Acwa Power tightens grip on GCC water
26 January 2024

This report also includes: Mena water delivers exceptional growth
Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.
This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.
The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.
In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.

Source: MEED
IWP awards
The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).
The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.
Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.
Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.
The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.
At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.
The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.
In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.
GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.
Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund.
Outlook
The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.
This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.
Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.
Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.
The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.
“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”
Tariff trend
Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.
“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.
“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.
“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.
The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.
Future projects
SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.
In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months.
Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.
In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.
In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.
Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.
MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.
Unstoppable
Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.
The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.
The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.
The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.
As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.
Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.
Exclusive from Meed
-
Aramco-backed firm tenders logistics hub expansion9 November 2026
-
Prequalification begins for multibillion-dollar Dubai road9 November 2026
-
Contractor begins early works on Ardara’s AlWadi project9 November 2026
-
Syria in talks for refinery project worth $6bn-8bn9 November 2026
-
Three Libya oil and gas projects see developments9 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Aramco-backed firm tenders logistics hub expansion9 November 2026

Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, has set a 15 November deadline for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.
The logistics hub will add over 124,000 square metres (sq m) at Spark.
Al-Khobar-based engineering firm House of Consulting Office is the project consultant.
The tender for the expansion works comes shortly after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.
The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.
Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.
The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21267403/main.gif -
Prequalification begins for multibillion-dollar Dubai road9 November 2026

Dubai’s Roads & Transport Authority (RTA) has begun prequalifying contractors for a design-and-build contract for a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.
Contractors have until 30 November to submit their prequalification statements.
The latest development follows contractors’ expressions of interest for the project on 10 October, as MEED reported.
The project’s scope covers about 30 kilometres (km) of works. These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.
The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.
Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.
The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through traffic while existing at-grade lanes served local access.
The plans ultimately became standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.
The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.
Planning for growth
Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.
In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan.
In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.
The policy aims to ensure residents can meet 80% of their daily needs within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21266194/main.gif -
Contractor begins early works on Ardara’s AlWadi project9 November 2026
Saudi Arabia’s Shibh Al-Jazira Contracting Company (Sajco) has started early construction works on the first cluster of its AlWadi mixed-use development in Abha.
Ardara, backed by the sovereign wealth vehicle the Public Investment Fund (PIF), is developing the AlWadi project.
Sajco will carry out sewerage works, while local engineering firm Dar Al-Riyadh will provide project management and supervision services for the infrastructure works.
The AlWadi project will cover 2.5 million square metres (sq m) and will be developed around architectural styles informed by the heritage and character of the Aseer region.
The masterplan has a planned gross floor area of about 2.02 million sq m. It includes 7,306 apartments, 90 villas and townhouses, and 2,783 hotel keys.
The scheme will also provide 154,082 sq m of retail and food and beverage space, 64,161 sq m of offices, and 59,075 sq m of leisure and entertainment facilities.
The wider development will comprise five districts and include 16 kilometres of waterfront assets and 17km of walking, cycling and sports tracks.
US-based Parsons is the infrastructure designer, while Miami-based OBMI is providing architectural and public realm design services.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21265927/main.jpg -
Syria in talks for refinery project worth $6bn-8bn9 November 2026
Register for MEED’s 14-day trial access
Discussions are under way with international companies to develop a refinery in Syria’s Furqlus area, worth $6bn-8bn, according to a senior official at state-owned Syrian Petroleum Company (SPC).
The project will be “very large” and, after completion, will replace Syria’s Homs refinery, according to SPC’s deputy executive president for refining affairs, Tariq Shalash Al-Abdullah, who spoke to Syria’s state-owned daily newspaper Al-Thawra Al-Souriya.
He said the international companies currently involved in talks about the planned refinery project specialise in design work, engineering and technical studies.
He also stated that, for large-scale projects of this type, consortiums are typically formed from a group of companies with complementary interests in study, manufacturing, financing, implementation and operation.
In June, SPC published an invitation for companies to submit proposals to finance, build and operate the refinery under a build-operate-transfer agreement.
The tender document published by SPC said the refinery would have the capacity to process 210,000 barrels a day (b/d).
It also said the facility would be developed with the option to add an “ancillary petrochemical complex”.
Al-Abdullah said the refinery’s total investment value would depend on the equipment's country of origin, adding that the equipment could potentially be procured from the US, Europe or China.
Another factor that could alter the project’s value is the technology licences selected for the project, according to Al-Abdullah.
The refinery project is expected to take around four years to develop from the date of signing the contract and completing other related preparatory activities.
The project will be developed on a site that covers 400 hectares, according to the document that was published by SPC in June.
SPC invited companies to submit three separate documents relating to their proposals.
These were:
- A package outlining the company’s qualifications and legal documents
- A technical proposal
- A financial and investment proposal
According to the tender document, the scope of the refinery project includes developing:
- Three independent atmospheric distillation units, each with a capacity of 70,000 b/d
- Two vacuum distillation units
- Hydrotreating units
- Sulphur recovery units
- A base oil unit
- Power and steam generation facilities
- A grid interconnection substation
- A safe shutdown system
- An environmental water treatment system
- A gas recovery system
- A unit to produce nitrogen and oxygen
- A fire water network
- Maintenance and repair workshops
- Tank farm and storage facilities
Under the plans outlined in SPC’s tender document, at least 85% of the refinery’s products should meet Euro-5 specifications.
SPC is also seeking a “plan for the establishment and integration of an advanced petrochemical complex”, which would be connected to the refinery, according to the document.
Because of this, it said the refinery design must allow diversion of some light and heavy naphtha and liquid petroleum gas (LPG) to be used as feedstock for the future petrochemical complex.
The petrochemical complex is planned to use 20% to 40% of the naphtha and LPG.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21263584/main.png -
Three Libya oil and gas projects see developments9 November 2026

Three key oil and gas projects in Libya have seen developments amid an uptick in activity in the North African country’s hydrocarbon sector.
The contract scopes include seismic work, subsea pipeline development and drilling services.
An invitation to prequalify has been issued for a project to provide two-dimensional (2D) and three-dimensional (3D) offshore seismic surveying services.
The survey area is the Libyan Offshore Area O1, located in the Sirte Basin.
The winner of the contract will be responsible for:
- Acquisition of approximately 6,100 square kilometres (sq km) of 3D full-fold marine seismic data
- Acquisition of approximately 3,000 sq km of 2D full-fold marine seismic data
The client on the project is the Italian oil and gas company Eni.
In a statement posted on the website of Libya’s National Oil Corporation (NOC), it said: “The objective of the survey is to acquire, within the required operational window from September 2027 to March 2028, high-quality broadband seismic data to improve the imaging of Cretaceous reservoir sequences and support future exploration activities.”
The deadline to submit prequalification documents is 2 December 2026.
Deadline extended
Libya’s Mellitah Oil & Gas Company (MOG) has extended the deadline for companies to submit prequalification documents for a major offshore package as part of its Mellitah complex expansion and CO2 management integrated development project, which is estimated to be worth about $8bn.
The previous deadline of 5 November 2026 has been extended to 3 December 2026.
MOG, a joint venture of NOC and Eni, is the project client.
The package, known as WP4B1, focuses on developing offshore pipelines and subsea systems for the E offshore installation and CO2 project.
The turnkey contract will use the engineering, procurement, installation and commissioning (EPIC) model.
As part of the Mellitah complex expansion and CO2 management integrated development project, two offshore structures – Structure A and Structure E – will be developed in Libya’s offshore block NC 41.
Structure A is also known as wellhead production fixed platform A (WHPA) and Structure E is also known as production platform E (PPE).
Structure A is in the central-western part of the area, about 80 kilometres (km) from the Libyan coast, with a water depth of 95-105 metres.
Structure E is located in the central-eastern part of the area, about 130km from the Libyan coast, in a water depth of 205-235 metres.
The scope of the wider project includes:
- A new production platform installed in about 220 metres of water depth as part of the development of Structure E (Package WP1)
- A new wellhead platform installed in 96 metres of water as part of the development of Structure A (Package WP2)
- Modification of the existing Sabratha platform (Package WP3)
- Sealines and subsea systems extending from the Sabratha platform to Structure A (Package WP4A1)
- Sealines and subsea systems for Structure E and the CO2 system (Package WP4B1)
- Supply of seamless carbon steel pipes for CO2 injection from the Mellitah complex to Sabratha platform (Package WP4B2)
- Subsea Production Systems (SPS) for Structure E and CO2 (Package WP4B3)
- Upgrading the existing onshore Mellitah complex (WP5)
The package known as WP4B1 has been broken down into two phases.
The first phase focuses on the installation of the project’s subsea CO2 pipeline and its related system network.
The second phase of WP4B1 is focused on the pipeline to structure E and its related subsea system network.
Monitoring drilling
MOG has also issued a separate invitation for prequalification relating to a contract to provide hydrogen sulphide monitoring services for offshore drilling.
The contract focuses on providing H2S monitoring services for 18 offshore development wells as part of the “Structures A&E” project.
Four of the wells will be subsea wet wells and a further 14 will be dry tree wells.
The deadline for submitting prequalification documents is 3 December 2026.
The work will be carried out in the zone known as Area D, Block NC41.
H2S monitoring in the oil and gas industry involves tracking H2S gas concentrations in the air using electronic sensors and detectors to protect workers, prevent fatal exposures and avoid equipment damage.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21263383/main.jpg