Aramco awards pair of key offshore contracts
10 July 2023

Register for MEED's guest programme
Saudi Aramco has awarded UAE-headquartered Lamprell two key contracts for engineering, procurement, construction and installation (EPCI) of several structures at the Abu Safah and Marjan offshore oil fields in Saudi Arabia.
Lamprell has been awarded Contract Release and Purchase Order (CRPO) numbers 125 and 126, according to sources.
The combined value of CRPOs 125 and 126 is estimated to be “upwards” of $400m, sources told MEED.
The letter of award for these two tenders was issued to Lamprell by Aramco “in late June”, the sources added.
Abu Safah and Marjan works
The scope of works on CRPO 125 covers EPCI of the following structures:
- Three offshore jackets
- Three production deck modules
- Two 12-inch pipelines stretching 3 kilometres and 1.7km
- Two 13.8kv subsea power cables covering distances of 7.5km and 3km.
Contractors in Aramco’s Long-Term Agreement (LTA) pool of offshore service providers submitted bids for CRPO 125 by the deadline of 16 January.
The scope of work on CRPO 126 involves EPCI of the following structures at the Marjan hydrocarbons field development:
- One gas lift production deck module
- Four jackets
- A 16-inch subsea pipeline running 6.5km
- 15kv subsea cables covering 6.5km
Offshore LTA contractors submitted bids for CRPO 126 by 9 April, MEED previously reported.
Robust offshore spending
Most of the kingdom’s oil and gas production comes from offshore hydrocarbon resources in fields including Abu Safah, Arabiyah, Hasbah, Berri, Karan, Manifa, Marjan, Ribyan, Safaniya and Zuluf.
It is crucial for Aramco to maintain and gradually increase productivity from these fields, some of which are mature.
To that end, the state enterprise is poised to award several billions of dollars of offshore EPCI deals to entities in its LTA pool of offshore contractors by the end of this year.
With the latest award of CRPOs 125 and 126 to Lamprell, Aramco’s spending on offshore projects so far this year is estimated to have exceeded $3bn.
A consortium of Indian contractor Larsen & Toubro Energy Hydrocarbon (LTEH) and UK-based Subsea7 has won six offshore EPCI contracts from Saudi Aramco, estimated to be worth nearly $2bn.
LTEH/Subsea7 won CRPOs 98, 120 and 121, which cover EPCI work on Saudi Arabia’s Zuluf, Hasbah and Manifa offshore oil and gas fields. The combined value of the three CRPOs, awarded to the consortium in March, is estimated to be $1bn.
In April, LTEH/Subsea7 won CRPOs 117, 118 and 119, which cover EPCI work on Saudi Arabia’s Marjan offshore oil and gas field development. The three tenders are thought to be worth over $900m.
Italian contractor Saipem confirmed in early April that it had won CRPO 96, estimated to have a value of $120m. The scope of work on the tender covers the EPCI of one platform topside and the associated subsea flexible, umbilical and cable systems at the Abu Safah and Safaniya fields.
Also in April, China Offshore Oil Engineering Company (COOEC) won the CRPO 122 contract, estimated to be worth $255m, covering the installation of 13 jackets at the Safaniya field. COOEC confirmed the award of CRPO 122 this week.
More recently, in May MEED reported that Aramco was closing in on awarding main contracts for at least five major CRPO tenders, and notifying contractors about their selection.
The following LTA contractors are in line to win the CRPOs in question, according to sources:
- CRPO 97 – National Petroleum Construction Company (NPCC) (UAE)
- CRPO 99 – McDermott (US)
- CRPO 100 – McDermott (US)
- CRPO 101 – McDermott (US)
- CRPO 124 – Saipem (Italy)
In late June, Saipem confirmed winning CRPO 124, although the Italian contractor did not reveal the value of its contract.
CRPO 124 represents the third phase of gas development at the Marjan offshore hydrocarbons field. Its scope of work entails the following:
- EPCI of five standardised, simplified and SIMOPS-capable (SSS) gas lift platforms
- Demolition of existing structures
- Five production deck modules
- Upgrade of TP 7 at gas oil separation plant (GOSP) 4
- Subsea flowlines of 4 and 6-inches covering a distance of 23km
- Subsea cables spanning 17km
- Fibre optic cables spread across 6km
The two other contractors – McDermott and NPCC – are yet to confirm their contract awards.
Exclusive from Meed
-
Read the December 2025 MEED Business Review28 November 2025
-
Petrofac’s UAE operations continue after layoffs28 November 2025
-
PDO starts Dhulaima field early phase development project28 November 2025
-
Top deals signed at Dubai Airshow 202527 November 2025
-
Prequalification begins for Riyadh King Salman Stadium27 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Read the December 2025 MEED Business Review28 November 2025
Download / Subscribe / 14-day trial access The region boasts a pipeline of over $140bn-worth of railway schemes, according to data from regional projects tracker MEED Projects.
This puts the GCC at the centre of global rail construction activity, with progress being made on several large-scale rail schemes.From the Qiddiya high-speed rail in Saudi Arabia to the planned expansion of Dubai’s metro network and the long-awaited revival of the GCC railway, a new wave of projects is shaping the region’s economic future.
As leading construction, engineering and technology firms either expand or return to the region after years of reduced activity, MEED’s latest issue of MEED Business Review looks at the scale and ambition of ongoing rail projects.
We also consider the region’s growing role as a rail hub, with an increasing need for ongoing servicing, upgrades and new technologies.
This month’s market focus covers Bahrain, where Manama is pushing ahead with diversification amid mounting fiscal constraints and external pressures.
MEED’s latest issue also includes our 2025 EPC contractor ranking, as well as analysis on the cost advantages, technological gains and strong execution giving Chinese contractors a regional edge.
This edition is bursting with features and interviews. The team looks at Libya's ramp up of oil activity; visits the under-construction Aramco Stadium in Khobar as it races towards completion; provides an update on Abu Dhabi's $6bn solar and storage project; and interviews Turki AlShehri, regional vice president for Saudi Arabia and the GCC at French power and water developer Engie.
We hope our valued subscribers enjoy the December 2025 issue of MEED Business Review.

Must-read sections in the December 2025 issue of MEED Business Review include:
> AGENDA:
> Regional rail construction surges ahead
> Middle East becomes a hub as rail networks matureINDUSTRY REPORT:
EPC contractor ranking
> Larsen & Toubro climbs EPC contractor ranking
> Chinese firms expand oil and gas presence> CURRENT AFFAIRS: Oil companies ramp up activity in Libya
> CONSTRUCTION: Aramco Stadium races towards completion
> RENEWABLES: UAE moves ahead with $6bn solar and storage project
> INTERVIEW: Engie pivots towards renewables projects
> BAHRAIN MARKET REPORT:
> COMMENT: Manama pursues reform amid strain
> GVT & ECONOMY: Bahrain’s cautious economic evolution
> BANKING: Mergers loom over Bahrain’s banking system
> OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
> POWER & WATER: Bahrain advances utility reform
> CONSTRUCTION: Bahrain construction faces major slowdown
> TRANSPORT: Air Asia aviation deal boosts connectivity
> DATABANK: Bahrain’s economy walks precarious path> MEED COMMENTS:
> Bahrain’s willingness to disrupt takes flight with Air Asia
> Projects shift from spending plans to investment opportunities
> Lukoil deal collapse puts $1.8bn of Iraq projects at risk
> Clear rules drive Saudi Arabia's tariff edge> GULF PROJECTS INDEX: UAE fuels Gulf projects expansion
> OCTOBER 2025 CONTRACTS: Saudi Arabia and UAE lead deal signings
> ECONOMIC DATA: November 2025: Data drives regional projects
> OPINION: Riyadh’s American bond
> BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts
To see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15168493/main.gif -
Petrofac’s UAE operations continue after layoffs28 November 2025
The UK-headquartered company Petrofac is continuing to work on projects in the UAE after issuing termination notices to around 180 of its staff in the country.
Operations across Petrofac’s portfolio in the UAE are progressing as normal, according to statements sent to several media organisations.
The employees were given notice of their early release from the company on 19 November as part of restructuring measures.
On 27 October, Petrofac announced that it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa (Mena) region.
The total value of projects awarded to Petrofac and under construction in the region is $5.83bn, according to information recorded by the regional project-tracking service MEED Projects.
Petrofac also has bids under evaluation for 15 projects in the region worth a total of $19.28bn, according to MEED Projects data.
Ongoing restructuring
On 25 November, Petrofac released a statement saying that it was seeking to appoint administrators to its subsidiary Petrofac International Limited (PIL).
This subsidiary was previously focused on the group’s engineering and construction activities in the Mena region.
In its statement, Petrofac said that its subsidiary would “shortly make an application to the Royal Court of Jersey seeking a letter of request under section 426 of the Insolvency Act 1986”.
It added: “The purpose of this application is to ask the Royal Court of Jersey to issue a letter of request to the High Court of England and Wales and seek its assistance in appointing administrators to PIL.”
Petrofac said that PIL had no ongoing contracts in the Mena region and it intends to redeploy PIL’s 120 staff to other subsidiaries “wherever possible”.
It added: “The administration of PIL is expected to facilitate the purpose of Petrofac Limited’s administration, to help preserve the value of the wider Group and to facilitate the planned M&A solutions.”
Petrofac has said that it is continuing to push ahead with options for alternative restructuring and M&A solutions with key creditors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15173959/main.jpg -
PDO starts Dhulaima field early phase development project28 November 2025

Petroleum Development Oman (PDO) has started the prequalification process for engineering, procurement and construction (EPC) works on a project to develop key on-plot facilities as part of an early phase development of the Dhulaima onshore field.
The Dhulaima Upper Shuaiba field is located in the Lekhwair cluster in PDO’s Block 6 concession area. The Dhulaima early phase development project is to be executed on an operation lease contract for a duration of five years, PDO said in the prequalification document.
Majority state-owned PDO floated the prequalification questionnaire on 18 November, and has set a deadline of 7 December for contractors to submit responses.
The broad scope of work on the Dhulaima early phase development project covers EPC, as well as all associated civil, mechanical, piping, electrical, fabrication, instrumentation, control, testing, and pre-commissioning commissioning, and de-commissioning activities of the following on-plot facilities:
- Gas injection compressor package: Complete gas injection compressor package with all auxiliary systems, associated piping, associated instrumentation for safeguarding and control, etc, as complete skid. All the necessary power, utilities as required for the compressor package and its driver shall be included as part of the scope, along with all associated systems, foundations, piping, electrical, instrumentation. Type of compressor and driver to be proposed by the bidders.
- Gas injection manifold package: Complete gas injection manifold including all tie-ins to existing facilities, pipe supports, control valves, and instrumentation.
PDO is the operator of the Block 6 hydrocarbons concession in Oman, which is the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields.
The Omani government holds a 60% stake in PDO, with the other shareholders being UK-based Shell (34%), France’s TotalEnergies (4%) and Thai state-owned PTTEP (2%).
https://image.digitalinsightresearch.in/uploads/NewsArticle/15169037/main.jpg -
Top deals signed at Dubai Airshow 202527 November 2025
The Dubai Airshow 2025 drew to a close on 21 November, with deals exceeding $202bn, double the $101bn secured at the 18th edition in 2023.
This new milestone reinforces Dubai’s position as a global aviation hub and central force shaping the future of the aviation and space industries, according to a statement from the Government of Dubai Media Office.
The 19th edition of the event, held at Dubai World Central under the theme ‘The Future is Here’, also drew record attendance, welcoming 248,788 visitors, including industry leaders, government officials and aviation specialists from across the globe.
More than 1,500 exhibitors took part, with 440 participating for the first time, along with 490 military and civil delegations from 115 countries. The show also included 21 national pavilions, 98 chalets, an extra 8,000 square metres of display space, and a startup ecosystem with 120 startups and 50 investors.
One of the most globally diverse editions to date, this year’s airshow featured the usual mega-orders, but also a surprise fleet pivot and an emerging picture of the region’s biggest players taking control of their futures by influencing the development of tomorrow’s jets and securing their supply chains.
Anchor customer
UAE national carriers placed orders for 502 aircraft during the five-day event, with Emirates leading the charge. On the first day of the airshow, Emirates announced a $38bn order for 65 new Boeing 777-9 aircraft. The airline also ordered 130 GE9X engines from GE Aerospace, which power the new twin-engined planes.
The deal gives Boeing a boost after the 777-9’s debut was delayed to 2027 – but equally significantly, it provides strong backing for Boeing’s feasibility study to develop the 777-10, a larger variant of its 777X family, as Emirates pushes to replace its Airbus A380 fleet.
“Emirates has been open about the fact that we are keen for manufacturers to build larger capacity aircraft, which are more efficient to operate, especially with projected air traffic growth and increasing constraints at airports,” said Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and chief executive of Emirates Airline and Group.
“We fully support Boeing’s feasibility study to develop the 777-10 and have options to convert our latest 777-9 order to the 777-10 or the 777-8.”
Several days later, Emirates also ordered eight more A350-900 aircraft, worth $3.4bn and powered by Rolls-Royce Trent XWB84 engines, while also urging Airbus to explore a larger version of its A350-1000 wide-body.
Emirates’ commitment to new aircraft at the Dubai Airshow 2025 is worth $41.4bn at list prices, and brings the airline’s total wide-body aircraft orders to 375, with deliveries scheduled through 2038.
It was also announced that Emirates would deploy Starlink Wi-Fi across its entire in-service fleet, beginning with Boeing 777 aircraft in November 2025 and completing the rollout by mid-2027.
Airbus pivot
Flydubai also signed a memorandum of understanding (MoU) with Boeing to purchase 75 Boeing 737 MAX aircraft valued at $13bn. In one of the show’s biggest strategic shifts, a further MoU was signed with Airbus for 150 A321neo aircraft, making the airline a new Airbus customer.
Sheikh Ahmed, also chairman and CEO of flydubai, said this addition would diversify the airline’s narrow-body fleet and “enable flydubai to play a key role in the success of Dubai World Central’s expansion plans, an airport we aim to become the largest airport in the world”.
“We look forward to establishing a strong and enduring partnership between flydubai and Airbus,” he said.
Etihad Airways confirmed an order for 32 new Airbus aircraft, including freighters, marking a significant expansion of its wide-body fleet, while Gulf Air, Bahrain’s national carrier, finalised a firm order for 15 787 Dreamliners with options for three more as the carrier looks to further develop its international network. The order adds three Boeing 787s to the airline’s commitment this July and brings Gulf Air’s order book to 17 of the versatile widebody jets.
Saudi Arabia's emerging airline, Riyadh Air, confirmed a purchase of 120 CFM LEAP-1A engines for its incoming A321neo fleet.
Taking control
In a clear sign that Gulf airlines are taking charge of their supply chains, Emirates and France's Safran Seats signed an MoU to bring a manufacturing and plane seat assembly factory to Dubai. The joint industrial cooperation, the first of its kind, will initially focus on Emirates’ business and economy class seats for cabin retrofit projects, with plans to expand into new aircraft in the future.
“This agreement with Safran marks a pivotal and strategic cooperation that establishes Dubai as an aerospace manufacturing hub,” commented Sheikh Ahmed. “We're bringing world-class seat production capabilities and supply chain to our doorstep, creating highly skilled jobs, and developing capabilities to support Emirates and produce seats for export to other carriers.”
Emirates is also securing its own engine maintenance capabilities, signing an MoU with Rolls Royce to conduct engine maintenance, repair and overhaul on its own A380 fleet at a new plant in Dubai from 2027.
Green airline fuel
Sustainability was a core priority at the airshow, with initiatives including the supply of sustainable aviation fuel (SAF) for participating aircraft, the use of electric and propane-powered ground support equipment in partnership with Jetex, and exhibition halls run entirely on renewable energy.
On the sidelines of the event, Emirates and Enoc Group signed a memorandum of understanding to explore and develop joint initiatives for the supply of SAF to Emirates at its Dubai hub.
Defence deals
Capping the exhibition were the 36 deals signed on behalf of the Ministry of Defence and Abu Dhabi Police by the UAE’s Tawazun council – the national authority mandated to enable, regulate and sustain the UAE’s defence and security industrial ecosystem. Valued at AED25.455bn, the deals included contracts for drones, rescue gear, aircraft parts and support.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15167232/main.gif -
Prequalification begins for Riyadh King Salman Stadium27 November 2025
Register for MEED’s 14-day trial access
Saudi Arabia’s Sports Ministry has issued a notice inviting companies to prequalify for a contract to design and build the King Salman International Stadium in Riyadh.
The notice was issued on 26 November, with a prequalification deadline of 16 February.
The stadium will cover an area of about 660,000 square metres (sq m) and will have a seating capacity of 92,000.
The stadium will feature a 150-seat royal suite, 120 hospitality suites, 300 VIP seats and 2,200 dignitary seats.
The plan also includes several sports facilities covering more than 360,000 sq m, including two training fields and fan zones; a closed sports hall; an Olympic-sized swimming pool; an athletics track; and outdoor courts for volleyball, basketball and padel.
The new stadium will host the final of the 2034 Fifa World Cup and will serve as the Saudi national football team’s main headquarters.
US-based architectural firm Populous is the lead architect for the stadium.
Construction of the stadium is expected to be completed by 2029.
The stadium will be located next to King Abdulaziz Park.
Saudi Arabia stadium plans
In August last year, MEED reported that Saudi Arabia plans to build 11 new stadiums to host the Fifa World Cup in 2034.
Eight stadiums will be located in Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.
An additional 10 cities will host training bases. These are Al-Baha, Jazan, Taif, Medina, Alula, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah.
There are expected to be 134 training sites across the kingdom, including 61 existing facilities and 73 new training venues.
The kingdom was officially selected to host the 2034 Fifa World Cup through an online convention of Fifa member associations at the Fifa Congress on 11 December 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15166460/main.jpg

