Aramco focuses on upstream capacity building

12 September 2023

This package on Saudi Arabias upstream sector also includes: 

Aramco sets new deadlines for Manifa offshore bids
Aramco gives gas plant expansion bidders more time
Riyadh and Moscow extend oil output cuts till year-end
Aramco receives bids for Safaniya field expansion
Aramco selects contractors for $10bn gas project
Development of Dorra field may stoke tensions


 

While Saudi Arabia is set to continue reducing its oil production until the end of the year, a measure that could lead to further declines in its oil revenues, the decision has not deterred state energy giant Saudi Aramco from investing in projects to build its oil and gas production potential.

On Tuesday 5 September, global benchmark Brent crude breached the $90-a-barrel mark for the first time this year, primarily due to the Opec+ alliance’s oil supply management mechanism and the kingdom’s voluntary output cuts.

Aramco is capitalising on this high oil price environment to push through projects that are critical to achieving its strategic upstream goals of raising oil production capacity to 13 million barrels a day (b/d) by 2027, from about 12 million b/d at present, and doubling gas production by the end of this decade.

The state enterprise expects its capital expenditure this year to be $45bn-$55bn, including external investments – at least 20 per cent higher than its $37.6bn capex in 2022.

Spending on offshore oil and gas engineering, procurement, construction and installation (EPCI) projects is expected to account for the bulk of this projected capex for 2023.

Robust offshore spending

Most of the kingdom’s oil and gas production comes from its offshore hydrocarbons resources in fields including Abu Safah, Arabiyah, Hasbah, Berri, Karan, Manifa, Marjan, Ribyan, Safaniya and Zuluf.

Aramco aims to maintain and gradually increase productivity at these fields, some of which are mature. In line with this, the state enterprise is poised to award approximately $4bn of offshore EPCI deals to entities in its long-term agreement (LTA) pool of offshore contractors by the end of this year.

So far this year, Aramco has already awarded about $3bn-worth of contracts as part of this projected spending.

A consortium of Indian contractor Larsen & Toubro Energy Hydrocarbon (LTEH) and UK-based Subsea7 has won seven offshore EPCI contracts from Saudi Aramco, estimated to be worth close to $2bn.

LTEH/Subsea7 won contract release and purchase order (CRPO) numbers 98, 120 and 121, which cover EPCI work on Saudi Arabia’s Zuluf, Hasbah and Manifa offshore oil and gas fields. The combined value of the three CRPOs, awarded to the consortium in March, is estimated to be $1bn.

In April, LTEH/Subsea7 won CRPOs 117, 118 and 119, which cover EPCI work on Saudi Arabia’s Marjan offshore oil and gas field development. The three tenders are thought to be worth over $900m.

The LTEH/Subsea7 consortium is also understood to have secured the contract for CRPO 97, which relates to the EPCI of various units at the Abu Safah field.

Italian contractor Saipem confirmed in early April that it had won CRPO 96, estimated to have a value of $120m. The scope of work on the tender covers the EPCI of one platform topside and the associated subsea flexible, umbilical and cable systems at the Abu Safah and Safaniya fields.

Also in April, China Offshore Oil Engineering Company (COOEC) won the CRPO 122 contract, estimated to be worth $255m, covering the installation of 13 jackets at the Safaniya field.

Saipem has also won CRPO 124, a key contract for the third gas development phase of the Marjan hydrocarbons field.

In early September, contractors in Aramco’s LTA pool of offshore service providers submitted bids for 10 EPCI packages of the Safaniya increment programme, estimated to be worth upwards of $5bn in total.

Increasing gas production

To grow its gas production potential, Aramco is tapping into the vast resources of the Jafurah unconventional gas reserve in Saudi Arabia’s Eastern Province. The Jafurah basin hosts the largest liquid-rich shale gas play in the Middle East, spread over an area measuring 17,000 square kilometres and holding an estimated 200 trillion cubic feet of gas.

Aramco awarded $10bn-worth of subsurface and engineering, procurement and construction (EPC) contracts in November 2021, marking the start of the development of the Jafurah unconventional gas field, said to be the largest non-associated gas resource base in Saudi Arabia.

As part of the next development phase, Aramco plans to build a facility with the potential to process up to 2 billion cubic feet a day (cf/d) of raw gas produced from the Jafurah field. The Jafurah second expansion phase will also include EPC of large gas compression facilities and key units for natural gas liquids (NGL) fractionation.

MEED recently reported that Aramco is close to officially awarding contracts for the five main EPC packages of the Jafurah second expansion phase, estimated to be worth $10bn combined.

Carbon capture scheme

Meanwhile, Aramco is endeavouring to make its core operations more environmentally friendly to meet its target of attaining net-zero carbon emissions by 2050 and in line with Saudi Arabia’s net-zero emissions by 2060 target.

To that end, Aramco has undertaken a project to develop a carbon capture and storage infrastructure in Saudi Arabia that will tap carbon dioxide (CO2) discharge from its gas processing plants.

The accelerated carbon capture and sequestration (ACCS) scheme aims to capture CO2 from Aramco’s northern gas plants of Wasit, Fadhili and Khursaniyah, as well as from the operations of its subsidiary Saudi Basic Industries Corporation (Sabic) and Saudi industrial gases provider Air Products Qudra.

Aramco is expected to reach a financial investment decision on the ACCS project by the end of the year. The two planned phases of the project are estimated to require a total capital expenditure of between $1.5bn and $2bn.

The ACCS project’s initial phase is expected to have a capacity of about 9 million tonnes a year, with the collection pipeline system designed to support its future expansion.

Aramco has brought on board US oil field services provider SLB (formerly Schlumberger) and Germany-headquartered Linde, the world’s largest industrial gas producer, as partners for the project’s initial phase. The second-phase partners are US-headquartered Air Products and oil field services provider Baker Hughes.

EPC works on the first phase of the ACCS project are expected to take three years, with commercial operation scheduled for 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11133645/main.gif
Indrajit Sen
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal