Acwa Power tightens grip on GCC water

26 January 2024

 

This report also includes: Mena water delivers exceptional growth


Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.

This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.

The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.

In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.


Source: MEED

IWP awards

The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).

The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.

Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.

Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.

The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.

At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.

The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.

In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.

GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.

Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund. 

Outlook

The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.

This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.

Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.

Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.

The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.

“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”

Tariff trend

Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.

“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.

“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.

“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.

The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.  

Future projects

SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.

In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months. 

Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.

In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.

In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.

Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.

MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.

Unstoppable

Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.

The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.

The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.

The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.

As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.

Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.

 Mena water delivers exceptional growth 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11438915/main.gif
Jennifer Aguinaldo
Related Articles
  • Contractor appointed for Oman power plants

    13 May 2026

     

    A consortium of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility has been appointed as the main contractor on the Misfah and Duqm combined-cycle gas turbine power plants in Oman.

    The contracts cover the construction of two independent power producer (IPP) projects, with work scheduled to begin in the third quarter of 2026.

    State offtaker Nama Power & Water Procurement (Nama PWP) had previously signed power-purchase agreements (PPAs) for the development and operation of the plants.

    The developer’s contract was awarded to a consortium comprising Korea Western Power (Kowepo), Qatar’s Nebras Power, the UAE’s Etihad Water & Electricity (EtihadWE) and Oman’s Bhawan Infrastructure Services.

    The Misfah IPP will be led by Nebras Power and located in Wilayat Bousher in Muscat Governorate, with a planned capacity of 1,600MW.

    The Duqm IPP will be led by Kowepo and located in Wilayat Duqm in Al-Wusta Governorate, with a capacity of 800MW.

    According to Nama PWP, the total investment for the two projects is estimated at approximately RO1bn ($2.6bn).

    MEED reported last October that Nama PWP had received three bids for the development and operation of the gas-fired IPPs.

    The other bids included a consortium comprising China’s Shenzhen Energy Group and Oman National Engineering & Investment Company, and a lone bid from Saudi Arabia’s Acwa Power.

    Synergy Consulting is the financial adviser and lead adviser to Nama PWP for these projects.

    In November, Oman’s OQ Gas Networks received final investment approval to proceed with gas supply connections for the facilities.

    The Misfah IPP will receive 8.5 million cubic metres a day (cm/d) of natural gas. The Duqm IPP will be supplied with 4.5 million cm/d of natural gas.

    In March 2025, the same Sepco 3 and Doosan Enerbility consortium signed an engineering, procurement and construction contract with Saudi Electricity Company for the expansion of the Riyadh Power Plant 12 (PP12).

    Located about 150 kilometres northwest of Riyadh, the 1,863MW power plant is expected to be completed in 2028.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16816237/main.jpg
    Mark Dowdall
  • Financial challenge tests Iraq’s resolve

    13 May 2026

     

    On 21 April, as a fragile ceasefire held between the US and Iran, the Trump administration halted a $500m shipment in cash headed for Iraq, as it sought to clamp down on Iranian-backed Shia militias in the country. 

    That cash, derived from Iraqi oil exports and routed via the US Federal Reserve to the Central Bank of Iraq (CBI), is a vital cog in Iraq’s financial arteries, enabling it to cover foreign exchange demand.

    This was not the first time that Iraq’s financial system has felt the US’s warm breath on its neck.

    Back in February 2025, the US Treasury Department blacklisted five Iraqi banks from participating in dollar transactions, citing concerns about their role in illicit financial flows that benefited Iran’s Islamic Revolutionary Guards Corps.

    Iraq has also itself often circumscribed dollar use within its own financial system.

    In July 2023, the CBI banned 14 banks from conducting dollar transactions in a crackdown on dollar smuggling. In February 2024, it banned a further eight banks from dollar transactions as part of a crackdown on fraud and money laundering.

    Dollar pressure

    The recent halt in US dollar cash shipments has nevertheless added pressure to Iraq’s parallel currency market gap, says Lucila Bonilla, lead emerging market economist at Oxford Economics.  

    “The gap between the parallel exchange rate has widened noticeably against the official peg, to around 20%,” she says.

    “Dollar demand has risen as citizens and traders seek to hedge uncertainty – dollar deposits are up, and there are reports of a notable shift in the composition of cash holdings toward dollars.”

    Ratings agencies see the US move on Iraqi dollar use as a challenge, but one that might not prove too onerous.

    “Iraq can overcome a short-term war as it has $100bn of reserves and its debt profile is bearable,” says Gilbert Hobeika, a director at Fitch Ratings.

    “But a longer-term conflict will hurt Iraq as the economy is reliant on oil revenues and government involvement, while facing at the same time risk from the US stopping delivery of US dollars.”

    How persistent the pressure proves will depend largely on the duration of the Hormuz shock and how the relationship with the US evolves.

    “Forming a new government that is palatable to the US could ease the pressure, though Iraq’s protracted government formation process adds uncertainty to that timeline,” says Bonilla.

    The US-Iran war is putting even more pressure on banks.

    “There are uncertainties with regard to depositors,” says Hobeika. “The public sector banks have weak management and governance structures. Financial reporting is weak, and that puts pressure on asset quality and capitalisation.”

    If the conflict lasts a long time, the government will start withdrawing funds to pay salaries and contractors.

    “That will affect deposits at the public sector banks in the near term,” says Hobeika.

    State-heavy system

    Iraq’s banking system is dominated by a handful of state-owned banks with a market share of 75%-80%, and then 60-plus private banks competing for the remaining 20%-25% of the pie. 

    “Private banks have struggled to compete in a market with limited opportunities, small deposit bases and a narrow range of products, often focusing on very basic activities,” says Lea Hanna, an analyst at Moody’s.

    “In 2019, we had a wave of Islamic banks getting bans on dealing with US dollars – reducing what had been a primary source of business.”

    A few private banks have benefitted since then, namely those with majority ownership by foreign banks such as National Bank of Iraq, a subsidiary of Capital Bank of Jordan, and Bank of Baghdad, a subsidiary of Jordan Kuwait Bank.

    “Supported by their affiliates, these banks are relatively well run compared to domestic peers and have ample capital buffers,” says Hanna.

    “They have captured a large market share of US dollar transfers thanks to their strong US correspondent banking relationships that allow them easier access to US dollars. They have seen a surge in their profitability and an increase in their deposit base.”

    Financial reform

    The CBI has attempted to introduce reforms to the banking system, as part of a wider effort to enable it to channel funding to the private sector.

    In early 2025, it increased the minimum issued and paid-up capital requirement to ID400bn ($305m), along with a requirement to establish correspondent banking relationships for foreign-currency trading. The plan was to increase these in ID50bn increments every six months, to hasten sector consolidation.

    However, of Fitch’s rated banks, just two – state-owned Trade Bank of Iraq and Mansour Bank, a subsidiary of Qatar National Bank – met the full capital requirement.

    “While a lot of banks managed to increase their capital, a number of them didn’t and have been struggling to improve their systems and compliance with anti-terrorism and anti-money laundering regulations,” says Hobeika.

    “These systems take a long time to improve, and it costs the banks too. For that reason, they have agreed with the central bank to postpone implementation to 2027/28.”

    The expectation is that the number of private Iraqi banks will shrink from 60 to about half that number by 2028.

    “Iraq’s banking sector is undergoing a significant overhaul, with the Central Bank pushing through higher capital requirements, improved anti-money-laundering compliance, and a shift towards commercial banks managing their own international correspondent relationships. These moves are welcomed,” says Bonilla.

    But the harder work remains, argues Bonilla: state-owned banks still carry high levels of non-performing loans, weak governance and a history of politically directed lending, while private sector credit remains among the lowest in the region.

    “The stakes are high as the IMF estimates that a comprehensive reform of the financial sector, alongside broader governance and regulatory changes, could double Iraq’s non-oil growth potential over the medium term, adding around 4 percentage points to GDP,” says Bonilla.

    “For now, the reforms address the plumbing. The structural transformation of a banking system to serve the private sector is still largely ahead.”

    Clouded outlook

    So far, Iraq’s financial system seems to have averted a worst-case scenario of large-scale deposit withdrawals related to the Iran conflict.

    Any deposit withdrawals seem to be more related to the introduction of a digital custom system ASYCUDA (Automated System for Customs Data) aimed at helping the government collect revenues, which saw a lot of traders trying to bypass the custom charges.

    “This drove some exporters or traders to source US dollars outside the banking system, in the parallel market, to avoid stricter requirements and up-front payment of customs duties. That has now eased,” says Hanna.

    Looking ahead, Fitch anticipates that most government financing is likely to come from the CBI through indirect purchases of government securities.

    The central bank’s total claims on the central government represented about 52% of the domestic debt stock and 25% of the total debt stock at end-2024, notes the agency.

    It envisages that a smaller portion will come from the government’s cash deposits, anticipated to fall to an average 12% by 2027.

    Fitch says the CBI’s balance sheet limits refinancing risks, while the FX reserves are large enough to absorb the expansion of that balance sheet without putting pressure on the exchange-rate peg with the US dollar.

    Surging foreign direct investment comes as a source of comfort, with annual inflows rising from around $2bn in 2022 to $5bn-$7bn from 2023 onwards. 

    Reform of the financial system will remain at the top of the new government’s in-tray.

    The regional environment is unconducive to this mammoth task, and it can only hope that an end to the conflict would support ongoing Iraqi efforts to build a financial system comparable to that of some of its Gulf neighbours.


    MEED’s June 2026 report on Iraq also includes:

    > OVERVIEW: Iraq enters era of resilience, reform and rising risks
    > OIL & GAS: Iraqi oil and gas sector in crisis
    > POWER & WATER: Focus shifts to delivery of Iraq utilities expansion
    > CONSTRUCTION: Momentum builds in Iraq’s post-war construction sector

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16799540/main.gif
    James Gavin
  • JinkoSolar signs 2GW deal for Abu Dhabi solar project

    13 May 2026

    China’s JinkoSolar has signed an agreement with Abu Dhabi Future Energy Company (Masdar) to supply 2GW of photovoltaic (PV) modules for the round-the-clock renewable energy project in Abu Dhabi.

    The agreement covers the supply of JinkoSolar’s Tiger Neo series modules for the project, which is being developed by Masdar in collaboration with Emirates Water & Electricity Company (Ewec).

    The landmark $6bn project combines a 5.2GW solar PV plant with a 19 gigawatt-hour battery energy storage system (bess).

    It entered construction in October 2025 with India’s Larsen & Toubro and Power China working as contractors. It is known as the world’s first gigascale round-the-clock renewable energy project.

    Masdar had earlier selected JinkoSolar and JA Solar as preferred suppliers for solar PV modules, and CATL (Contemporary Amperex Technology) as preferred supplier for the bess segment.

    The project is designed to provide baseload renewable power and address intermittency challenges associated with solar generation. The developers said the scheme will serve as a model for similar projects internationally.

    JinkoSolar said the Tiger Neo modules supplied for the project are based on N-type TOPCon technology and have been adapted to meet the technical requirements of the development.

    Senior executives from both companies attended the signing ceremony in Abu Dhabi, including Mohamed Jameel Al-Ramahi, CEO of Masdar, and Charlie Cao, CEO of JinkoSolar.

    Jinko has won several major contracts in recent years, including a contract to supply solar PV modules with a capacity of 3GW for Saudi Arabia’s Haden and Al-Khushaybi solar projects.

    It also recently announced the signing of a 2GW solar PV module supply agreement with China Energy Engineering Corporation (CEEC) for Saudi Arabia’s Phase Six Khurais PV project.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16813268/main1816.jpg
    Mark Dowdall
  • Dubai opens prequalification for Jebel Ali STP expansion

    13 May 2026

     

    Dubai Municipality has issued a request for qualifications for the Jebel Ali sewerage treatment plant (STP) expansion – phase 3 project.

    The DS150/3 project will be delivered under a public-private partnership (PPP) model on a design, build, finance, own, operate and transfer basis.

    The project involves the development of a new water resource recovery facility with an ultimate treatment capacity of up to 1 million cubic metres a day (cm/d).

    It is being procured through Dubai Municipality’s Sewerage and Recycled Water Projects Department and will be delivered through a two-stage operational approach over a 30-year concession period.

    The bid submission deadline is 18 June.

    UK-headquartered Deloitte is acting as financial adviser, Aecom as technical adviser and CMS as legal adviser.

    Dubai Municipality said the project will also include additional land uses and community-focused amenities as part of broader sustainability and urban integration objectives.

    Phase one and two expansion

    In April, the deadline was extended for contractors to submit bids for an engineering, procurement and construction (EPC) contract covering the expansion of the Jebel Ali STP phases one and two.

    Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cm/d, with the expansion estimated to cost $300m.

    The new bid submission deadline is 11 June.

    UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16812872/main.jpg
    Mark Dowdall
  • Iraq LNG project delayed until next year

    13 May 2026

    Register for MEED’s 14-day trial access 

    Iraq’s first liquefied natural gas (LNG) import terminal, which has an estimated project value of $450m, is now expected to become operational in 2027 due to delays caused by the regional war and disruption to shipping through the Strait of Hormuz.

    Work on jetty reinforcement and fixed terminal infrastructure at the Port of Khor Al-Zubair has been delayed, according to a statement from US-based Excelerate Energy, which is contracted to develop the facility.

    In its statement, the company said: “We are revising our full-year guidance to reflect the delayed startup of our Iraq terminal due to the ongoing conflict in the Middle East.”

    It added: “The Iraq project fundamentals remain unchanged. Looking ahead, we continue to have confidence in our sequenced earnings growth through 2028.”

    In October 2025, Excelerate signed a definitive commercial agreement with a subsidiary of Iraq’s Ministry of Electricity for the development of the country’s first LNG import terminal.

    The integrated project includes a five-year agreement for regasification services and LNG supply, with extension options, and a minimum contracted offtake of 250 million standard cubic feet a day (cf/d).

    Excelerate said: “Jetty reinforcement and construction of the fixed terminal infrastructure have been delayed temporarily due to the conflict in the Middle East and the terminal is no longer expected to commence operations in the third quarter of 2026 as previously disclosed.

    “Project startup is now expected in 2027. The long-term fundamentals supporting the project remain unchanged, driven by chronic power shortages and limited domestic gas processing capacity in Iraq.

    “Current conditions further reinforce the country’s need for reliable and scalable LNG import infrastructure and construction will resume as conditions allow.”

    Earlier this year, Iraq’s Ministry of Electricity said that the terminal was on track to come online on 1 June, ahead of expected gas shortages during the summer months.

    Then, in late April, the ministry said the project had been delayed by several months and was expected to come online in August at the earliest.

    Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.

    Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16803348/main.jpg
    Wil Crisp