Adnoc Gas awards $550m of Estidama contracts
15 July 2024
Register for MEED's 14-day trial access
Adnoc Gas has awarded contracts worth a total of $550m for two engineering, procurement and construction (EPC) packages of its sales gas pipeline network upgrade project, also known as Estidama.
The combined packages four and seven of the Estidama project were awarded to the UAE unit of Oman's Galfar Engineering & Contracting. The value of the contract is understood to be about $295m.
Abu Dhabi’s NMDC Energy has won package six. The value of the contract is $255m, NMDC Energy said in a filing with the Abu Dhabi Securities Exchange.
The main scope of work on Estidama Package 4+7 involves laying a new pipeline from the Al-Shuwaib pig launcher and pig receiver station in Abu Dhabi to the Sajaa gas facility in the emirate of Sharjah.
The scope also covers building a new gas pipeline between BVS-2/KP28.7 in Abu Dhabi and Dubai’s Margham gas facility, to meet increased demand from Adnoc Gas’ customer Dubai Supply Authority (Dusup).
The EPC scope of work on Estidama Package 6 entails the installation of a 52-inch, 74-kilometre (km) pipeline from Sweihan to Al-Shuwaib in Abu Dhabi, and building two block valve stations.
Adnoc Gas received technical and commercial bids for package six and the combined packages four and seven in 2022 and 2023, respectively.
Contractors submitted technical bids for package six in August 2022 and commercial bids by 21 November of that year.
Contractors submitted technical bids for the combined packages four and seven by 27 March last year, and commercial bids by 9 August.
in late May, MEED reported that Adnoc Gas had asked contractors to extend the validity of their bids for the two packages until 30 June. This was the latest in a series of bid validity extension requests made by the project operator.
Estidama scheme
Adnoc Gas, the natural gas producing and processing subsidiary of Abu Dhabi National Oil Company (Adnoc) has made significant progress with the Estidama project, which will enhance Adnoc’s sales gas pipeline network across the UAE. The objective of the scheme is to cater to rising demand for gas from industrial consumers, particularly in the Northern Emirates.
Through the Estidama scheme, Adnoc Gas aims to extend the existing 3,200km pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers across the UAE.
EPC works on the estimated $2bn-plus Estidama project have been divided into seven packages.
China Petroleum Pipeline Engineering performed the Estidama project’s front-end engineering and design works as part of a contract worth about $6m that Adnoc Gas Processing awarded to the Chinese state-owned firm in October 2020.
MEED reported in December 2021 that Abu Dhabi-based contractor Integrated Specialised General Contracting Company (Iscco) had won package one of the project, which is understood to have a contract value of $18m. Iscco later sub-contracted the detailed engineering works on package one to the Abu Dhabi branch of Sweden-headquartered consultancy Rejlers.
In July 2023, Adnoc Gas awarded the EPC contract for package two, estimated to be worth $720m, to UK-based Petrofac, and package three, valued at $630m, was won by a consortium of NMDC Energy and Lebanon’s CAT Group.
Separately, Adnoc Gas received technical bids from contractors for package five of the Estidama project on 24 June, MEED reported. Package five was previously part of package two but was later split off and tendered as a separate package by Adnoc Gas.
The scope of work on package five involves EPC works to upgrade the Habshan gas processing complex in Abu Dhabi.
MEED also recently reported that contractors were preparing technical bids for package eight of the Estidama scheme, which involves building a new pipeline that will transport gas as feedstock from the Habshan gas processing complex in Abu Dhabi to its upcoming liquefied natural gas terminal in Ruwais. The proposed pipeline will cover about 190km and will be built in two sections.
Exclusive from Meed
-
Syria seeks interest for $1.16bn Euphrates dam7 October 2026
-
Arada launches UAE construction arm with Roberts7 October 2026
-
Expo Riyadh sets October deadline for Saudi Arabia pavilion7 October 2026
-
Kuwait on track to hit oil production target7 October 2026
-
Roshn plans new flagship development in Riyadh7 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Syria seeks interest for $1.16bn Euphrates dam7 October 2026
Register for MEED’s 14-day trial access
Syria’s Ministry of Energy has invited expressions of interest (EoIs) for the development of the Halabiyeh-Zalabiyeh dam project on the Euphrates River.
The project has an indicative total cost of $1.16bn, according to the ministry’s EoI document. This includes $433.7m for the dam and hydropower plant and $729.6m for the pumped-storage power plant (PSP).
The scheme includes an 81MW hydroelectric power plant and a pumped-storage facility with a capacity of up to 1,200MW. The project will also include the construction of the dam and associated water-storage infrastructure.
The ministry seeks interest from qualified local and international companies, investors and other entities. Interested parties can participate in studies, design, financing, construction, and operation and maintenance of the project.
The ministry is considering several potential development structures, including build-own-operate-transfer, build-operate-transfer and public-private partnership models, as well as an engineering, procurement and construction (EPC) structure. It has said it is also open to proposals covering consultancy and financing services.
The EoI covers several stages, including pre-feasibility and feasibility studies, financing and bankability studies, detailed and executive design, EPC execution, and operation and maintenance.
The technical specifications envisage a 23-metre-high dam with a reservoir storage capacity of about 219 million cubic metres.
The hydropower plant will have three generating units, while the 1,200MW PSP will have 3.5 hours of storage capacity and four reversible units.
The deadline for submitting EoIs is 10 November, with enquiries accepted until 26 October.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20336025/main.jpg -
Arada launches UAE construction arm with Roberts7 October 2026
Register for MEED’s 14-day trial access
UAE developer Arada has integrated Australian contractor Roberts into the UAE market as part of its wider business strategy.
Arada acquired Roberts in 2025 after entering the Australian market. The tier-one contractor delivers projects in the healthcare, education, commercial, residential, hospitality, industrial, life sciences and defence sectors.
At the time of the acquisition, Arada said it planned to invest about $20m in Roberts. The investment is intended to give the developer greater control over the delivery of its Australian projects and support Roberts’ expansion into markets including the UAE.
Arada has said it could invest up to $100m in Roberts’ expansion into new sectors and markets. The company is targeting $1bn in annual revenue from Roberts by 2028.
Roberts has established a UAE office, with a head office team already in place. Arada said the contractor’s capabilities will support the delivery of its high-rise residential and social infrastructure projects.
The contractor’s first UAE project will be phase two of Arada Central Business District, a commercial development within Aljada in Sharjah. Arada is developing the AED35bn ($9.5bn) mixed-use project.
Roberts is also providing preconstruction services for several Arada projects in Dubai and Sharjah, ahead of starting site work.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20334926/main.jpg -
Expo Riyadh sets October deadline for Saudi Arabia pavilion7 October 2026

Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, has set a deadline of 25 October for bids for a contract to build the Saudi Arabia pavilion.
The tender was issued on 19 May, with an initial bid submission deadline of 26 August.
The pavilion is a major asset located within the KSA District on the eastern side of the Expo 2030 Riyadh masterplan, in the Loop of Nations district.
Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Last month, MEED reported that ERC had received contractor interest on 14 September for a contract to design and build a convention centre in the site’s Collaboration District.
ERC also tendered a contract to deliver the Souq areas within the Expo site, as MEED exclusively reported on 8 September.
These areas are divided into five precincts, with a total development area of about 300,000 square metres.
Also in September, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to construct a new metro station serving the Expo 2030 site.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle (EV) charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, as well as EV charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated north of the Saudi capital, the site will be near the future King Salman International airport and will provide direct access to Riyadh landmarks.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20334856/main.jpg -
Kuwait on track to hit oil production target7 October 2026
Kuwait is on track to meet its target of having 4 million barrels a day (b/d) of oil production capacity by 2035, according to Kuwait Petroleum Corporation (KPC) chief executive Shaikh Nawaf Al-Sabah.
Al-Sabah also said Kuwait is on course to increase non-associated gas production to 2 billion cubic feet a day by 2040.
His comments come amid an ongoing crisis in Kuwait’s oil and gas sector linked to the regional conflict that began when the US and Israel attacked Iran on 28 February.
The subsequent war has significantly disrupted shipping through the Strait of Hormuz, which is a crucial export route for Kuwaiti crude oil.
Kuwait is currently producing around 2 million b/d of oil, down from 2.6 million b/d before the US and Israel attack.
Speaking at a conference in London, Al-Sabah said: “We have the capacity to go back up to our current maximum sustainable capacity of 3 million b/d, if we have the export routes available, and this comes down to the ability to move oil through the Strait.”
KPC is investing $9bn-$10bn a year in capital expenditure to meet its oil and gas production goals, according to Al-Sabah.
He said: “We are doing this because we recognise that it is our hydrocarbons that will be most in demand a decade from now, and two decades from now – in fact, for the rest of our lifetimes.”
Project Seef
KPC is pushing ahead with the Al-Seef project, which focuses on developing three large offshore oil discoveries, Al-Sabah said.
The offshore fields are known as Nokhatha, Julaia and Jazza. The development was first announced in February this year, about two weeks before the US and Israel attack on Iran.
Al-Sabah said KPC is continuing with the project and believes the three fields collectively hold more than 3 billion barrels of recoverable oil.
He said: “We are asking international oil companies to partner with us to develop those resources under an operating services contract.
“So, we’re moving ahead according to the exact same schedule that we had put together even before the war began.”
Al-Sabah did not say which international oil companies KPC has approached to help develop the three offshore fields.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20315147/main.jpg -
Roshn plans new flagship development in Riyadh7 October 2026

Saudi developer Roshn Group plans to develop its next flagship scheme in north Riyadh, spanning an area of 13.7 square kilometres.
Roshn is looking to appoint lead design consultants to deliver detailed design, tender documentation and construction documents across the scheme, known as Plot 1.
The scope covers all infrastructure, utilities, public realm works and site adaptation of Roshn’s residential prototypes, split across two work packages.
Part 1 covers phases A, B and E, which collectively span about 7.8 million square metres (sq m) and will comprise 17,000 units.
Part 2 includes phases C and D, which will span about 4.7 million sq m and comprise more than 15,000 units.
The development is bordered by Expo 2030, King Abdulaziz Park, the Sports Innovation Lab Zone and the National Housing Company-developed Khozam district.
It will be a residential-led mixed-use development, also featuring retail, offices, hospitality, education and civic facilities.
Connectivity is a core plank of the masterplan, with two metro stations planned: one at the existing Line 4/proposed Line 7 interchange and another dedicated Line 7 stop. The scheme would also be served by the future Qiddiya high-speed rail and a possible King Salman Road diversion.
Plot 1 builds on Roshn’s existing footprint in the capital, notably the multi-phase Sedra community, as the developer expands beyond single-family housing into mixed-use districts under its Roshn 3.0 strategy.
Last month, Roshn Group announced that it had signed a preliminary agreement with Talaat Moustafa Group (TMG) Saudi, the local subsidiary of Egyptian developer Talaat Moustafa Group, to establish a joint venture to explore and develop a mixed-use project in Riyadh.
Under the agreement, TMG will hold a 51% stake in the joint company, while Roshn Group will hold 49%.
The agreement sets out a framework for the two groups to assess a potential partnership for the project’s phased development, which is planned as a residential-led, mixed-use community featuring retail, commercial, hospitality, leisure, healthcare and education facilities, alongside parks and public spaces.
Roshn Group and TMG Saudi plan to conduct detailed master planning and develop the project’s business case.
Preliminary studies indicate the development could include more than 55,000 residential units across all phases.
Roshn Group did not disclose the exact project location in its announcement.
As a Public Investment Fund-owned developer, Roshn remains a key vehicle for delivering Vision 2030’s housing programme, which targets 70% Saudi home ownership, alongside the kingdom’s wider quality-of-life and economic diversification agendas.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19786131/main.jpg