement and construction (EPC) basis, according to a local media report.

The award follows the signing of another EPC contract last month between SEC and a team of Chinese and South Korean contractors to expand Riyadh Power Plant 12 (PP12).

MEED reported in September last year that companies had received limited notices to proceed from SEC for several gas-fired power plant expansions in the kingdom.

These include contracts to expand Ghazlan 2 and Qurayyah, in addition to Ghazlan 1.

China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea's Doosan Enerbility formally signed the EPC contract with SEC to expand PP12 in March. 

The expansion project comprises a greenfield combined-cycle gas turbine (CCGT) power generation plant with a capacity of 1,800MW.

In the same month, Hajr Two Electricity Company, a consortium of Saudi utility developer and investor Acwa Power, SEC and Haji Abdullah Alireza & Company (Haaco), awarded a joint venture of Egypt's Orascom Construction and Madrid-based Tecnicas Reunidas an EPC contract for the Qurayyah independent power producer (IPP) expansion project in Saudi Arabia.

The 50:50 joint venture will build the 3,010MW combined-cycle gas-fired power plant in the Eastern Province of Saudi Arabia.

The EPC contract is valued at more than $2.6bn, Orascom said.

30GW booking

According to industry sources, SEC had booked in advance 30GW of gas turbine capacity with the industry's leading original equipment manufacturers in anticipation of domestic and overseas demand for gas-fired generation power plants.

Experts also say that Saudi Arabia's liquid fuel displacement programme and the need to increase the flexibility of its electricity grid to accommodate more renewable power underpin moves to expand the state utility's gas-fired capacity. 

Saudi Arabia envisages that renewable energy sources will account for half of its installed electricity generation capacity by 2030.


MEED’s April 2025 report on Saudi Arabia includes:

> GOVERNMENT: Riyadh takes the diplomatic initiative
> ECONOMY: Saudi Arabia’s non-oil economy forges onward
> BANKING:
 Saudi banks work to keep pace with credit expansion
> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> DATABANK: Saudi Arabia’s growth trend heads up

https://image.digitalinsightresearch.in/uploads/NewsArticle/13726228/main.jpg
Jennifer Aguinaldo
Related Articles
  • Bidders await NWC decision on sewage contract

    17 February 2026

     

    Saudi Arabia’s National Water Company (NWC) is evaluating five bids for package 12 of its long-term operations and maintenance (LTOM12) sewage treatment programme.

    Known as the North Western B Cluster, LTOM12 forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    The contract covers the construction and upgrade of seven sewage treatment plants with a combined capacity of about 162,000 cubic metres a day (cm/d).

    As MEED understands, the companies that have submitted proposals include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • Miahona (Saudi Arabia)
    • Beijing Enterprises Water Group – BEWG (Hong Kong)
    • Al-Yamama (Saudi Arabia)

    Earlier this month, MEED exclusively reported that six contractors are competing for the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11), which has an estimated value of about $211m.

    The project involves the construction and upgrade of two sewage treatment plants with a combined capacity of about 440,000 cm/d.

    The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component. 

    It is understood that contracts for LTOM11 and LTOM12 will be awarded in May.

    In January, a consortium of United Water (China), Prosus Energy (UAE) and Armada Holding (Saudi Arabia) won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).

    This contract was the first to be awarded under the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    NWC previously awarded $2.7bn-worth of contracts for the first phase of its LTOM programme. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15670141/main.jpg
    Mark Dowdall
  • Dubai tenders Al-Maktoum airport superstructure

    17 February 2026

     

    Dubai Aviation Engineering Projects (DAEP) has tendered three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.

    Interested bidders have until 23 March to submit their proposals.

    MEED understands that the selected contractor will undertake superstructure works on three packages:

    • West Terminal and concourse one
    • Concourse two
    • Concourse three

    Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.

    In August, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport. 

    The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Construction progress

    Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    The statement added that the project will create housing demand for 1 million people around the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    Project history

    The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.

    An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.

    Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15669879/main.jpg
    Yasir Iqbal
  • Contractors submit revised prices for Habshan 7 project

    17 February 2026

     

    Adnoc Gas has received revised commercial proposals from contractors for engineering, procurement and construction (EPC) works on a major project to add a new gas processing train at its Habshan complex in Abu Dhabi.

    Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), processes about 10 billion standard cubic feet a day (cf/d) of gas across several sites, including its Asab, Bab, Bu Hasa and Habshan facilities, as well as a natural gas liquids (NGL) fractionation plant at Ruwais.

    The Habshan complex is one of the largest gas processing facilities in the UAE and across the Middle East and North Africa. Its output capacity is 6.1 billion cf/d. The complex comprises five trains and 14 processing units that receive gas feedstock from onshore and offshore fields in Abu Dhabi.

    With Adnoc Group pressing ahead with its P5 programme to raise oil production potential to 5 million barrels a day by 2027, high volumes of associated gas are set to enter the grid.

    The new train at the Habshan complex, which Adnoc Gas expects to commission in 2029, will play a key role in handling these additional gas volumes.

    MEED previously reported that contractors had submitted commercial bids for the new Habshan 7 gas train project to Adnoc Gas by the deadline of 10 December.

    Following an initial evaluation of commercial bids received, Adnoc Gas sought “best offers” from contractors for the project. Bidders submitted their revised prices by 6 February, according to sources.

    The following contractors are understood to be competing for the Habshan 7 project’s main EPC contract, as per sources:

    • Enppi (Egypt) / Petrojet (Egypt)
    • Jereh (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • Petrofac (UK)
    • Sinopec (China)
    • Wison Engineering (China)

    MEED previously reported that contractors submitted technical bids for the project to Adnoc Gas by the deadline of 6 October.

    Adnoc Gas intends to install the Habshan 7 train adjacent to the Habshan 5 train. This will enable the new train to utilise the ullage in the Habshan 5 sulphur recovery and tail gas treatment units and optimise operations.

    The scope of work on the Habshan 7 gas train project covers the EPC of the following units:

    • New high-pressure pipeline from the main Habshan complex to the new gas train
    • Separation and condensate stabiliser unit
    • Acid gas removal unit
    • Mercury removal unit
    • Deep NGL recovery unit
    • Sales gas and residue gas compressor
    • NGL product storage and transfer pump, as well as metering skid
    • Utility units (IA, N2, PW, FW, steam generation, DM)
    • Flare unit, to be located in Habshan 5 on common derrick
    • Flare gas recovery package
    • Water treatment package
    • Non-process buildings, to be located outside the Habshan 5 train
    • Power generation system
    • NGL pipeline from Habshan 5 to Ruwais, based on an existing pipeline assessment
    • Sales gas pipeline from Habshan 5 to sales gas network.

    UK-headquartered Wood Group has performed the concept study and initial engineering design for the project.

    The Habshan 7 gas train project represents the third phase of Adnoc Gas’ Rich Gas Development programme and is estimated to be valued at $3.5bn-$4bn, according to the company’s chief financial officer, Peter Van Driel.

    In a recent call with journalists to discuss Adnoc Gas’ financial results for the full year and fourth quarter of 2025, Van Driel said Adnoc Gas expects to achieve a final investment decision on the Habshan 7 gas train project, which is designed to increase the company’s production of high-value liquids such as liquefied petroleum gas, naphtha and condensates, in the first quarter of 2026.

    Adnoc Gas issued the main EPC tender for the new Habshan 7 gas train project to contractors between 5 and 8 August, MEED previously reported. It later extended the initial technical bid submission deadline from mid‑September to 6 October.

    In April, MEED reported that Adnoc Gas had started an early engagement process with contractors for the EPC tendering phase of the Habshan 7 gas train project.

    Prior to that, Adnoc Gas issued an expression of interest (EoI) document for the project in March, to which contractors submitted responses by 8 April.

    Separately, Adnoc Gas also completed the EoI exercise for early civil and site preparation works on the Habshan 7 project in June, and is understood to have issued the main tender in the third quarter.

    ALSO READ: Adnoc Gas stalls decision on Ruwais NGL project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15663150/main5247.jpg
    Indrajit Sen
  • Dubai seeks contractors for Jebel Ali STP expansion

    16 February 2026

    Dubai Municipality has invited contractors to prequalify for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).

    The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.

    The bid submission deadline is 2 April.

    Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.

    As MEED understands, the project is part of long-term plans to treat about 1.05 million cm/d a day once all future phases are completed.

    The main element of the expansion, which is estimated to cost $300m, involves modifications to the secondary treatment process at Jebel Ali STP phase two.

    This includes conversion to Moving Bed Biofilm Reactor or Integrated Fixed-Film Activated Sludge systems.

    The project also includes decommissioning existing surface aerators. New blowers and associated works will be installed as part of the upgrade.

    UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15661388/main.jpg
    Mark Dowdall
  • AD Ports to develop Douala port in Cameroon

    16 February 2026

    Abu Dhabi’s AD Ports Group and Africa Ports Development (APD) have signed an agreement to design, build and operate a new dry bulk terminal at the Port of Douala in Cameroon.

    AD Ports Group will invest about AED320m ($87m) in the development of the terminal’s first phase, which will comprise two berths and more than 450 metres of quay wall, with an annual handling capacity of about 4 million tonnes of dry bulk cargo.

    Construction is expected to begin this year, and the first phase is slated for completion in 2028.

    The concession period is 30 years.

    AD Ports Group has committed to long-term investments and operations across Africa, including in Egypt, Morocco, Tunisia, Kenya, Tanzania, Angola and the Republic of the Congo.

    The latest announcement comes shortly after it signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.

    AD Ports will manage and operate the port under a 30-year concession agreement.

    In December last year, AD Ports Group signed a shareholder agreement with Tajikistan’s private industrial firm Avesto Group to establish a new joint venture that will provide integrated logistics and freight forwarding services across Tajikistan.

    Under the agreement, the joint venture will initially operate as an asset-light freight forwarder. It will have exclusive rights to consolidate and manage all freight and logistics activities across Avesto Group’s subsidiaries, while also offering services to third-party customers in the wider market.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15661385/main.jpg
    Yasir Iqbal