Acwa Power tightens grip on GCC water

26 January 2024

 

This report also includes: Mena water delivers exceptional growth


Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.

This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.

The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.

In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.


Source: MEED

IWP awards

The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).

The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.

Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.

Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.

The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.

At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.

The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.

In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.

GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.

Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund. 

Outlook

The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.

This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.

Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.

Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.

The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.

“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”

Tariff trend

Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.

“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.

“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.

“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.

The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.  

Future projects

SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.

In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months. 

Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.

In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.

In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.

Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.

MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.

Unstoppable

Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.

The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.

The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.

The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.

As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.

Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.

 Mena water delivers exceptional growth 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11438915/main.gif
Jennifer Aguinaldo
Related Articles
  • Decarbonising the global energy grid

    3 May 2024

    As the effort to tackle the climate crisis continues, global demand for renewable energy has been increasing. Unfortunately, the windiest and sunniest parts of the world are not necessarily where the need for energy is highest. This is where transmission plays a big role, linking energy generation to energy use as a product of global interconnection, and diversifying production from renewable sources to create a steadier supply of clean power. 

    Transporting energy across vast distances is not easy though. From the regulatory complexities of navigating cross-border infrastructure projects to the high costs of financing and the need for long-term planning and advanced technical capabilities, the challenges involved in successfully deploying long-distance transmission projects are varied. Overcoming these challenges is not a single party affair, but requires close collaboration across government, industry and non-governmental organisations. 

    We conducted a study with nearly 600 industry experts from across the world who highlighted the pressing need for co-ordinated global action to rapidly develop grid infrastructure. Integrating renewable energy into existing grids was cited by participants as one of the most significant barriers to achieving net-zero objectives, alongside supply chain vulnerabilities and ability to access the required capital.

    Multiple challenges

    From a technical standpoint, there are multiple considerations when implementing cross-border interconnections. Regions can operate using different technical parameters, such as different voltages or frequencies. Even within the same country, interregional variations can create bottlenecks. Adopting regional or international grid codes could mitigate these issues.

    Further challenges emerge when we take trading into account. This is where regulation can act as an enabler, facilitating the flow of electricity between countries. The European Union’s efforts to co-ordinate the design of its member state’s energy markets enables an increasingly smooth transmission of energy across the continent. Alongside this, existing infrastructure is outdated, requiring significant upfront investment to upgrade. Clarity on regulatory requirements and more transparency around plans for grid buildout, derisk funding for capital-intensive mega projects.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy

    Positive benefits

    Despite these challenges, the upside must be stressed. Integrating power systems across borders has many positive societal benefits, decreasing costs and hence energy bills through economies of scale, increasing energy security and lowering the environmental impact of operations. On the latter more specifically, larger power systems are able to integrate higher shares of variable renewables. Globally, the sun is always shining and the wind blowing somewhere. 

    A common element, therefore, emerges: the need for increased cross-border co‑ordination. Whether it is bilateral, multi-lateral or unified, different models of inter-jurisdictional arrangements are needed for large-scale projects to support global energy interconnections. Our Xlinks project, which is using high-voltage direct current (HVDC) for transmission, is a standout example. 

    Such projects represent what is needed more in the world, the combination of infrastructure and renewable power across borders, bringing together the public and private sectors for energy security, supply and affordability in an environmentally friendly way. Transporting clean energy using HDVC cables is a crucial step in powering a net-zero and equitable future, and more of this is needed to aid the transition to lower-carbon and prosperous economies. 

    Political, technical and market hurdles can be overcome through collaboration and partnerships. Leveraging the collective expertise and resources of governments, regulators and the private sector can help ensure interconnections are developed quickly enough to support the energy transition. Grid buildout takes time. We have the resources required to meet ambitions, but stopping now is not viable. We must continue planning, building and maintaining large-scale infrastructure projects to meet the rising demand.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy. This was the message from Cop28 and the UAE Consensus: to help progress and secure a cleaner, brighter future for us all, we must break down barriers and come together. 

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11736994/main.gif
  • Libya allocates $1.2bn for upstream oil project

    3 May 2024

     

    Register for MEED's guest programme 

    Libya has allocated LD6bn ($1.23bn) to develop the Hamada NC-7 concession in its latest budget, which was approved by Libya’s eastern-based parliament on 30 April, according to industry sources.

    The field development project was previously estimated to be worth between $4bn and $5bn.

    The project aims to develop 2.7 trillion cubic feet of gas reserves in the NC-7 block of the Ghadames basin.

    A consortium led by Italy’s Eni and including France’s TotalEnergies and UAE-based Adnoc operates the block.

    Development of the field was included in the 2024 annual budget of LD90bn ($18.5bn), excluding an item for development projects, which the Benghazi-based government of Osama Hamad unanimously approved.

    Hamad came to power in March 2023 and is allied with the military commander Khalifa Haftar, who controls the east and large parts of the southern region of Libya.

    Progress on developing the Hamada NC-7 concession has been slow amid concerns among politicians about the involvement of foreign oil companies in key hydrocarbon assets.

    On 15 December 2023, the Tripoli-based Ministry of Oil & Gas issued a statement condemning the terms of the planned gas development contract between Libya’s state-owned National Oil Corporation (NOC) and the consortium led by Eni.

    In the statement, the Ministry of Oil & Gas described the deal as a “violation of Libyan legislation on oil contracts”.

    Earlier this year, NOC announced a plan to execute 45 greenfield and brownfield projects to try to boost the country’s oil production from 1.25 million barrels a day (b/d) to 2 million b/d.

    Farhat Bengdara, the chairman of NOC, said that the projects had a total estimated cost of $17bn-$18bn.

    Bengdara also confirmed plans to launch an oil and gas licensing round at the end of 2024 or early 2025.

    Libya is aiming to hit its 2 million b/d target within three years.

    Bengdara said that gas monetisation will remain a strategic focus as the country pushes to increase exports to Europe.

    Libya is only using 25% of the capacity of its Greenstream pipeline to Italy.

    The North African country also flares significant volumes of natural gas and has 12 projects under way that aim to reduce gas flaring to almost zero, according to Bengdara.

    In recent years, Libya has struggled to execute large projects amid significant political instability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11735260/main.gif
    Wil Crisp
  • GE Vernova invests in Xlinks

    2 May 2024

    US-headquartered GE Vernova has invested $10.2m in Xlinks First, the investment company established by UK-based startup Xlinks to deliver the $18bn Morocco-UK power project.

    This investment equates to a minority shareholding in the company, which is developing a project comprising wind and solar generation as well as battery storage, with a total combined capacity of 3,600MW, to be transmitted from Morocco to the UK.

    Xlinks said the investment will “further accelerate delivery and buildout of the project”.

    GE Vernova joins at least four other investors in the project.

    Other investors include Africa Finance Corporation, which invested $14.1m in April; Abu Dhabi National Energy Company (Taqa), $30.7m; the UK’s Octopus Energy, $6.23m; and France’s Total Energies, $25.4m.

    The planned electricity generation and battery storage facilities, located in south Morocco, will be connected exclusively to the UK via 4,000-kilometre high-voltage, direct current (HVDC) cables.

    In December last year, Xlinks signed a contract with Canada-headquartered WSP to provide technical advisory services for the project.

    WSP will support Xlinks with route optimisation, power systems and interface management for the plan to construct the project.

    The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre HVDC cables.

    The HVDC network is envisaged to run from the UK’s south coast, passing France, Spain and Portugal undersea and then onshore to a planned solar and wind energy project in Morocco.

    This renewable energy-sourced electricity amounts to nearly 8% of the UK’s current requirements, equivalent to powering 7 million homes by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11734222/main5830.jpg
    Jennifer Aguinaldo
  • Awards buoy Oman’s green hydrogen strategy

    2 May 2024

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    Oman has awarded two additional land blocks designed to develop green hydrogen projects.

    The latest land block concessions in Dhofar were awarded to two consortiums. One comprises a team of France's EDF Group and EDF Renewables, with partners Japanese Electric Power Development Company (J-Power) and the UK-headquartered Yamna Company.

    Another team comprises UK investment firm Actis and Australian metals firm Fortescue.

    This brings the total number of land blocks awarded through the public auction process spearheaded by Hydrogen Oman (Hydrom) to four, exclusive of the four legacy initiatives signed or agreed upon already.

    *Budgets are MEED estimates if not publicly disclosed. Sources: MEED, Hydrom

    A limited gas supply and network strongly incentivises Oman to build a green hydrogen-centric downstream sector that will provide feedstock to domestic industrial plants and generate derivatives for the local and export markets.

    Stakeholders have implemented a strategy, including setting up an infrastructure company catering to these projects. The target is to generate 1 to 1.5 million tonnes a year (t/y) of green hydrogen by 2030 and 7.5 to 8.5 million t/y by 2050.

    The blueprint envisages a complete green hydrogen ecosystem, from the production of renewable energy and its distribution to electrolysis plants and hydrogen derivatives conversion plants to storage and export terminals.

    Omani ports' existing relationships with European stakeholders and growing alliances with other countries could also help seal future offtake agreements for the planned facilities.

    As things stand, the consortiums that won the land auctions and the legacy initiative partners provide much gravitas to Oman's green hydrogen programme. They comprise energy old guards such as BP and Shell that are keen to decarbonise, private companies aiming to balance their investment portfolios with clean energy investments, and offtakers or trading companies that are grappling with net-zero targets.

    Yet the most obvious question remains. Given the eye-popping foreign direct investments these complex projects entail, not all are likely to achieve a final investment decision within three years. This seems to be the window required for the projects to start production before 2030.

    But like any emerging industry, the risks can only be properly assessed and mitigated as the first projects move toward the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11733331/main.gif
    Jennifer Aguinaldo
  • Operationalise loss and damage fund says Al Jaber

    2 May 2024

    Steps must be taken to ensure a fully functioning Loss and Damage Fund, following an agreement at Cop28 to operationalise the fund, according to Cop28 President Sultan Al Jaber.

    “While delivering an agreement to operationalise the Fund at Cop28 was a huge breakthrough for climate progress more needs to be done,” Al Jaber said during the first board meeting of the fund on 30 April.

    The Loss and Damage Fund, which was first proposed in the 1990s, aims to help developing countries cope with the impact of extreme global warming events such as droughts and floods.

    Al Jaber cited the need to build a fully functioning fund, which will be endorsed at Cop29 in Baku, which will be “disbursing funds soon after and a Fund that delivers lasting, positive, socio-economic impact for decades to come."

    "While it took over three decades to establish this Fund, climate change has not stood still. Every region of the world is now vulnerable…the impacts of climate change are a clear and present danger to lives and livelihoods everywhere."

    Al Jaber’s message resonates closer home given the recent storms hitting the UAE, which brought some emirates to a standstill in mid-April.

    Heavy rainfall inundated Dubai and the Northern Emirates on 16 April, causing flooding and significant property and infrastructure damages.

    A total of $792m has been pledged for loss and damage funding arrangements – of which $662m has been pledged to the Fund to date – including a $100m contribution each from the UAE and Germany and $75m from the UK.   

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11732746/main.jpg
    Jennifer Aguinaldo