Still time to express interest in Lower Zakum

14 April 2023

Adnoc Offshore has given contractors additional time to express interest in the first phase of the Lower Zakum Long-Term Development Plan (LTDP-1) project.

The Lower Zakum LTDP-1 project is the larger of two projects that the offshore arm of Abu Dhabi National Oil Company has undertaken in line with its ambition to raise the oil and gas production potential of Abu Dhabi’s Lower Zakum offshore hydrocarbon concession over the long term.

Contractors participating in the prequalification process for the LTDP-1 project have until 27 April to express interest to Adnoc Offshore.

Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, sources previously told MEED, with contractors initially asked to respond by 10 April.

Lower Zakum oil production

The Lower Zakum hydrocarbons zone is 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60 per cent stake in the Lower Zakum asset. Foreign partners include an Indian consortium of companies led by ONGC Videsh (10 per cent), Japan’s Inpex Corporation (10 per cent), China National Petroleum Corporation (10 per cent), Italy’s Eni (5 per cent) and France’s TotalEnergies (5 per cent).

Adnoc Offshore and its partners in the Lower Zakum concession intend to sustain oil production from the asset at its current level of 450,000 barrels a day (b/d) until 2025, and then increase output to 470,000 b/d. This target will be achieved through the Lower Zakum early production scheme 2 (EPS 2) and proved developed producing (PDP) project.

The larger, longer-term objective is to raise Lower Zakum’s oil production to 520,000 b/d by 2027 and maintain that level until 2034. This goal is to be accomplished through the LTDP-1 project.

Raising oil and gas production levels from the Lower Zakum asset is vital for Adnoc to achieve its accelerated target of increasing oil production capacity to 5 million b/d by 2027, and raising gas output potential by 3 billion cubic feet a day (cf/d) by the end of this decade.

Lower Zakum EPS 2/PDP project

Front-end engineering and design (feed) is progressing on the Lower Zakum EPS 2/PDP project and is being performed by UK-headquartered Wood Group.

Adnoc Offshore, which, according to sources, awarded Wood the contract in November last year, expects feed work on the project to be completed by June.

The basic scope of work on the project involves the drilling of 17 additional producer and water injection wells on two new wellhead towers (WHTs) and the expansion of the gas compression capacity of the Zakum West Super Complex (ZWSC).

Integration of the Lower Zakum complexes with the onshore power grid at UZ AGI for electricity supply to the EPS 2/PDP project is also part of the scope.

Demolition of structures and as-built documentation and surveying are also included in the scope of work.

Adnoc Offshore solicited interest for the Lower Zakum EPS 2/PDP project EPC works in December last year. Contractors expressed interest in participating in the main contract tendering process in January, sources told MEED.

As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in June, with the award of contracts to take place in September.

Lower Zakum LTDP-1 project

Feed work is progressing on the Lower Zakum LTDP-1 project and is being performed by France’s Technip Energies.

According to sources, Adnoc Offshore awarded Technip Energies the contract in November last year. The operator expects feed work on the project, which began in December, to be completed by January 2024.

Adnoc Offshore issued the expression of interest for the Lower Zakum LTDP-1 EPC tendering exercise “earlier in March”, with contractors asked to respond by 10 April.

The detailed scope of work on the Lower Zakum LTDP-1 project is as follows:

Topside facilities on G Island – Civil works on process facilities and associated buildings on the artificial greenfield G Island.

Process facilities include well pads, inlet and export reception, production separation, export pumps, gas compression, dehydration and lift, produced water treatment and disposal, vapour recovery units, water injection units, riser tower, flare towers, accommodation, drilling of high-pressure flare knock out drum, power distribution facility, substations and local equipment rooms.

Offshore WHTs and pipelines – Seven WHTs will be installed: six in the east area, and one in the AGI area. Five of the WHTs are to be 16-slot, while the two others are to be 9-slot.

Das Island Terminal, ZCSC and ZWSC – The five existing oil processing trains at the Lower Zakum offshore development are to be decommissioned in 2028, with the new configuration of the main processing plant at Das Island to be:

  • Two existing trains with a processing/stabilisation capacity of 110,000 b/d each
  • Three new trains with a processing/stabilisation capacity of 150,000 b/d

The scope of work also covers the installation of other structures such as:

  • Three high-pressure separator trains
  • High-pressure scrubber
  • Three low-pressure separator trains
  • Low-pressure scrubber
  • Three atmospheric separator trains
  • Four crude charge pumps
  • Three crude charge heaters
  • Three cold strippers integrated with a degassing vessel
  • Six stripped crude product pumps
  • Common ejector with a spare for three cold strippers
  • Closed drain drum with transfer pump
  • Blow case vessel

As per the schedule, Adnoc Offshore expects to issue the project’s main EPC tender in December, with the award of contracts to take place in March next year.

The operator expects the Lower Zakum LTDP-1 project to be commissioned by the end of 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10758018/main1632.jpg
Indrajit Sen
Related Articles
  • Neom’s industrial pivot gathers pace

    1 October 2026

    Commentary
    Colin Foreman
    Editor

    Reprioritisation has been the buzzword in Saudi Arabia over the past two years and nowhere has that been more evident than at Neom. 

    The slowdown of development at The Line and the postponement of the 2029 Asian Winter Games at Trojena have dominated international headlines. As these projects scale back, Oxagon’s industrial and logistics base has become the $500bn gigaproject’s flagship development. There are tangible results: in August, the $8.5bn Neom Green Hydrogen project was commissioned, marking Neom’s most significant completion to date. 

    Construction activity elsewhere at Oxagon supports this trend. The AI data-centre campus being developed by Humain and DataVolt has broken ground on its first 100MW phase, backed by $5bn of investment and targeted for service in 2028. Neom has issued an expression of interest for a rail line linking the Port of Neom to Saudi Arabia Railways’ North-South network, tenders are out for an industrial wastewater plant and the upgrade of Highway 55, and the port itself is advancing towards a 2030 capacity target of 1.5 million TEUs. 

    The regional conflict that began in February has strengthened the business case by giving Oxagon’s Red Sea port added strategic weight as a second maritime gateway outside the Strait of Hormuz, at a time when Riyadh has committed to directing about 80% of the Public Investment Fund’s portfolio into domestic investment.

    These developments reflect a kingdom recalibrating rather than retreating

    Elsewhere, Saudi Arabia’s wider projects market is holding steady despite conflict-related disruption, with contract awards reaching $68bn so far this year. The regional power market is also diversifying, with Aljomaih, EDF and Kepco all more than tripling net capacity in recent years as Acwa retains its lead.

    These developments reflect a kingdom recalibrating rather than retreating, with priority given to projects capable of delivering commercial returns.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20178338/main.gif
    Colin Foreman
  • Contractor wins Dammam airport water infrastructure deal

    1 October 2026

    Saudi Arabia-based Alkhorayef Water & Power Technologies has won an SR80m ($21.3m) contract to rehabilitate water and wastewater infrastructure at King Fahd International airport in Dammam in the kingdom’s Eastern Province.

    The contract was awarded by Dammam Airports Company (DACO), and work is scheduled to be completed within 18 months, the firm said in a disclosure to the Saudi Exchange (Tadawul) on 29 September.

    The scope covers the design, construction, supply, installation, replacement, rehabilitation and integration of water and wastewater infrastructure.

    It includes pumps, storage tanks and reservoirs, reverse osmosis facilities, piping and tie-ins, as well as electrical and instrumentation works.

    The award comes as DACO advances a wider programme of investment at King Fahd International airport.

    DACO signed more than SR1.2bn ($320m) in agreements in June covering airport infrastructure, including a new power station, a medium-voltage distribution network and upgrades to the existing electrical grid. 

    In September, it also appointed WSP Middle East, the regional arm of Canadian engineering firm WSP, to develop the airport’s expansion under its masterplan.

    The expansion is intended to increase annual passenger capacity to more than 19.3 million by 2030, with a longer-term target of 32 million passengers. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20169118/main.jpg
    Mark Dowdall
  • Kuwait tenders LNG project

    1 October 2026

     

    State-owned Kuwait Integrated Petroleum Industries Company (Kipic) has tendered a project to develop a reliquefaction unit at the Al-Zour liquefied natural gas (LNG) import terminal.

    The project focuses on developing a boil-off gas (BOG) unit at the terminal, with bids due on 22 December.

    A meeting for contractors to discuss the project is scheduled for 18 October.

    The project scope includes engineering, procurement and construction works, along with pre-commissioning, commissioning and performance testing services.

    The list of prequalified companies is:

    • Fluor (US)
    • GS Engineering & Construction (South Korea)
    • Tecnicas Reunidas (Spain)
    • Larsen & Toubro (India)
    • Hyundai Engineering (South Korea)
    • CTCI Corporation (Taiwan)
    • Daewoo Engineering & Construction (South Korea)
    • Hyundai Engineering & Construction (South Korea)
    • Saipem (Italy)
    • Samsung Engineering (South Korea)
    • Sinopec Engineering (China)
    • JGC Holdings (Japan)
    • KBR (US)
    • China National Petroleum Corporation (China)
    • Technip (France)

    A BOG unit at an LNG facility captures, compresses and processes natural gas vapours that evaporate from cryogenic storage tanks, enabling the gas to be recycled back into the system rather than flared.

    In April, MEED revealed that contractors expected the project to be worth about $200m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20168625/main2005.jpg
    Wil Crisp
  • Riyadh approaches contractors for 2km tower

    1 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has reached out to contractors as part of a market-sounding exercise for the construction of the proposed 2-kilometre megatall tower project.

    MEED understands that a PIF subsidiary, the Tower District Real Estate Development Company, is undertaking the process.

    It is understood that several experienced international contractors, as well as some prominent local contractors, have been approached.

    The latest development follows PIF receiving offers in June last year from firms seeking a contract to provide project management consultancy (PMC) services for a new central business district (CBD) on the outskirts of Riyadh, which includes the proposed 2km tower.

    The PMC role covers both the tower and the surrounding district.

    Firms understood to have been invited to bid include US-based Aecom, Jacobs, Parsons and Turner, as well as the UK’s Mace.

    UK-based Foster & Partners is working as the architect for the tower after winning a design competition launched in late 2022.

    Record breaker

    The proposed tower would be more than double the height of the world’s tallest building, Dubai’s Burj Khalifa, which stands 828 metres tall. It is expected to be at least several hundred metres taller than the 1,000-metre-plus tower under construction in Jeddah.

    Contractors that have priced megatall towers in the region say a 2km-tall structure could cost about $5bn to construct, depending on the final design.

    The 2km tower and the surrounding CBD – known as Project Rise – sit within a larger masterplanned development to the north of Riyadh called the North Pole.


    MEED’s October 2026 report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20156496/main.jpg
    Yasir Iqbal
  • Singapore’s Temasek plans Middle East expansion

    1 October 2026

    Singapore’s Temasek plans to open offices in Riyadh and Abu Dhabi early next year as it targets investment and partnership opportunities in Saudi Arabia, the UAE, Qatar and the wider region.

    The state-owned investor had a net portfolio value of S$518bn ($401bn) as of 31 March 2026.

    It said the new offices will serve as regional hubs for Temasek and its portfolio companies, with some businesses expected to co-locate to work more closely with partners and pursue deals alongside the group. The openings are subject to regulatory approvals.

    Temasek said it will also step up engagement with institutions in Qatar, although it has not announced plans to establish an office there.

    The company said the expansion reflects its confidence in the region’s long-term fundamentals and the economic transformation being driven by national diversification programmes.

    It added that a presence in Riyadh and Abu Dhabi will also support investment activity beyond the region by improving access to opportunities across the wider Middle East, Central Asia and Africa.

    Several Temasek-owned or Temasek-backed companies are already active in the GCC, providing a platform for the group’s planned expansion.

    These include Singapore-headquartered engineering and consultancy firm Surbana Jurong, which has been involved in masterplanning and advisory work on major regional developments, alongside other portfolio companies with interests spanning infrastructure, logistics, financial services and technology.

    According to data from regional project tracker MEED Projects, Surbana Jurong is involved in several major projects in Saudi Arabia, including King Abdulaziz International airport (KAIA) in Jeddah, Jeddah Islamic Port, Red Sea Global’s Amaala masterplan, the Trojena dams scheme, Oxagon, King Salman International airport and Saudi Arabia Railway’s North-South Phosphate Railway 3.

    The firm has also worked on projects in the wider region, including the West Link project, Urban Loop, Musaffah Innovation District masterplan, Etihad Rail’s high-speed rail programme and Abu Dhabi airport’s Midfield Terminal.

    Surbana Jurong has also secured masterplanning contracts from Abu Dhabi’s Department of Municipalities & Transport and Abu Dhabi Ports.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20157511/main.jpg
    Yasir Iqbal