Acwa Power tightens grip on GCC water
26 January 2024

This report also includes: Mena water delivers exceptional growth
Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.
This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.
The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.
In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.

Source: MEED
IWP awards
The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).
The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.
Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.
Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.
The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.
At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.
The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.
In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.
GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.
Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund.
Outlook
The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.
This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.
Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.
Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.
The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.
“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”
Tariff trend
Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.
“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.
“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.
“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.
The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.
Future projects
SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.
In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months.
Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.
In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.
In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.
Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.
MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.
Unstoppable
Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.
The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.
The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.
The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.
As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.
Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.
Exclusive from Meed
-
Dewa opens bids for MBR Solar Park phase seven3 August 2026
-
Three groups bid for $5bn Asir-Jizan highway3 August 2026
-
-
Lebanon seeks interest for power generation projects3 August 2026
-
Saudi economy swings to 4.8% contraction3 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dewa opens bids for MBR Solar Park phase seven3 August 2026

Dubai Electricity & Water Authority (Dewa) has opened bids for the seventh phase of the Mohammed Bin Rashid Al-Maktoum Solar Park.
According to a source, technical and financial offers were opened last month. The utility received bids on 1 July.
Phase seven will add 2,000MW from photovoltaic solar panels and include a 1,400MW battery energy storage system (bess) with a six-hour capacity, providing a total storage capacity of 8,400 megawatt-hours.
It is understood that Saudi Arabia’s Acwa, the UAE’s Etihad Water & Electricity and Abu Dhabi Future Energy Company (Masdar) are among the companies that submitted bids for the project.
The winning bidder “is likely” to come from one of those three, a source told MEED.
As MEED understands, the previously prequalified Electricite de France did not submit a bid for the project.
Dewa completed the prequalification process for the latest phase of the world’s largest single-site solar park in 2025.
As previously reported, 47 firms submitted their responses to Dewa’s expression of interest request for the contract in March 2025. The main tender was issued last November.
The following companies were among those prequalified to submit main contract bids on the project:
- Acwa (Saudi Arabia)
- Abu Dhabi Future Energy Company (Masdar)
- Electricite de France (EDF)
- Etihad Water & Electricity (EtihadWE)
- China Machinery Engineering Corporation
- China Construction Eighth Engineering Division
- Power China
- Larsen & Toubro (India)
- Shanghai Electric Group
The transaction advisory team for the project comprises UK-headquartered Deloitte and US-based CMS and Sargent & Lundy as financial, legal and technical advisers, with Deloitte acting as lead adviser.
Meanwhile, construction on the 1,800MW sixth phase of the MBR Solar Park is nearing completion, with commissioning expected by the end of the third quarter.
Dewa and Masdar reached financial close for the $1.5bn project in 2024. Once completed, the sixth phase will increase the solar park’s total production capacity to 4,660MW.
Dewa increased its flagship solar project’s 2030 installed capacity target by 45% in 2025, from 5,000MW to 7,260MW. This comprises a total investment of AED50bn ($13.6bn).
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18031819/main.jpg -
Three groups bid for $5bn Asir-Jizan highway3 August 2026

Three groups have submitted bids for an estimated SR20bn ($5bn) contract to develop and operate the Asir-Jizan highway project on a public-private partnership (PPP) basis.
According to sources close to the project, the consortiums that bid are:
- Lamar Holding (local) / Shaanxi Construction Engineering (China) / Safari (local)
- Vision Invest (local) / China Harbour Engineering Company (China)
- Plenary (Australia) / Alayuni (local) / Limak Holding (Turkey) / Nesma & Partners (local)
Saudi Arabia’s Roads General Authority, the National Centre for Privatisation & PPP and the Aseer Development Authority (Asda) are the government agencies managing the tender and project.
The 136-kilometre Asir-Jizan highway will have three lanes in each direction and include six intersections, 57 bridges totalling 18km and 11 tunnels totalling 9km.
The project is one of four planned highway schemes in the kingdom’s privatisation and public-private partnership pipeline.
The route begins in Al-Farah in Asir and extends to the Red Sea through Jizan.
The 30-year contract will follow a design, build, finance, operate and maintain model.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18031383/main1110.jpg -
Adnoc Onshore extends bid deadline for field facilities project3 August 2026

Abu Dhabi National Oil Company’s onshore business (Adnoc Onshore) has given contractors extra time to prepare bids for a project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields, part of the Northeast Bab cluster of oil fields in Abu Dhabi.
The project aims to enhance and sustain oil production at the Rumaitha and Shanayel fields at a rate of 45,000 barrels a day (b/d). It forms part of Adnoc Onshore’s contribution to parent company Adnoc Group’s broader objective of increasing oil production capacity to 5 million b/d by 2027 through its Accelerated Integrated Programme 5 (AiP5). Adnoc Group currently has a production capacity of 4.85 million b/d.
Adnoc Onshore issued the main tender for the engineering, procurement and construction (EPC) works package for the Rumaitha and Shanayel on-plot and off-plot facilities project on 19 June, MEED previously reported.
The project operator has now extended the deadline for contractors to submit technical bids to 5 August, from 2 August previously, according to sources. The prior deadline had been 30 July.
Adnoc Onshore issued the expression of interest for the Rumaitha and Shanayel on-plot and off-plot facilities project in early December, with contractors submitting their responses later that month, MEED previously reported.
The prequalification and ongoing tendering process is understood to result from Adnoc Onshore revising its strategy for executing EPC works on an earlier, larger project covering the Northeast Bab cluster, which comprises the Al-Nouf, Rumaitha and Shanayel fields.
MEED reported in December that Adnoc Onshore had cancelled the engineering, procurement and construction management (EPCm) phase it launched in 2024 for the Northeast Bab on-plot and off-plot facilities project in favour of executing the scheme under a conventional EPC model.
The operator awarded a contract to state-owned China Petroleum Engineering & Construction Corporation (CPECC) to carry out EPCm services for the Northeast Bab off-plot facilities package in October 2024. However, the contract was subsequently cancelled last year.
Separately, Adnoc Onshore received bids during the second quarter of 2025 for the EPCm tender covering the Northeast Bab on-plot facilities package, but that procurement process was also later cancelled.
Project scope of work
The detailed scope of work on the Rumaitha and Shanayel on-plot and off-plot facilities project is as follows:
On-plot facilities:
- Oil train: One new oil train with slug catcher, two-stage separation, desalting, exchangers for crude heating and stabilisation, and all associated interconnections, utilities and civil/structural works, etc.
- Produced water treatment (PWT): New produced water treatment package to enable 100% produced water reinjection (PWRI), including chemical dosing, tanks, pumps, all associated controls and blending with aquifer water, etc.
- Water injection system: New water injection system, including surface water injection pumps, necessary connections and controls from produced water systems, headers, chemical dosing, power and controls, etc.
- Gas handling and export:
- Low-pressure gas compression system
- Medium-pressure gas compression system
- Gas dehydration and regeneration system
- Export gas compression system
- Utilities and offsites: Plant air and instrument air systems, nitrogen generation system, potable water system, vapour recovery system (liquid ejector package), fuel gas import and distribution, closed and open drain systems, hot oil heater, snuffing nitrogen package, enclosed ground flare systems (high-pressure and tank flares), etc.
- Modifications in existing systems, including, but not limited to, installation of a slug catcher at phase-I, connectivity of gas systems, water systems, existing high-pressure compressors modifications, etc
- Electrical, instrumentation and control, and safety: Electrical systems, instrumentation and control system (ICSS, F&G system, field instrumentation, HIPPS, etc.), substation and ITR room building, fire water system, etc.
- Overhead line (220 kV): Installation and extension of overhead lines and 220 KV GIS compound or equivalent power distribution solutions to the central processing plant and other designated areas, as necessary.
Off-plot facilities:
- New gas-lifted oil producers and water injectors installation with necessary piping, controls, etc. and their connections to the new or existing clusters and pipeline networks
- New clusters with facilities such as control panels, ITR, production and test manifolds, headers, chemical injection skids, multiphase flow meters, closed drain systems, HIPPS valves, WHCPs, pig traps, ICSS/telecom extensions, etc.
- Modifications in existing clusters, including the addition or extension of manifolds, headers, additional pipelines with pig traps, ICSS/telecom extensions, chemical injection kids, etc.
- Gathering and injection networks: Construction of new and modified oil gathering and water injection trunklines/laterals, pigging facilities (launchers/receivers), valve stations, block valves, corrosion protection and monitoring, and all associated equipment, etc.
- Export gas pipelines and Adnoc Gas interface: Provision for export gas pipeline and facilities from Rumaitha central processing plant to new manifold station and from NMS to Adnoc Gas, including isolation/blowdown, etc.
- Overhead line: Installation and extension of 33kV overhead lines to clusters, etc., as required.
The tendering exercise for the Rumaitha and Shanayel on-plot and off-plot facilities project is taking place as Adnoc Onshore continues to make progress with EPC works on another, similar project to build off-plot facilities at the Southeast cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.
The Southeast cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.
MEED previously reported that Adnoc Onshore had awarded EPC works on the Southeast off-plot facilities project to state-owned China Petroleum Engineering & Construction Corporation (CPECC), with the value of the contract estimated to be around $1.2bn.
The overall scope of work on the Southeast off-plot facilities project includes tying in more than 150 wells across the area’s fields, upgrading remote and central degassing stations, laying more than 270 kilometres of flowlines, digitising wells for remote monitoring, and implementing artificial intelligence-driven telemetry technologies.
MEED also recently reported that CPECC awarded subcontracts on the Southeast off-plot facilities project, in its capacity as the main EPC contractor.
The off-plot facilities project is a component of the overall $2bn-$3bn South East AIP5 development, with the on-plot facilities project forming the other part of the programme.
CPECC is also performing EPC works on the Southeast on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18022436/main2622.jpg -
Lebanon seeks interest for power generation projects3 August 2026
Lebanon’s Electricity Regulatory Authority (ERA) has invited the private sector to submit expressions of interest (EoIs) for several upcoming power generation projects.
The EoI covers up to five grid-connected solar photovoltaic projects with a combined installed capacity of 350MWp. The projects are also expected to include battery energy storage systems (bess) with a combined capacity of 1,000MWh.
The regulator is also seeking proposals for distributed dual-fired thermal power plants with net capacities ranging from 20MW to 100MW. The plants are expected to operate on natural gas as the primary fuel and heavy fuel oil as a backup fuel.
The submission deadline is 31 August.
Regulatory progress
The EoI follows the establishment of Lebanon’s Electricity Regulatory Authority earlier this year, more than two decades after it was envisaged under Law No. 462/2002 but not implemented due to political delays. The electricity sector had previously been overseen by the Ministry of Energy & Water and state utility Electricite du Liban.
Lebanon’s electricity sector continues to face insufficient generation capacity, fuel supply constraints, ageing generation assets and limited grid flexibility. These challenges have led to prolonged electricity shortages and increased reliance on private diesel generation and distributed solar systems, prompting the government to seek additional private investment in new generation capacity.
IPP model
According to the EoI document, the projects are expected to be structured as independent power producer (IPP) schemes. Any future contractual arrangements, including power-purchase agreements, will be determined by the competent public authority under the applicable legal framework.
The ERA said the EoI is open to private investors, IPP operators, engineering, procurement and construction contractors, equipment suppliers and consortiums. It is intended to assess market interest, identify potential generation projects and evaluate the technical and financial capabilities of prospective developers.
Respondents are required to provide information on their technical and financial capabilities, proposed project locations, grid connection plans and relevant project experience.
For solar projects, developers are required to provide details including module and inverter technology, annual generation estimates and battery storage specifications where applicable. Thermal project submissions must include information on technology type, efficiency, fuel strategy, emissions performance and readiness for future natural gas operation.
The EoI states that developers will be responsible for land acquisition or leasing, permitting, financing, design, construction, grid interconnection, commissioning, and long-term operation and maintenance of the projects.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18018733/main.jpg -
Saudi economy swings to 4.8% contraction3 August 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s economy contracted 4.8% year-on-year in the second quarter of 2026, as a sharp fall in oil activities outweighed continued growth in the non-oil economy, according to flash estimates from the General Authority for Statistics (Gastat).
The contraction was driven by a 24.7% year-on-year drop in oil activities, which cut 5.4 percentage points from the headline figure. Non-oil activities grew 0.6% and government activities rose 0.9%, contributing 0.4 and 0.1 percentage points respectively. Net taxes on products added a further 0.1 percentage points.
On a seasonally adjusted basis, real GDP fell 4.9% from the first quarter, with oil activities down 21.5% quarter-on-quarter. Non-oil activities eased 0.5% over the same period, while government activities rose 0.2%.
The second-quarter figures mark a reversal from the first quarter, when the economy grew 3% year-on-year. In the first quarter, both oil and non-oil activities expanded by 2.9% and government activities rose 1.5%, with growth recorded across all major sectors. Oil activities have since swung from that modest expansion to a steep contraction, while non-oil growth has slowed from 2.9% to 0.6%.
The divergence between the oil and non-oil economy has widened as a result. While crude output fell steeply in the second quarter, the broader non-oil sector, the focus of the kingdom’s economic diversification programme, continued to expand, albeit at a slower pace than in the opening months of the year.
Public finances
The contraction came in a quarter when higher oil revenue improved the public finances. The budget deficit narrowed to SR34.29bn in the second quarter, down from SR125.71bn in the first, as oil revenue rose 22% year-on-year to SR185.13bn, according to the Finance Ministry’s quarterly budget performance report. Total revenue reached SR338.78bn, up 12% on the same period of 2025, while non-oil revenue increased 3% to SR153.66bn.
Total spending rose 11% year-on-year to SR373.07bn. The sharpest increases were in grants, up 199% to SR1.24bn, subsidies, up 73% to SR13.27bn, and financing expenses, up 41% to SR16.81bn. Capital spending rose 16% to SR46.23bn.
For the first half, the deficit totalled SR160bn, financed entirely through borrowing with no drawdown on government reserves. Revenue for the six months rose 6% year-on-year to SR599.76bn, while spending increased 15% to SR759.76bn. Actual first-half spending reached 58% of the full-year budget of SR1.312tn. Health and social development recorded the highest sectoral outlay at SR170.61bn, followed by the military at SR124.57bn and education at SR109.73bn.
Public debt reached SR1.684tn by the end of the first half, up from an opening balance of SR1.519tn. Domestic debt stood at SR1.060tn and external debt at SR624.9bn. The government reserve closing balance was SR399.07bn.
The kingdom has continued to tap the domestic debt market. The National Debt Management Centre closed its July 2026 issuance under the Saudi Arabian Government riyal-denominated sukuk programme at SR5.35bn, divided into five tranches. The largest, at SR3.83bn, matures in 2031, with further tranches of SR515m maturing in 2033, SR204m in 2036, SR300m in 2039 and SR500m in 2041.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18015899/main.gif