Neom Green Hydrogen mulls next phase

23 November 2023

 

Neom Green Hydrogen Company (NGHC) received the first set of wind turbines for one of the two renewable energy plants that will power its integrated green hydrogen and ammonia production facility in early October.

The initial panels for the project’s solar power plant and hydrogen storage tanks are expected to arrive soon. The first air separation units, meanwhile, will be delivered in the first quarter of 2024.

“We are on track to meet our 2026 target commercial operation date, with the first ammonia production expected sometime between mid to late summer of 2026,” David Edmondson, CEO of NGHC (pictured), tells MEED.

Announced in the summer of 2020, the region’s first, and probably the world’s largest, green hydrogen and ammonia production facility reached financial close in May this year. The project required a final investment of $8.4bn.

“The decision to develop the project was made in 2019 in the strong belief that there would be a market for green hydrogen,” explains Edmondson.

“Having Air Products was certainly a major factor in that decision because of their hydrogen knowledge and experience. They already have an existing infrastructure for the production and distribution of hydrogen, including for mobility.”  

The US-headquartered industrial gases firm, Saudi utility developer and investor Acwa Power and Public Investment Fund-backed Neom equally own NGHC.

The scale of the integrated project is unprecedented. It will require over 4GW of wind and solar power and 400MW of battery energy storage systems. A 190-kilometre electricity transmission grid will link these to a 2GW electrolysis plant in Neom’s Oxagon industrial city.

The plant will produce up to 600 tonnes of hydrogen daily, which will be converted into roughly 1.2 million tonnes of ammonia a year. Air Products will ship the ammonia to Europe to be cracked back to hydrogen for mobility applications.

Despite some pushback on the business model's efficiency and the feasibility of green hydrogen applications in transport and mobility, Edmondson assures MEED that years of due diligence and compliance with EU carbon intensity policies support the business case. Twenty-three banks are financing the project, he points out.

“The NGHC plant is designed to ensure that the carbon intensity of the end product will be beneath the required threshold in Europe,” he says.

Edmondson acknowledges the premium costs currently involved in a low-carbon-intensity supply chain. However, this is expected to change as companies implement their net-zero commitments and suppliers scale their production to meet rising demand.

Air Products’ key role

In addition to being the exclusive offtaker for over 30 years for the green ammonia produced at the plant, Air Products is also the project’s main engineering, procurement and construction (EPC) contractor.

The firm’s triple role as an equity investor, EPC contractor and offtaker ensures that “we keep the focus on lowest cost of green hydrogen or ammonia”, notes Edmondson.

“Despite being the EPC contractor and a major investor in NGHC, Air Products’ primary objective is to generate revenue out of selling the ammonia that they have agreed to offtake from NGHC, not through the EPC contract,” he adds.

Phase two

With construction well under way for the integrated Neom green hydrogen and ammonia project, NGHC and its shareholders are now looking at a potential second phase.

“The Neom green hydrogen project is not expected to be a single investment,” says Edmondson.

“With all the ammonia to be produced at the plant under construction already sold to Air Products, there remains an interest in looking at additional investments for both the export market as well as the local market requirements for green hydrogen.”

Neom, which aims to be carbon-free and 100 per cent powered by renewable energy, is considering alternative fuels such as green hydrogen to achieve that goal.

Potential applications include mobility, given the plan to develop a rail system and other modes of transport for Neom.

“There was no domestic demand for green hydrogen fuel when the project was originally conceived in 2019. The market is continuing to evolve and we now see a stronger business case for local supply of green hydrogen,” says Edmondson.

The next phase is envisaged to be another large-scale project addressing domestic and international demand for green hydrogen and green ammonia.

Edmondson says more serious discussions about the project’s next phase will be on the agenda in 2024.

Ongoing innovation

The groundwork for the more widespread adoption of green hydrogen in Neom and across Saudi Arabia is under way.

In 2024, Neom’s energy and water subsidiary Enowa will open the Hydrogen and Innovation Development Centre (HIDC), which aims to produce and adopt decarbonised and clean synthetic fuels in partnership with Saudi Aramco. 

Initially, the NGHC project at the HIDC will gather operational data from the facility’s first 20MW electrolyser from Germany’s ThyssenKrupp Nucera, which will be used at the NGHC plant.

This will help advance Enowa’s plans with Air Products Qudra to test advanced hydrogen fuel cell-based mobility and logistics solutions at Neom. 

Neom factor

As a trailblazing project, Edmondson recognises the many opportunities that Neom has provided.

“We have had excellent support from Neom on both our land and permitting requirements as we have developed the project,” he says.

“We have also benefitted from legislation that allowed the first private grid in the kingdom and were granted the first industrial licence in Saudi Arabia for a green hydrogen plant.

“Neom has certainly risen to the challenge of supporting investors to make the project a reality.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/11317662/main2557.jpg
Jennifer Aguinaldo
Related Articles
  • Chinese and Saudi partners set up Hithium Manat

    17 October 2024

    Register for MEED's 14-day trial access 

    Chinese energy storage solutions firm Hithium Energy Storage Technology Company (Hithium) and the local Nabilah AlTunisi have formed a joint venture that will manufacture battery energy storage systems (bess) in Saudi Arabia.

    The joint venture is called Hithium Manat. The planned manufacturing facility has an annual production capacity target of 5 gigawatt-hours (GWh), according to an official statement.

    Hithium launched energy storage solutions designed for the region's harsh environment during a solar and storage conference held in Riyadh.

    According to Hithium, "These systems feature advanced sandstorm protection and robust high and low-temperature designs, supporting ultra-long discharge cycles of 12+ hours."

    It added that the new product line is "customised to meet the unique demands of the Middle East and Africa region".

    Nabilah AlTunisi is the founder and owner of Hithium Manat's local partner.

    "This strategic alliance will not only provide access to world-class energy storage technology but also generate local employment opportunities, stimulate technological innovation and actively contribute to realising the kingdom's Vision 2030 objectives," AlTunisi said.

    Battery energy storage market

    In August, National Grid Saudi Arabia, a subsidiary of state utility Saudi Electricity Company, awarded the engineering, procurement and construction (EPC) contracts for three energy storage systems to Riyadh-based investment group Algihaz Holding. The estimated $800m projects are located in Najran, Madaya and Khamis Mushait.

    National Grid also recently tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW across the kingdom.

    The planned facilities, each with a capacity of 500MW or roughly 2,000 megawatt-hours, are located in or within proximity of the following key cities and load centres:

    • Riyadh
    • Qaisumah
    • Dawadmi
    • Al-Jouf
    • Rabigh

    Every utility in the region is procuring or planning to procure bess capacity in light of growing intermittent renewable power in their grids. 

    The overall capacity of deployed bess globally is expected to reach 127GW by 2027, up from an estimated cumulative deployment of 36.7GW at the end of 2023, a GlobalData report issued in June said.

    The report cited Chinese companies BYD and CATL and South Korean companies LG Energy Solutions and Samsung SDI among the top battery technology providers globally.

    Related read: Battery storage gains foothold

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742375/main.jpg
    Jennifer Aguinaldo
  • Kahramaa invites Ras Laffan substation bids

    17 October 2024

    Qatar state utility General Electricity & Water Corporation (Kahramaa) has tendered a contract to upgrade the Ras Laffan C substation.

    The scope of work covers the upgrade of existing 220-kilovolt (kV) and 400kV substations and the addition of 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.

    Kahramaa issued the tender on 15 October and expects to receive bids by 28 November.

    The project bid bond is valued at QR1.5m ($410,000).

    Separately, Kahramaa invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.

    Kahramaa expects to receive bids for this contract, with a bid bond of QR3m, by 14 November.

    Kahramaa is expanding its power generation capacity. Negotiations are under way with the sole bidder led by Japan's Sumitomo Corporation for a contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day.

    Earlier this month, Qatar Electricity & Water Company announced plans to develop a 500MW peak power unit in Qatar's Ras Abu Fontas area.

    Construction is also under way for two solar farms with a total combined capacity of 875MW in Mesaieed and Ras Laffan.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742343/main.jpg
    Jennifer Aguinaldo
  • Neom starts Tabuk highway prequalifications

    17 October 2024

     

    Saudi Arabian gigaproject developer Neom expects firms to submit their prequalification applications for a project to build a mountain road near Tabuk later this month.

    The 11.5-kilometre (km) Tabuk mountain road project comprises a 4km tunnel and 7.5km dualisation of an existing road, according to an industry source.

    Neom expects to receive statements of qualifications from interested engineering, procurement and construction contractors by 29 October.

    The tender proceedings for Neom's transport infrastructure projects are gathering momentum.

    Neom received expressions of interest for a contract to build a coastal highway and infrastructure project catering to the Magna development on the Gulf of Aqaba on 15 October.

    The project, called Magna Infrastructure Packages, is split into three. Package one is 13km, package two is 42km and package three is 41km. The packages cater to the development’s north, central and south areas.

    The design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways, in addition to the coastal highway. The project is expected to be completed by 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12738632/main.gif
    Jennifer Aguinaldo
  • Adnoc completes Fertiglobe stake acquisition

    16 October 2024

    Register for MEED's 14-day trial access 

    Abu Dhabi National Oil Company (Adnoc) has completed the transaction to acquire a majority stake in UAE-headquartered Fertiglobe, the largest nitrogen-based fertiliser producer in the Middle East and North Africa region.

    Adnoc has increased its shareholding in Fertiglobe to 86.2% through the acquisition of 50% + 1 share held by Netherlands-based OCI Global, which is backed by Egyptian billionaire Nassef Sawiris. The Abu Dhabi energy giant previously held a 36.2% stake in Fertiglobe.

    The remaining 13.8% of Fertiglobe’s shares trade on the Abu Dhabi Securities Exchange following the company's stock listing in October 2022.

    Adnoc announced the transaction to become the majority shareholder in Fertiglobe last December. Fertiglobe’s shares were priced at AED3.2 ($0.87) a share, valuing the deal at $3.62bn.

    Following the completion of the majority acquisition, “Fertiglobe’s current management team will stay in place”, including Ahmed El-Hoshy in his role as CEO, Adnoc said in a statement on 15 October.

    “Ahmed El-Hoshy spent 15 years growing OCI’s US and European business in ammonia and methanol via greenfields, brownfields and acquisitions, generating significant value for shareholders by leading recent divestments,” Adnoc said.

    Growing chemicals business

    Fertiglobe is the world’s largest seaborne exporter of urea and ammonia combined, exporting to 53 countries with a collective market share of about 10% of global trade in these products.

    “The acquisition represents … the expansion of Adnoc’s low-carbon fuels business, and supports its goal to become a top-five global chemicals player,” Adnoc said.

    “Fertiglobe will become the platform for Adnoc’s growth in fertiliser and low-carbon ammonia,” Adnoc said in its statement.

    Adnoc added it will transfer its stakes in existing and future low-carbon ammonia projects to Fertiglobe “at cost and when ready for startup”, including its two projects in Abu Dhabi and other projects in its global portfolio. Adnoc has yet to specify the low-carbon ammonia and blue ammonia production projects.

    MEED understands that the first Abu Dhabi project in question is the blue ammonia facility in the Taziz Industrial Chemicals Zone in Ruwais. Fertiglobe has partnered with South Korea’s GS Energy Corporation and Japanese investment firm Mitsui & Company to build the complex, which will have a production capacity of 1 million tonnes a year (t/y).

    In February last year, the joint venture awarded Italian firm Tecnimont the main contract for executing the engineering, procurement and construction works on the Taziz blue ammonia project.

    The second Abu Dhabi blue ammonia project that Adnoc could be referring to in its statement is a proposed scheme for which it signed a joint feasibility study agreement with British energy producer BP in May 2022.

    Adnoc further said that the two projects in Abu Dhabi will add 2 million t/y of output potential, more than doubling Fertiglobe’s current commercial ammonia capacity of 1.6 million t/y and increasing its total sellable capacity to 8.6 million t/y of net ammonia and urea combined, in addition to other announced global projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12735570/main1542.jpg
    Indrajit Sen
  • Neom receives interest for Magna coastal highway

    16 October 2024

     

    Saudi Arabia’s gigaproject developer Neom has received interest from firms for the contract to build a coastal highway and infrastructure project linking Neom to the Magna development on the Gulf of Aqaba.

    The project, called Magna Infrastructure Packages, is split into three. 

    Package 1 is 13 kilometres, package 2 is 42km and package 3 is 41km.

    The packages cater to the development’s north, central and south areas.

    According to an industry source, the design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways. It could cost between $250m and $500m.

    Local and international engineering, procurement and construction (EPC) contractors are understood to have submitted their expressions of interest to participate in the tender on 15 October.

    The coastal highway and infrastructure project is expected to be completed by 2027, the source said.

    Magna consists of 12 developments featuring 15 hotels that offer 1,600 hotel rooms, suites and apartments and over 2,500 residences.

    The development will span a 120km-long coastal strip with an average width of 3.5km. The total land area is about 430 square kilometres.

    The Magna infrastructure is divided into six districts, as follows:

    • District 1 – Northern Gateway: includes 13 bridges and underpasses with a length of 1.9km, 18 wadi culverts and five drainage culverts
    • District 2 – Romantic Bay and the Cube: includes two bridges and underpasses spanning 360 metres, 40 wadi culverts and 24 drainage culverts
    • District 3 – Wadi Tayyib: includes two bridges and underpasses, 26 wadi culverts and nine drainage culverts
    • District 4 – Jungle Club: includes three bridges and underpasses and 17 wadi culverts
    • District 5 – Magna: includes two bridges and underpasses, 14 wadi culverts and two drainage culverts
    • District 6 – Southern Gateway: includes three bridges and underpasses, 31 wadi culverts and one drainage culvert
    https://image.digitalinsightresearch.in/uploads/NewsArticle/12735899/main.jpg
    Jennifer Aguinaldo