Aramco focuses on upstream capacity building

12 September 2023

This package on Saudi Arabias upstream sector also includes: 

Aramco sets new deadlines for Manifa offshore bids
Aramco gives gas plant expansion bidders more time
Riyadh and Moscow extend oil output cuts till year-end
Aramco receives bids for Safaniya field expansion
Aramco selects contractors for $10bn gas project
Development of Dorra field may stoke tensions


 

While Saudi Arabia is set to continue reducing its oil production until the end of the year, a measure that could lead to further declines in its oil revenues, the decision has not deterred state energy giant Saudi Aramco from investing in projects to build its oil and gas production potential.

On Tuesday 5 September, global benchmark Brent crude breached the $90-a-barrel mark for the first time this year, primarily due to the Opec+ alliance’s oil supply management mechanism and the kingdom’s voluntary output cuts.

Aramco is capitalising on this high oil price environment to push through projects that are critical to achieving its strategic upstream goals of raising oil production capacity to 13 million barrels a day (b/d) by 2027, from about 12 million b/d at present, and doubling gas production by the end of this decade.

The state enterprise expects its capital expenditure this year to be $45bn-$55bn, including external investments – at least 20 per cent higher than its $37.6bn capex in 2022.

Spending on offshore oil and gas engineering, procurement, construction and installation (EPCI) projects is expected to account for the bulk of this projected capex for 2023.

Robust offshore spending

Most of the kingdom’s oil and gas production comes from its offshore hydrocarbons resources in fields including Abu Safah, Arabiyah, Hasbah, Berri, Karan, Manifa, Marjan, Ribyan, Safaniya and Zuluf.

Aramco aims to maintain and gradually increase productivity at these fields, some of which are mature. In line with this, the state enterprise is poised to award approximately $4bn of offshore EPCI deals to entities in its long-term agreement (LTA) pool of offshore contractors by the end of this year.

So far this year, Aramco has already awarded about $3bn-worth of contracts as part of this projected spending.

A consortium of Indian contractor Larsen & Toubro Energy Hydrocarbon (LTEH) and UK-based Subsea7 has won seven offshore EPCI contracts from Saudi Aramco, estimated to be worth close to $2bn.

LTEH/Subsea7 won contract release and purchase order (CRPO) numbers 98, 120 and 121, which cover EPCI work on Saudi Arabia’s Zuluf, Hasbah and Manifa offshore oil and gas fields. The combined value of the three CRPOs, awarded to the consortium in March, is estimated to be $1bn.

In April, LTEH/Subsea7 won CRPOs 117, 118 and 119, which cover EPCI work on Saudi Arabia’s Marjan offshore oil and gas field development. The three tenders are thought to be worth over $900m.

The LTEH/Subsea7 consortium is also understood to have secured the contract for CRPO 97, which relates to the EPCI of various units at the Abu Safah field.

Italian contractor Saipem confirmed in early April that it had won CRPO 96, estimated to have a value of $120m. The scope of work on the tender covers the EPCI of one platform topside and the associated subsea flexible, umbilical and cable systems at the Abu Safah and Safaniya fields.

Also in April, China Offshore Oil Engineering Company (COOEC) won the CRPO 122 contract, estimated to be worth $255m, covering the installation of 13 jackets at the Safaniya field.

Saipem has also won CRPO 124, a key contract for the third gas development phase of the Marjan hydrocarbons field.

In early September, contractors in Aramco’s LTA pool of offshore service providers submitted bids for 10 EPCI packages of the Safaniya increment programme, estimated to be worth upwards of $5bn in total.

Increasing gas production

To grow its gas production potential, Aramco is tapping into the vast resources of the Jafurah unconventional gas reserve in Saudi Arabia’s Eastern Province. The Jafurah basin hosts the largest liquid-rich shale gas play in the Middle East, spread over an area measuring 17,000 square kilometres and holding an estimated 200 trillion cubic feet of gas.

Aramco awarded $10bn-worth of subsurface and engineering, procurement and construction (EPC) contracts in November 2021, marking the start of the development of the Jafurah unconventional gas field, said to be the largest non-associated gas resource base in Saudi Arabia.

As part of the next development phase, Aramco plans to build a facility with the potential to process up to 2 billion cubic feet a day (cf/d) of raw gas produced from the Jafurah field. The Jafurah second expansion phase will also include EPC of large gas compression facilities and key units for natural gas liquids (NGL) fractionation.

MEED recently reported that Aramco is close to officially awarding contracts for the five main EPC packages of the Jafurah second expansion phase, estimated to be worth $10bn combined.

Carbon capture scheme

Meanwhile, Aramco is endeavouring to make its core operations more environmentally friendly to meet its target of attaining net-zero carbon emissions by 2050 and in line with Saudi Arabia’s net-zero emissions by 2060 target.

To that end, Aramco has undertaken a project to develop a carbon capture and storage infrastructure in Saudi Arabia that will tap carbon dioxide (CO2) discharge from its gas processing plants.

The accelerated carbon capture and sequestration (ACCS) scheme aims to capture CO2 from Aramco’s northern gas plants of Wasit, Fadhili and Khursaniyah, as well as from the operations of its subsidiary Saudi Basic Industries Corporation (Sabic) and Saudi industrial gases provider Air Products Qudra.

Aramco is expected to reach a financial investment decision on the ACCS project by the end of the year. The two planned phases of the project are estimated to require a total capital expenditure of between $1.5bn and $2bn.

The ACCS project’s initial phase is expected to have a capacity of about 9 million tonnes a year, with the collection pipeline system designed to support its future expansion.

Aramco has brought on board US oil field services provider SLB (formerly Schlumberger) and Germany-headquartered Linde, the world’s largest industrial gas producer, as partners for the project’s initial phase. The second-phase partners are US-headquartered Air Products and oil field services provider Baker Hughes.

EPC works on the first phase of the ACCS project are expected to take three years, with commercial operation scheduled for 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11133645/main.gif
Indrajit Sen
Related Articles
  • Arada completes Sokoon buildings construction

    26 March 2026

    Sharjah-based private real estate developer Arada has announced the completion of five additional buildings in the Naseej District of its Aljada development.

    Kuwaiti firm Mohammad Abdulmohsen Al-Kharafi & Sons secured the construction contract for the Sokoon buildings in 2023, replacing Airolink Building Contracting as the project’s main contractor.

    The first four Sokoon buildings were completed in December 2023.

    In April last year, Arada also announced the completion of all eight Tiraz buildings in the Naseej District. The Tiraz buildings comprise 920 homes, including studios, one-bedroom and two-bedroom apartments.

    With the completion of the five Sokoon buildings, Aljada’s total number of completed residential units has risen to more than 8,200.

    Spanning 2.2 square kilometres, Aljada features residential districts, retail spaces, educational institutions, healthcare services and other facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16141382/main.png
    Yasir Iqbal
  • Local contractor wins Medina substation contract

    26 March 2026

    Danway Saudi Arabia has won a contract with National Grid SA to construct a new 110/13.8kV substation in Medina.

    The contract is valued at more than SR100m ($26.7m) and covers the construction of the King Abdulaziz Road substation, including design, engineering, supply, installation, testing and commissioning.

    The project is expected to take approximately 23 months to complete.

    Key components include 110kV gas-insulated switchgear (GIS), 50/67MVA 110/13.8kV power transformers and 13.8kV switchgear.

    National Grid SA is a wholly owned subsidiary of Saudi Energy, formerly Saudi Electricity Company. It owns and operates the kingdom’s high-voltage transmission network and is responsible for grid planning, interconnection and system reliability.

    The operator recently appointed another local firm, Nesma Infrastructure & Technology, as the contractor for the construction of two 380kV double-circuit overhead transmission lines in Riyadh, connecting an existing substation to a wind power substation, referred to as Samha Wind BSP.

    As MEED understands, National Grid SA is also due to begin construction on the replacement of 132kV oil-filled underground cable circuits between several substations in the Central Operation Area in Murabba in Riyadh.

    Riyadh-based Keir International is the engineering, procurement and construction contractor for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16139578/main.jpg
    Mark Dowdall
  • Neom terminates $5bn Trojena dams contract with WeBuild

    26 March 2026

    Register for MEED’s 14-day trial access 

    Neom has terminated its contract with Italian contractor Webuild for the construction of three dams feeding a freshwater lake, as well as ‘The Bow’ architectural structure at Trojena in northwest Saudi Arabia.

    In a statement posted on its website, Webuild said: “The termination will become effective on 29 March. As of that date, the works are approximately 30% complete, with a remaining project backlog for Webuild of approximately €2.8bn ($3.2bn).”

    Neom awarded Webuild a SR20bn ($5bn) contract to build the dams in late 2023, which MEED exclusively reported at the time.

    The termination is the latest in a series of high-profile contract cancellations by Neom in recent weeks. Earlier this week, Neom terminated its contract with Malaysian contractor Eversendai Corporation for the steel structural works on the Ski Village project in Trojena.

    In a statement published on its website, Eversendai said it had received an official notice that the termination would take effect from 26 March.

    In January this year, Saudi Arabia confirmed the postponement of the 2029 Asian Winter Games, which were scheduled to be held at Trojena. Trojena was chosen to host the event in October 2022.

    Neom has also cancelled contracts for the construction of the tunnel sections of The Line in northwest Saudi Arabia.

    In a stock exchange filing dated 13 March, South Korean contractor Hyundai E&C said Neom cancelled its contract on 29 December last year.

    Hyundai E&C was executing the drill-and-blast section of The Line’s tunnels in a joint venture with Greece’s Archirodon and South Korean counterpart Samsung C&T.

    These developments follow a wider strategic review of Neom last year, as Saudi Arabia reassesses priorities under its Vision 2030 programme.

    With tighter liquidity at the sovereign wealth fund level, resources are being redirected towards projects linked to the Fifa World Cup 2034, Expo 2030, and essential housing, healthcare and education initiatives.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16140200/main.jpg
    Yasir Iqbal
  • Iraq gas field project disrupted by regional conflict

    26 March 2026

     

    Register for MEED’s 14-day trial access 

    Progress on Iraq’s project to develop the strategically important Akkas gas field has been disrupted by security issues related to the US and Israel’s ongoing war with Iran, according to industry sources.

    Work activity at the project site has been significantly reduced due to security concerns, and the project is now expected to take longer to complete.

    Iraq held a ceremony in January this year to mark the restart of drilling operations at the site as part of the field development project.

    In July last year, Iraq’s Oil Ministry announced signing a contract with the US-based oil field services provider SLB to develop production at Iraq’s Akkas gas field.

    Under the terms of the deal, SLB will drill wells at the Akkas field, aiming to initially raise production to 100 million cubic feet a day (cf/d).

    Many of SLB’s non-Iraqi employees have now been evacuated from the country.

    Over the long term, Iraq is targeting gas production of 400 million cf/d from the field.

    The contract with SLB replaces a previous deal with Ukraine-based Ukrzemresurs, which has been terminated.

    It also covers the construction of surface infrastructure and pipelines to connect Akkas to central processing units.

    The gas produced at Akkas will be used to fuel the Anbar combined-cycle power plant, which is under construction by the Electricity Ministry.

    Akkas gas field development

    The Akkas gas field, located in Anbar province in western Iraq, has 5.6 trillion cubic feet of proven reserves. The field was discovered in 1992 and began production in 1993.

    Since then, Iraq’s plans to develop the Akkas gas field to its full potential have experienced several setbacks.

    In April last year, the Iraqi Oil Ministry signed an agreement with Ukrzemresurs to develop the field.

    At the time, the Oil Ministry said that the partners were aiming to produce 100 million cf/d in the first two years, as per the agreement, with output targeted to increase to 400 million cf/d within four years.

    Prior to Ukrzemresurs, South Korean company Kogas was responsible for developing the field.

    Rights to the field were originally awarded to a consortium of Kogas and Kazakhstan’s state-owned oil company KazMunaiGas (KMG) in the third licensing round, which was launched in October 2011.

    KMG pulled out, leaving Kogas as the sole investor and operator on new contract terms.

    When the deal with Ukrzemresurs was originally announced last year, it was negatively received by some Iraqi politicians, with the Oil and Gas Committee in Iraq’s parliament rejecting the contract signing.

    At the time, Ali Al-Mashkour, a member of the Oil and Gas Committee, told Iraq’s Shafaq News Agency: “This contract involves a great waste of Iraq’s wealth, and there will be a waste of Iraq’s oil, and this confirms that Iraq is once again failing to choose reputable companies to work with in the most important economic field in the country.”

    He added: “We will work to uncover and expose the suspicions in this contract during the next stage, especially since this contract was made by some representatives for specific interests, which we will reveal soon with evidence.”

    Plans to sign the contract to develop the Akkas gas field with a Ukrainian company were first announced by the Oil Ministry in September 2023, but Ukrzemresurs was not named at the time.

    Iraq’s government is trying to transform the country into a gas-exporting nation. Currently, Iraq is reliant on Iran for gas imports.

    Both Saudi Arabia and the US, which are looking to contain Iranian influence in the region, have been supporting Iraq in developing its non-associated gas fields as this will reduce Iraq’s economic reliance on Iran.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16138892/main.png
    Wil Crisp
  • Dubai seeks contractors for Nadd Hessa stormwater project

    26 March 2026

    Dubai Municipality has invited contractors to prequalify for a contract to build a sewerage and stormwater system in the Nadd Hessa area.

    The project is being procured through the Sewerage and Recycled Water Projects Department.

    The submission deadline is 2 April.

    Nadd Hessa is an emerging development area, located between Dubai Silicon Oasis and Academic City along the E311 corridor.

    It has been earmarked for future residential expansion, with enabling infrastructure now being tendered to support planned housing and community developments in the area.

    The scheme, known as DS 328/1–C1, covers the construction of sewerage and stormwater infrastructure, including approximately 12.4 kilometres of sewerage lines with diameters of up to 400 millimetres.

    The scope also includes about 14km of stormwater lines with diameters of up to 1,000 millimetres.

    In addition, the project involves around 500 metres of microtunnelling works for both sewerage and stormwater networks.

    The municipality is currently prequalifying contractors for several upcoming water projects, including the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).

    Bid submissions for this project are also due by 2 April.

    In addition, the authority is planning a broader review of Dubai’s water and wastewater infrastructure to support future population growth, including identifying locations for future infrastructure. 

    Two separate consultancy tenders were issued in March.

    One involves a study to develop a sustainable urban drainage systems strategy across the emirate. The other covers a review of the emirate’s sewage treatment and recycled water distribution strategy. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16138660/main.jpg
    Mark Dowdall