Aramco focuses on upstream capacity building

12 September 2023

This package on Saudi Arabias upstream sector also includes: 

Aramco sets new deadlines for Manifa offshore bids
Aramco gives gas plant expansion bidders more time
Riyadh and Moscow extend oil output cuts till year-end
Aramco receives bids for Safaniya field expansion
Aramco selects contractors for $10bn gas project
Development of Dorra field may stoke tensions


 

While Saudi Arabia is set to continue reducing its oil production until the end of the year, a measure that could lead to further declines in its oil revenues, the decision has not deterred state energy giant Saudi Aramco from investing in projects to build its oil and gas production potential.

On Tuesday 5 September, global benchmark Brent crude breached the $90-a-barrel mark for the first time this year, primarily due to the Opec+ alliance’s oil supply management mechanism and the kingdom’s voluntary output cuts.

Aramco is capitalising on this high oil price environment to push through projects that are critical to achieving its strategic upstream goals of raising oil production capacity to 13 million barrels a day (b/d) by 2027, from about 12 million b/d at present, and doubling gas production by the end of this decade.

The state enterprise expects its capital expenditure this year to be $45bn-$55bn, including external investments – at least 20 per cent higher than its $37.6bn capex in 2022.

Spending on offshore oil and gas engineering, procurement, construction and installation (EPCI) projects is expected to account for the bulk of this projected capex for 2023.

Robust offshore spending

Most of the kingdom’s oil and gas production comes from its offshore hydrocarbons resources in fields including Abu Safah, Arabiyah, Hasbah, Berri, Karan, Manifa, Marjan, Ribyan, Safaniya and Zuluf.

Aramco aims to maintain and gradually increase productivity at these fields, some of which are mature. In line with this, the state enterprise is poised to award approximately $4bn of offshore EPCI deals to entities in its long-term agreement (LTA) pool of offshore contractors by the end of this year.

So far this year, Aramco has already awarded about $3bn-worth of contracts as part of this projected spending.

A consortium of Indian contractor Larsen & Toubro Energy Hydrocarbon (LTEH) and UK-based Subsea7 has won seven offshore EPCI contracts from Saudi Aramco, estimated to be worth close to $2bn.

LTEH/Subsea7 won contract release and purchase order (CRPO) numbers 98, 120 and 121, which cover EPCI work on Saudi Arabia’s Zuluf, Hasbah and Manifa offshore oil and gas fields. The combined value of the three CRPOs, awarded to the consortium in March, is estimated to be $1bn.

In April, LTEH/Subsea7 won CRPOs 117, 118 and 119, which cover EPCI work on Saudi Arabia’s Marjan offshore oil and gas field development. The three tenders are thought to be worth over $900m.

The LTEH/Subsea7 consortium is also understood to have secured the contract for CRPO 97, which relates to the EPCI of various units at the Abu Safah field.

Italian contractor Saipem confirmed in early April that it had won CRPO 96, estimated to have a value of $120m. The scope of work on the tender covers the EPCI of one platform topside and the associated subsea flexible, umbilical and cable systems at the Abu Safah and Safaniya fields.

Also in April, China Offshore Oil Engineering Company (COOEC) won the CRPO 122 contract, estimated to be worth $255m, covering the installation of 13 jackets at the Safaniya field.

Saipem has also won CRPO 124, a key contract for the third gas development phase of the Marjan hydrocarbons field.

In early September, contractors in Aramco’s LTA pool of offshore service providers submitted bids for 10 EPCI packages of the Safaniya increment programme, estimated to be worth upwards of $5bn in total.

Increasing gas production

To grow its gas production potential, Aramco is tapping into the vast resources of the Jafurah unconventional gas reserve in Saudi Arabia’s Eastern Province. The Jafurah basin hosts the largest liquid-rich shale gas play in the Middle East, spread over an area measuring 17,000 square kilometres and holding an estimated 200 trillion cubic feet of gas.

Aramco awarded $10bn-worth of subsurface and engineering, procurement and construction (EPC) contracts in November 2021, marking the start of the development of the Jafurah unconventional gas field, said to be the largest non-associated gas resource base in Saudi Arabia.

As part of the next development phase, Aramco plans to build a facility with the potential to process up to 2 billion cubic feet a day (cf/d) of raw gas produced from the Jafurah field. The Jafurah second expansion phase will also include EPC of large gas compression facilities and key units for natural gas liquids (NGL) fractionation.

MEED recently reported that Aramco is close to officially awarding contracts for the five main EPC packages of the Jafurah second expansion phase, estimated to be worth $10bn combined.

Carbon capture scheme

Meanwhile, Aramco is endeavouring to make its core operations more environmentally friendly to meet its target of attaining net-zero carbon emissions by 2050 and in line with Saudi Arabia’s net-zero emissions by 2060 target.

To that end, Aramco has undertaken a project to develop a carbon capture and storage infrastructure in Saudi Arabia that will tap carbon dioxide (CO2) discharge from its gas processing plants.

The accelerated carbon capture and sequestration (ACCS) scheme aims to capture CO2 from Aramco’s northern gas plants of Wasit, Fadhili and Khursaniyah, as well as from the operations of its subsidiary Saudi Basic Industries Corporation (Sabic) and Saudi industrial gases provider Air Products Qudra.

Aramco is expected to reach a financial investment decision on the ACCS project by the end of the year. The two planned phases of the project are estimated to require a total capital expenditure of between $1.5bn and $2bn.

The ACCS project’s initial phase is expected to have a capacity of about 9 million tonnes a year, with the collection pipeline system designed to support its future expansion.

Aramco has brought on board US oil field services provider SLB (formerly Schlumberger) and Germany-headquartered Linde, the world’s largest industrial gas producer, as partners for the project’s initial phase. The second-phase partners are US-headquartered Air Products and oil field services provider Baker Hughes.

EPC works on the first phase of the ACCS project are expected to take three years, with commercial operation scheduled for 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11133645/main.gif
Indrajit Sen
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp