Acwa Power tightens grip on GCC water

26 January 2024

 

This report also includes: Mena water delivers exceptional growth


Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.

This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.

The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.

In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.


Source: MEED

IWP awards

The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).

The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.

Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.

Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.

The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.

At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.

The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.

In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.

GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.

Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund. 

Outlook

The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.

This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.

Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.

Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.

The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.

“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”

Tariff trend

Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.

“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.

“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.

“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.

The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.  

Future projects

SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.

In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months. 

Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.

In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.

In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.

Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.

MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.

Unstoppable

Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.

The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.

The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.

The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.

As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.

Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.

 Mena water delivers exceptional growth 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11438915/main.gif
Jennifer Aguinaldo
Related Articles
  • Facility E nears 25 July bid deadline

    19 July 2024

     

    The tender closing date of 25 July remains unchanged for the contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    At least one developer team is highly likely to submit a proposal to develop the gas-fired plant, sources close to the project tell MEED.

    Qatar state utility General Electricity & Water Corporation (Kahramaa) had previously extended the tender closing date for the contract in response to developers’ requests, as MEED reported.

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day (MIGD).

    “We hear that at least one consortium is being formed … others are preparing proposals, but appear unsure if they will ultimately submit them or not,” a source close to the project told MEED in November last year. 

    Kahramaa initially expected to receive bids on 14 December 2023.

    The contract to develop the Facility E IWPP was first tendered in 2019. The three teams that submitted bids for the contract in August 2020 were:   

    • Engie (France) / Mitsui (Japan) / Yonden (Shikoku Electric, Japan)
    • Sumitomo / Kansai Electric (Japan)
    • Marubeni / Kyushu Electric (Japan)

    The original plan was for the Facility E IWPP to have a power generation capacity of about 2,300MW and a desalination component of 100MIGD once fully operational.

    However, the project owner revised the power plant’s design capacity to 2,600MW and sought alternative prices from bidders. 

    Kahramaa eventually cancelled and reissued the tender in September 2023. The current tender entails a power generation plant with the same capacity as initially tendered in 2019.

    MEED understands that the new target commercial operation date for the Facility E IWPP project has been moved to 2027. 

    The state utility’s transaction advisory team includes UK-headquartered PwC and Clyde & Co as financial and legal advisers, respectively, led by Belgrade-headquartered Energoprojekt as technical adviser.

    Facility E is Qatar’s fifth IWPP scheme. Completed and operational IWPPs include three projects in Ras Laffan – known as Facilities A, B and C – and Facility D in Umm Al-Houl.

    Awarded in 2015 and completed in 2018, Facility D was developed by a Japanese consortium of Mitsubishi Corporation and Tokyo Electric Power Company (Tepco). South Korea's Samsung C&T was the engineering, procurement and construction contractor.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12177605/main.jpg
    Jennifer Aguinaldo
  • Masdar’s second bond issue raises $1bn

    19 July 2024

    Abu Dhabi Future Energy Company (Masdar) has raised $1bn through its second bond issuance under its Green Finance Framework.

    The announcement comes one year after the company’s first successful issuance of $750m on the International Securities Market of the London Stock Exchange.

    Masdar said the issuance comprises dual tranches of $500m each, with tenors of five and 10 years and coupons of 4.875% and 5.25%, respectively.

    It said there was strong appetite from regional and international investors, with the order book peaking at $4.6bn – 4.6 times oversubscribed.

    The company finalised the allocation with an average split of 70% to international investors and 30% to Middle East and North Africa investors.

    The $1bn proceeds from the issuance will be deployed to fund Masdar’s equity commitments on new greenfield projects, including several in developing economies, as the company pursues a target portfolio capacity of 100GW by 2030.

    In line with Masdar’s corporate credit ratings, the second issuance was rated AA- by Fitch and A2 by Moody’s.

    First Abu Dhabi Bank, Abu Dhabi Commercial Bank, Citibank, HSBC, Standard Chartered, Credit Agricole CIB, Natixis and MUFG were the lead managers and bookrunners on the issuance.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12177600/main.jpg
    Jennifer Aguinaldo
  • Firms seek to prequalify for 12 Saudi water projects

    18 July 2024

     

    Local and international utility developers have submitted their statements of qualifications (SOQs) for the contracts to develop and operate 12 water public-private partnership (PPP) projects in Saudi Arabia. 

    State-backed offtaker Saudi Water Partnership Company (SWPC) received separate responses from companies for five independent water projects (IWPs) and seven independent sewage treatment plant (ISTP) projects by 4 July, industry sources tell MEED.

    Local and regional companies, in addition to Japanese, Spanish, French and Chinese utility developers, are understood to have sought to prequalify to bid for the contracts, which are set to be tendered in 2024-26. 

    SWPC's shift from a single-project to a multiple-project prequalification process saves time and resources, according to one of the companies that submitted an SOQ.

    "This is particularly true for international developers, which need to allocate resources across various geographies," the source said.

    Another source said he believes SWPC will prequalify companies for lead and technical roles, among others, and then allow these companies to form teams at a later stage.  

    The client previously said that the programme "will provide the opportunity to local and international developers to obtain pre-qualification approval and receive the request for proposal documents for its future projects … without the need to submit a separate qualification application for each project".

    The five IWP schemes have a total combined capacity of 1.7 million cubic metres a day (cm/d). The seven ISTP projects have a total combined capacity of 700,000 cm/d.

    The kingdom's water sector has been undergoing a restructuring programme, with the capacity procurement process linked to the National Water Strategy being undertaken by three other clients: Saline Water Conversion Company, which has been renamed Saudi Water Authority; Water Transmission & Technologies Company; and the National Water Company.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12167522/main.gif
    Jennifer Aguinaldo
  • Nama appoints 2027-29 procurement advisers

    18 July 2024

     

    Oman's Nama Power & Water Procurement (Nama PWP) has appointed a transaction advisory team to support its 2027-29 power and water procurement strategy.

    According to an industry source, the team comprises UK-headquartered Deloitte as lead transaction and financial adviser, Canada-based engineering consultancy WSP as technical adviser, and US firm CMS as legal adviser.

    The scope of work won by the advisory team includes preparing the overall procurement strategy, extending existing contracts expiring between 2027 and 2029, and undertaking procurement for new-build plants.

    The contracts for three independent power projects (IPPs) in Oman with a total combined capacity of 3,518MW are expiring between 2028 and 2029, according to the state offtaker's latest Seven-Year Planning Statement, which covers the years 2023 to 2029.

    These gas-fired plants and their power generation capacities are:

    • Barka 3 IPP: 750MW (2028)
    • Sohar 3 IPP: 750MW (2028)
    • Sur IPP: 2,018MW (2029)

    Phoenix Power Company, the project company for the 2,018MW Sur IPP, comprises Japan's Marubeni Corporation and Jera and Qatar's Nebras Power. 

    Shinas Generating Company – owned by Saudi Arabia's Acwa Power, Japan's Mitsui and China's Didic – is the project company for Sohar 3.

    Al-Suwaidi Power is the project company for Barka 3. It comprises France's Engie, Japan's Shikoku Electric and the local Suhail Bahwan Group.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12166689/main1708.jpg
    Jennifer Aguinaldo
  • UAE keen to start next nuclear plant phase

    18 July 2024

    The UAE government could start the tendering process this year for the state's next nuclear power plant, located in Abu Dhabi, according to a Reuters report citing a senior UAE government official.

    According to the report, Hamad Alkaabi, the UAE's permanent representative to the Austria-based International Atomic Energy Agency, said: "The government is looking at this option. No final decision has been made in terms of the tender process but I can tell you that the government is actively exploring this option."

    The government has yet to budget for a second power plant or decide on the size or location of such a project, but Alkaabi said it is possible a tender could be issued this year, the report added.

    A significant increase in electricity use over the next decade, driven by population growth and an expanding industrial sector, underpins the plan to proceed with the next phase of the state's civilian nuclear power programme.

    Any new power plant would likely consist of two or four reactors, said Alkaabi, who also serves as the deputy chairman of the board of management of the UAE's Federal Authority for Nuclear Regulation.

    The next phase of the Barakah power plant, comprising reactors five to eight, has been in the planning stage since 2019, according to regional projects tracker MEED Projects.

    The UAE became the first Arab state to operate a nuclear power plant when the first of the four reactors at Abu Dhabi’s Barakah nuclear power plant became operational in 2021.

    Each of the four reactors at the Barakah nuclear power plant can produce 1,400MW of electricity.

    Three of the plant’s four reactors are operational. Emirates Nuclear Energy Corporation's operating and maintenance subsidiary, Nawah Energy Company, completed the loading of fuel assemblies into Unit 4 in December 2023. 

    Unit 4 will raise the Barakah plant’s total clean electricity generation capacity to 5,600MW, equivalent to 25% of the UAE’s electricity needs.

    Korea Power Corporation is the prime contractor for the $24.4bn first phase of the Barakah nuclear power plant.

    GlobalData expects nuclear power capacity in the Middle East and North Africa region to grow from zero in 2020 to an estimated 7.1GW by 2030, mainly thanks to Abu Dhabi’s Barakah nuclear energy plant and the first reactors of Egypt’s El-Dabaa nuclear power plant.

    The UAE is one of more than 20 countries that committed to tripling global nuclear energy capacity by 2050 at the UN climate change summit Cop28, which was held in Dubai in late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12165779/main1220.jpg
    Jennifer Aguinaldo