Managing risk in the GCC construction market
19 December 2025

The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.
Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.
MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.
The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.
Systemic risk
The regional market is characterised by several systemic issues that amplify risks for contractors.
The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.
Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.
Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:
> Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.
> Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.
> Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.

Supply-chain erosion
The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly.
Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.
The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.
Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.
The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is.
A 10-point checklist for contractors in 2026
|
1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract. |
|
2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement. |
|
3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing. |
|
4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects. |
|
5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement. |
|
6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues. |
|
7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client. |
|
8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively. |
|
9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit. |
| 10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need. Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site. |
MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:
Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com
Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com
Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com
Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com
IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com
White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com
Exclusive from Meed
-
-
UAE cuts trade and financial links with Iran19 August 2026
-
Abu Dhabi begins Dar Al-Funoon Saadiyat construction19 August 2026
-
Contractor wins Dubai Canal drainage deal19 August 2026
-
Maaden and Aramco sign deal to create joint venture18 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Libya and Tunisia reschedule joint oil and gas licensing round19 August 2026
The Libyan-Tunisian Joint Oil Exploration, Exploitation and Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.
The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.
Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.
The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.
Significant data are available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.
The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.
Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).
LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.
Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.
The key dates from the new schedule for the licensing round are:
- 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
- 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
- 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
- 31 December 2026: Bid round closes
- 8 January 2027: Bid submissions due
- 26 February 2027: Winning bidders notified
- 30 April 2027: Formal awards expected
Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.
Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.
A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.
Despite this, the field has remained undeveloped for over three decades.
One of the key challenges to developing the reserve is its high carbon dioxide content.
Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main.jpg -
UAE cuts trade and financial links with Iran19 August 2026
Register for MEED’s 14-day trial access
The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.
The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.
The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.
It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.
The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.
The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg -
Abu Dhabi begins Dar Al-Funoon Saadiyat construction19 August 2026

Register for MEED’s 14-day trial access
Abu Dhabi-based piling contractor APCC Piling & Marine Contracting has started the enabling works on Dar Al-Funoon, a cultural development near the Saadiyat Cultural District.
The project, commissioned by the Department of Culture & Tourism – Abu Dhabi, was designed by the late Canadian-American architect Frank Gehry.
The venue is scheduled to open in 2030.
MEED understands that the main contract bids are under evaluation and the project is slated for award soon.
The complex will feature a multipurpose hall with more than 2,000 seats, a 3,500-seat open-air amphitheatre, a 400-seat studio theatre and a 250-seat jazz venue, bringing total capacity to more than 6,000 across its performance spaces.
The venue will host leading international productions, delivering high-quality cultural experiences for audiences locally, regionally and globally.
Upon completion, it will become one of the region’s largest performing arts venues.
The project was announced by Sheikh Khaled Bin Mohamed Bin Zayed Al-Nahyan, Crown Prince of Abu Dhabi and Chairman of the Abu Dhabi Executive Council in June, as MEED reported.
During a review of the plans, he was briefed on the architectural concept and the development and construction phases, as well as the venue’s advanced technical capabilities, which are being designed to meet the highest international standards for staging major global productions.
The announcement is part of the ongoing development of Saadiyat Island, which already includes Louvre Abu Dhabi, Zayed National Museum, Natural History Museum Abu Dhabi, teamLab Phenomena Abu Dhabi and the upcoming Guggenheim Abu Dhabi.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18852155/main4145.jpg -
Contractor wins Dubai Canal drainage deal19 August 2026

Register for MEED’s 14-day trial access
Local firm Detech Contracting has won an engineering, procurement and construction (EPC) contract to upgrade and rehabilitate the East Dubai Canal stormwater system.
The project, known as TF-16-C1, is part of Dubai’s Tasreef strategic plan to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
According to a source, Lebanon's Khatib & Alami has also been appointed as a consultant on the project.The works will focus on upgrading existing stormwater infrastructure to increase capacity and improve reliability during heavy rainfall.
The scope includes upgrading the stormwater drainage system, laying pipelines and constructing manholes and gullies. It also includes the construction of pumping stations and diversion works, site clearance and other associated facilities.
In February, MEED reported that the municipality had invited consultants to qualify for a contract to supervise three stormwater drainage projects (TF-16-C1, TF-15-C2 and TF-13-C1)
China State Construction Engineering Corporation announced in July that it had won the EPC contract for the TF-15-C2 stormwater drainage network project located on Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
MEED understands contractor bids are still being evaluated for the TF-13-C1 project, which focuses on developing a drainage system for the Al-Marmum area.
Detech has been awarded several packages under the Tasreef programme in the past 18 months.
These include:
- TF-16-C1: upgrading and rehabilitation of East Dubai Canal stormwater system
- TF-15-C1: stormwater drainage system at Al-Wasl Road for communities west of Dubai Canal
- TF-05-C1: stormwater drainage system in Jebel Ali
- TF-04: stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road
- DS-419: Tasreef rainwater drainage network: West Deira stormwater system upgrade and rehabilitation
As MEED exclusively reported, the municipality recently issued a letter of award for the TF-15-C1 project, covering the construction of a stormwater drainage system on Al-Wasl Road and communities west of Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
This week, Dubai Municipality also issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.
The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.
All three have bid submission deadlines of 10 September.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18850438/main.jpg -
Maaden and Aramco sign deal to create joint venture18 August 2026
Register for MEED’s 14-day trial access
Saudi Arabian Mining Company (Maaden) and Saudi Aramco have signed a shareholders’ agreement to form a joint venture (JV). Maaden will hold a 51% stake in the JV, while Aramco will own the remaining 49%.
Before signing the shareholders’ agreement, the two Saudi state-owned companies signed a non-binding heads of agreement in January 2025 aimed at establishing the JV.
“Combining the strengths of two leaders in their respective fields, the JV will focus on copper and other minerals critical to the energy transition,” the two parties said in a joint statement.
The JV will focus on exploration across Zone 4, also known as the Transition Zone, within the Arabian Platform in Saudi Arabia. Spanning approximately 182,000 square kilometres – nearly 10% of the kingdom’s total land area – the expected exploration area stretches along a 100-kilometre-wide corridor running parallel to the Arabian Shield.
“It represents a major new opportunity for mineral discovery in the kingdom,” Maaden and Aramco said.
Copper, which is increasingly significant for electric vehicles, power networks, energy storage and renewable energy systems, will be a main focus of the JV.
Copper accounts for more than 20% of the $1.2tn mined-metals market. The copper market is currently valued at about $250bn and is projected to grow to more than $400bn by 2035.
The JV will also explore for other energy transition minerals, including zinc, lead and rare earth elements, “that are expected to be crucial to industries of the future”.
“Leveraging advanced computational algorithms, [artificial intelligence] AI, and high-performance computing, the JV intends to target areas most likely to contain copper and valuable minerals, accelerating the path from regional screening to target definition and discovery. This is expected to support long-term sector development, reinforce the kingdom’s role in the global minerals value chain, and help meet rising demand for transition minerals,” the partners said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18833329/main.jpg