Acwa Power tightens grip on GCC water
26 January 2024

This report also includes: Mena water delivers exceptional growth
Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.
This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.
The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.
In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.

Source: MEED
IWP awards
The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).
The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.
Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.
Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.
The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.
At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.
The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.
In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.
GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.
Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund.
Outlook
The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.
This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.
Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.
Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.
The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.
“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”
Tariff trend
Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.
“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.
“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.
“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.
The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.
Future projects
SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.
In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months.
Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.
In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.
In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.
Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.
MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.
Unstoppable
Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.
The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.
The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.
The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.
As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.
Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.
Exclusive from Meed
-
-
Aldar launches Al-Ghadeer Gardens project19 May 2026
-
-
-
Emirates awards $5bn engineering complex deal18 May 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Construction advances on Riyadh King Salman airport19 May 2026
King Salman International Airport (KSIA) is advancing airside infrastructure works under its long-term expansion programme in Riyadh, including the delivery of a third runway and new private aviation facilities.
Construction activity on the central runway programme is progressing across several operational zones, with works covering excavation, grading, site preparation and taxiway-enabling infrastructure to support upcoming phases.
The third runway is intended to increase airfield capacity and cater to the airport’s future operational requirements.
In a separate development, KSIA has completed initial landside works for the private aviation apron, marking a milestone in the rollout of its executive aviation infrastructure.
The completed scope includes pavement markings, waterproofing systems, firefighting infrastructure chambers and final operational inspections to support readiness for the next stages.
KSIA has also secured General Authority of Civil Aviation (GACA) approval for phase one airside works, which includes the planned connection of Taxiway Alpha to the private aviation facilities, strengthening operational integration between executive aviation assets and airfield movement areas.
The packages form part of the wider KSIA masterplan, which covers about 57 square kilometres and supports Saudi Arabia’s objective of positioning Riyadh as a global aviation and logistics hub.
The airport aims to accommodate up to 100 million passengers by 2030.
Saudi Arabia plans to invest $100bn in its aviation sector. The Saudi Aviation Strategy, announced by GACA, aims to triple annual passenger traffic to 330 million travellers by 2030. It also targets air cargo growth to 4.5 million tonnes and an increase in total air connections to more than 250 destinations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16906496/main.jpeg -
Aldar launches Al-Ghadeer Gardens project19 May 2026
Abu Dhabi-based real estate developer Aldar Properties has launched the Al-Ghadeer Gardens project, located on the Abu Dhabi-Dubai border.
The new residential development will feature 437 villas and townhouses, offering two-, three- and four-bedroom homes.
Al-Ghadeer Gardens will include more than 30,000 square metres of landscaped open space, supporting a pedestrian-friendly layout and outdoor-focused living.
As part of its sustainability and wellbeing approach, the project is targeting Estidama Pearl 2 and Fitwel 2-star certifications.
Earlier this month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).
Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.
UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.
The group attributed its performance to revenue from its development backlog and steady income from its investment properties.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16906154/main.jpg -
Iraq trucks oil from the south to Kurdish pipeline19 May 2026

Iraq is trucking crude from Basra to the north of the country to be exported via the Iraq-Turkiye Pipeline (ITP), according to industry sources.
The oil is being loaded into trucks at fields in Basra before being driven to the north, where it is injected into the pipeline network at Khurmala Dome, in the northern section of the Kirkuk field.
Once it has entered the network at Khurmala Dome, it is transported to the main ITP export pipeline and eventually to the port of Ceyhan in Turkiye, where it can be loaded onto ships.
The volumes of crude being transported using trucks have surged in Iraq since the US and Israel attacked Iran on 28 February, starting a regional conflict that has disrupted shipping through the Strait of Hormuz.
One source said: “Most of the crude that is being trucked out of Iraqi oil fields at the moment is going to Syria, but some is being trucked to the north where it is being funnelled through the pipeline.”
Even with the additional volumes being trucked from the south, Iraq is struggling to boost exports using the ITP.
At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day (b/d) through the ITP.
At the time, he said that the pipeline, which runs from Kirkuk in Iraqi Kurdistan to the port of Ceyhan in Turkiye, was expected to start transporting 300,000 b/d “in the near future”.
As of early May, the pipeline was still exporting about 200,000 b/d, despite having a nameplate capacity of 1.4 million b/d.
One of the factors said to be stopping increased volumes from being shipped through the pipeline is that several key oil fields in northern Iraq evacuated staff and stopped production after the US and Israel started their war with Iran.
Another factor is that Iraq has not invested in domestic pipeline infrastructure to pipe production from Basra to Kurdistan, where it could be exported via the Kurdish ITP route.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16902345/main1824.jpg -
Kuwaiti oil services company secures credit facility19 May 2026
The Kuwaiti drilling and oilfield services provider Action Energy Company (AEC) has secured a new credit facility and renewed and expanded an existing facility in order to support the company’s rig fleet expansion.
The new facility and the expansion were obtained from two Kuwaiti banks and had a combined value of KD40.9m ($132.8m).
In its statement, AEC said that the facilities support the financing and deployment of new rigs linked to contract awards previously announced with the state-owned upstream operator Kuwait Oil Company (KOC).
The company added: “They further reinforce AEC’s financing structure and strengthen its ability to execute its contracted fleet expansion plan through 2026 and beyond, while maintaining a disciplined approach to capital allocation.”
The new credit facility was obtained from Kuwait International Bank (KIB).
It is worth KD7.3m ($23.7m) and will finance two new 750-horsepower (HP) rigs.
The renewal and expansion of the existing facility is worth KD33.6m ($109.1m) and was obtained from Commercial Bank of Kuwait (CBK) to finance four new 1,500 HP rigs and one 1,000 HP rig, in addition to the renewal of the existing facilities.
AEC announced its financial and operational performance for the first quarter earlier this month.
The company reported a net profit of KD2.2m ($7.1m).
The company’s revenue grew by 69.2% year-on-year, primarily driven by the expansion of the operating rig fleet from 13 rigs in the first quarter of 2025 to 20 rigs in the first quarter of 2026, including the full-quarter contribution of 10 new rigs deployed during 2025.
The company is benefitting from a substantial multi-year contracted backlog with KOC.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16902234/main.jpg -
Emirates awards $5bn engineering complex deal18 May 2026
Register for MEED’s 14-day trial access
Emirates Airline has awarded a AED19bn ($5bn) contract to build one of the world's largest engineering complexes in Dubai South.
The contract was awarded to Beijing-headquartered China Railway Construction Corporation (CRCC).
CRCC is being supported by French firm Artelia, as the project consultant.
The complex will cover over 1 million square metres (sq m).
It will comprise 77,000 sq m of dedicated workshop space for maintenance and repairs, 380,000 sq m of storage and logistics capacity, a 50,000 sq m administrative building for Emirates Engineering and 15,000 sq m of training facilities.
It will be the world's only complex with a capacity to service 28 wide-body aircraft simultaneously.
The airline officially broke ground on the project on 18 May.
The groundbreaking ceremony was attended by Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and CEO of Emirates Group; Tim Clark, president of Emirates Airline; Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai South; and Dai Hegen, chairman of CRCC.
The facility will enable large-scale retrofits, cabin redesigns and structural modifications to be performed in-house, thereby reducing turnaround times.
The engineering complex is scheduled for completion in 2030 and will be located at Al-Maktoum International airport.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16895218/main.jpg