Saudi Arabia stands at a pivotal moment. Its population – around 35 million and rising – is overwhelmingly young and increasingly urban. Major cities like Riyadh – approaching 8 million residents – and Jeddah are experiencing rapid growth in population and activity, increasing demand for efficient mobility solutions. After decades of car-focused development, there now exists an opportunity to introduce new modern multimodal transport solutions in line with the objectives of Vision 2030.
Rail offers an answer to urban and economic pressures. Each train can remove hundreds of cars from the roads, cutting congestion and commuting times. Rail also aligns with Saudi Arabia’s environmental commitments.
Efficient mobility is key to Riyadh’s ambition to rank among the world’s top city economies. A reliable metro bolsters productivity as workers spend less time in traffic, boosts retail and tourism, with easier access to malls and attractions, and increases real estate values around stations. It also expands access to opportunity by providing safe and convenient transportation for women and youth entering the workforce. Similarly, intercity rail links can unite labour markets and connect people to jobs and services across the region.
Rail development is also central to Saudi Arabia’s strategy to become a global logistics and tourism hub. Launched in 2021 as part of Vision 2030, the National Transport and Logistics Strategy (NTLS) explicitly prioritises expanding the rail network to connect key cities, ports and economic zones. The kingdom aims to roughly double its rail network, adding more than 5,000 kilometres of new tracks. Saudi Arabia can unlock economic potential in underdeveloped regions, facilitate domestic tourism (e.g. convenient travel to cultural and religious sites) and streamline freight movement.
An integrated rail system also enhances resilience by providing alternative transport modes to complement roads and aviation, making the overall economy more robust against shocks such as oil price fluctuations or air travel disruptions.
The time is ripe for rail – it addresses urgent urban challenges and propels the kingdom towards its Vision 2030 objectives of sustainability, connectivity and diversified growth
Current and planned projects
Public transportation in Saudi cities is targeted to rise from 1% to 15% by 2030. Major investments are already under way or planned across both passenger and freight rail:
Riyadh Metro: A flagship $22.5bn project, the new six-line Riyadh Metro network (176km, 85 stations) is set to carry more than a million passengers daily and reduce traffic volumes by an estimated 30%.
Haramain High-Speed Railway: Completed in 2018, this 450km electric high-speed line connects the holy cities of Mecca and Medina via Jeddah at speeds up to 300km/h. The Haramain line, with a capacity of 60 million passengers a year, has already transported more than 20 million travelers – dramatically cutting travel times for pilgrims and residents while offering a comfortable, climate-friendly alternative to highway driving.
Saudi Landbridge Project: The Landbridge is a planned 1,300km railway linking the Red Sea coast to the Arabian Gulf. This new line will connect Jeddah’s port with Riyadh and onward to Dammam on the Gulf, including a spur to the industrial city of Jubail. By creating the first direct east-west rail corridor across Saudi Arabia, the Landbridge will revolutionise freight logistics. Transport times for containers and goods will shrink from days by truck or ship to mere hours by rail, slashing logistics costs. The Landbridge will also carry passengers, enabling fast travel between major cities.
GCC Regional Rail Connectivity: This 2,100+km network – slated for completion around 2030 – will tie together all six GCC states. Key corridors for Saudi Arabia include a line north to Kuwait City-Riyadh, and another south linking Riyadh with Doha, Qatar (via the Saudi-Qatar border at Salwa). There is also a planned connection from Dammam eastward via a new causeway to Bahrain. Saudi Arabia, by virtue of its geography, will host the largest share of the GCC rail route, effectively becoming the backbone of Gulf connectivity.
Q-Express to Qiddiya: Qiddiya, an upcoming entertainment city west of Riyadh and one of the Vision 2030 gigaprojects, will be connected to Riyadh’s King Khalid International airport by a high-speed rail line. Planners envision using cutting-edge technology such as magnetic-levitation (maglev) trains to whisk visitors from the airport to Qiddiya in record time. This roughly 40km connection, being structured as a public-private partnership (PPP), will enhance Qiddiya’s accessibility for international tourists and Riyadh residents, while showcasing futuristic transit tech. The Q-Express is part of a broader strategy to integrate new economic cities, such as Qiddiya, Neom and others, into the national transport grid from the outset, ensuring these developments are well-connected and sustainable.
Financing Rail Projects in Saudi Arabia
Given the Vision 2030 emphasis on private sector participation, Saudi Arabia has a diverse range of financing tools for its rail programme:
PPPs: In a PPP, private consortiums can design, build, finance and often operate infrastructure, sharing risks and rewards with the public sector. Saudi authorities see PPPs as a way to deliver projects efficiently while conserving public capital for other priorities. The Riyadh Metro, while government-funded during construction, will involve private operators for its operations and maintenance contracts. More directly, the upcoming Qiddiya rail link is planned as a PPP concession, with international firms invited to invest and bring innovative technology. The long-delayed Landbridge project, after earlier attempts, is now also expected to be executed via a PPP/BOT (build-operate-transfer) structure, overseen by Saudi Railway Company (SAR) and the Public Investment Fund (PIF).
Islamic Finance: Saudi Arabia’s leadership in Islamic finance makes sharia-compliant funding mechanisms a natural fit for its rail investments. Project sponsors and government-related entities have the option to issue sukuk (Islamic bonds) or use Islamic project finance structures to fund rail construction. These instruments attract capital from local and regional banks and funds that prefer sharia-compliant assets. For example, the PIF has raised billions through sukuk to support infrastructure development. Rail projects – which generate steady long-term cash flows and tangible assets – are well-suited to Islamic finance principles like asset-backing and profit-sharing. This approach also resonates with the cultural and religious context, making public support for these projects even stronger.
Sustainable Finance: Saudi Arabia is turning to sustainable finance to fund rail and transit as sustainability becomes a global investment theme. Green bonds and loans fund environmental projects and rail qualifies by cutting emissions. Through their green bond frameworks, the government and PIF have issued multibillion-dollars bonds that include clean transport. By identifying projects aiming to improve environmental outcomes, Saudi Arabia can tap into the growing pool of internal ESG-focused investors who are eager to finance low-carbon infrastructure. This can potentially lower borrowing costs and enhance the kingdom’s image as a sustainable development champion. Additionally, global development banks and export credit agencies have shown interest in supporting Gulf rail projects on climate grounds. For instance, a significant portion of the Riyadh Metro’s rolling stock and systems was financed via export credits, and future rail lines could attract sustainable development loans.
Transforming transport
The time is ripe for rail – it addresses urgent urban challenges and propels the kingdom toward its Vision 2030 objectives of sustainability, connectivity and diversified growth. As of October 2025, Saudi Arabia’s rail sector has a clear baseline: strong urban demand and Vision 2030 policy direction; a proven Haramain high-speed corridor; the six-line Riyadh Metro; and a pipeline centered on the Landbridge, GCC links and connectors such as the Q-Express. The kingdom has set targets to raise public transport’s share from 1% to 15% by 2030 and plans to add more than 8,000km of track under the NTLS. Financing pathways are established with early application on major assets. Together, these facts define the current state and provide a benchmark against which delivery, ridership, emissions and broader economic outcomes can be measured as projects move from plan to operation.

Exclusive from Meed
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
-
What actually slows a gigaproject down9 September 2026
-
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026
-
Jordan tenders advisory for wastewater treatment plant9 September 2026
-
Consultants bid for Abu Dhabi light rail project management9 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
Register for MEED’s 14-day trial access
Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.
Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.
The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.
Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.
At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.
US strikes on Iranian tankers
US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.
The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.
Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.
The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.
Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.
Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.
The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.
Houthi attacks raise supply concerns
The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.
On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.
Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.
The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.
Riyadh condemns attacks
Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.
In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.
Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg -
What actually slows a gigaproject down9 September 2026

Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.
“None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.
For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.
“The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.
The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.
“Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”
Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.
Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.
Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.
“The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”
Integration needs to be well understood
“Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.
Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.
Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.
“The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”
That shared view, he argues, will be what the next phase of Gulf delivery is judged on.
Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.
“This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.
From reporting progress to managing risk before it lands
Digital tools have a role here, Caldwell says, but not as a headline in themselves.
Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.
“The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."
None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”
Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.
With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.
“The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.
What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.
“The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif -
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026

Register for MEED’s 14-day trial access
Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.
The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.
The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.
Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.
US-based architect Populous is the project consultant.
The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg -
Jordan tenders advisory for wastewater treatment plant9 September 2026
The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.
The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).
The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.
The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.
The submission deadline is 21 September.
The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.
The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.
The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.
WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.
The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.
The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg -
Consultants bid for Abu Dhabi light rail project management9 September 2026

Register for MEED’s 14-day trial access
Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.
The notice was issued on 7 September, with a submission deadline of 9 November.
The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.
The key sections of the tram are:
AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.
This section covers 13km and includes 13 at-grade stations and one underground station.
Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.
Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.
The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.
The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.
Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.
Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.
Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.
The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.