Saudi downstream programmes gain traction
13 September 2024
Progress on a programme as mammoth as Saudi Aramco’s liquids-to-chemicals scheme is expected to be measured and laboured. The programme’s central ambition is to derive greater economic value from every barrel of crude produced in the kingdom by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.
Aramco and its subsidiary, Saudi Basic Industries Corporation (Sabic) – the two primary stakeholders of the liquids-to-chemicals programme – are still in the initial phase and are giving shape to various projects and components.
Considering that the operators are “still working out” how best to attain the liquids-to-chemicals conversion goal from across their global portfolio, achieving “cohesion and synergies” with the consultants they have appointed during the conceptualisation phase is proving to be a “sticking point”, several sources told MEED.
While day-to-day progress might appear sluggish, Amin Nasser, Aramco’s president and CEO, assured earlier in the year that the Saudi energy giant is on track to achieve its crude oil-to-chemicals (COTC) conversion goal by 2030.
“We are on track to achieve our target of 4 million b/d liquids-to-chemicals [conversion capacity] by 2030,” Nasser said during an online press conference held on 30 May to discuss Aramco’s secondary shares offering.
“We’re slightly above 2 million b/d liquids-to-chemicals [output], so progressing very well in our programme,” he said in response to a question by MEED during the media briefing.
Liquids-to-chemicals programme
When completed, the liquids-to-chemicals programme will make Saudi Arabia one of the world’s largest petrochemicals producers. Aramco, along with Sabic, have been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which include greenfield developments and expansions of existing facilities, will be built both in Saudi Arabia and in overseas markets.
The Saudi energy giant is said to have been allocated a total capital expenditure budget of up to $100bn for projects as part of this campaign, MEED has previously reported.
Aramco has divided its liquids-to-chemicals programme in Saudi Arabia into four main projects. It took a major step forward in September last year by appointing project management consultants (PMC) for the different segments of the scheme.
Aramco selected US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia-headquartered Worley to provide PMC services for the four projects, which include:
- Project East (PMC 1) – involves converting the Saudi Aramco Jubail Refinery Company (Sasref) complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery. China’s Rongsheng Petrochemical Company recently signed a preliminary agreement with Aramco to potentially become a 50% investor in this project.
- Project West (PMC 2) – involves converting the Yanbu Aramco Sinopec Refining Company (Yasref) complex in Yanbu into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. Aramco and state-owned China Petroleum & Chemical Corporation (Sinopec) signed a memorandum of understanding in October for joint investment in the project, known as the Yanbu Refinery+ project.
- Project X (PMC 3) – involves converting the Saudi Aramco Mobil Refinery Company (Samref) complex in Yanbu into an integrated refinery and petrochemicals complex by building a mixed-feed cracker.
- Project RTC (PMC 4) – involves establishing a COTC complex in Ras Al-Khair in the Eastern Province. Sabic is a partner in the Ras Al-Khair COTC project.
Aramco has initiated a separate tendering exercise to provide front-end engineering and design (feed) services on the projects in the future. Feed contracts are scheduled to be awarded in 2024, while the main EPC contracts are due for award in 2025.
Ramping up gas processing capacity
To process incremental volumes of gas entering the grid due to Aramco spiking its conventional and unconventional gas production, the state enterprise has already spent $16.5bn on gas processing and transportation projects this year.
In April, Aramco awarded $7.7bn in EPC contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.
On 30 June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Aramco has divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.
The expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028 through installing about 4,000 kilometres of pipelines and 17 new gas compression trains.
Going forward, Aramco is expected to pursue other projects this year to boost the gas processing potential of its key plants, such as Haradh, Shedgum and Uthmaniya.
Aramco has already received interest from contractors for the main tender for a project to expand the Haradh Gas Oil Separation Plant 3 (GOSP 3). The state enterprise is in the feed stage of a separate project to expand the Shedgum and Uthmaniya plants, with the main EPC tender expected to be issued by the end of the year.
Exclusive from Meed
-
Three bids submitted for Riyadh-Qassim IWTP
18 September 2025
-
Saudi Arabia seeks firms for six renewable projects
17 September 2025
-
Qatar tenders Smaisma infrastructure contract
17 September 2025
-
Dragon Oil to boost exploration and production in Egypt
17 September 2025
-
Construction launched for final major projects of Iraq’s GGIP
17 September 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Three bids submitted for Riyadh-Qassim IWTP
18 September 2025
Register for MEED’s 14-day trial access
State water offtaker Saudi Water Partnership Company (SWPC) has received three bids from the private sector for the development of the Riyadh-Qassim independent water transmission pipeline (IWTP) project.
The bids were submitted by two consortiums and one individual company.
The first consortium comprises Saudi firms Al-Jomaih Energy & Water, Al-Khorayef Water & Power Technologies, AlBawani Capital and Buhur for Investment Company.
The second consortium comprises Bahrain/Saudi Arabia-based Lamar Holding, the UAE's Etihad Water & Electricity and China’s Shaanxi Construction Installation Group.
The third bid was submitted by Saudi Arabia's Vision Invest.
In August, MEED exclusively reported that SWPC had extended the bid submission deadline again for a contract to develop and operate the project.
The deadline for bids was 17 September.
The project will have a transmission capacity of 685,000 cubic metres a day. It will include a pipeline length of 859 kilometres (km) and a total storage capacity of 1.59 million cubic metres.
The scheme is the third IWTP contract to be tendered by SWPC since 2022.
The first two are the 150km Rayis-Rabigh IWTP, which is under construction, and the 603km Jubail-Buraydah IWTP, the contract for which was awarded to a team of Riyadh-based companies comprising Al-Jomaih Energy & Water, Nesma Group and Buhur for Investment Company.
Like the first two IWTPs, the Riyadh-Qassim IWTP project will be developed using a 35-year build-own-operate-transfer contracting model.
Commercial operations are expected to commence in the first quarter of 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14691078/main.jpg -
Saudi Arabia seeks firms for six renewable projects
17 September 2025
Register for MEED’s 14-day trial access
Saudi Arabia's principal buyer, Saudi Power Procurement Company (SPPC), has invited interested companies to prequalify for the contracts to develop and operate solar photovoltaic (PV) and wind independent power producer (IPP) projects with a total combined capacity of 5,300MW.
The following schemes comprise round seven of the kingdom's National Renewable Energy Programme (NREP):
- 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf Province)
- 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail Province)
- 600MW Tathleeth solar PV IPP (Tathleeth, Aseer Province)
- 500MW South Al-Ula solar PV IPP (Al-Ula, Medina Province)
- 1,300MW Bilgah wind IPP (Bilgah, Medina Province)
- 900MW Shagran wind IPP (Shagran, Medina Province)
These projects are part of the NREP, which aims to achieve an optimal energy mix and supply 50% of the kingdom's electricity from renewable energy by 2030.
Earlier rounds under the NREP have already put in place large capacities.
Round six solicited around 4,500MW of solar and wind projects:
- 1,500MW Dawadmi wind IPP (Riyadh)
- 1,400MW Najran solar PV IPP (Najran)
- 600MW Samtah solar PV IPP (Jizan)
- 600MW Al-Darb solar PV IPP (Jizan)
- 400MW Al-Sufun solar PV IPP (Hail)
In April, MEED reported that prequalified developers were forming teams to bid for the contracts to develop solar farms under the sixth round of the NREP.
A separate set of bidders were prequalified for the 1,500MW Dawadmi wind farm, with contracts due to be awarded before the end of the year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14684103/main3708.jpg -
Qatar tenders Smaisma infrastructure contract
17 September 2025
Register for MEED’s 14-day trial access
Qatar’s Public Works Authority (Ashghal) has tendered a contract inviting construction firms to bid for the remaining works on roads and infrastructure in the small seaside town of Smaisma.
The contract covers package two in the south area of Smaisma, located 52 kilometres (km) north of Hamad International airport.
The scope of work includes the completion of the remaining works and remedial works on three zones. Each zone is further divided into three sub-zones.
The scope also covers the remaining works on road C1017.
The contract duration is two years from the start of construction works.
The tender was floated on 15 September with a bid submission date of 28 October.
The latest notice follows the tendering for the construction of roads and infrastructure in Wadi Al-Banat North (Zone 70).
Market overview
After 2019, there was a consistent year-on-year decline in contract awards in Qatar’s construction and transport sectors. The total value of awards in that year was $13.5bn, but by 2023 it had fallen to just over $1.2bn.
In 2024, the value of project contract awards increased to $1.7bn, bucking the downward trend in the market in the preceding four years.
Of last year’s figure, the construction sector accounted for contract awards of over $1.2bn, while transport contract awards were about $200m.
There are strategic projects in the bidding phase in Qatar worth more than $5bn, and these are expected to provide renewed impetus to the construction and transportation market, presenting opportunities for contractors in the near term.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14682452/main.jpg -
Dragon Oil to boost exploration and production in Egypt
17 September 2025
Register for MEED’s 14-day trial access
Dubai-based Dragon Oil has signed a deal with the state-owned national oil company Egyptian General Petroleum Corporation (EGPC), agreeing to increase exploration and production activities in the Gulf of Suez.
Under the terms of the agreement, Dragon Oil will make investments worth about $30m.
This will fund activities including a programme to drill at least two new wells in the East El-Hamd area.
Abdulkarim Ahmed Al-Mazmi, the acting chief executive of Dragon Oil, said: “The signing of this agreement reaffirms Dragon Oil’s commitment to strengthening its strategic presence in the Arab Republic of Egypt and supporting EGPC’s efforts to develop energy resources in the Gulf of Suez region, in line with the company’s vision for growth and sustainability.”
Dragon Oil is wholly owned by Emirates National Oil Company, which is fully owned by the Government of Dubai.
Al-Mamzi said that the new investments are part of Dragon Oil’s broader strategy to expand in regional markets and to strengthen its position in the oil and gas sector, in line with the directions of the government of the UAE, and in particular the Government of Dubai.
The agreement was signed at the EGPC headquarters in Cairo.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14680456/main.png -
Construction launched for final major projects of Iraq’s GGIP
17 September 2025
Register for MEED’s 14-day trial access
Officials have announced the start of construction on Iraq’s Common Seawater Supply Project (CSSP) and the full field development of the Ratawi oil field, which is also known as the Artarwi field.
The two projects are the two last major contracts of the Gas Growth Integrated Project (GGIP).
The GGIP is led by France’s TotalEnergies, which is the operator and has a 45% stake in the project.
Its partners are Iraq’s state-owned Basra Oil Company, which has a 30% stake, and QatarEnergy, which has a 25% stake.
An event in Baghdad to mark the launch of the two projects was attended by senior officials including Patrick Pouyanne, the chairman and chief executive of TotalEnergies; and Saad Sherida Al-Kaabi, who is Qatar’s Minister of State for Energy Affairs, as well as the president and chief executive of QatarEnergy.
In a statement, TotalEnergies said: “All four parts (natural gas, solar, oil, water) of the GGIP are now in the execution phase.”
The CSSP will be built on Iraq's coast, near the town of Um Qasr. It will process and transport 5 million barrels a day (b/d) of seawater to the main oil fields in southern Iraq.
Treated seawater will be substituted for the freshwater currently taken from the Tigris, Euphrates and aquifers to maintain pressure in the oil wells.
The project is expected to help alleviate water stress in the region and free up to 250,000 cubic metres of freshwater a day for irrigation and local agriculture needs, according to TotalEnergies.
The Ratawi redevelopment was launched in September 2023. Phase one aims to increase production to 120,000 b/d of oil and is expected to come on stream by early 2026.
The launch of phase two, the full field development, will enable production to be increased to 210,000 b/d starting in 2028, with no routine flaring, according to TotalEnergies.
In a statement, it said that all 160,000 cubic feet a day (cf/d) of associated gas produced will be fully processed by the 300,000 cf/d Gas Midstream Project (GMP), the construction of which began in early 2025.
The GMP, which will also treat previously flared gas from two other fields in southern Iraq, will deliver processed gas into the national grid, where it will fuel power plants with a production capacity of approximately 1.5GW, providing electricity to 1.5 million Iraqi households.
An early production facility to process 50,000 cf/d of associated gas will start in early 2026, together with the Ratawi phase one oil production.
Pouyanne said: “We are delighted today to award the two final contracts of the GGIP, in particular the seawater treatment plant, which has been long awaited by the oil industry in Iraq.
“In less than two years since the GGIP effective date in August 2023, TotalEnergies and its partners have fully executed their commitment towards the people of Iraq and launched all projects included in the multi-energy GGIP project, the best showcase of TotalEnergies' transition strategy.
“All these projects will bring a significant contribution to the Iraq economy and employ during the construction phase 7,000 Iraqi nationals.
“Furthermore, I am proud to confirm that the first phase of the associated gas, oil and solar projects will start up as soon as early 2026.”
Turkiye’s Enka has signed a contract to develop a central processing facility at the Ratawi oil field as part of the second phase of the field’s development.