UAE power sector shapes up ahead of Cop28

3 April 2023

This package on the UAE's power sector also includes:

Ewec rules out solar in desalination projects

Dewa receives K station bid

Dewa briefs 1.8GW solar bidders

Italian firms pursue energy transition roles

Majid al-Futtaim signs 36MW clean energy agreement

Abu Dhabi eyes power and water contracts extension


There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.

Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.

Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.

As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.

The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy

Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.

Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.

This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).

In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.

Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.

By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.

The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.

Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.

This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.

Dubai green story

Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa)  has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).

This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic. 

As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.

Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.

The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.

Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.

“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.

The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.

Diversification

The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.

The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.

The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10723958/main.jpeg
Jennifer Aguinaldo
Related Articles
  • Decarbonising the global energy grid

    3 May 2024

    As the effort to tackle the climate crisis continues, global demand for renewable energy has been increasing. Unfortunately, the windiest and sunniest parts of the world are not necessarily where the need for energy is highest. This is where transmission plays a big role, linking energy generation to energy use as a product of global interconnection, and diversifying production from renewable sources to create a steadier supply of clean power. 

    Transporting energy across vast distances is not easy though. From the regulatory complexities of navigating cross-border infrastructure projects to the high costs of financing and the need for long-term planning and advanced technical capabilities, the challenges involved in successfully deploying long-distance transmission projects are varied. Overcoming these challenges is not a single party affair, but requires close collaboration across government, industry and non-governmental organisations. 

    We conducted a study with nearly 600 industry experts from across the world who highlighted the pressing need for co-ordinated global action to rapidly develop grid infrastructure. Integrating renewable energy into existing grids was cited by participants as one of the most significant barriers to achieving net-zero objectives, alongside supply chain vulnerabilities and ability to access the required capital.

    Multiple challenges

    From a technical standpoint, there are multiple considerations when implementing cross-border interconnections. Regions can operate using different technical parameters, such as different voltages or frequencies. Even within the same country, interregional variations can create bottlenecks. Adopting regional or international grid codes could mitigate these issues.

    Further challenges emerge when we take trading into account. This is where regulation can act as an enabler, facilitating the flow of electricity between countries. The European Union’s efforts to co-ordinate the design of its member state’s energy markets enables an increasingly smooth transmission of energy across the continent. Alongside this, existing infrastructure is outdated, requiring significant upfront investment to upgrade. Clarity on regulatory requirements and more transparency around plans for grid buildout, derisk funding for capital-intensive mega projects.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy

    Positive benefits

    Despite these challenges, the upside must be stressed. Integrating power systems across borders has many positive societal benefits, decreasing costs and hence energy bills through economies of scale, increasing energy security and lowering the environmental impact of operations. On the latter more specifically, larger power systems are able to integrate higher shares of variable renewables. Globally, the sun is always shining and the wind blowing somewhere. 

    A common element, therefore, emerges: the need for increased cross-border co‑ordination. Whether it is bilateral, multi-lateral or unified, different models of inter-jurisdictional arrangements are needed for large-scale projects to support global energy interconnections. Our Xlinks project, which is using high-voltage direct current (HVDC) for transmission, is a standout example. 

    Such projects represent what is needed more in the world, the combination of infrastructure and renewable power across borders, bringing together the public and private sectors for energy security, supply and affordability in an environmentally friendly way. Transporting clean energy using HDVC cables is a crucial step in powering a net-zero and equitable future, and more of this is needed to aid the transition to lower-carbon and prosperous economies. 

    Political, technical and market hurdles can be overcome through collaboration and partnerships. Leveraging the collective expertise and resources of governments, regulators and the private sector can help ensure interconnections are developed quickly enough to support the energy transition. Grid buildout takes time. We have the resources required to meet ambitions, but stopping now is not viable. We must continue planning, building and maintaining large-scale infrastructure projects to meet the rising demand.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy. This was the message from Cop28 and the UAE Consensus: to help progress and secure a cleaner, brighter future for us all, we must break down barriers and come together. 

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11736994/main.gif
  • Libya allocates $1.2bn for upstream oil project

    3 May 2024

     

    Register for MEED's guest programme 

    Libya has allocated LD6bn ($1.23bn) to develop the Hamada NC-7 concession in its latest budget, which was approved by Libya’s eastern-based parliament on 30 April, according to industry sources.

    The field development project was previously estimated to be worth between $4bn and $5bn.

    The project aims to develop 2.7 trillion cubic feet of gas reserves in the NC-7 block of the Ghadames basin.

    A consortium led by Italy’s Eni and including France’s TotalEnergies and UAE-based Adnoc operates the block.

    Development of the field was included in the 2024 annual budget of LD90bn ($18.5bn), excluding an item for development projects, which the Benghazi-based government of Osama Hamad unanimously approved.

    Hamad came to power in March 2023 and is allied with the military commander Khalifa Haftar, who controls the east and large parts of the southern region of Libya.

    Progress on developing the Hamada NC-7 concession has been slow amid concerns among politicians about the involvement of foreign oil companies in key hydrocarbon assets.

    On 15 December 2023, the Tripoli-based Ministry of Oil & Gas issued a statement condemning the terms of the planned gas development contract between Libya’s state-owned National Oil Corporation (NOC) and the consortium led by Eni.

    In the statement, the Ministry of Oil & Gas described the deal as a “violation of Libyan legislation on oil contracts”.

    Earlier this year, NOC announced a plan to execute 45 greenfield and brownfield projects to try to boost the country’s oil production from 1.25 million barrels a day (b/d) to 2 million b/d.

    Farhat Bengdara, the chairman of NOC, said that the projects had a total estimated cost of $17bn-$18bn.

    Bengdara also confirmed plans to launch an oil and gas licensing round at the end of 2024 or early 2025.

    Libya is aiming to hit its 2 million b/d target within three years.

    Bengdara said that gas monetisation will remain a strategic focus as the country pushes to increase exports to Europe.

    Libya is only using 25% of the capacity of its Greenstream pipeline to Italy.

    The North African country also flares significant volumes of natural gas and has 12 projects under way that aim to reduce gas flaring to almost zero, according to Bengdara.

    In recent years, Libya has struggled to execute large projects amid significant political instability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11735260/main.gif
    Wil Crisp
  • GE Vernova invests in Xlinks

    2 May 2024

    US-headquartered GE Vernova has invested $10.2m in Xlinks First, the investment company established by UK-based startup Xlinks to deliver the $18bn Morocco-UK power project.

    This investment equates to a minority shareholding in the company, which is developing a project comprising wind and solar generation as well as battery storage, with a total combined capacity of 3,600MW, to be transmitted from Morocco to the UK.

    Xlinks said the investment will “further accelerate delivery and buildout of the project”.

    GE Vernova joins at least four other investors in the project.

    Other investors include Africa Finance Corporation, which invested $14.1m in April; Abu Dhabi National Energy Company (Taqa), $30.7m; the UK’s Octopus Energy, $6.23m; and France’s Total Energies, $25.4m.

    The planned electricity generation and battery storage facilities, located in south Morocco, will be connected exclusively to the UK via 4,000-kilometre high-voltage, direct current (HVDC) cables.

    In December last year, Xlinks signed a contract with Canada-headquartered WSP to provide technical advisory services for the project.

    WSP will support Xlinks with route optimisation, power systems and interface management for the plan to construct the project.

    The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre HVDC cables.

    The HVDC network is envisaged to run from the UK’s south coast, passing France, Spain and Portugal undersea and then onshore to a planned solar and wind energy project in Morocco.

    This renewable energy-sourced electricity amounts to nearly 8% of the UK’s current requirements, equivalent to powering 7 million homes by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11734222/main5830.jpg
    Jennifer Aguinaldo
  • Awards buoy Oman’s green hydrogen strategy

    2 May 2024

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    Oman has awarded two additional land blocks designed to develop green hydrogen projects.

    The latest land block concessions in Dhofar were awarded to two consortiums. One comprises a team of France's EDF Group and EDF Renewables, with partners Japanese Electric Power Development Company (J-Power) and the UK-headquartered Yamna Company.

    Another team comprises UK investment firm Actis and Australian metals firm Fortescue.

    This brings the total number of land blocks awarded through the public auction process spearheaded by Hydrogen Oman (Hydrom) to four, exclusive of the four legacy initiatives signed or agreed upon already.

    *Budgets are MEED estimates if not publicly disclosed. Sources: MEED, Hydrom

    A limited gas supply and network strongly incentivises Oman to build a green hydrogen-centric downstream sector that will provide feedstock to domestic industrial plants and generate derivatives for the local and export markets.

    Stakeholders have implemented a strategy, including setting up an infrastructure company catering to these projects. The target is to generate 1 to 1.5 million tonnes a year (t/y) of green hydrogen by 2030 and 7.5 to 8.5 million t/y by 2050.

    The blueprint envisages a complete green hydrogen ecosystem, from the production of renewable energy and its distribution to electrolysis plants and hydrogen derivatives conversion plants to storage and export terminals.

    Omani ports' existing relationships with European stakeholders and growing alliances with other countries could also help seal future offtake agreements for the planned facilities.

    As things stand, the consortiums that won the land auctions and the legacy initiative partners provide much gravitas to Oman's green hydrogen programme. They comprise energy old guards such as BP and Shell that are keen to decarbonise, private companies aiming to balance their investment portfolios with clean energy investments, and offtakers or trading companies that are grappling with net-zero targets.

    Yet the most obvious question remains. Given the eye-popping foreign direct investments these complex projects entail, not all are likely to achieve a final investment decision within three years. This seems to be the window required for the projects to start production before 2030.

    But like any emerging industry, the risks can only be properly assessed and mitigated as the first projects move toward the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11733331/main.gif
    Jennifer Aguinaldo
  • Operationalise loss and damage fund says Al Jaber

    2 May 2024

    Steps must be taken to ensure a fully functioning Loss and Damage Fund, following an agreement at Cop28 to operationalise the fund, according to Cop28 President Sultan Al Jaber.

    “While delivering an agreement to operationalise the Fund at Cop28 was a huge breakthrough for climate progress more needs to be done,” Al Jaber said during the first board meeting of the fund on 30 April.

    The Loss and Damage Fund, which was first proposed in the 1990s, aims to help developing countries cope with the impact of extreme global warming events such as droughts and floods.

    Al Jaber cited the need to build a fully functioning fund, which will be endorsed at Cop29 in Baku, which will be “disbursing funds soon after and a Fund that delivers lasting, positive, socio-economic impact for decades to come."

    "While it took over three decades to establish this Fund, climate change has not stood still. Every region of the world is now vulnerable…the impacts of climate change are a clear and present danger to lives and livelihoods everywhere."

    Al Jaber’s message resonates closer home given the recent storms hitting the UAE, which brought some emirates to a standstill in mid-April.

    Heavy rainfall inundated Dubai and the Northern Emirates on 16 April, causing flooding and significant property and infrastructure damages.

    A total of $792m has been pledged for loss and damage funding arrangements – of which $662m has been pledged to the Fund to date – including a $100m contribution each from the UAE and Germany and $75m from the UK.   

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11732746/main.jpg
    Jennifer Aguinaldo