BP gas project in Egypt to be ready in two years

25 May 2023

The Raven Infills project to tie back two gas wells in Egypt’s West Nile Delta block is expected to be completed within two years of the contract award, according to industry sources.

On 3 May, it was announced that the contract for the project had been awarded to Subsea Integration Alliance by UK-based BP and its joint-venture partner Wintershall Dea.

Subsea Integration Alliance is a non-incorporated strategic global alliance between Subsea7 and OneSubsea.

“This is a fast-track project and that means we will see it executed very quickly,” said one source. “It is likely to be fully commissioned within two years.”

The contract is estimated to be worth $200m and, in a statement, Subsea7 described it as “substantial”.

The scope includes the engineering, procurement, transport and installation of approximately six kilometres of flexible pipes, umbilicals and associated subsea structures in water depths of around 800 metres.

Project management and engineering have commenced and will be managed from Subsea7 offices in France, the UK and Portugal.

When the contract was awarded, Olivier Blaringhem, Subsea Integration Alliance CEO, said: “This award further solidifies our ongoing partnership with BP in Egypt.

“Through our early collaboration on this project, BP and Subsea Integration Alliance have worked together to develop an optimised solution for the Raven field, showcasing our effective teamwork.”

Franck Louvety, the Africa, Middle East and Caspian vice-president of Subsea7, said: “We are excited to strengthen our presence in Egypt and continue to build on our longstanding and successful relationship with BP.

“We look forward to working with BP to deliver the project successfully and safely while maximising the client’s production objectives.”

In January, MEED revealed that technical and commercial bids by contractors were submitted in late December 2022.

BP started gas production from the Raven field in April 2021, saying the field initially produced about 600 million standard cubic feet a day (cf/d) of gas.

In November, BP said it was producing around 900 million cf/d of gas from the asset and 27,000 barrels a day (b/d) of condensates.

The Raven gas field was brought online as part of the West Nile Delta (WND) project off Egypt’s Mediterranean coast.

The $9bn WND development comprises five gas fields across the North Alexandria and West Mediterranean deepwater offshore concession blocks in the Mediterranean Sea.

The field was originally expected to come online in October 2019, but corrosion issues were noticed during the commissioning process.

Bringing Raven online was part of the third stage of the WND development to develop 5 trillion cubic feet of gas resources and 55 million barrels of condensates from two BP-operated offshore concession blocks.

The original Raven project included eight wells and was developed as a deepwater long-distance tie-back to shore, where a new onshore plant was located.

The plans for further development of the Raven field have been accelerated due to higher energy prices and increased demand for gas from European nations as they seek alternatives to Russian imports.

Exploration blocks

In November, BP announced that it had been awarded new exploration blocks in Egypt’s Offshore Nile Delta.

One of these was the Northwest Abu Qir Offshore Area.

BP is now the operator of this block, holding an 82.75 per cent stake, while Germany’s Wintershall Dea has the other 17.25 per cent.

The block is located west of the North King Mariout block, in which BP has a 100 per cent stake. It is located north of the Raven field.

The Northwest Abu Qir offshore area covers approximately 1,038 square kilometres with water depths between 600 and 1,600 metres.

The second block it was awarded in November was the Bellatrix-Seti East block. This is operated by Italy’s Eni, which holds a 50 per cent stake. BP also has a 50 per cent stake in the block, located west of the Atoll field and North Tabya blocks.

It covers an area of approximately 3,440 sq km with water depths between 100 and 1,200 metres.

BP says it has invested more than $35bn in Egypt over the past 60 years.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10881282/main.jpg
Wil Crisp
Related Articles
  • Contractors submit bids for next phase of Duba port

    2 June 2023

    Contractors have submitted bids for the next phase of the Duba port expansion at Oxagon industrial city.

    The bidders are Belgium’s Deme with Greece’s Archirodon; Van Oord of the Netherlands with South Korea’s Hyundai Engineering & Construction; a Belgian joint venture of Jan de Nul and Besix; Netherlands-based Boskalis with France’s Soletanche Bachy; South Korea’s Daewoo; and China Harbour Engineering Company.

    The tender for the project’s second phase follows the award of a contract to deliver the first phase of the port expansion. A team of Boskalis, Besix and the local Modern Building Leaders (MBL) was awarded that estimated SR3bn ($800m) contract in mid-January.

    The scope of the Duba port expansion package includes excavation and dredging, revetments for channel widening, demolition, container terminal quay expansion and earthworks, in addition to the development of a flexible quay, a roll-on/roll-off (RoRo) berth and quay walls to a marine services berth and a coast guard facility.

    Jacobs is the main design consultant, with Moffatt & Nichol, IGO and Trent as the main sub-consultants.

    Contractors are preparing to submit bids in June for a contract to build tunnels connecting the offshore elements of the Oxagon industrial city at Neom to the mainland.

    The design-and-build contract involves digging a 6.5-metre-diameter tunnel using a tunnel boring machine (TBM) under the sea that will link the Neom Connector with the offshore elements of Oxagon port. It will house utilities including water pipelines, fibre optic cables and electricity cables.

    Crown Prince Mohammed bin Salman launched Oxagon in late 2021. It will include onshore elements as well as floating structures offshore. Construction works on the 48 square-kilometre, eight-sided industrial city have already started.

    An expanded Duba port is a critical component of Oxagon and the broader Neom development, as it will allow greater volumes of materials to be imported for the project. With an expected investment value of $500bn, Neom is the largest programme of construction work in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10909320/main.jpeg
    Colin Foreman
  • Egypt makes steady progress on Assiut refinery

    2 June 2023

    Egypt is making steady progress on the $2bn hydrocracking complex package that forms part of the wider Assuit oil refinery upgrade project, according to industry sources.

    Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation (EGPC), is the project operator.

    “Work on the main units is continuing with no significant issues,” said one source.

    During 2021, the project faced disruption due to issues related to the Covid-19 pandemic.

    In 2023, many projects in Egypt’s oil and gas sector have been disrupted by currency issues due to the declining value of the Egyptian pound.

    Most of the projects that the currency issues have significantly impacted have been in their early stages, with the problems related to the procurement of materials and equipment.

    France’s Technip Energies is the main contractor performing engineering, procurement and construction (EPC) works on the Assiut hydrocracking complex, as part of a $2bn contract it was awarded by ASORC in February 2020.

    In April 2021, Switzerland-based Burckhardt Compression announced being selected by Technip Energies as the gas compressor supplier for the hydrocracker package.

    ASORC held a kick-off meeting for the project in September 2020.

    Egyptian contractors Enppi and Petrojet are supporting Technip Energies on the project. Enppi has undertaken the engineering work, while Petrojet is carrying out construction work.

    In 2021, contractors completed the construction of a $450m high-octane gasoline complex in the Assiut governorate as part of the broader $3.8bn Assuit oil refinery upgrade project.

    Assiut refinery

    The Assiut hydrocracking complex will be one of Egypt’s major strategic refineries, and will help meet growing local demand for cleaner products.

    The project will also become the largest oil refining facility to be implemented in Upper Egypt so far.

    Once completed, the project will transform lower-value petroleum by-products, such as mazut, into cleaner, higher-value products.

    It is expected to have an output of about 2.8 million tonnes a year of Euro-5 diesel, in addition to other petroleum products.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10908534/main3340.jpg
    Wil Crisp
  • Mawani implements $950m of Saudi port projects

    2 June 2023

    Saudi Ports Authority (Mawani) is implementing a series of projects over the coming 18 months as part of its efforts to improve and expand infrastructure at ports and increase their utilisation rates.

    The programme, worth about SR3.5bn ($950m), comprises just over 150 projects, of which 48 are strategic in nature, 90 infrastructure-focused and 14 targeting security enhancements.

    The most significant projects are:

    At Jeddah Islamic Port

    • A four-year contract to build a new road, interchanges and flyovers to link Gate 9 with the Al-Khumrah integrated logistics park.
    • Deepening over three years of the north basin approach channel to 14 metres and the construction of a bull nose dike

    At Ras al-Khair Port

    • Increasing the draft depth of berths 11 and 12 to 16 metres
    • A three-year job to widen and dredge the approach channel from 300 metres to 500 metres and deepen it by 3 metres to 19 metres

    Other key investments include installing integrated security systems at Jeddah Islamic Port and King Abdulaziz Port in Dammam and constructing a new 40MVA substation at King Fahd Port in Yanbu.

    The contracts are expected to be tendered and awarded by the end of 2024.

    Mawani’s planned investment comes on the back of several major contracts awarded over the past 12 months, including an agreement with DP World to set up the Al-Khumrah logistics park, the reconstruction and expansion of the first and second container terminals at King Abdulaziz Port, and the upgrade of berth infrastructure and draft depths at Jeddah Islamic Port and King Fahd Port.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10909176/main.jpg
    Edward James
  • Dubai unveils new masterplan for Palm Jebel Ali

    1 June 2023

    Dubai has released details of the new masterplan for Palm Jebel Ali, an artificial island located south of Jebel Ali Freezone.

    Double the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature over 80 hotels and resorts, along with a diverse range of entertainment and leisure facilities.

    Strategic masterplan

    The unveiling of the masterplan aligns with Dubai's commitment to doubling the size of its economy by 2033, as outlined in the Dubai Economic Agenda.

    The project, approved by Sheikh Mohammed bin Rashid al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, includes seven connected islands, catering to approximately 35,000 families. The development also emphasises sustainability, with 30 per cent of public facilities powered by renewable energy.

     

    MEED reported in January that local developer Nakheel had approached contractors to complete the reclamation works for Palm Jebel Ali.

    As with Palm Jumeirah, it is estimated that it could take around 20 years for Palm Jebel Ali to reach its full development potential. Nakheel has previously secured AED17bn ($4.6bn) in funding to expedite the development of various projects, including the Dubai Islands and other waterfront schemes.

    The upcoming dredging contract for Palm Jebel Ali is anticipated to involve 5-6 million cubic metres of material, contributing to the completion of the man-made offshore island.

    While reclamation work for Palm Jebel Ali is mostly finished, the project was put on hold in 2009. Nakheel had made some progress with infrastructure development, including the construction of bridges on the island by Samsung C+T.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10906519/main.jpg
    Colin Foreman
  • Swedish firm to deliver apartments for Neom

    1 June 2023

    Swedish modular home manufacturer SIBS has been awarded a contract to deliver 2,174 apartments for Neom.

    The engineered equipment supply contract involves SIBS constructing 35 buildings within Neom’s primary staff accommodation and office cluster.

    The apartments will cater to professionals involved in the planning, engineering and construction of Neom. The entire project is expected to be delivered and commissioned by the third quarter of 2024.

    The $500bn Neom development in northwestern Saudi Arabia is the region’s largest construction project and employs thousands of staff.

    Elements of the project that have been officially launched so far are The Line, Oxagon, Trojena and Sindalah. There are also plans for an international airport and a coastal strip of hotels known as the Gulf of Aqaba.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/10905700/main.gif
    Colin Foreman