Acwa Power tightens grip on GCC water

26 January 2024

 

This report also includes: Mena water delivers exceptional growth


Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.

This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.

The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.

In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.


Source: MEED

IWP awards

The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).

The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.

Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.

Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.

The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.

At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.

The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.

In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.

GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.

Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund. 

Outlook

The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.

This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.

Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.

Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.

The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.

“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”

Tariff trend

Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.

“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.

“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.

“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.

The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.  

Future projects

SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.

In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months. 

Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.

In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.

In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.

Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.

MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.

Unstoppable

Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.

The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.

The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.

The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.

As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.

Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.

 Mena water delivers exceptional growth 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11438915/main.gif
Jennifer Aguinaldo
Related Articles
  • Partners launch feed-to-EPC contest for Duqm petchems project

    27 April 2026

     

    Register for MEED’s 14-day trial access 

    Omani state energy conglomerate OQ Group and Kuwait Petroleum International (KPI), the overseas subsidiary of Kuwait Petroleum Corporation, have initiated a feed-to-EPC competition among contractors to develop a major petrochemicals complex at Duqm.

    Under a feed-to-EPC model, the project operator selects contractors to carry out front-end engineering and design (feed). It then awards the engineering, procurement and construction (EPC) contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.

    OQ8, the 50:50 joint venture of OQ and KPI, is understood to have issued the tender for the Duqm petrochemicals project’s feed-to-EPC competition in mid-March, with a deadline of 6 May for contractors to submit proposals, sources told MEED.

    Several local and international contractors based in Oman are believed to be participating in the competition, according to sources.

    OQ Group CEO Ashraf Bin Hamad Al-Maamari and KPI’s CEO Shafi Bin Taleb Al-Ajmi signed an agreement on 3 February, during the Kuwait Oil & Gas Show and Conference, to develop a major petrochemicals-producing complex in Oman’s Duqm. The parties did not disclose details at the time.

    ALSO READ: Duqm petrochemicals revival provides fillip to Gulf projects market

    The agreement represented a significant step forward in Oman and Kuwait’s long-held plans to jointly develop a petrochemicals complex next to the existing Duqm refinery, which will benefit from favourable feedstock access and strong cost competitiveness.

    The planned facility will also benefit from  in Al-Wusta governorate, along Oman’s Arabian Sea coastline.

    OQ8 had struggled to make meaningful progress on the Duqm petrochemicals project since the plan was conceived as early as 2018, for a variety of reasons.

    The original plan for the Duqm petrochemicals facility, estimated at $7bn, centred on a mixed-feed steam cracker with a capacity to produce 1.6 million tonnes a year (t/y) of ethylene. The project also included a polypropylene (PP) plant with a capacity of 280,000 t/y and a high-density polyethylene (HDPE) plant with a capacity of 480,000 t/y.

    The complex was also expected to include an aromatics plant, as well as storage facilities for naphtha and liquefied petroleum gas (LPG).

    The project’s prospects were temporarily boosted when Saudi Basic Industries Corporation (Sabic) expressed interest in investing by signing a non-binding memorandum of understanding with OQ in December 2021.

    Reuters reported in December that Sabic was withdrawing from the project, leaving OQ to look for other partners. The new agreement between OQ and KPI is understood to have followed the Saudi chemical giant’s departure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577785/main.jpg
    Indrajit Sen
  • Nakheel awards $953m Palm Jebel Ali villas deal

    27 April 2026

    Dubai-based real estate developer Nakheel, now part of Dubai Holding, has awarded two contracts worth AED3.5bn ($953m) to local firms for the construction of 544 villas at its Palm Jebel Ali project in Dubai.

    The first contract was awarded to Ginco General Contracting for the construction of 354 villas across fronds A to D.

    The second contract was awarded to United Engineering Construction Company (Unec) for the construction of 190 villas on fronds E and F.

    Construction is expected to begin in Q2 this year, with completion scheduled for 2028.

    Earlier phases

    In October 2024, Nakheel awarded three contracts worth AED5bn ($1.3bn) for the construction of 723 villas on fronds K to P. The contracts went to Ginco, Unec and the local Shapoorji Pallonji.

    Under these awards, Ginco is delivering 197 villas on fronds O and P, Shapoorji Pallonji is constructing 275 villas on fronds M and N, and Unec is building 251 villas on fronds K and L. Villa construction is expected to be completed by 2026.

    Infrastructure works

    This was followed by Nakheel awarding infrastructure contracts worth over AED750m ($204m) to local firm Dutco Construction for works on Palm Jebel Ali.

    The infrastructure work includes utility connections, excavation, backfilling, and the construction of roads and pavements across fronds A to G. It also covers 11-kilovolt power distribution and telecommunications-related utility works.

    Reclamation contract

    In August 2024, Nakheel awarded an AED810m ($220m) contract to complete the reclamation works for the project.

    The contract was awarded to Belgium’s Jan De Nul. Its scope includes dredging, land reclamation, beach profiling and sand placement to support the construction of villas across all fronds.

    Masterplan details

    Nakheel released details of the new masterplan for Palm Jebel Ali in June 2023. Twice the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature more than 80 hotels and resorts, along with a range of entertainment and leisure facilities.

    It includes seven connected islands that will cater to approximately 35,000 families. The development also emphasises sustainability, with 30% of public facilities expected to be powered by renewable energy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577782/main.jpg
    Yasir Iqbal
  • Iraq’s first LNG terminal to be completed in June

    27 April 2026

    Iraq’s first liquefied natural gas (LNG) import terminal is expected to be completed in early June, according to the country’s Ministry of Electricity.

    The terminal, which has an estimated investment value of $450m, is being developed at the Port of Khor Al-Zubair and will have a capacity of 750 million standard cubic feet a day (cf/d).

    Ministry spokesperson Ahmed Mousa told the Iraqi News Agency that “work is proceeding at an accelerated pace to complete the LNG platform”, noting that “the government has set 1 June as the date for finishing the project”.

    In October last year, US-based Excelerate Energy signed a commercial agreement with a subsidiary of Iraq’s Ministry of Electricity to develop the floating LNG terminal.

    The contract was signed at the office of Iraq’s Prime Minister Mohammed Shia Al-Sudani during a ceremony attended by senior officials from both countries, including the US deputy secretary of energy James Danly.

    The contract included a five-year agreement for regasification services and LNG supply with extension options, featuring a minimum contracted offtake of 250 million cf/d.

    Ahmed Mousa said that “under the contract, the company is responsible for completing the facility as well as securing the agreed gas quantities from any source, in line with the specified terms”.

    He added: “Work is continuing according to the planned timelines to complete the project on schedule, as part of the Ministry of Electricity’s plans to keep pace with peak summer loads.”

    Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.

    Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.

    Recently, Iraq’s oil and gas sector has been disrupted by fallout from the US and Israel’s attack on Iran on 28 February and the subsequent regional conflict.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% amid problems shipping crude through the Strait of Hormuz.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577746/main.jpg
    Wil Crisp
  • Iraqi LNG import terminal raises questions about energy strategy

    27 April 2026

    Commentary
    Wil Crisp
    Oil & gas reporter

    Iraq’s first LNG import terminal is set to come online in early June, at a time when global LNG prices are likely to remain close to their highest levels in more than three years.

    The disruption to global oil and gas exports in the wake of the US and Israel’s attack on Iran on 28 February led to LNG prices soaring, with natural gas prices in Asia and Europe rising to their highest levels since January 2023 during March.

    So far, there has been little progress towards a diplomatic or military solution to reopen the Strait of Hormuz, and most analysts do not forecast significant price declines in the near term.

    On 24 April, the International Energy Agency (IEA) said that the combined effect of short-term supply losses and slower capacity growth could result in a cumulative loss of around 120 billion cubic metres of LNG supply between 2026 and 2030.

    While the IEA expects new liquefaction projects in other regions to offset these losses over time, it still believes the crisis will lead to prolonged tight market conditions through 2026 and 2027.

    This means that Iraq will likely have to pay elevated prices for imported LNG for some time to come – if it can receive shipments at all.

    The port of Khor Al-Zubair is located in the Arabian Gulf, and LNG shipments from the US or Australia would need to pass through the Strait of Hormuz before reaching the terminal.

    This will only be possible if a solution is found to the ongoing blockade of the shipping route.

    Investment debate

    Iraq’s project to develop a floating LNG terminal is estimated to cost $450m, and many in Iraq may question whether this was the best use of these funds.

    While it may have been difficult for Iraqi policymakers to foresee the attack by the US and Israel on Iran and its impact on LNG markets, Iraq had several strong options to enhance domestic energy security rather than turning to LNG imports.

    The most obvious of these was investing in infrastructure to enable it to utilise its domestic gas reserves.

    According to the World Bank’s 2025 Global Gas Flaring Tracker Report, in 2024, Iraq burned off more unused gas than any other country, except Russia and Iran, which ranked first and second, respectively.

    That year, an estimated total of more than 18 billion cubic metres of natural gas was flared in Iraq due to a lack of infrastructure to properly capture and process it.

    It is highly likely that projects to gather and process this gas would have been more reliable and cost-effective than investing in a new floating LNG terminal, which increases the country’s exposure to global LNG price fluctuations and shipping disruptions.

    Other options could have included developing domestic gas fields or investing in solar and battery storage projects, which have become increasingly affordable in recent years.

    The cost of solar panels has fallen by more than 95% over the past decade.

    Power shortfall

    As things stand, Iraq is likely to face severe electricity shortages this summer.

    On 21 April, Iraq’s Ministry of Electricity said it plans to produce 30,000MW this summer, well short of the predicted peak demand of around 55,000MW.

    Ahmed Musa, a spokesperson for the Electricity Ministry, told the state-run Iraqi News Agency that the shortfall will result in planned outages across the country.

    He also said that even meeting the 30,000MW target is contingent on sufficient gas supplies.

    If Iraq experiences the same level of power outages as last year – or worse – many are likely to view the $450m spent on an LNG import terminal as a waste of money and an expensive symbol of poor planning.

    Power cuts this summer could stoke unrest at a time that is already politically precarious due to the ongoing regional conflict.

    In recent years, electricity shortages have repeatedly fuelled protests in Iraq during the summer months, particularly in Basra, where blackouts and poor public services have driven people to take to the streets.

    If the Strait of Hormuz does not reopen soon, Iraq’s economic crisis will deepen, and electricity shortages are likely to further undermine the country’s stability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577743/main.jpg
    Wil Crisp
  • Kuwait approves Doha desalination plant award

    27 April 2026

    Kuwait’s Central Agency for Public Tenders has approved the recommendation of the Ministry of Electricity & Water to award a KD114.28m ($371.5m) contract to supply, install, operate and maintain the second phase of the Doha seawater reverse osmosis (SWRO) desalination plant.

    A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag has been selected for the project, with the award understood to be pending final approval from the Audit Bureau.

    The project will deliver a production capacity of about 60 million imperial gallons a day (MIGD) and will include the desalination plant with full reverse osmosis trains, pre- and post-treatment systems, recarbonation equipment, booster pumps, and safety and filtration systems.

    The total project duration is 96 months. The Doha SWRO desalination plant is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.

    MEED previously reported that the Heisco/Wabag joint venture submitted the lowest bid. Bidders and prices included:

    • Heavy Engineering Industries & Shipbuilding / Wabag: $373.2m
    • Cox Water (Spain): $538.1m
    • Orascom Construction (Egypt): $568.4m

    In April 2025, MEED reported that Kuwait had retendered the contract for the facility after the ministry cancelled the initial tender in June 2024.

    The Ministry of Electricity & Water awarded South Korea’s Doosan Heavy Industries & Construction – now known as Doosan Enerbility – a $422m contract in May 2016 to build the 60 MIGD Doha 1 SWRO plant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577722/main.jpg
    Mark Dowdall