Acwa Power tightens grip on GCC water
26 January 2024
This report also includes: Mena water delivers exceptional growth
Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.
This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.
The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.
In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.
Source: MEED
IWP awards
The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).
The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.
Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.
Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.
The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.
At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.
The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.
In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.
GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.
Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund.
Outlook
The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.
This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.
Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.
Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.
The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.
“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”
Tariff trend
Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.
“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.
“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.
“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.
The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.
Future projects
SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.
In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months.
Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.
In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.
In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.
Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.
MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.
Unstoppable
Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.
The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.
The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.
The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.
As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.
Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.
Exclusive from Meed
-
Kuwait retenders Doha desalination package
30 April 2025
-
Kuwait tenders 900MW Subiya plant contract
30 April 2025
-
Read the May 2025 MEED Business Review
30 April 2025
-
Oman seeks firms for geothermal plant study
30 April 2025
-
Kurdistan plant to deploy GE Vernova technology
30 April 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Kuwait retenders Doha desalination package
30 April 2025
Kuwait’s Electricity, Water and Renewable Energy Ministry (MEWRE) has retendered a contract to design and build the planned second phase of a seawater reverse osmosis (SWRO) plant in Doha.
The Doha SWRO phase two project was expected to have a capacity of 60 million imperial gallons a day (MIGD) when it was first tendered.
The tender closing date for the retendered contract is 27 May.
The scope of work entails the supply, installation, operation and maintenance of phase 2 of the Doha SWRO plant, inclusive of alkalinisation equipment for produced water.
The ministry cancelled the tender for the contract in June last year.
Contractors submitted bids for the contract in September 2022. At the time, the MEW did not disclose the engineering, procurement and contracting firms that were invited to bid for the contract.
The MEW awarded South Korea’s Doosan Heavy Industries & Construction, now known as Doosan Enerbility, the $422m contract to build the 60MIGD Doha 1 SWRO in May 2016.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13784666/main.gif -
Kuwait tenders 900MW Subiya plant contract
30 April 2025
Kuwait’s Electricity, Water & Renewable Energy Ministry (MEWRE) has reissued the tender for a contract to build a combined-cycle gas turbine (CCGT) plant in Subiya.
The fourth phase of the Subiya power and water complex is expected to have a capacity of 900MW.
The ministry issued the tender on 27 April and expects to receive bids by 27 May.
The ministry announced earlier this month that the Kuwait Central Authority for Public Tenders has approved issuing the tender for the 36-month contract.
MEWRE first tendered the contract to design and build the 900MW Subiya phase 4 CCGT in 2022.
According to MEED Projects data, the bidders and their offers were:
- Al-Ghanim International General Trading & Contracting (local): $837.3m
- Al-Zain United General Trading & Contracting (local): $866.17m
MEED understands that Al-Ghanim International emerged as the preferred bidder after agreeing to a revised contract value of $662m.
The planned project, along with a scheme to convert an existing 250MW simple-cycle plant into a CCGT plant, aims to boost the generation capacity at the Subiya power complex by 1,150MW.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13784621/main5321.gif -
Read the May 2025 MEED Business Review
30 April 2025
Download / Subscribe / 14-day trial access Global stock markets suffered some of their worst days on record following US President Donald Trump's announcement of his 'Liberation Day' tariffs on 2 April. Although a 90-day pause was quickly announced for most trading partners, the 10% baseline import duty and levies on aluminium and industrial metals led to selloffs across regional indices. Oil prices also took a hit, as Brent crude dropped to under $60 a barrel for the first time since 2021.
The GCC is well positioned to survive the trade wars, however. Oil, energy and various petrochemicals products remain exempt from US tariffs, and with low regulatory barriers and the capacity to engage in manufacturing-intensive activities, the region's economies pride themselves on being trade-friendly. By building on the strong relations that regional leaders enjoy with the Trump administration, GCC states can hope to emerge from the assault relatively unscathed.
In the May edition of MEED Business Review, we take an in-depth look at how regional governments hope to avoid the worst of the hits from US tariffs, examine the impact of the tariff regime on Gulf stock markets and assess the additional damage that falling prices will cause for oil exporters across the Middle East and North Africa region.
MEED's latest issue also includes a 17-page market report on the UAE, which explores how solid fiscal and macroeconomic fundamentals will help the country ride out the global uncertainty caused by the imposition of US tariffs. UAE financial institutions remain on a strong growth heading, and an expected increase in oil production, continued chemicals sector growth, expansionary government spending on infrastructure and renewed investment in real estate will all help the UAE to weather the storm.
In addition, this month's issue features MEED's 2025 GCC Contractor Ranking, which reveals an increase in orders across the region in the past year. While the GCC’s most active contractor is Saudi Arabia’s Nesma & Partners, with $13.9bn of work at the execution stage, Beijing-based China State Construction Engineering Corporation has continued to grow strongly to secure second place this year, just $300m behind Nesma with $13.5bn.
This issue is also packed with analysis. We examine the steps that are being taken by Damascus to reassure regional partners and lay the groundwork for the reconstruction of war-torn Syria; look at what Saudi Arabia and Oman are doing to attract local and international miners; and learn how UAE sovereign wealth fund Mubadala is investing in a low-carbon future.
In the May issue, the team also speaks exclusively to Walter Simpson, the former managing director of CC Energy Development (CCED), about the oil producer’s plans for growth in Oman; and Iain McBride, head of commercial for gigaproject multi-asset developer Roshn Group, who lays out the procurement strategy that is enabling the company to navigate the challenges presented by Saudi Arabia’s construction boom.
We hope our valued subscribers enjoy the May 2025 issue of MEED Business Review.
Must-read sections in the May 2025 issue of MEED Business Review include:
> AGENDA:
> GCC shelters from the trade wars
> Gulf markets slide as US tariff shockwaves hit
> Lower oil prices raise Gulf’s fiscal pressure> CURRENT AFFAIRS:
> Syria makes progress towards reunificationINDUSTRY REPORT:
2025 GCC contractor ranking
> Contractors take on more work in 2025> MINERALS: Saudi Arabia and Oman open up their minerals potential
> INTERVIEWS:
> CCED seeks growth in Oman’s hydrocarbons sector
> A case study in procurement> LEADERSHIP: Rethinking investments for a lower-carbon future
> UAE MARKET REPORT:
> COMMENT: UAE is poised to weather the storm
> GOVERNMENT & ECONOMY: UAE looks to economic longevity
> BANKING: UAE banks dig in for new era
> UPSTREAM: Adnoc in cruise control with oil and gas targets
> DOWNSTREAM: Abu Dhabi chemicals sector sees relentless growth
> POWER: AI accelerates UAE power generation projects sector
> CONSTRUCTION: Dubai construction continues to lead region
> TRANSPORT: UAE accelerates its $60bn transport push
> DATABANK: UAE growth prospects head north> MEED COMMENTS:
> Opec+ shows defiance in the face of sliding oil prices
> Corruption may hinder Iraqi oil pipeline reopening
> Mall of the Emirates sets trends again with $1.4bn revamp
> Abu Dhabi infrastructure entity will help forge partnerships> GULF PROJECTS INDEX: Gulf projects index inches upwards
> MARCH 2025 CONTRACTS: Region records $70.3bn of deal signings in first quarter of 2025
> ECONOMIC DATA: Data drives regional projects
> OPINION: Trump’s new world order
> BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts
To see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/13755806/main.gif -
Oman seeks firms for geothermal plant study
30 April 2025
Oman’s Nama Power & Water Procurement Company (PWP) has invited companies to bid for a contract to provide technical and economic consultancy services for the sultanate’s first planned geothermal power plant project.
Known as the Hot Springs geothermal project, the site being considered for the project’s first phase is the area between Wilayat Fanja and Al-Ansab in Wilayat Bausher in Muscat.
PWP expects to receive bids from technical and financial consultancy firms by 22 May.
The selected bidder will conduct a feasibility assessment of geothermal energy potential within the specified sites.
The project supports Oman Vision 2040 and renewable energy targets as well as its net-zero committed target.
The tender proceedings are under way for several renewable energy projects in Oman.
In February, PWP received four bids for the contract to develop and operate the Ibri 3 solar independent power producer (IPP) project.
The 500MW scheme is Oman’s fourth utility-scale solar power plant project.
The bidding process is also under way for two wind IPPs in Oman.
The Jalan Bani Bu Ali wind IPP will cater to the Main Interconnection System (MIS), while the Dhofar 2 wind IPP will cater to the smaller Dhofar Power System (DPS).
The Jalan Bani Bu Ali wind IPP, located in South Sharqiyah Governorate, will have a capacity of 91MW-105MW and has a commercial operation target of Q1 2027.
Adjacent to the existing Dhofar Wind 1 IPP in Shaleem and Al-Hallaniyat Islands in Dhofar Governorate, the Dhofar 2 wind plant will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Photo credit: Pixabay, for illustrative purposes only
https://image.digitalinsightresearch.in/uploads/NewsArticle/13784148/main.jpg -
Kurdistan plant to deploy GE Vernova technology
30 April 2025
The 1,250 MW Bazyan power plant in the Iraqi Kurdistan region will deploy the US-based GE Vernova's first upgrade of its Advanced Gas Proven (AGP) technology that runs on its 9E.03 gas turbine fleet.
Known as AGP Xpand, the technology can increase their 9E.03 gas turbines' output by up to approximately 7%, with an approximately 1% incremental efficiency, GE Vernova said.
Taurus Energy, a portfolio company of Onex Group, operated the Bazyan power plant. Onex Group is a private energy group with a portfolio of power generation, utilities, energy trading, shipping and refining companies.
Qubad Talabani, deputy prime minister of the Kurdistan Regional Government, Kamal Mohammad Salih Khalil, Minister of Electricity in the Kurdistan Regional Government and Steven Bitner, consul general at the US Consulate General Erbil, along with other senior government officials and local business leaders witnessed the signing of the agreement held in Sulaymaniyah.
In addition to increasing the gas turbines' efficiency, the technology enables exhaust energy to increase by up to 2.6% to produce more steam or power, for combined heat and power (CHP) plants or combined cycle plants, like the Bazyan power plant.
Taurus is welcoming this technology, which could modernize its
The Bazyan power plant is powered by
Four GE Vernova 9E.03 and two 9F.04 gas turbines power the Basyan power plant, which uses natural gas as the primary fuel source and light fuel oil as backup fuel.
Taurus designed and engineered the power plant for baseload operations with an expected lifetime of 25-30 years.
The AGP XPAND upgrade is expected to enhance the current capacity and deliver additional, much-needed electricity to the Kurdistan Region as well as nearby cities and governorates such as Mosul and Salahaddin.
In addition, GE Vernova and Taurus Energy signed a new 17-year long-term service agreement covering four GE Vernova’s 9E units with the first 9E rotor life extension package in Iraq.
“By utilising Kurdistan Region’s natural gas resources and power generation capacity, we are laying the foundation to create an energy hub," said Saad Tayeb Hasan, Onex founder and chairman.
"Through projects like Bazyan, we can contribute to the efforts to meet local energy needs as well as transmit additional power to other parts of the country."
According to GE Vernova, it has added more than 19GW of power capacity in Iraq since 2011, built and energised more than 30 substations since 2015, and mobilised over $3bn in financing for energy projects since 2015.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13783196/main.jpg