Aramco awards pair of key offshore contracts

10 July 2023

Register for MEED's guest programme 

Saudi Aramco has awarded UAE-headquartered Lamprell two key contracts for engineering, procurement, construction and installation (EPCI) of several structures at the Abu Safah and Marjan offshore oil fields in Saudi Arabia.

Lamprell has been awarded Contract Release and Purchase Order (CRPO) numbers 125 and 126, according to sources.

The combined value of CRPOs 125 and 126 is estimated to be “upwards” of $400m, sources told MEED.

The letter of award for these two tenders was issued to Lamprell by Aramco “in late June”, the sources added.

Abu Safah and Marjan works

The scope of works on CRPO 125 covers EPCI of the following structures:

  • Three offshore jackets
  • Three production deck modules
  • Two 12-inch pipelines stretching 3 kilometres and 1.7km
  • Two 13.8kv subsea power cables covering distances of 7.5km and 3km.

Contractors in Aramco’s Long-Term Agreement (LTA) pool of offshore service providers submitted bids for CRPO 125 by the deadline of 16 January.

The scope of work on CRPO 126 involves EPCI of the following structures at the Marjan hydrocarbons field development:

  • One gas lift production deck module
  • Four jackets
  • A 16-inch subsea pipeline running 6.5km
  • 15kv subsea cables covering 6.5km

Offshore LTA contractors submitted bids for CRPO 126 by 9 April, MEED previously reported.

Robust offshore spending

Most of the kingdom’s oil and gas production comes from offshore hydrocarbon resources in fields including Abu Safah, Arabiyah, Hasbah, Berri, Karan, Manifa, Marjan, Ribyan, Safaniya and Zuluf.

It is crucial for Aramco to maintain and gradually increase productivity from these fields, some of which are mature.

To that end, the state enterprise is poised to award several billions of dollars of offshore EPCI deals to entities in its LTA pool of offshore contractors by the end of this year.

With the latest award of CRPOs 125 and 126 to Lamprell, Aramco’s spending on offshore projects so far this year is estimated to have exceeded $3bn.

A consortium of Indian contractor Larsen & Toubro Energy Hydrocarbon (LTEH) and UK-based Subsea7 has won six offshore EPCI contracts from Saudi Aramco, estimated to be worth nearly $2bn.

LTEH/Subsea7 won CRPOs 98, 120 and 121, which cover EPCI work on Saudi Arabia’s Zuluf, Hasbah and Manifa offshore oil and gas fields. The combined value of the three CRPOs, awarded to the consortium in March, is estimated to be $1bn.

In April, LTEH/Subsea7 won CRPOs 117, 118 and 119, which cover EPCI work on Saudi Arabia’s Marjan offshore oil and gas field development. The three tenders are thought to be worth over $900m.

Italian contractor Saipem confirmed in early April that it had won CRPO 96, estimated to have a value of $120m. The scope of work on the tender covers the EPCI of one platform topside and the associated subsea flexible, umbilical and cable systems at the Abu Safah and Safaniya fields.

Also in April, China Offshore Oil Engineering Company (COOEC) won the CRPO 122 contract, estimated to be worth $255m, covering the installation of 13 jackets at the Safaniya field. COOEC confirmed the award of CRPO 122 this week.

More recently, in May MEED reported that Aramco was closing in on awarding main contracts for at least five major CRPO tenders, and notifying contractors about their selection.

The following LTA contractors are in line to win the CRPOs in question, according to sources:

  • CRPO 97 – National Petroleum Construction Company (NPCC) (UAE)
  • CRPO 99 – McDermott (US)
  • CRPO 100 – McDermott (US)
  • CRPO 101 – McDermott (US)
  • CRPO 124 – Saipem (Italy)

In late June, Saipem confirmed winning CRPO 124, although the Italian contractor did not reveal the value of its contract.

CRPO 124 represents the third phase of gas development at the Marjan offshore hydrocarbons field. Its scope of work entails the following:

  • EPCI of five standardised, simplified and SIMOPS-capable (SSS) gas lift platforms
  • Demolition of existing structures
  • Five production deck modules
  • Upgrade of TP 7 at gas oil separation plant (GOSP) 4
  • Subsea flowlines of 4 and 6-inches covering a distance of 23km
  • Subsea cables spanning 17km
  • Fibre optic cables spread across 6km

The two other contractors – McDermott and NPCC – are yet to confirm their contract awards.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10994344/main2028.jpg
Indrajit Sen
Related Articles
  • Iranian missiles hit Qatari and Kuwaiti fuel tankers

    1 April 2026

    Iranian missiles have struck fuel tankers in Gulf waters belonging to Qatar and Kuwait, as Tehran continues to target energy, industrial and logistical assets in GCC countries.

    A fuel oil tanker chartered by QatarEnergy, named Aqua 1, was struck by missiles in Qatar’s northern territorial waters in the early hours of 1 April, the company said in a statement.

    “None of the crew members on board were injured, and there is no impact on the environment as a result of this incident,” QatarEnergy said.

    Earlier, on 31 March,  said one of its very large crude carriers, Al-Salmi, caught fire after being hit by an Iranian missile while anchored in UAE waters just outside Dubai.

    The vessel’s crew, with support from UAE authorities, extinguished the fire by 04:26 Kuwait time on 31 March, KPC said. It added that all 24 crew members were safe and that no oil spill or environmental damage occurred.

    “KPC is continuing to assess the damage in coordination with relevant authorities,” the Kuwaiti state energy conglomerate said.

    ALSO READ: Iran strikes Gulf aluminium assets after hits on its steel sector
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16217670/main4010.jpg
    Indrajit Sen
  • One killed and one injured in drone attacks on the UAE

    1 April 2026

    Debris falling from Iranian drones intercepted by the UAE’s air defence systems has killed one person in the emirate of Fujairah and injured another in Umm Al-Quwain in two separate incidents on 1 April.

    A successful interception of a drone by UAE air defence forces resulted in debris falling on a farm in Fujairah, leading to the death of a Bangladeshi national.

    The latest fatality brings the total death toll in the UAE since the start of the US-Israel-Iran war to 12. Most of the deaths have been caused by falling debris following interceptions. Among the deceased are two members of the UAE armed forces who died while performing their duties, as well as a Moroccan civilian contracted by the armed forces.

    The remaining victims were of Bangladeshi, Indian, Nepali, Pakistani and Palestinian nationalities.

    Hours after the Fujairah incident, authorities in Umm Al-Quwain confirmed that an Indian national was injured when debris from an intercepted drone fell in the emirate.

    In a statement posted on its official social media channels, the Umm Al-Quwain government media office said the incident occurred near an industrial facility in the Umm Al-Thuoob area, after air defence systems successfully intercepted an unmanned aerial vehicle (UAV).

    Meanwhile, the latest data from the UAE Ministry of Defence, released on 31 March, showed that air defence systems had engaged 36 UAVs, four cruise missiles and eight ballistic missiles in the previous 24 hours. Cumulatively, authorities said 1,977 drones, 19 cruise missiles and 433 ballistic missiles have been intercepted since the onset of the war on 28 February.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16218126/main.jpg
    Indrajit Sen
  • Contractors submit Al-Maktoum airport superstructure bids

    1 April 2026

     

    Dubai Aviation Engineering Projects (DAEP) received proposals on 31 March from contractors for three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.

    MEED understands that the selected contractor will undertake superstructure works on three packages:

    • West Terminal and concourse one
    • Concourse two
    • Concourse three

    Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.

    In August last year, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport. 

    The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Construction progress

    Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    The statement added that the project will create housing demand for 1 million people around the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    Project history

    The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.

    An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.

    Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16215664/main.jpg
    Yasir Iqbal
  • Drone strikes Kuwait International airport

    1 April 2026

    Register for MEED’s 14-day trial access 

    Kuwait International airport was hit by further drone attacks on Wednesday, with strikes on fuel tanks sparking a major fire.

    Kuwait’s state news agency Kuna said the attack caused significant damage to fuel tanks belonging to Kuwait Aviation Fuelling Company. No casualties were reported.

    This was the second reported incident at the airport in recent days. Local media reported that the airport was attacked on 28 March by multiple drones, causing significant damage to its radar system.

    The airport is currently undergoing expansion works that are expected to be completed by 2027, as MEED reported previously.

    Project execution of the second terminal began in 2017, with the completion date pushed back from the original 2022 target.

    The second terminal project consists of three packages.

    These are:

    • Package 1: Main works – $4,329m
    • Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
    • Package 3: Aircraft parking, runways and service buildings – $950m

    Turkiye’s Limak Holding is executing the main works.

    The terminal building was designed by Foster+Partners and Gulf Consult.

    Spanish firm Ineco is providing the project management services for the new terminal building and the airfield.

    The scope of the main package includes the new terminal building, a building for cooling and electricity supply facilities, and a building for the water supply and the future Automatic People Mover (APM) connection to the satellite building.

    The terminal building will be three times the size of the original building and will have 36 boarding gates.

    The building will cover more than 700,000 square metres and have five floors, one of which will be underground.

    It will have the capacity, at maximum service level, for 25 million passengers a year once the first phase has been completed and up to 50 million passengers after further phases are completed.

    The second package of works includes a new car park with approximately 5,000 parking spaces, connected to the new passenger terminal.

    It also includes all new access roads to the airport and landscaping.

    The scope of the third package comprises the main platform, new taxiways and several tunnels, including one under the platform between the terminal building and the future cargo area of the airport.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16216797/main.png
    Yasir Iqbal
  • Saudi Arabia’s Sadara halts chemical production

    1 April 2026

    Register for MEED’s 14-day trial access 

    Sadara Chemical Company (Sadara), the Saudi Aramco-Dow Chemical joint venture producing petrochemicals and specialty chemicals, has announced a temporary shutdown of production, citing ongoing supply chain disruptions.

    Sadara operates a sprawling chemical production complex in Jubail in Saudi Arabia’s Eastern Province, with a total output capacity of more than 3 million metric tonnes a year. Aramco and Dow established the Sadara petrochemicals complex – estimated to have cost $13bn – in 2016.

    The suspension was announced in a filing on the Saudi Exchange (Tadawul) by Sadara Basic ​Services, which issues sukuk, or Islamic bonds, ​for its parent. “The shutdown was successfully completed in accordance with Sadara’s high safety standards and in a manner that safeguards operations and reduces risk,” the entity said in its filing on 31 March

    “Sadara cannot provide, at the present ‌time, ⁠an estimate for the return to production, as this is contingent on domestic and international factors,” it said, ​adding ​the shutdown ⁠is expected to impact this year’s financial results.

    The month-long war between Israel, the US and Iran has spread across the Middle East, disrupting energy supplies and threatening the global economy, as Tehran has responded to US and Israeli attacks by targeting regional energy and industrial infrastructure, as well as shipping.

    ALSO READ: Sultan Al-Jaber calls Strait of Hormuz blockade “economic terrorism”

    Separately, Sadara, in another Tadawul filing on 31 March, announced a net loss of SR5,793bn ($1.54bn) for the full year 2025, a further decline of about 40% compared to 2024. The company’s revenue in 2025 fell by about 15% year-on-year to $2.63bn.

    The chemicals producer attributed the deepening of its losses in 2025 to a reduction in sales volumes, “which resulted from unplanned operational events and extended maintenance activities that temporarily impacted production availability”.

    Sadara also pinned its augmented losses to “margin compression, and higher fixed costs associated with unplanned operational events and extended maintenance activities.

    “In addition, the company experienced lower average selling prices across certain portfolio lines, which further contributed to the overall decrease in revenue,” Sadara said in the disclosure.

    In addition, “the net loss for 2025 increased compared to 2024, mainly due to an accounting adjustment related to a debt modification that had a favourable impact on the prior year’s results,” the company added.

    ALSO READ: Sabic registers $6.87bn net loss in 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16215635/main2446.jpg
    Indrajit Sen