Local firms rise in GCC Power Developer Ranking
24 September 2024

Two Saudi Arabia-headquartered firms have joined Acwa Power in the top 10 of MEED’s 2024 GCC Power Developer Ranking.
Aljomaih Energy & Water Company and Ajlan & Bros have entered the list, occupying the sixth and ninth spots, respectively.
The latest developer ranking included a survey of 109 privately owned and financed power generation plants in the six GCC states, including those with attached water desalination facilities. These plants have a collective gross electricity generation capacity of approximately 112,400MW.
These projects include seven solar, two wind and two gas-fired plants, as well as one industrial steam and cogeneration facility, with a total combined gross capacity of 19,635MW, for which contracts were awarded between September 2023 and August 2024.
Of the total capacity awarded during the 12-month period, solar photovoltaic (PV) and wind capacity accounted for 58%, or 11,400MW. Three solar PV contracts with a total capacity of 5,500MW, directly negotiated between Saudi Arabia’s Public Investment Fund (PIF) and a team led by Riyadh-headquartered Acwa Power, comprised nearly half of the awarded renewable IPP capacity.
These three contracts, along with a fourth for the development and operation of the 3,800MW Taiba 1 and Qassim 1 combined-cycle gas turbine (CCGT) IPP, helped boost Acwa Power’s dominance over its competitors.
Acwa Power's 35.1% stake in the 2,000MW Haden, the 2,000MW Muwayh and 1,500MW Al-Khushaybi solar PV projects, and its 40% share in Taiba 1 and Qassim 1, increased the company's total net capacity by 3,200MW, up 23% from last year’s 13,340MW. This figure takes into account the dilution of its shares in Rabigh Arabian Water & Electricity Company. As a result of the contracts it won, Acwa Power’s gross capacity also rose by 8,800MW to reach a total of 45,150MW.
Acwa Power has occupied the top spot in MEED’s GCC Power Developer Ranking in terms of net capacity since 2021, but it overtook its main rival, French utility developer and investor Engie, in terms of gross capacity only the following year.
Excluding the capacity of the directly negotiated solar IPP contracts that Acwa Power secured with the PIF in the past
three years does not change the company’s dominant position in the ranking, although it decreases its net and gross capacities by 25% and 24%, respectively.
Contenders
With no new contracts won, Engie still managed to retain second place in the ranking, with a net capacity of close to 8,000MW.
The successful bids of a team comprising Japan’s Marubeni Corporation and Ajlan & Bros for the contracts to develop and operate the 600MW Al-Ghat and 500MW Waad Al-Shamal wind schemes in Saudi Arabia increased Marubeni’s net capacity to 4,257MW, up 555MW compared to the previous year.
As with Engie, Japan’s Mitsui did not win any new contracts but retained its fourth place in the ranking, just above EDF, which climbed two positions to claim this year’s fifth spot and registered a net capacity that nearly doubled to reach 2,047MW.
EDF’s impressive performance accrued from its equities in three contracts: the 1,100MW Hinakiyah solar PV and the 3,960MW Taiba 2 and Qassim 2 CCGT projects in Saudi Arabia, and Abu Dhabi’s 1,500MW Al-Ajban solar PV scheme.
EDF knocked Japanese developer Sumitomo down the ranking; it landed in the seventh spot this year. Saudi Arabia’s Aljomaih Energy & Water Company – which was not part of the top 10 last year – rose past Sumitomo to claim sixth position.
Aljomaih’s 30% shareholding in the Taiba 2 and Qassim 2 IPP increased its net capacity by close to 1,200MW from just 775MW in the previous 12-month period.
Previously ranked sixth, Japan’s Jera fell to eighth place, despite having won the contract to develop the Najim cogeneration plant catering to Saudi Arabia’s Amiral petrochemicals complex, which it secured along with Abu Dhabi National Energy Company (Taqa).
Below Jera in the ranking is Ajlan & Bros, which is Marubeni’s partner for the contract to develop the Al-Ghat and Waad Al-Shamal wind IPPs. Ajlan is also understood to have taken a 30% stake in the consortium that won the contract to develop the Taiba 2 and Qassim 2 CCGT project.
China’s Jinko Power rounded out the top 10. It led the team that won the contract to develop the 400MW Tubarjal solar IPP in Saudi Arabia in November last year.
Local developers
The rise of Aljomaih and Ajlan & Bros, which led to South Korea’s Korea Electric Power Corporation (Kepco) and Singapore’s Sembcorp dropping out of the power developer ranking’s top 10 this year, confirms the improving profile of regional utility developers.
The resurgence of gas-fired power generation IPPs – in part due to Saudi Arabia’s liquid fuel displacement programme and the overall demand for baseload to address rising renewable energy capacity – is helping local developers to strengthen their footing.
“The reduced interest from European and Japanese contractors in bidding for gas-fired power generation projects could present an opportunity for local developers and investors,” says a senior executive with an international developer.
“As these firms are less constrained by their 2040-50 net-zero targets, they might focus on efficiency and quick deployment rather than on adhering to decarbonisation timelines, allowing for more flexibility in CCGT projects.”
The fact that only two teams submitted bids for the contracts to develop the next pair of CCGT IPPs in Saudi Arabia supports this observation. Similarly, Qatar’s General Electricity & Water Corporation (Kahramaa) received only one bid from a team led by Sumitomo for the contract to develop the Facility E independent water and power producer (IWPP) project earlier this year.
Conscious of its own net-zero targets, and those of its partners, Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) is adopting a slightly different approach for its next CCGT project in Taweelah by announcing that a carbon-capture facility will be installed as part of the project once such solutions become commercially viable.
In addition, the power-purchase agreement (PPA) for Taweelah C is expected to expire by 2049, making it several years shorter than previous PPAs and in line with the UAE's plan to reach net-zero carbon emissions by 2050.
So far, the market has responded positively, with nine companies having met Ewec’s prequalification requirements for Taweelah C.
However, the scale and volume of gas and renewable energy projects planned by Saudi Arabia, which has said it could procure up to 20GW of renewable energy capacity annually starting this year, is expected to continue to boost the net capacity of local developers and their less net-zero-constrained counterparts for the foreseeable future.
There is also an expectation that the exclusion of Acwa Power from the latest round of tenders for Saudi Arabia’s National Renewable Energy Programme (NREP) could further open up opportunities for other companies, regardless of their origin and net-zero targets.
Tariffs
There are mixed expectations in terms of how levelised electricity costs (LCOE) will behave over the next 12 months. Compared to the preceding decade, when unsubsidised renewable energy production costs consistently and sharply declined, tariffs have become less predictable since 2022.
In the region, solar PV tariffs in particular have trended upward since Acwa Power offered to develop the Shuaibah 1 solar IPP scheme for $cents 1.04 a kilowatt-hour (kWh) in 2020-21.
These tariffs have remained highly competitive relative to those seen in other, less renewable energy-intense regions, however, disincentivising some developers that felt they could not compete on price.
The next six to 12 months could prove decisive, according to one industry expert.
“It is possible that the surge in renewable projects could limit the availability of competent engineering, procurement and construction (EPC) contractors. The combination of aggressive national targets and competition for EPC services may drive up prices and slow project timelines,” the Dubai-based executive tells MEED.
“With raw materials and commodity prices trending downward, it's feasible that renewable energy tariffs could remain low in the short term. However, sustained record-low tariffs will also depend on the availability of financing, local regulations and grid integration costs.”
The LCOE trend for gas-fired power generation schemes seems more predictable.
According to the executive, the limited capacity of original equipment manufacturers, particularly for turbines and other key components of CCGT plants, will likely push tariffs up over the next 12 months.
“Limited availability of high-efficiency equipment will increase procurement costs and construction timelines, influencing the overall project cost.”
This extends to CCGTs incorporating carbon capture, where the LCOE will likely increase due to additional capital and operational expenses. “Whether these costs are absorbed through renegotiation or passed on to the state offtaker will depend on the power-purchase agreement structure,” he says.
Exclusive from Meed
-
Managing risk in the GCC construction market19 December 2025
-
Diriyah signs land lease deal with King Saud University19 December 2025
-
Kuwait to sign Mubarak port agreement next week19 December 2025
-
Metito consortium wins Mecca sewage scheme19 December 2025
-
Morocco awards $1bn Casablanca airport terminal deal19 December 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Managing risk in the GCC construction market19 December 2025

The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.
Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.
MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.
The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.
Systemic risk
The regional market is characterised by several systemic issues that amplify risks for contractors.
The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.
Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.
Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:
> Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.
> Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.
> Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.

Supply-chain erosion
The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly.
Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.
The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.
Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.
The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is.
A 10-point checklist for contractors in 2026
1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.
2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.
3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.
4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.
5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.
6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.
7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.
8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.
9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.
10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need. Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site. MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:
Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com
Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com
Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com
Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com
IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com
White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com
https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif -
Diriyah signs land lease deal with King Saud University19 December 2025
Saudi Arabia gigaproject developer, Diriyah Company, has signed a long-term land lease agreement with Riyadh Valley Company, an investment arm of King Saud University.
Diriyah Company will lease 552,000 square metres (sq m) of land from King Saud University for a period of 70 years.
The deal will enable the company to add the land bank to its second phase of the Diriyah Project, which is also known as DG2.
The agreement was signed by Diriyah Company's Group CEO, Jerry Inzerillo, and the acting president of King Saud University and Riyadh Valley Company chairman, Ali Masmali.
Diriyah Company is already developing the area adjacent to King Saud University. In April, it awarded an estimated SR4bn ($1.1bn) contract for a utilities relocation package for the King Saud University project located in the second phase of the Diriyah Gate development (DG2).
The contract was awarded to the joint venture of Beijing-headquartered China Railway Construction Corporation and China Railway Construction Group Central Plain Construction Company.
The scope of the contract covers the design, construction and relocation of KSU's utilities and administration offices, as well as the construction of a district cooling plant, water storage facilities, a sewage treatment plant, a natural gas plant, a diesel transfer pumping station, a utility tunnel, irrigation water storage tanks, office buildings, warehouses and maintenance workshops.
In addition to KSU, DG2 will feature residential developments, hotels, an opera house, the Saudi Museum of Contemporary Art, six academies, an arena and a mosque.
The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh’s city centre, it will cover 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15287776/main.jpg -
Kuwait to sign Mubarak port agreement next week19 December 2025
Kuwait and China are expected to sign the agreement to develop the subsequent phases of Kuwait’s Grand Mubarak Port next week.
According to media reports, the announcement was made by Kuwait’s Public Works Minister Noura Al-Mashaan on Thursday.
The contract value is estimated to be about KD1.2bn ($4bn).
In May, Beijing-headquartered China Harbour Engineering Company, a subsidiary of China Communications Construction Company (CCCC), signed an early contractor involvement (ECI) agreement with Kuwait to develop the next phases of the project.
The initial works include surveying, investigation, hydrological observation, geophysical exploration, testing, model testing, process simulation, design review, owner inspection, preliminary design of sand-retaining embankments, and on-site services and management.
The project launch ceremony was held in mid-April. It was attended by several high-profile representatives from Kuwait and China, including Fu Xuyin, China’s vice-minister of the Ministry of Transport, Zhang Jianwei, the Chinese ambassador to Kuwait, and Nora Mohammad Al-Mashaan, Kuwait’s minister of public works.
In January, MEED reported that Kuwait’s cabinet had approved a bid from China Communications Construction Company to implement all stages of its Mubarak Al-Kabeer Port project.
The country ramped up its efforts on the project after meetings between Kuwaiti and Chinese officials in June last year.
In 2023, the two countries signed a memorandum of understanding to develop port infrastructure.
Phase one of the project cost $1.2bn and was completed in 2014.
The project’s first phase included site levelling and the development of a marina, quay walls, berths, a navigational terminal and port buildings.
The port is not operational because the phase one works did not include vital equipment such as cranes.
It is understood that the completion of phase two will allow the port to start operations.
The full scope for phase two of the project is expected to include:
- Construction of loading and unloading facilities
- Construction of quay walls and reclamation
- Construction of the container yard and the back of the port
- Infrastructure works
- Construction of buildings
- Construction of a container terminal
- Construction of associated facilities
- Installation of safety and security systems
A third phase is also planned to further expand the port.
The latest developments follow a series of agreements signed in September 2023 to deliver some of Kuwait’s immediate development goals for 2024-28. These agreements will position Chinese companies to play a leading role in the Fourth Kuwait Master Plan 2040.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15287252/main.jpg -
Metito consortium wins Mecca sewage scheme19 December 2025
A team comprising Metito (UAE), Etihad Water & Electricity Company (UAE) and SkyBridge Company (UK) has been awarded a contract to develop the Hadda independent sewage treatment plant (ISTP) project in Mecca Province, Saudi Arabia.
The contract was awarded by Saudi Water Partnership Company (SWPC), the kingdom’s principal off-taker for water and wastewater public-private partnership (PPP) projects.
The project will be developed on a build-own-operate-transfer basis and is expected to begin operations in 2028, followed by a 25-year operating term.
The plant will provide an initial treatment capacity of 100,000 cubic metres a day and will feature a treated sewage effluent (TSE) reuse system with a storage tank and a 38-kilometre pipeline designed to handle 350,000 cubic metres a day.
Earlier in December, MEED reported that the team had been named preferred bidder at a levelised tariff of SR2.354 ($0.63) a cubic metre.
SWPC selected the Miahona-led consortium as the reserve bidder for this project with the second-lowest submitted bid of SR2.599($0.69) a cubic metre.
According to SWPC, the TSE reuse system accounted for 31% of the preferred tariff for the Arana ISTP and 27% for the Hadda ISTP.
In March last year, SWPC signed a 25-year water-purchase agreement with a team comprising the local Miahona Company and Belgium-based Besix for the contract to develop and operate the Al-Haer ISTP in Riyadh, as part of the third batch of the kingdom’s ISTP programme.
Four months later, the Saudi-listed Power & Water Utility Company for Jubail & Yanbu (Marafiq) joined the developer consortium.
The Miahona/Besix team offered to develop the project for SR1.9407 ($0.5173) a cubic metre, while the second-lowest bid, from a team comprising Spain’s Acciona and the local Tawzea, was SR2.2041($0.588) a cubic metre.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15287185/main.jpg -
Morocco awards $1bn Casablanca airport terminal deal19 December 2025
Morocco’s National Airports Office (ONDA) has awarded a MD12bn ($1.2bn) contract to build the new terminal at Casablanca’s Mohammed V International airport.
The contract was awarded to the joint venture of local firms Societe Generale des Travaux du Maroc (SGTM) and Travaux Generaux de Construction de Casablanca (TGCC).
Construction work on the Mohammed V International airport expansion is expected to begin immediately.
The project is slated for completion in 2029.
The expansion will cover more than 600,000 square metres (sq m) and increase the airport’s capacity to 30 million passengers a year.
The project is designed by a consortium comprising the local branch of French engineering firm Egis Batiment International, Morocco’s Ala Concept and UK-based RSHP Architects.
The scope of work covers preparatory works, structural works, waterproofing, steel structural works, building facades, electrical, mechanical and plumbing (MEP) works, data centre works, HVAC systems and other associated works.
The tender also covers the construction of a 300-key airside hotel.
The new terminal is expected to be ready in time for the 2030 Fifa World Cup, which Morocco is co-hosting alongside Portugal and Spain.
ONDA tendered the project contract on 4 November, with a bid submission deadline of 16 December, as MEED reported.
In July, ONDA began early works on the new terminal building, awarding an estimated MD294m ($29m) deal for enabling works to local firm Societe de Travaux Agricoles Marocaine.
In January, Morocco’s Transport & Logistics Minister, Abdessamad Kayouh, said that the study to expand the airport’s capacity was nearing completion.
The project is part of Morocco’s MD42bn ($4.3bn) plan to expand key airports in anticipation of increased passenger flow for the 2030 football World Cup.
Morocco plans to upgrade several airports, including those in Tangier, Marrakech and Agadir, increasing their respective annual passenger capacities to 7 million, 16 million and 7 million.
There are also plans to add a new terminal at Rabat-Sale airport, raising its capacity to 4 million passengers annually, and to increase Fez airport’s capacity to 5 million passengers annually.
The new terminal at Mohammed V International airport will be connected to a high-speed train network linking Kenitra to Marrakech.
READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFProspects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges
Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:
> AGENDA 1: Regional rail construction surges ahead> INDUSTRY REPORT 1: Larsen & Toubro climbs EPC contractor ranking> INDUSTRY REPORT 2: Chinese firms expand oil and gas presence> CONSTRUCTION: Aramco Stadium races towards completion> RENEWABLES: UAE moves ahead with $6bn solar and storage project> INTERVIEW: Engie pivots towards renewables projects> BAHRAIN MARKET FOCUS: Manama pursues reform amid strainTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15287093/main.jpg

