Cairo monorail nears completion

1 December 2023

 

Register for MEED's guest programme 

The Greater Cairo Monorail project, one of Egypt’s most significant infrastructure developments, is advancing towards completion.

The $4.5bn project, led by Egypt’s National Authority for Tunnels (NAT), aims to improve Cairo’s transportation network by linking the old city centre with the New Administrative Capital.

The monorail encompasses two main lines: a 54-kilometre line connecting East Cairo to the New Administrative Capital and a 43km line from 6 October City to Giza. The system is designed to handle 45,000 passengers an hour in each direction.

Canada’s Bombardier, later acquired by France’s Alstom, along with Egyptian companies Arab Contractors and Orascom Construction, was awarded a $4.16bn contract for the design and construction of the monorail in 2019.

In September 2020, US-based Hill International and another US firm, HJI Group, were appointed to provide project management and design review services.

Global disruption

Global events created major challenges for the project, according to Waleed Abdel-Fatteh, Hill International’s president for the Middle East and North Africa region.

“The impact of Covid-19 is still being felt in the project due to the commodity price fluctuations and supply chain disruptions during the period,” he says.

“The ongoing conflict between Ukraine and Russia has further affected supply chain and logistics, while the ongoing exchange rate fluctuations present a definitive stress on project finance for all stakeholders.

“NAT is actively working with the contractors to ensure smooth construction of the lines despite these challenges,” he says.

Over 90 per cent of the engineering for the project has now been completed. Civil works for the East of Nile (EoN) Line are 75 per cent finished and guideway beam construction is 90 per cent done. Station construction stands at 45 per cent complete.

The depot for the EoN Line is also progressing rapidly and is around 70 per cent complete.

All 40 of the trainsets for the EoN Line have been delivered. “Static tests on the trains have started in the EoN depot. With the construction substantially progressed, power cables are finally being installed to form the power ring main in the EoN Line,” says Abdel-Fatteh.

“Installation of signalling and communications equipment has also started in several stations. One of the highlights of the WoN Line is the installation of a long span in 6 October City’s Juhayna Square.”

The West of Nile (WoN) Line reports 52 per cent overall construction completion, with progress initially slowed due to land acquisition issues.

Next steps

The following six months are crucial for the project.

“The next six months will see the completion of works in all line segments of the EoN Line and in the seven line segments of the WoN Line,” says Abdel-Fattah.

“Power-on of the systems may happen in the next few weeks, depending on a review by the local electricity authorities. This will be the formal start of the testing and commissioning phase of the EoN Line.

“The WoN Line will see the completion of depot construction and the start of major installation activities up to station 7, and significant progress is expected in Zone 4 line segments and stations.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/11339535/main.gif
Colin Foreman
Related Articles
  • Oman’s Barka 5 IWP solar plant begins full operations

    1 May 2026

    Spain’s GS Inima has begun permanent operations at the solar photovoltaic (PV) plant serving the Barka 5 independent water project (IWP) in Oman.

    The solar facility is the third of its kind in Oman to power a large-scale desalination facility through a self-supply model.

    In a statement, GS Inima said it will provide up to 50% of the desalination plant’s electricity needs during daytime operations, improving efficiency and reducing reliance on external power sources.

    The PV plant has an installed capacity of 6.5MWp. It is designed to optimise energy consumption at the adjacent reverse osmosis desalination facility.

    The project was developed by GS Inima in collaboration with local firm Nafath Renewable Energy as the engineering, procurement and construction (EPC) contractor. China-based OCA Global provided owner’s engineering services.

    The Barka 5 IWP has a desalination capacity of approximately 100,000 cubic metres a day.

    GS Inima won the contract to develop the Barka 5 IWP project in November 2020. As previously reported, financial close was reached in 2022, and construction of the facility was completed in 2024.  

    The self-supply solar PV plant is equipped with 10,504 bifacial modules supplied by China’s Jinko Solar. These are mounted on fixed structures provided by Mibet Energy.

    Power is managed through 18 Sungrow inverters with a total capacity of 320kWac each, while electricity is fed into the desalination plant through an 11kV connection.

    The integration of solar power supports the efficiency of the Barka 5 facility, which has an energy consumption rate of 2.7kWh per cubic metre. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16645971/main.jpg
    Mark Dowdall
  • Qiddiya receives high-speed rail PPP prequalifications

    1 May 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company (QIC) and the National Centre for Privatisation & PPP, received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh.

    This follows the submission of prequalification statements for the engineering, procurement, construction and financing (EPCF) package on 16 April, as reported by MEED.

    The prequalification notice was issued on 19 January, and a project briefing session was held on 23 February at Qiddiya Entertainment City.

    The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.

    The line is expected to be developed in two phases. The first phase will connect Qiddiya with KAFD and King Khalid International airport.

    The second phase will start from a development known as the North Pole and travel to the New Murabba development, King Salman Park, central Riyadh and Industrial City in the south of the city.

    In November last year, MEED reported that more than 145 local and international companies had expressed interest in developing the project, including 68 contracting companies, 23 design and project management consultants, 16 investment firms, 12 rail operators, 10 rolling stock providers and 16 other services firms.

    In November 2023, MEED reported that French consultant Egis had been appointed as the technical adviser for the project. UK-based consultancy Ernst & Young is acting as the transaction adviser, and Ashurst is the legal adviser.

    Qiddiya is one of Saudi Arabia’s five official gigaprojects and covers a total area of 376 square kilometres (sq km), with 223 sq km of developed land. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16641057/main.gif
    Yasir Iqbal
  • Bid deadline extensions hint at tighter project market

    1 May 2026

    Commentary
    Mark Dowdall
    Power & water editor

    There has been a steady run of bid deadline extensions across major power and water projects in recent weeks.

    The latest is the Al-Dibdibah and Al-Shagaya solar independent power producer (IPP) plant in Kuwait, where the submission date has been moved again to 31 May, following an earlier shift from February to the end of April. Similarly, bidding for the first phase of the Al-Khairan IWPP has also been extended.

    In Bahrain, bidding for the 1.2GW Sitra IWPP has been pushed back by another month to 17 May, having already been under main contract tender since last August.

    Meanwhile, in Dubai, contractors have been given additional time to submit bids for both the Jebel Ali sewage treatment plant expansion and a dams rehabilitation project in Hatta.

    Individually, these shifts are not unusual, and extensions are a routine part of the procurement cycle, especially with large, capital-intensive schemes.

    However, amid regional tensions and increasingly complex risk profiles, stakeholders are having to weigh up how much they can absorb, whether that is performance guarantees, financing exposure or delivery risk.

    For contractors and developers, this could mean looking more closely at supply chains, insurance costs and the potential for disruption. Lenders, too, are likely taking a more measured view on long-term exposure.

    This caution can show up in the bid process. More internal approvals, more conservative pricing, and in some cases, perhaps a hesitation to commit altogether.

    At the same time, strong pipelines across the GCC mean contractors are not short of work. Firms can afford to be selective, focusing on projects where risk and return are better aligned.

    Clients, in turn, face a choice. Push ahead with more limited competition or extend and try to draw in stronger participation. Most appear to be opting for the latter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16640998/main.jpg
    Mark Dowdall
  • Saudi Arabia launches $2bn Jawharat Al-Arous project

    1 May 2026

    Saudi Arabia has launched Jawharat Al-Arous, an SR8bn ($2bn) private-sector-led residential development in north Jeddah.

    The scheme covers 107 million square metres and comprises 18 residential neighbourhoods planned to accommodate more than 700,000 residents. It will provide more than 80,000 residential and commercial plots.

    The masterplan also includes 41 government-backed infrastructure and service zones to support large-scale urban expansion.

    The project was unveiled by Mecca Region Governor Khalid Al-Faisal and will be overseen by Saud Bin Mishaal Bin Abdulaziz.

    According to a recent report by real estate firm Cavendish Maxwell, Jeddah’s residential stock stood at about 1.09 million units at the end of 2025, following the completion of around 4,000 units that year.

    An expanding pipeline of about 18,000 units in 2026 and 22,000 units in 2027 is expected to bring total stock to around 1.14 million units by 2027, gradually adding supply without destabilising market equilibrium.

    GlobalData expects the Saudi construction industry to grow by 3.6% in real terms in 2026, supported by increased foreign direct investment (FDI) and investment in the housing and manufacturing sectors.

    The residential construction sector is forecast to grow by 3.8% in real terms in 2026 and to record an average annual growth rate of 4.7% between 2027 and 2030, supported by Saudi Vision 2030’s goal of increasing homeownership from 65.4% in 2024 to 70% by 2030, including through the delivery of 600,000 homes by 2030.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16640863/main.png
    Yasir Iqbal
  • Damage to US bases in region expected to cost more than $15bn

    1 May 2026

    The $25bn estimate a Pentagon official gave US lawmakers on 29 April did not include the cost of repairing damage to US bases in the Middle East, and the real cost of the war is likely to be between $40bn and $50bn, according to CNN.

    That would put the cost of repairing bases and replacing destroyed assets at between $15bn and $25bn.

    Jules Hurst III, the Pentagon official serving as the agency’s comptroller, told the House Armed Services Committee that “most” of the $25bn he cited had been spent on munitions. Defence Secretary Pete Hegseth declined to say whether the figure included repairs to damaged US bases.

    Iranian strikes across the Gulf in the early days of the war significantly damaged at least nine US military sites in 48 hours, hitting facilities in Bahrain, Kuwait, Iraq, the UAE and Qatar.

    Six US servicemembers were killed in an attack on a command post in Kuwait, and 20 more were injured.

    Three sources told CNN that the figure provided to the House Armed Services Committee did not include the cost of rebuilding US military installations and replacing destroyed assets.

    One source said the true cost would likely be between $40bn and $50bn.

    US contractors such as KBR and Fluor, as well as local firms, are likely to be among the leading contenders for contracts to repair and rebuild US bases in the region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16638663/main.gif
    Wil Crisp