Acwa Power tightens grip on GCC water

26 January 2024

 

This report also includes: Mena water delivers exceptional growth


Time-bound sustainability objectives and improving economic conditions kept the GCC region’s water sector projects buoyant in 2023.

This coincided with the key milestones achieved by independent water producer (IWP) contracts awarded between 2020 and 2021, which reached either the commissioning or commercial operation stages in 2023 following two years of disruption caused by the Covid-19 pandemic.

The UAE awarded three IWP contracts in 2023 and Saudi Arabia awarded one. This was a remarkable recovery considering that there was only one contract award in 2021 and none in 2022, barring the directly negotiated contract for the development of Shuaibah 3 in Saudi Arabia.

In contrast, there were no new awards for independent water and power producer (IWPP) projects – a model that worked successfully from the 1990s until the mid-2010s, when policies started to shift away from thermal desalination technologies and towards IWPs that rely on reverse osmosis technology for water treatment.


Source: MEED

IWP awards

The IWP contracts awarded in 2023 include Mirfa 2 and Shuweihat 4 in Abu Dhabi, Rabigh 4 in Saudi Arabia and Hassyan 1 in Dubai. The four IWP schemes have a total combined capacity of about 2.3 million cubic metres a day (cm/d).

The award of these contracts resulted in higher net and gross capacities for Saudi utility developer Acwa Power, France’s Engie and Spain-headquartered GS Inima, relative to the last MEED water developer ranking published in January 2023.

Acwa Power’s overall net capacity leapt by 20 per cent in 2023 to reach approximately 3.5 million cm/d. This resulted from its 40 per cent equity in Dubai’s Hassyan 1 IWP project, which has a capacity of over 818,000 cm/d; and its 45 per cent shareholding in the 600,000 cm/d Rabigh 4 IWP.

Engie likewise posted an impressive two-digit rise in terms of its net capacity, growing from 1.67 million cm/d to 1.87 million cm/d, thanks to its 40 per cent equity in the Mirfa 2 IWP project in Abu Dhabi.

The size of the two projects that Acwa Power won in 2023, however, meant it managed to further widen its lead over Engie and the other private water developers operating assets across the GCC states.

At 3.5 million cm/d, Acwa Power’s overall net capacity is equivalent to the total combined net capacity of the next five developers in the ranking: Malaysia’s Malakoff, Japan’s Marubeni and Sumitomo, and GS Inima, in addition to Engie.

The Saudi utility developer has also for the first time overtaken Engie in terms of gross water desalination capacity. As
of the end of 2023, its gross capacity crossed 7.7 million cm/d compared to Engie’s 7.0 cm/d.

In terms of ranking, GS Inima registered the most significant improvement among the top 10 private water developer companies, advancing three spots to rank fifth, having grown its net equity capacity nearly 50 per cent to reach close to 383,000 cm/d. This change takes into consideration that Kuwait’s Gulf Investment Corporation (GIC), which was included in the previous index, has been excluded this year due to its role as an investor rather than a developer of water desalination projects.

GS Inima will maintain a 60 per cent shareholding in Abu Dhabi’s Shuweihat 4 IWP scheme, which is expected to reach commercial operation by mid-2026.

Despite not having won any new contracts, Saudi Brothers Commercial Company and Abdulaziz al-Ajlan, both Riyadh-based, managed to land in the top 10 ranking of water developers this year, mainly due to the exclusion of both GIC and Water & Electricity Holding Company (Badeel), which is fully owned by Saudi Arabia’s Public Investment Fund. 

Outlook

The next 12 months will likely be an active period for the water industry, particularly in Saudi Arabia.

This is mainly due to the target set by the kingdom’s Environment, Water & Agriculture Ministry to meet 92 per cent of Saudi Arabia’s water demand using desalinated water by 2030, to reduce reliance on ground and surface water.

Both Saudi Water Conversion Corporation, the world’s largest desalinator, which supplies 69 per cent of Saudi Arabia’s water, and Saudi Water Partnership Company (SWPC) will have to get “plants up and running as soon as possible to make this target”, says Robert Bryniak, CEO of Dubai-based Golden Sands Management Consulting.

Elsewhere – particularly in the UAE and, to a lesser extent, Oman – expiring contracted capacity and growing demand are expected to continue to drive the procurement of additional seawater reverse osmosis (SWRO) capacity.

The past few years have seen several international and local developers and investors enter the GCC’s water desalination market.

“The water industry could benefit by having more engineering, procurement and construction (EPC) contractors and developers, but I do not see this holding back procurers in launching new projects,” says Bryniak. “Having said that, there is definitely room for the water industry to accommodate more developers and EPC contractors.”

Tariff trend

Tariffs, or the long-term levelised costs that offtakers pay for water that private developers produce, are expected to trend upwards in 2024. This is due to higher interest rates and inflationary pressures on materials and supplies.

“These considerations, coupled with a limited number of experienced EPC contractors with excess contracting capacity, suggest that it will be tough seeing lower tariffs this year,” Bryniak says.

“We expect this trend due to the expected higher costs,” says another water desalination expert based in the UAE.

“The tariff for the Hassyan 1 IWP was low, but I see that as an anomaly,” says Bryniak, referring to the $cents 36.5 a cubic metre ($c/cm) tariff that Acwa Power proposed last year to develop the Hassyan 1 IWP in Dubai.

The previous tariff bid for the project was about 30 per cent lower than that proposed by Acwa Power last year, and it is likely that the bidder “had tremendous pressure to maintain a relatively low tariff to secure the project”, says Bryniak.  

Future projects

SWPC issued the tender for the contract to develop the Jubail 4 and 6 IWP schemes on 1 January, and the tendering process is also under way for the Ras Mohaisen IWP. Both contracts are expected to be awarded before the end of this year.

In addition, SWPC has indicated that four more IWPs are expected to reach commercial operation by 2027, which implies that it could start seeking interest from developers for these projects in the next 12-24 months. 

Under the latest plan, the Ras al-Khair 2 and 4, Al-Rais 2 and Tabuk 1 IWP projects will have a combined total capacity of 1.7 million cm/d.

In the UAE, Acwa Power is understood to be the sole bidder for the 400,000 cm/d Hamriyah IWP in Sharjah. The contract could be awarded in the first half of 2024.

In Abu Dhabi, the tendering process is under way for two SWRO plants that will be developed under one contract. The Abu Dhabi Islands SWRO projects will each have a capacity of 227,000 cm/d.

Kuwait’s two IWPPs – Al-Zour North 2 & 3 and Al-Khiran 1 – and the Facility E IWPP in Qatar include water desalination units with capacities of 695,000 cm/d and 454,000 cm/d, respectively.

MEED understands that an option is open for the bidders to use membrane technology for the desalination units of these planned facilities.

Unstoppable

Acwa Power thus appears unstoppable given its plans to further consolidate its presence in the region’s water industry, and pursue new technologies and partnerships, as its CEO Marco Arcelli told MEED in July last year.

The company plans to work with Japanese membrane technology provider Toray Industries to explore energy-saving technologies for SWRO. It is also working with other suppliers located in the US, Japan and China, as well as with Saudi Arabia’s King Abdullah University of Science & Technology to explore energy-efficient solutions for treating seawater.

The scale of the IWP projects Acwa Power has won between 2019 and 2023 enables it to outprice key competitors, or bid for projects deemed too risky by other developers.

The firm’s offer to develop Rabigh 4 for $c0.458/cm, for instance, was lower than what some of its competitors anticipated Acwa Power was capable of offering, although it lost Mirfa 2 to Engie a few months earlier.

As it is, Acwa Power won five of the 12 IWP contracts that were tendered and awarded in Saudi Arabia, the UAE and Oman during the past four years, equivalent to more than 56 per cent of the gross capacity awarded over that period.

Other developers should take note as they establish strategies to win more contracts in the future and potentially slow down Acwa Power's three-year sector dominance.

 Mena water delivers exceptional growth 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11438915/main.gif
Jennifer Aguinaldo
Related Articles
  • Building resilience into infrastructure delivery

    21 October 2026

     

    The regional disruptions earlier this year tested Gulf supply chains, challenging the movement of goods and construction materials and raising questions about the ability of infrastructure programmes to maintain momentum.

    For the UAE Ministry of Energy & Infrastructure, the experience reinforced the importance of the systems that support project delivery, from transport networks and customs procedures to domestic manufacturers and international suppliers.

    “The disruption reinforced an important principle: infrastructure resilience is ultimately about the ability of the national system to continue operating under pressure,” says Mohammed Al-Mansoori, undersecretary for infrastructure and transport affairs.

    Supply resilience

    The ministry worked with ports, customs authorities, transport and rail operators, contractors, suppliers and the private sector to maintain the flow of essential goods and construction materials. It monitored critical materials and project schedules, identified alternative sources and adjusted procurement and delivery arrangements.

    The response included movement exemptions and facilitation measures for more than 6,600 lorries, while rail freight operations increased from approximately one journey a week to as many as seven journeys a day. Priority and green corridors were activated, customs procedures facilitated and critical shipments prioritised at ports.

    According to Al-Mansoori, these measures contributed to an estimated 25% reduction in transport costs, a 40% improvement in customs clearance times and an increase of approximately 15% in port capacity during the response period.

    For infrastructure projects, the ministry worked with local manufacturers and suppliers to identify alternative sources of road and construction materials meeting the required technical specifications and quality standards. This helped reduce reliance on disrupted international supply routes and support ongoing projects.

    The experience also highlighted the value of existing coordination mechanisms and partnerships.

    “It also reinforced a fundamental principle: resilience means ensuring that critical infrastructure delivery does not depend on a single supplier, a single route or a single mode of transport,” Al-Mansoori says.

    The ministry is planning to build on this experience by diversifying suppliers, strengthening domestic manufacturing and improving supply-chain monitoring.

    Resilience is increasingly being incorporated into procurement planning. For critical materials and services, the ministry aims to identify risks early, broaden the pool of qualified suppliers and ensure viable alternatives are available.

    The approach supports the UAE’s wider industrial objectives, including the national in-country value programme, which seeks to direct a greater share of procurement expenditure into the national economy.

    “Our objective is not simply to purchase more locally. It is to help create competitive national supply chains,” Al-Mansoori says.

    Domestic suppliers must be able to meet the technical requirements, quality standards and volumes demanded by major infrastructure programmes. Localisation is therefore about developing competitive industrial capabilities while shortening supply chains, improving responsiveness and encouraging investment.

    “Localisation is not simply a procurement choice; it is an investment in national capability and long-term resilience,” Al-Mansoori says.

    The ministry is also working with contractors to manage pressures from fluctuating material, insurance and transport costs. Its approach combines commercial discipline with early engagement to prevent external pressures from affecting project delivery.

    “Our approach is based on early engagement, transparency and disciplined commercial management,” Al-Mansoori says. “Long-term infrastructure delivery depends on strong contractors as much as it depends on strong contracts.”

    Contractors remain responsible for normal market and contractual risks, but the ministry seeks to assess exceptional pressures objectively, supported by evidence of their impact on costs and schedules. Realistic planning, early procurement and proactive risk management also help maintain momentum.

    “The objective is to strike the right balance between protecting the government’s commercial interests and securing best value for money, while maintaining an efficient, sustainable contracting market capable of continuing to deliver strategic infrastructure projects,” Al-Mansoori says.

    Resilience means ensuring that critical infrastructure delivery does not depend on a single supplier, a single route or a single mode of transport

    Project delivery

    The ministry’s focus on measurable outcomes is reflected in the Emirates Road enhancement project, which involves widening approximately 25 kilometres of Emirates Road from three to five lanes in each direction, alongside major improvements to Interchange No. 7.

    The works are expected to increase road capacity by up to 65% and reduce journey times by up to 45%.

    The project illustrates the ministry’s emphasis on assessing infrastructure by the benefits it delivers, rather than simply the scale of construction.

    “Infrastructure success should be measured by the value it creates – not just by the kilometres we build,” Al-Mansoori says.

    That principle is increasingly important as the UAE balances new construction with the long-term costs of operating and maintaining its assets. Decisions made during planning and construction can influence maintenance requirements, operating costs and performance for decades.

    For Al-Mansoori, resilience, domestic capability and effective delivery are closely connected. Stronger local supply chains can reduce exposure to external shocks, while closer engagement with contractors can help projects withstand cost pressures. 


    Don’t miss MEED’s MENA Construction Summit 2026, taking place under the patronage of the UAE Ministry of Energy & Infrastructure
     Secure your place as an attendee or request the sponsorship deck by clicking here or emailing us at meedevents@meed.com


     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20810056/main.gif
    MEED Editorial
  • Riyadh tenders Expo 2030 Adaptation and Innovation Pavilion

    21 October 2026

     

    Register for MEED’s 14-day trial access 

    Expo 2030 Riyadh has tendered the design-and-build main contract for the Adaptation and Innovation Pavilion in the exhibition’s Technology District.

    The pavilion will be built on a plot of at least 12,710 square metres and will feature a two-level basement, ground-level public areas, an elevated skywalk, visitor experience areas, food and beverage outlets, retail space, VIP facilities, offices, back-of-house areas, exhibition spaces, an amphitheatre and a resonance hall.

    The facility is being designed to accommodate a minimum of 20,000 visitors a day at peak periods, with an anticipated average of about 15,000 visitors a day. The project targets LEED Gold certification.

    The tender was issued on 1 October, with bids due on 6 January 2027.

    The design-and-build contractor will be responsible for completing, reviewing, verifying, coordinating and technically integrating the design, including specialist contractor design portions and coordination with the novated lead design consultant.

    The scope includes completing early works and substructure activities, including grading, bulk earthworks, excavation, cut and fill, soil improvement, raft foundations, reinforced-concrete basement walls, basement columns through to the ground-floor slab, waterproofing, mechanical, electrical and plumbing (MEP) provisions, and backfilling.

    The contractor will also deliver the superstructure and building envelope, including structural works, facade engineering and installation, roofs, waterproofing, external finishes, and permanent facade access and maintenance systems. The internal works will cover front-of-house and back-of-house areas, public and core spaces, internal finishes, fixtures, fixed fittings, joinery, circulation areas, lobbies, stairs, toilets, storage, waste areas and associated builder’s works.

    The building services package includes MEP systems, information and communications technology, extra-low-voltage systems, building management systems, security, fire and life safety systems, specialist lighting and vertical transportation.

    The contract also covers the visitor experience package, including procurement, installation, integration, testing, commissioning and handover of visitor-facing environments, media, immersive and audiovisual technologies, interactive elements, experiential lighting, digital content, interpretive and wayfinding systems, controls and supporting infrastructure.

    Within-plot infrastructure and utilities, landscaping, public realm works, paving, planting, irrigation, signage, street furniture, drainage, stormwater systems, external lighting, security, and fire and life safety systems are also included.

    The contractor will be responsible for procurement, off-site fabrication, construction, testing and commissioning, performance verification, training, operations and maintenance documentation, operational readiness, handover, defects rectification and close-out.

    The main works tender is based on a 60% RIBA Stage 3 design, with the Stage 3 design to be completed to 100% through an addendum.

    Early works and substructure works, as well as the lead design consultant, will be novated to the contractor. Visitor experience works are included as a provisional sum.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20801465/main.jpeg
    Yasir Iqbal
  • Mubadala Bio lands Lilly logistics deal

    21 October 2026

    Mubadala Bio, the life sciences subsidiary of Abu Dhabi state investor Mubadala Investment Company, has signed an agreement with US drugmaker Eli Lilly to localise the packaging and logistics of Lilly’s glucagon-like peptide-1 (GLP-1) medicines in Abu Dhabi.

    The work will take place at a 125,000-square-metre site in Khalifa Economic Zones Abu Dhabi (Kezad), which includes packaging and warehousing facilities. Mubadala Bio said the facilities would strengthen its pharmaceutical contract manufacturing, packaging and logistics capabilities and its ability to serve international clients from the UAE.

    The packaging and logistics activities will be introduced in phases and will be subject to technical, quality and regulatory requirements. The companies did not disclose the value of the agreement or a timeline for the first phase.

    The Emirates Drug Establishment approved Lilly’s oral GLP-1 drug Foundayo (orforglipron) for chronic weight management in April. The companies said this made the UAE the second country in the world to register the medicine.

    In Abu Dhabi, the treatment is available to eligible patients under a weight management programme launched by the Abu Dhabi Department of Health and the Abu Dhabi Public Health Centre in June 2025. The UAE was also an early launch market for Lilly’s injectable treatment Mounjaro (tirzepatide) in August 2022.

    Mubadala launched Mubadala Bio in 2025 to expand domestic drug manufacturing and distribution, with a focus on national drug security. It is one of Mubadala’s designated national champions, set up to support strategic sectors. At launch, its combined facilities covered 110,000 square metres, with an annual capacity of more than 2.5 billion tablets and capsules and 120 million intravenous and injectable units.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20801279/main.jpg
    Colin Foreman
  • Chinese/local joint venture wins Qiddiya stadium facade

    21 October 2026

    Register for MEED’s 14-day trial access 

    A joint venture of China’s Fangda Group and Saudi Arabia’s IKK Group has secured a SR1.15bn ($306m) contract to deliver curtain wall facade works for the Prince Mohammed Bin Salman Stadium in Qiddiya City, Riyadh.  

    The contract was awarded by the joint venture of Spain’s FCC Construccion and local contractor Nesma & Partners, which is building the stadium under an estimated SR15bn ($4bn) main contract awarded by Qiddiya Investment Company (QIC) in October 2024.  

    The IKK-Fangda joint venture will design, supply and install curtain wall façade systems for the main stadium (Lot 1), as well as for the museum and ancillary buildings (Lot 3).

    The contract has an execution period of 863 days.  

    The stadium will seat about 47,000 spectators and will be the home ground for Saudi Pro League clubs Al-Nassr and Al-Hilal.

    The facade award follows the appointment of Elegancia Arabia, a subsidiary of Qatar-based Elegancia MEP and Estithmar Holding, to deliver the stadium’s mechanical, electrical and plumbing works.

    The SR829m ($221m) contract is Elegancia Arabia’s largest award in Saudi Arabia to date.

    The project is being designed by US-based consultant Populous.

    It is among the venues planned for the 2034 Fifa World Cup and will also host the Saudi King Cup, the AFC Asian Cup and the 2034 Asian Games.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20799367/main.jpg
    Yasir Iqbal
  • Zamil Steel wins $82m Qiddiya tennis centre contract

    21 October 2026

    Advanced Building Industries Company (Senaat) has announced that its subsidiary, Zamil Structural Steel Company (Zamil Steel), has secured a SR308m ($82m) contract for the National Tennis Centre in Qiddiya City, Riyadh.  

    The 19-month contract was awarded by the joint venture of France’s Bouygues Batiment International and local contractor Almabani General Contractors Company.  

    Zamil Steel’s scope includes the fabrication, supply and installation of structural steel and external facades for the scheme.   

    MEED reported in June that the Bouygues Batiment International-Almabani joint venture had started construction of the National Tennis Centre.  

    The development will include 30 tennis courts, comprising 28 hard courts and two clay courts. The main Centre Court will seat 15,000 spectators and feature a retractable roof.

    The facility is being designed to meet standards set by the Association of Tennis Professionals, the Women’s Tennis Association and the International Tennis Federation.  

    The development will also include an 8,000-seat multipurpose arena with a retractable roof, known as Court 3. Other facilities include a 5,000-seat Court 1, a 2,000-seat Court 2, six competition courts, six indoor courts and 14 practice courts. Each outdoor match court will provide 450 seats.  

    Total seating capacity across the complex will be 33,000. US-based architect Populous designed the project.  

    Qiddiya Investment Company officially announced the project on 15 June. The developer has said the centre will be the region’s largest tennis complex and will host international tennis events.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20799055/main.jpg
    Yasir Iqbal