Acwa Power tightens grip on GCC water

26 January 2024

 

This report also includes: Mena water delivers exceptional growth


Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.

This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.

The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.

In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.


Source: MEED

IWP awards

The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).

The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.

Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.

Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.

The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.

At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.

The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.

In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.

GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.

Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund. 

Outlook

The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.

This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.

Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.

Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.

The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.

“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”

Tariff trend

Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.

“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.

“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.

“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.

The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.  

Future projects

SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.

In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months. 

Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.

In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.

In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.

Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.

MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.

Unstoppable

Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.

The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.

The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.

The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.

As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.

Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.

 Mena water delivers exceptional growth 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11438915/main.gif
Jennifer Aguinaldo
Related Articles
  • Firms prepare bids for NWC sewage treatment package 14

    4 September 2026

     

    At least three contractors are preparing to make offers for package 14 of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, according to sources.

    Known as Eastern A Cluster (LTOM14), the package was tendered by the state-owned National Water Company (NWC) in April, with a bid submission deadline of 30 September.

    The contract covers the upgrade of six existing sewage treatment plants (STPs), with a capacity expansion of 30,000 cubic metres a day (cm/d) at the Al-Jarodia STP.

    This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.

    According to sources, the firms preparing to submit bids include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • Miahona (Saudi Arabia)

    The latest phase follows the formal signing of a $347m contract between NWC and a Saudi-Chinese consortium for Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) on 2 September.

    The same consortium led by United Water (China) is not planning to bid for LTOM14 and is expected to formally sign a contract for LTOM11 in the coming months, a source said.

    In April, MEED exclusively reported that the group had won the contract for package 11, which will have a combined capacity of about 440,000 cm/d.

    It is also understood that Beijing Enterprises, a bidder for North Western B Cluster (LTOM12), is not preparing to bid for package 14.

    In the meantime, the contract for LTOM12 is moving towards award, with bids currently under evaluation.

    The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d. As previously reported, NWC opened financial bids for the project in April.

    Future phases

    In total, the LTOM programme comprises 19 packages split into two phases. In May 2024, NWC announced it had awarded $2.5bn-worth of contracts in the first phase. Phase two of the programme includes 10 packages covering 117 treatment plants.

    In April, MEED exclusively reported that NWC had held several discussions regarding changes in scope details and potential expansions to upcoming projects. This involved “grouping some upcoming projects”.

    The request for proposals for LTOM13 was subsequently put on hold and it is now understood that this tender has likely been merged with other packages in the programme.

    According to a source, Eastern B Cluster (LTOM15) has also been cancelled and has likely been merged. LTOM15 had comprised two STPs with a total capacity of 152,000 cm/d.

    The next contract to be tendered will be Central Cluster (LTOM16), potentially in November, a source added.

    Under the original scope, LTOM16 covers the construction of 14 STPs with a total capacity of 153,000 cm/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19358188/main.jpg
    Mark Dowdall
  • Egyptian contractor wins Abu Dhabi Ramhan Island deal

    4 September 2026

    Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.

    The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.

    The development comprises two residential towers offering 187 residential units.

    The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.

    The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Mohamed Alabbar launched the Ramhan Island development in May 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg
    Yasir Iqbal
  • Dubai sets deadline for Jebel Ali waste-to-energy PPP

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.

    The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.

    The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.

    The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.

    Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.

    It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.

    That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.

    The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.

    Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.

    In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.

    Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.

    The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation. 

    The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg
    Mark Dowdall
  • Egypt to invest $4.5bn in refinery upgrades

    4 September 2026

    Egypt is planning to invest $4.5bn in refinery upgrades, according to the country’s Minister of Petroleum and Mineral Resources, Karim Badawi.

    Egyptian refineries are operating at 80% of capacity compared with 66% two years ago, according to Badawi, who wants further increases in utilisation of existing facilities.

    “We aim to invest around $4.5bn to develop existing refineries and build new units to reduce imports and achieve self-sufficiency in refined products,” he said in a statement.

    In May, Egypt said that it had increased its fuel import budget by almost 40% for the 2026-27 fiscal year amid higher global prices driven by the Iran war, which started when the US and Israel launched an attack on Iran on 28 February.

    Brent crude prices are up about a third since the conflict started, trading at more than $90 a barrel for most of this month so far.

    Badawi said a decline in Egypt’s oil and gas production between 2021 and 2024 occurred because foreign companies were reluctant to invest in the country’s energy sector due to unpaid government debts.

    He said: “We have settled all the debt, which reached $6.1bn in June 2024. As a result, hydrocarbon exploration and production activity grew by nearly 20% this year.

    “We are now moving in the right direction to increase oil and gas output gradually.”

    Despite the ongoing push to develop projects in the country’s oil and gas sector, several key projects have seen significant delays in recent years.

    These include a $2bn hydrocracking complex package that forms part of the wider Assiut oil refinery upgrade project.

    Earlier this month, MEED revealed that mechanical completion of the hydrocracking package is now unlikely to be reached until early next year due to complications in the final stages of construction.

    The hydrocracking complex package has experienced extensive delays over several years.

    In April this year, Badawi called for work to accelerate on the Assiut oil refinery upgrade project, saying it is important for reducing the country’s spending on imported refined products.

    At the time, the oil ministry said the project was 88% complete, with trial operations planned by the end of the year.

    Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation, is the project operator.

    France’s Technip Energies is the main contractor, performing engineering, procurement and construction work on the Assiut hydrocracking complex under a $2bn contract awarded by ASORC in February 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19353521/main.jpg
    Wil Crisp
  • North Field West platform bidders get extra time

    4 September 2026

     

    QatarEnergy has granted contractors additional time to prepare bids for a key tender for the engineering, procurement, construction and installation (EPCI) of large platforms for the giant North Field gas field in Qatari waters.

    The tender, issued earlier this year, forms part of the wider North Field West (NFW) project, the third and last phase of the state enterprise’s North Field liquefied natural gas (LNG) expansion programme.

    The core scope comprises the EPCI of four production deck modules (PDMs) and associated structures. The new PDMs will increase gas production from North Field reservoirs and provide additional gas feedstock for the NFW LNG development.

    QatarEnergy has set 15 September as the deadline for technical bid submissions, while commercial bids are due on 10 November, according to sources.

    The previous deadlines for submission of technical and commercial bids were 30 August and 25 October, respectively, MEED previously reported.

    The following contractors, among others, are understood to be bidding:

    • China Offshore Oil Engineering Company (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem (Italy)

    Before issuing the PDM tender, QatarEnergy awarded McDermott a contract for the EPCI of four offshore jackets that will also support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.

    North Field LNG expansion

    QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three giant projects are progressing.

    QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.

    QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.

    QatarEnergy took the final investment decision on NFW this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting (GAC) in February.

    Chiyoda carried out the front-end engineering and design (feed) work for the NFW LNG project.

    The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.

    In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and LPG.

    With all three phases now under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers over the long term.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19352006/main.jpg
    Indrajit Sen