Risks remain for GCC railway project

28 August 2023

 

Register for MEED's guest programme 

When the GCC secretariat agreed to restart the GCC Railway Project in 2021, it set the tone for one of the region’s most ambitious transnational projects.

The endeavour aims to connect the six Gulf nations with a sprawling railway network that will be a game-changer for the region’s infrastructure. The potential to boost trade, connectivity and regional economic development is enormous. 

But risks and challenges also lie ahead, including cost overruns and technical risks related to the project design, engineering and complexity that must be assessed, managed and monitored to ensure the project’s successful delivery.

Political risks

Political factors play a significant role in the development and operation of the GCC railway. Given that the network will traverse multiple geographies, one of its biggest tests is manoeuvring through the regional political landscape.

First and foremost among political considerations is the level of cooperation and diplomatic relations between the member states. The railway’s seamless operation relies on harmonised regulations, standard operating procedures and open communication between nations, as well as geopolitical stability. 

In this respect, the Al-Alu agreement of 2021 is key, as it laid the strong foundations for a more robust mechanism to ensure better cooperation between the GCC countries.

“The Qatar blockade was a big challenge to manage and the GCC countries have seen the consequences of the situation,” Alexandre Busson (right), director of rail, Hill International, tells MEED.

“They realised that there was no benefit in it for the region. So the Al-Ula declaration is really important.”

But while the agreement mitigates the political risk related to the GCC railway project to some extent, the potential for geopolitical tensions or disputes between the involved states remains and could impede the project’s progress by delaying decisions, complicating negotiations and disrupting work.

The GCC countries' wide-ranging economic interests and priorities could also impact their commitment to the railway project. Member states will need to consider their existing investments in other forms of transportation infrastructure, such as ports and highways. Balancing these interests requires careful negotiations and alignment of economic visions.

PPP contracts are more complex to negotiate and manage. But it [will be] very interesting to see how it goes because a successful PPP project could lead to the opening up of the market
Alexandre Busson, Hill International

Financial risks

The enormity of the GCC Railway Project becomes apparent when considering the huge costs involved. Laying tracks spanning six countries and crossing diverse terrains and urban areas, building stations, installing signalling systems and ensuring the safety of the network demands billions of dollars’ worth of investment.

With the financial stability of GCC nations closely tied to the global oil market, fluctuations in oil prices could significantly impact the ability and political will of governments to allocate funds to the GCC Railway Project.

“When GCC countries budget for infrastructure projects, they are very conservative with regards to the oil price in their budget,” says Busson. “And in terms of projects financing, they realise [the need] to diversify the economy and not be too dependent on oil prices.” 

Nevertheless, economic diversification plans mean each GCC nation faces its own set of budget constraints and priorities. Regional governments must juggle allocating limited funds to sectors such as healthcare, education, defence and infrastructure. The GCC Railway Project’s financial demands could strain these budgets, potentially diverting resources away from critical sectors.

To bridge the financial gap, governments are likely to explore a combination of public financing and private investment. Public-private partnerships (PPPs) have attracted interest from large-scale infrastructure projects in the region and the GCC railway will be no different. Luring private investors, however, requires a stable and attractive investment environment, coupled with clear revenue-generation models and risk-sharing agreements.

“The PPP model is quite new in the GCC. Even more so in transport,” says Busson. “Those kinds of contracts are more complex to negotiate and manage. But it [will be] very interesting to see how it goes because a successful PPP project could lead to the opening up of the market.”

You need to look at the consortium members and say, do we have the right balance within that particular consortium to be able to manage this project
Christopher Harding, Hill International

Technical risks

The technical risks of rail systems running across international borders are well documented. Examples include the Tan-Zam railway between Tanzania and Zambia and the rail link connecting Spain and France, where the adoption of different gauges meant construction was fraught with technical difficulties when joining the networks to each other.

“Inaccurate or complex specifications sometimes lead to extra efforts [needing] to be put into the interface management and getting interface agreements between the contractors,” explains Christopher Harding (right), a senior project management professional currently working on the Cairo Metro project for US-based consultant Hill International.

“That leads to claims from contractors and hence may lead to cost overruns.”

The complexity of the GCC Railway Project raises the stakes when it comes to technical risks. Meticulous planning and implementation will be required to ensure seamless connectivity across deserts, mountains and coastal areas, while the need for bridges, tunnels and viaducts to overcome geographical obstacles demands robust engineering solutions. 

Addressing these engineering risks requires a comprehensive understanding of the local environment, as well as innovative and consistent engineering techniques.

“There needs to be a common policy on the control systems for each country and how they talk to each other,” says Harding.

The involvement of multiple contractors will bring contractor-related risks too. Coordination between these entities will be key, as delays in one segment could cascade through the entire network, causing misalignments and operational bottlenecks.

“You need to look at the consortium members and say, do we have the right balance within that particular consortium to be able to manage this project,” says Harding.

Another significant challenge will be maintaining uniform quality standards across the contractors working on the GCC Railway Project to prevent differing construction techniques, materials and safety practices from potentially compromising the railway’s overall integrity and efficiency. 

“The rules around aspects like recruitment localisation, In-country Value (ICV), In-Kingdom Total Value Add (IKTVA) and regional headquarters requirement could be a challenge for new companies,” adds Busson.

The establishment of the GCC Railway Authority to oversee the overall implementation of the project will go some way towards resolving the technical issues outlined here. The authority is tasked with ensuring common standards and specifications, and supervising the railway’s interoperability and regional integration.

For the project to succeed, the authority must develop robust risk management strategies, effective communication channels among contractors, stringent quality control measures and transparent procurement processes.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11099328/main.jpg
Yasir Iqbal
Related Articles
  • Tabreed finishes the year on a high

    17 December 2025

     

    Tabreed is consolidating its position as a leading regional district cooling provider following a series of major transactions and new concessions that will reshape its portfolio in the UAE and beyond.

    In 2025, the company completed the AED3.87bn ($1bn) acquisition of PAL Cooling Holding (PCH) in consortium with CVC DIF, and finalised the long-term district cooling concession for Palm Jebel Ali in Dubai as part of a joint venture (JV) with Dubai Holding Investments.

    The PCH deal will eventually add about 600,000 refrigeration tons (RT) of capacity across eight long-term concessions in Abu Dhabi, raising Tabreed’s total connected capacity by 13% to 1.55 million RT. The AED1.5bn Palm Jebel Ali JV will ultimately deliver a further 250,000RT.

    Speaking to MEED, Tabreed CEO Khalid Al-Marzooqi outlined how the company is integrating the newly acquired brownfield assets, developing greenfield projects and advancing a new generation of sustainable cooling solutions, including geothermal energy for data centres.

    Tabreed’s recent milestones span both greenfield and brownfield investments, each requiring a different approach, says Al-Marzooqi. 

    Greenfield projects, such as Palm Jebel Ali, remain Tabreed’s preferred route for new capacity, he adds. “The beauty of a greenfield is that you can optimise it the way you want. You build it as you want.” 

    For new plants, Tabreed designs the civil structure to accommodate long-term capacity, while phasing in mechanical equipment in line with demand. By contrast, the acquisition of PCH is a large-scale brownfield integration, bringing in a portfolio of existing and future plants and networks, mainly on Abu Dhabi’s main island and Reem Island.

    The immediate focus is on integration and driving network synergies. “That’s the beauty of district cooling. If you achieve the synergies, the benefits literally double up and triple up as well,” Al-Marzooqi says.

    By interconnecting plants, Tabreed can avoid building for peak capacity at each individual site and instead leverage shared spare capacity across the network.

    Growth strategy

    Acquiring a competitor in Abu Dhabi is part of a strategy to sustain growth in a sector where many contracts follow build-own-operate-transfer or similarly time-bound models.

    Organic growth via new concessions and inorganic growth via acquisitions are both seen as key to maintaining and expanding the asset base.

    Tabreed’s portfolio remains weighted towards the UAE, with the home market accounting for the bulk of its business. 

    Beyond the UAE, Tabreed has built a regional presence, with a partially owned business in Saudi Arabia, where it sees significant growth potential as district cooling is integrated into gigaprojects and major urban developments; a wholly owned operation in Bahrain; and a majority stake in Tabreed Oman, a market that Al-Marzooqi says is expanding well.

    Despite the energy and lifecycle cost benefits of district cooling, Al-Marzooqi says tariff subsidies on conventional, building-level cooling are a barrier to adoption in parts of the UAE.

    “The killer for us is subsidy,” he says, explaining that artificially low tariffs for individual customers make it harder for district cooling to compete on price in Abu Dhabi compared to Dubai.

    He says that policy support and regulatory mandates are needed, particularly as existing buildings approach the end of life for their standalone cooling systems. At that point, compulsory connection to district cooling could lock in significant energy savings and emissions reductions at city scale.

    Raising Abu Dhabi’s district cooling penetration from about 15% towards Dubai’s estimated 30% remains a key concern and strategic objective.

    In Abu Dhabi, Tabreed has developed … the Middle East’s first geothermal-powered district cooling plant

    Geothermal breakthrough

    Alongside portfolio growth, Tabreed is investing in new technologies to decarbonise cooling, with a focus on large campuses, major developments and, increasingly, data centres.

    At Masdar City in Abu Dhabi, Tabreed has developed what Al-Marzooqi describes as the Middle East’s first geothermal-powered district cooling plant. 

    “We have started off by building the region’s first geothermal plant, to prove the concept of using geothermal energy to provide cooling,” he says. 

    The pilot plant is already achieving efficiency levels in the range of 0.5-0.6 kilowatts per ton (kW/ton) of cooling, better than Tabreed’s typical district cooling benchmark of about 0.85kW/ton. Conventional, standalone cooling systems generally consume about twice as much energy per ton.

    “This is proof that if you really want to pursue a sustainable cooling solution for data centres in this area, this is the one,” he says.

    Data centres are emerging as a priority growth segment for Tabreed. The facilities have high, continuous cooling loads and increasingly stringent decarbonisation requirements, making them a natural fit with both district cooling and geothermal systems.

    Al-Marzooqi says geothermal cooling is a “godsend solution” for data centres, combining 24/7 availability with the potential for near-zero operational emissions.

    For hyperscale and colocation data centre operators facing mounting pressure to reduce their carbon footprint, geothermal district cooling could offer a differentiated, long-term solution in the Gulf region, particularly where grid power is still largely fossil-fuel based.

    Tabreed’s technology agenda is not limited to low-carbon generation. The utility is in the second phase of connecting its plants to a centralised digital control centre, enabling remote operation and optimisation.

    The long-term goal is for the majority of plants to be unmanned, with operations centrally monitored and controlled. This integrated view of the network will enable the application of artificial intelligence and advanced analytics to fine-tune performance, optimise energy use and predict maintenance requirements. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15266676/main.gif
    Colin Foreman
  • Kuwait Oil Company seeks higher project budgets

    17 December 2025

     

    Contractors in Kuwait expect to have answers by the end of the year on whether budgets for several key upstream projects in the oil and gas sector will be increased, according to industry sources.

    State-owned upstream operator Kuwait Oil Company (KOC) is seeking approvals for at least three upstream projects, for which bids came in significantly over budget.

    The first project, with a low bid of $2.47bn, involves the development of two facilities: Separation Gathering Centre 1 (SGC-1) and Water Injection Plant 1 (WIP-1).

    The second project, with a low bid of $2.48bn, focuses on developing SGC‑3 and WIP‑3.

    The third project, which involves developing effluent water disposal plants for injector wells, had a low bid of $1.3bn.

    For KOC to increase the budgets for all three projects, approvals will be required from Kuwait Petroleum Corporation (KPC) and the country’s Ministry of Finance.

    Already cancelled

    One Kuwaiti oil project tender that received bids significantly above budget has already been cancelled.

    On 7 October, MEED reported that the tender for the SGC-2 oil project – focused on the installation of a separation gathering centre – was cancelled by Kuwait’s Central Agency for Public Tenders.

    Earlier this year, UK-based Petrofac had submitted a bid more than double the project’s proposed budget.

    Petrofac’s bid was KD422.45m ($1.37bn), while the provisional budget stood at KD207m ($670.2m).

    This contract is expected to be retendered, but there is significant uncertainty about when a new invitation to bid will be issued and how the scope may change.

    Earlier in December, MEED reported that KOC was discussing whether to retender the contract using a different contract model.

    Initially, the project was tendered using the engineering, procurement and construction (EPC) contract model.

    Discussions are ongoing on whether it will be relaunched under a build-own-operate (BOO) contract model.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15263996/main.png
    Wil Crisp
  • Morocco awards $185m Guercif-Nador road contracts

    17 December 2025

     

    Morocco’s Ministry of Equipment, Transport, Logistics & Water has awarded three contracts totalling MD1.7bn ($185m) for building three lots of the 40-kilometre (km) section two of the Guercif to Nador highway between Saka and Driouch.

    The contracts were awarded to local firms.

    Casablanca-based Groupe Mojazine won a $64m contract for lot one, which covers the construction of 14km of highway.

    The other two contracts covering construction works on lots two and three were awarded to the local firm Bioui Travaux.

    The contract value for lot two is over $56m and covers the 12km highway section. The lot three contract is worth about $69m and covers 40km of highway construction.

    The 104km Guercif to Nador highway is being implemented in three sections. Prequalification for section two from Saka to Driouch was completed in June, as MEED reported.

    The estimated $700m project, partly funded by the African Development Bank, is part of the kingdom’s plans to upgrade its public infrastructure in preparation for co-hosting the 2030 Fifa World Cup alongside Portugal and Spain. The programme includes the expansion of over 1,000km of highways.

    In May, Societe Nationale des Autoroutes du Maroc awarded MD5bn ($540m) of contracts for nine packages covering construction works on the Rabat-Casablanca continental expressway.

    Morocco’s construction and infrastructure sector is gearing up for billions of dollars in projects as the North African nation continues to award contracts for building infrastructure for the 2030 Fifa World Cup.

    Morocco has made a strong head start in ensuring that the necessary infrastructure is ready for the tournament.

    According to data from regional project tracker MEED Projects, 2024 was the best year in the past decade for construction and transport contract awards in Morocco, with contracts worth over $3.6bn signed with local construction firms and international companies from South Korea, China, France and Spain.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15266606/main.jpg
    Yasir Iqbal
  • Egypt plans $5.7bn oil and gas exploration campaign

    17 December 2025

    Egypt plans to drill 480 exploratory wells, with total investment estimated at $5.7bn, over the next five years, according to Karim Badawi, the country’s minister of petroleum and mineral resources.

    Speaking at a conference in Cairo, Badawi said that Egypt’s oil and gas sector was stabilising after a period of decline.

    He said that his ministry was targeting an increase in gas production for the first time in four years.

    The government is also aiming for self-sufficiency in crude oil production within five years, he said.

    Egypt is aiming to boost crude production by introducing investment incentive packages and utilising new production technologies.

    Badawi highlighted specific capital commitments from international partners to develop oil and gas resources over the next five years. These included Italian company Eni’s commitment to invest $8bn, as well as London-headquartered BP’s plan to invest $5bn.

    He also highlighted Arcius Energy’s plan to invest $3.7bn. Arcius Energy is a joint venture of BP and Adnoc’s XRG.

    The $5.7bn exploration programme includes 101 wells scheduled for drilling in 2026.

    Badawi said that seismic survey operations would expand to cover 100,000 square kilometres in the Western Desert and 95,000 square kilometres in the Eastern Mediterranean using Ocean Bottom Node (OBN) technology.

    Renewable energy strategy

    Addressing the national energy strategy, Badawi said the government aims to increase the share of renewable energy in electricity generation to 42% by 2030.

    He said this would enable natural gas to be redirected to value-added industries, such as petrochemicals and fertilisers, to boost exports.

    On the transition to green energy, the minister cited plans to reduce reliance on traditional fuels and open investment in sustainable aviation fuel (SAF), green ammonia and bioethanol.

    Efficiency measures in the sector have already reduced carbon emissions by 1.4 million tonnes, he said.

    Recently, Egypt announced a $200m deal with Qatar to produce aviation fuel from used cooking oil.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15264077/main0508.jpg
    Wil Crisp
  • Saudi Arabia to award Abha airport expansion by March

    17 December 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Civil Aviation Holding Company (Matarat) and the National Centre for Privatisation & PPP (NCP) are expected to award the contract to develop and operate a new passenger terminal building and related facilities at Abha International airport by March next year.

    The announcement was made by Abdulaziz Al-Duailej, president of the General Authority of Civil Aviation (Gaca), at the Supply Chain and Logistics Conference 2025 in Riyadh on Tuesday.

    The companies prequalified to bid for the contract are:

    • GMR Airports (India)
    • Mada TAV: Mada International Holding (local) / TAV Airports Holding
    • Touwalk Alliance: Skilled Engineers Contracting (local) / Limak Insaat (Turkiye) / Incheon International Airport Corporation (South Korea) / Dar Al-Handasah Consultants (Shair & Partners, Lebanon) /  Obermeyer Middle East (Germany/Abu Dhabi)
    • VI Asyad DAA: Vision International Investment Company (local) / Asyad Holding (local) / DAA International (Ireland)

    Located in Asir Province, the first phase of the Abha International airport public-private partnership (PPP) project will expand the terminal area from 10,500 square metres (sq m) to 65,000 sq m.

    In early March this year, the clients held one-on-one meetings with prospective bidders in Riyadh, as reported by MEED.

    The contract scope includes a new rapid-exit taxiway on the existing runway, a new apron to serve the new terminal, access roads to the new terminal building and a new car park area.

    Additionally, the scope includes support facilities, such as an electrical substation expansion and a new sewage treatment plant. 

    Construction is scheduled for completion in 2028.

    The project will be developed under a build-transfer-operate (BTO) model and involves designing, financing, constructing and operating a greenfield terminal.

    This will be the kingdom’s third airport PPP project, following the Hajj terminal at Jeddah’s King Abdulaziz International airport and the $1.2bn Prince Mohammed Bin Abdulaziz International airport in Medina.

    Higher capacity

    According to Matarat, Abha airport’s capacity will increase to accommodate over 13 million passengers annually—a 10-fold rise from its current 1.5 million capacity.

    Once completed, the airport will handle more than 90,000 flights a year, up from 30,000.

    The new terminal is also expected to feature 20 gates and 41 check-in counters, including seven new self-service check-in kiosks.

    The BTO contract duration is 30 years.

    The existing terminal, which served 4.4 million passengers in 2019, will be closed once the new terminal becomes operational.

    Matarat’s transaction advisory team for the project comprises UK-headquartered Deloitte as financial adviser, ALG as technical adviser and London-based Ashurst as legal adviser.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15264715/main.jpg
    Yasir Iqbal