Saudi water begins next growth phase

10 March 2023

 

Saudi Arabia’s National Water Strategy 2030 continues to drive investments in the kingdom’s water desalination, treatment and distribution sector.

The strategy aims to reduce the water demand-supply gap and ensure desalinated water accounts for 90 per cent of the national urban supply to reduce reliance on non-renewable ground sources.

The need to boost the security of supply amid rising demand, volatile costs and increased compliance with sustainability goals is also driving project activity – particularly in terms of using more energy-efficient technologies to convert seawater into potable water – as well as improving storage capacity.

As of March, an estimated 2.66 million cubic metres a day (cm/d) of water desalination capacity is under construction by the main water utility provider Saline Water Conversion Corporation (SWCC) and state water offtaker Saudi Water Partnership Company (SWPC). 

At least a further 2.4 million cm/d of capacity is under procurement using both the independent water producer (IWP) model, mainly through SWPC, and the engineering, procurement and construction (EPC) model, primarily via SWCC. 

Following the award of successive IWP contracts in 2019-20, SWPC paced the award of new contracts and also tendered new jobs in 2021-22.

As in most sectors and geographies, the Covid-19 pandemic and war in Ukraine impacted project finance costs and inflation in Saudi Arabia, both particularly relevant to IWP projects.

New developments in the latter part of last year and the first few months of 2023, including the imminent award of the contract to develop the Rabigh 4 IWP, indicate that SWPC is reestablishing its projects momentum.

Similarly, there has been increased activity in water desalination EPC projects being procured by SWCC, such as the proposed seawater reverse osmosis (SWRO) facilities in Shuaibah and Yanbu, which have a combined capacity of over 1 million cm/d.

These are in addition to the under-construction Jubail 2 SWRO plant, with a capacity of 1 million cm/d, and the 400,000 cm/d Shuqaiq 1 SWRO facility, whose main contracts were awarded in 2021 and 2020, respectively.

Along with meeting rising demand, these projects address the decarbonisation requirements of Saudi Arabia’s water sector, which the kingdom’s pledge last year to reach net-zero carbon emissions by 2060 has made more urgent.

This drive is highlighted by the Shuaibah 3 IWP project, for which a team led by Riyadh-headquartered utility developer Acwa Power won the directly-negotiated contract in 2022.

The 600,000 cm/d SWRO plant will replace the existing multi-stage flash (MSF)-based desalination unit that is being decommissioned in 2025 at the existing Shuaibah 3 independent water and power project (IWPP).

The Shuaibah 3 project was the lone IWP contract awarded by SWPC last year.

The same carbon emissions reduction incentive is driving the Yanbu 2 SWRO project. According to SWCC, the project aligns with improving the environmental impact of the desalination water unit of Yanbu phase 2.

Power & Water Utility Company for Jubail & Yanbu (Marafiq) owns the Yanbu 2 integrated water and power desalination plant, which came onstream in 2015. Like the Shuaibah 3 IWPP, the facility’s desalination unit utilises the older, energy-intensive MSF technology.

Saudi Arabia reinvigorates power sector

Other water PPP projects 

The procurement processes are proceeding simultaneously for several independent sewage treatment plants (ISTP), water transmission pipelines and water reservoir facilities being overseen by SWPC across Saudi Arabia.

SWPC tendered the first scheme under the third round of its ISTP programme in November. The Al-Haer ISTP will have a design capacity of 200,000 cm/d.

The tender is also expected in the first half of the year for the two other schemes under batch three, the Riyadh East and Khamis Mushait ISTP schemes.

At least five other ISTP projects are in the planning stage. 

In November, the Taif ISTP scheme, one of the first-round ISTP projects awarded in 2019, entered commercial operation. 

SWPC has received three bids for its first water transmission pipeline public-private partnership (PPP) project, which links Rayis in Medina to Rabigh in Mecca, with prequalification under way for three similar schemes.

Bids are due in April for the contract to develop the kingdom’s first independent strategic water reservoir (ISWR) project. The Juranah ISWR project will be implemented in Mecca, using a build, own, operate and transfer model. The project includes a water reservoir and associated infrastructure and facilities.

It supports Saudi Arabia’s goal to increase municipal water storage capacity to an average of seven days by 2030. In addition, the government aims to increase water storage capacity to an equivalent of 20 days of Hajj demand in Mecca and 40 days of Hajj demand in Medina by 2022. 

Two other IWTP schemes are planned for Mecca under SWPC’s 2020 seven-year planning statement.

Wastewater treatment

Over the past year, the kingdom’s chief wastewater collection and treatment firm, National Water Company (NWC), has tendered a series of contracts across governorates and provinces.

They include contracts for the construction of networks and pumping stations in Aziziyah in Mecca and other areas in Al-Khobar; three lifting stations and ejection lines with diameters of up to 700mm serving different areas in Jubail; and a sewage project in the King Fahd suburb in the Eastern Province and adjacent schemes west of Abu Hadriya Road in Dammam.

Requests for proposals (RFPs) have also been issued to complete sewage facilities in Al-Khafji governorate, West Safwa and Fayhaa.

These projects are part of NWC’s five-year, SR108bn ($29bn) investment plan for the kingdom’s water infrastructure. The latest five-year plan allocates an estimated SR39bn to Mecca, SR16bn to the Eastern Province and SR14.2bn to Riyadh.

The privatisation of NWC’s sewage treatment plant network is also being undertaken in parallel with improving its underlying infrastructure.

Under long-term operation and management (LTOM) agreements, private sector companies can bid to operate and upgrade water treatment plants.

The first package, for Mecca, was awarded in September 2022 to a team of the local Miahona and Thabat Construction Company. The rehabilitate-operate-transfer scheme is for 10 years and is valued at SR392m. Eight other packages are expected to be tendered under the LTOM programme.   


MEED's April 2023 special report on Saudi Arabia also includes:

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10660701/main.jpg
Jennifer Aguinaldo
Related Articles
  • Decarbonising the global energy grid

    3 May 2024

    As the effort to tackle the climate crisis continues, global demand for renewable energy has been increasing. Unfortunately, the windiest and sunniest parts of the world are not necessarily where the need for energy is highest. This is where transmission plays a big role, linking energy generation to energy use as a product of global interconnection, and diversifying production from renewable sources to create a steadier supply of clean power. 

    Transporting energy across vast distances is not easy though. From the regulatory complexities of navigating cross-border infrastructure projects to the high costs of financing and the need for long-term planning and advanced technical capabilities, the challenges involved in successfully deploying long-distance transmission projects are varied. Overcoming these challenges is not a single party affair, but requires close collaboration across government, industry and non-governmental organisations. 

    We conducted a study with nearly 600 industry experts from across the world who highlighted the pressing need for co-ordinated global action to rapidly develop grid infrastructure. Integrating renewable energy into existing grids was cited by participants as one of the most significant barriers to achieving net-zero objectives, alongside supply chain vulnerabilities and ability to access the required capital.

    Multiple challenges

    From a technical standpoint, there are multiple considerations when implementing cross-border interconnections. Regions can operate using different technical parameters, such as different voltages or frequencies. Even within the same country, interregional variations can create bottlenecks. Adopting regional or international grid codes could mitigate these issues.

    Further challenges emerge when we take trading into account. This is where regulation can act as an enabler, facilitating the flow of electricity between countries. The European Union’s efforts to co-ordinate the design of its member state’s energy markets enables an increasingly smooth transmission of energy across the continent. Alongside this, existing infrastructure is outdated, requiring significant upfront investment to upgrade. Clarity on regulatory requirements and more transparency around plans for grid buildout, derisk funding for capital-intensive mega projects.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy

    Positive benefits

    Despite these challenges, the upside must be stressed. Integrating power systems across borders has many positive societal benefits, decreasing costs and hence energy bills through economies of scale, increasing energy security and lowering the environmental impact of operations. On the latter more specifically, larger power systems are able to integrate higher shares of variable renewables. Globally, the sun is always shining and the wind blowing somewhere. 

    A common element, therefore, emerges: the need for increased cross-border co‑ordination. Whether it is bilateral, multi-lateral or unified, different models of inter-jurisdictional arrangements are needed for large-scale projects to support global energy interconnections. Our Xlinks project, which is using high-voltage direct current (HVDC) for transmission, is a standout example. 

    Such projects represent what is needed more in the world, the combination of infrastructure and renewable power across borders, bringing together the public and private sectors for energy security, supply and affordability in an environmentally friendly way. Transporting clean energy using HDVC cables is a crucial step in powering a net-zero and equitable future, and more of this is needed to aid the transition to lower-carbon and prosperous economies. 

    Political, technical and market hurdles can be overcome through collaboration and partnerships. Leveraging the collective expertise and resources of governments, regulators and the private sector can help ensure interconnections are developed quickly enough to support the energy transition. Grid buildout takes time. We have the resources required to meet ambitions, but stopping now is not viable. We must continue planning, building and maintaining large-scale infrastructure projects to meet the rising demand.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy. This was the message from Cop28 and the UAE Consensus: to help progress and secure a cleaner, brighter future for us all, we must break down barriers and come together. 

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11736994/main.gif
  • Libya allocates $1.2bn for upstream oil project

    3 May 2024

     

    Register for MEED's guest programme 

    Libya has allocated LD6bn ($1.23bn) to develop the Hamada NC-7 concession in its latest budget, which was approved by Libya’s eastern-based parliament on 30 April, according to industry sources.

    The field development project was previously estimated to be worth between $4bn and $5bn.

    The project aims to develop 2.7 trillion cubic feet of gas reserves in the NC-7 block of the Ghadames basin.

    A consortium led by Italy’s Eni and including France’s TotalEnergies and UAE-based Adnoc operates the block.

    Development of the field was included in the 2024 annual budget of LD90bn ($18.5bn), excluding an item for development projects, which the Benghazi-based government of Osama Hamad unanimously approved.

    Hamad came to power in March 2023 and is allied with the military commander Khalifa Haftar, who controls the east and large parts of the southern region of Libya.

    Progress on developing the Hamada NC-7 concession has been slow amid concerns among politicians about the involvement of foreign oil companies in key hydrocarbon assets.

    On 15 December 2023, the Tripoli-based Ministry of Oil & Gas issued a statement condemning the terms of the planned gas development contract between Libya’s state-owned National Oil Corporation (NOC) and the consortium led by Eni.

    In the statement, the Ministry of Oil & Gas described the deal as a “violation of Libyan legislation on oil contracts”.

    Earlier this year, NOC announced a plan to execute 45 greenfield and brownfield projects to try to boost the country’s oil production from 1.25 million barrels a day (b/d) to 2 million b/d.

    Farhat Bengdara, the chairman of NOC, said that the projects had a total estimated cost of $17bn-$18bn.

    Bengdara also confirmed plans to launch an oil and gas licensing round at the end of 2024 or early 2025.

    Libya is aiming to hit its 2 million b/d target within three years.

    Bengdara said that gas monetisation will remain a strategic focus as the country pushes to increase exports to Europe.

    Libya is only using 25% of the capacity of its Greenstream pipeline to Italy.

    The North African country also flares significant volumes of natural gas and has 12 projects under way that aim to reduce gas flaring to almost zero, according to Bengdara.

    In recent years, Libya has struggled to execute large projects amid significant political instability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11735260/main.gif
    Wil Crisp
  • GE Vernova invests in Xlinks

    2 May 2024

    US-headquartered GE Vernova has invested $10.2m in Xlinks First, the investment company established by UK-based startup Xlinks to deliver the $18bn Morocco-UK power project.

    This investment equates to a minority shareholding in the company, which is developing a project comprising wind and solar generation as well as battery storage, with a total combined capacity of 3,600MW, to be transmitted from Morocco to the UK.

    Xlinks said the investment will “further accelerate delivery and buildout of the project”.

    GE Vernova joins at least four other investors in the project.

    Other investors include Africa Finance Corporation, which invested $14.1m in April; Abu Dhabi National Energy Company (Taqa), $30.7m; the UK’s Octopus Energy, $6.23m; and France’s Total Energies, $25.4m.

    The planned electricity generation and battery storage facilities, located in south Morocco, will be connected exclusively to the UK via 4,000-kilometre high-voltage, direct current (HVDC) cables.

    In December last year, Xlinks signed a contract with Canada-headquartered WSP to provide technical advisory services for the project.

    WSP will support Xlinks with route optimisation, power systems and interface management for the plan to construct the project.

    The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre HVDC cables.

    The HVDC network is envisaged to run from the UK’s south coast, passing France, Spain and Portugal undersea and then onshore to a planned solar and wind energy project in Morocco.

    This renewable energy-sourced electricity amounts to nearly 8% of the UK’s current requirements, equivalent to powering 7 million homes by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11734222/main5830.jpg
    Jennifer Aguinaldo
  • Awards buoy Oman’s green hydrogen strategy

    2 May 2024

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    Oman has awarded two additional land blocks designed to develop green hydrogen projects.

    The latest land block concessions in Dhofar were awarded to two consortiums. One comprises a team of France's EDF Group and EDF Renewables, with partners Japanese Electric Power Development Company (J-Power) and the UK-headquartered Yamna Company.

    Another team comprises UK investment firm Actis and Australian metals firm Fortescue.

    This brings the total number of land blocks awarded through the public auction process spearheaded by Hydrogen Oman (Hydrom) to four, exclusive of the four legacy initiatives signed or agreed upon already.

    *Budgets are MEED estimates if not publicly disclosed. Sources: MEED, Hydrom

    A limited gas supply and network strongly incentivises Oman to build a green hydrogen-centric downstream sector that will provide feedstock to domestic industrial plants and generate derivatives for the local and export markets.

    Stakeholders have implemented a strategy, including setting up an infrastructure company catering to these projects. The target is to generate 1 to 1.5 million tonnes a year (t/y) of green hydrogen by 2030 and 7.5 to 8.5 million t/y by 2050.

    The blueprint envisages a complete green hydrogen ecosystem, from the production of renewable energy and its distribution to electrolysis plants and hydrogen derivatives conversion plants to storage and export terminals.

    Omani ports' existing relationships with European stakeholders and growing alliances with other countries could also help seal future offtake agreements for the planned facilities.

    As things stand, the consortiums that won the land auctions and the legacy initiative partners provide much gravitas to Oman's green hydrogen programme. They comprise energy old guards such as BP and Shell that are keen to decarbonise, private companies aiming to balance their investment portfolios with clean energy investments, and offtakers or trading companies that are grappling with net-zero targets.

    Yet the most obvious question remains. Given the eye-popping foreign direct investments these complex projects entail, not all are likely to achieve a final investment decision within three years. This seems to be the window required for the projects to start production before 2030.

    But like any emerging industry, the risks can only be properly assessed and mitigated as the first projects move toward the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11733331/main.gif
    Jennifer Aguinaldo
  • Operationalise loss and damage fund says Al Jaber

    2 May 2024

    Steps must be taken to ensure a fully functioning Loss and Damage Fund, following an agreement at Cop28 to operationalise the fund, according to Cop28 President Sultan Al Jaber.

    “While delivering an agreement to operationalise the Fund at Cop28 was a huge breakthrough for climate progress more needs to be done,” Al Jaber said during the first board meeting of the fund on 30 April.

    The Loss and Damage Fund, which was first proposed in the 1990s, aims to help developing countries cope with the impact of extreme global warming events such as droughts and floods.

    Al Jaber cited the need to build a fully functioning fund, which will be endorsed at Cop29 in Baku, which will be “disbursing funds soon after and a Fund that delivers lasting, positive, socio-economic impact for decades to come."

    "While it took over three decades to establish this Fund, climate change has not stood still. Every region of the world is now vulnerable…the impacts of climate change are a clear and present danger to lives and livelihoods everywhere."

    Al Jaber’s message resonates closer home given the recent storms hitting the UAE, which brought some emirates to a standstill in mid-April.

    Heavy rainfall inundated Dubai and the Northern Emirates on 16 April, causing flooding and significant property and infrastructure damages.

    A total of $792m has been pledged for loss and damage funding arrangements – of which $662m has been pledged to the Fund to date – including a $100m contribution each from the UAE and Germany and $75m from the UK.   

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11732746/main.jpg
    Jennifer Aguinaldo