Top 15 Saudi stadium projects
30 August 2024

Saudi Arabia formally kicked off its World Cup participation process in October last year after announcing that it planned to bid to host the event. The announcement was a culmination of Riyadh’s football-focused strategy launched two years before when a consortium led by the kingdom’s sovereign wealth vehicle, the Public Investment Fund (PIF), completed the full acquisition of UK football club Newcastle United from St James Holdings in 2021.
The move was further solidified when Saudi Arabia was effectively confirmed as the host after Australia, the only other bidder for the tournament, withdrew from the race in October last year.
This was followed by Saudi Arabia’s official bid campaign reveal and the submission of its bid to Fifa to host the World Cup 2034 event in July. The official selection of Saudi Arabia as the 2034 host is expected to be confirmed on 11 December.
Saudi Arabia will likely invest hundreds of billions of dollars in developing the required infrastructure to host the event. Experience from previous World Cups, including the most recent one in Qatar, has shown that hosting the tournament can transform a country’s economy.
The tournament brings in fans from around the world to enjoy a month-long festival of football. After the 2022 tournament, Qatar issued a statement saying that more than 1.4 million fans had visited the country during the event.
The decision to host the Fifa World Cup 2034 is a pivotal moment for Saudi Arabia as it validates much of the social and economic change that the kingdom has embarked upon since Crown Prince Mohammed Bin Salman launched Vision 2030 back in 2016.
Building stadiums is the most prominent part of the bid to host the coveted Fifa World Cup.
According to the official bid book document submitted by Saudi Arabia in July, it will construct 11 new stadiums as part of its bid to host the Fifa World Cup 2034.
Eight out of the 15 stadiums are located in the capital, Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.
The event requires a minimum of 14 all-seater stadiums, of which at least four should be existing structures. The capacity must be at least 80,000 seats for the opening and final matches, and for the semi-finals, there must be at least 60,000 seats. For all other matches, at least 40,000 seats are needed.
The kingdom has recently ramped up its announcements regarding building new stadiums across the country in preparation to host the event.
1. King Salman Stadium
The King Salman Stadium will be the showpiece venue for the tournament. The US-based architectural firm Populous-designed stadium will cover an area of about 660,000 square metres (sq m) and have a seating capacity of over 92,000 spectators.
The stadium will host the opening and final games of the Fifa World Cup 2034 tournament. The construction of the stadium is expected to be completed by 2029.
- Location: Riyadh
- Companies involved: Populous
- Match category: Opening and final games
2. King Fahad Sports City Stadium
The King Fahad Sports City Stadium is expected to be the venue for the semi-final. The stadium will be refurbished to increase its seating capacity from its current 58,000 seats to 70,200 seats.
The main contract bid submission process is ongoing and the project’s expansion works are expected to begin early next year. The stadium will also be a venue for the AFC Asian Cup 2027.
- Location: Riyadh
- Companies involved: Populous
- Match category: Semi-final
3. Prince Mohammed Bin Salman Stadium, Qiddiya City
The Prince Mohammed Bin Salman Stadium will be built on top of a 200-metre-high Tuwaiq cliff located in the new sports and entertainment district of Qiddiya City.
The stadium will have a capacity to accommodate 46,979 spectators and will feature a fully combined retractable pitch, roof and LED wall. The construction works are expected to begin later this year.
- Location: Riyadh
- Companies involved: Qiddiya Investment Company, Populous
- Match category: Third-place playoff
4. New Murabba Stadium
The New Murabba Stadium will have the capacity to accommodate 46,010 spectators and will be built as part of the New Murabba downtown project in Riyadh.
The construction of the stadium is expected to be completed by 2032.
- Location: Riyadh
- Companies involved: New Murabba Development Company
- Match category: Round of 32
5. Roshn Stadium
The Roshn stadium will be built in the southwest of Riyadh. The planned facility will have the capacity to accommodate 46,000 spectators and will span an area of over 450,000 sq m.
- Location: Riyadh
- Companies involved: Roshn
- Match category: Round of 32
6. Prince Faisal Bin Fahad Sports City Stadium
The Prince Faisal Bin Fahad Stadium is earmarked for an expansion that aims to increase its seating capacity from its current 22,188 seats to 46,865 seats.
The facility will also host the AFC Asian Cup in 2027.
The refurbishment works will change the geometry of the seating bowl from an athletics stadium to a football stadium.
- Location: Riyadh
- Companies involved: Populous
- Match category: Round of 32
Saudi World Cup bid bucks global trend for sporting events
7. South Riyadh Stadium
The Populous-designed stadium will be located in southwest Riyadh close to the Wadi Namar. The stadium will have the capacity to host 47,060 spectators. It is expected to be ready by 2032.
- Location: Riyadh
- Companies involved: Populous
- Match category: Round of 32
8. King Saud University Stadium
The King Saud University Stadium, located on the university’s campus in the west of Riyadh, is one of the venues that will undergo expansion and refurbishment to host the event.
The expansion will increase the stadium’s capacity to 46,319 spectators and the construction works are expected to be completed by 2032.
- Location: Riyadh
- Companies involved: Populous
- Match category: Round of 32
9. King Abdullah Sports City Stadium
The King Abdullah Sports City Stadium is the home ground for the Al-Ittihad and Al-Ahli football clubs. The venue will undergo expansion works that will increase its seating capacity to 58,432 people. The stadium will host the quarter-final games.
- Location: Jeddah
- Companies involved: Arup
- Match category: Quarter-final
10. Qiddiya Coast Stadium, Jeddah
The Populous-designed stadium will be situated at the heart of the Qiddiya Coast development in Jeddah. The multi-purpose stadium will have a 46,096 seating capacity and will be one of the venues for the round of 16 matches.
- Location: Jeddah
- Companies involved: Populous
- Match category: Round of 16
11. Jeddah Central Stadium, Jeddah
The already under-construction football stadium is part of the Jeddah Central Project in Jeddah and has a seating capacity of 45,794 spectators. The stadium is expected to be completed by 2027.
- Location: Jeddah
- Companies involved: Jeddah Central Development Company, Khatib & Alami, Gerkan Marg & Partner, China Railway Construction Corporation, Sama Construction for Trading & Contracting, Geoharbour
- Match category: Round of 32
12. King Abdullah Economic City Stadium, Jeddah
The planned stadium will have a seating capacity of 45,700 and will be built in the King Abdullah Economic City on the Red Sea Coast, north of Jeddah.
- Location: Jeddah
- Companies involved: Populous
- Match category: Round of 32
13. Aramco Stadium
The Aramco Stadium in Al-Khobar is under construction and is expected to be completed by 2026. The stadium will have a capacity of 46,096 seats.
- Location: Al-Khobar
- Companies involved: Saudi Aramco, Roshn, Foster + Partners, Populous, Besix, Albawani, Al-Osais International Holding
- Match category: Round of 16
14. King Khalid University Stadium
The stadium will undergo expansion works that will see its capacity raised to 45,428 seats. The facility is expected to be ready by 2032.
- Location: Abha
- Companies involved: Populous
- Match category: Round of 16
15. Neom Stadium
The 46,010-seat stadium in Neom is “designed to stand out among the world’s most iconic landmarks”, according to the bid book. It is planned to be built 350 metres above ground level within The Line project at Neom.
The stadium is expected to be ready by 2032.
- Location: Neom
- Companies involved: Neom
- Match category: Quarter-final
Exclusive from Meed
-
Dubai seeks consultants for drainage projects6 February 2026
-
Modon tenders Ras El-Hekma construction contracts6 February 2026
-
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
-
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
-
Chinese firm wins Ceer automotive supplier park deal6 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai seeks consultants for drainage projects6 February 2026
Dubai Municipality has invited consultants to qualify for a contract to supervise three stormwater drainage projects under the $8bn Tasreef programme.
The contract, titled TF-15-S1 Supervision of Stormwater Drainage System projects – Package 2, will be awarded as a single package with dedicated teams assigned to each project.
The request for qualifications (RFQs) was issued by the municipality’s Sewerage and Recycled Water Projects Department (SRPD).
The bid submission deadline is 26 February.
The first scheme under the package is TF-16-C1, which involves upgrading and rehabilitating the stormwater system east of the Dubai Canal.
The second, TF-15-C2, will deliver stormwater links along Umm Suqeim Road to serve the Al-Barsha and Al-Quoz communities.
The third project, TF-13-C1, focuses on developing a drainage system for the Al-Marmum area.
Several engineering, procurement and construction (EPC) contracts have been awarded under the Tasreef initiative, which aims to expand Dubai’s rainwater drainage capacity by 700% by 2033
In January, local firm DeTech Contracting won the main contract to construct a stormwater drainage system in Jebel Ali.
The project, listed under TF-05-C1, covers approximately 27 kilometres of stormwater network and will serve major transport routes, including Sheikh Zayed Road and Al-Jamayel Road.
Separately, Dubai Municipality has opened bidding for EPC contracts to expand and rehabilitate the emirate’s sewerage networks.
The four projects cover more than 95km of recycled water and sewerage pipelines.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593832/main.jpg -
Modon tenders Ras El-Hekma construction contracts6 February 2026

Abu Dhabi-based developer Modon Holding has tendered several contracts as part of the first phase of development at Ras El-Hekma, a planned new city on Egypt’s Mediterranean coast.
MEED understands that the tenders were issued in January.
These include:
DP3 assets: covering 146 residential villas, 590 three-bedroom townhouses, 356 four-bedroom townhouses, a mall and other associated works.
Bids due on 23 February.
DP4 assets: DP4 includes 54 villas, a clubhouse and other associated infrastructure.
Bids due on 2 March.
DP5 assets: The scope covers the construction of two hotels, branded residences, a retail facility and other associated works.
Bids due on 10 March.
DP6 assets: This package covers a 200-key Montage hotel, 96-unit Montage-branded residences and related infrastructure.
Bids due on 17 March.
DP7 assets: 120 five-bedroom villas, 230 seven-bedroom villas, 284 branded residential units and other infrastructural works.
Bids due on 3 March.
MEED understands that the contract duration for all these packages is 21 months from the start of construction.
Modon has accelerated development works at Ras El-Hekma this year. In January, MEED reported that Modon Holding had awarded a E£15bn ($316m) contract for the construction of a project at Ras El-Hekma.
The contract was awarded to the local firm Orascom Construction.
The scope of the contract covers the construction of residential units, commercial facilities and a 70-key hotel.
In September, MEED reported that Modon Holding had tendered contracts for the infrastructure works for the first phase of the Ras El-Hekma project.
As part of the first phase, Modon plans to develop more than 50 million square metres (sq m), including hotels and a marina.
Ras El-Hekma is on a spur of land on Egypt’s northern Mediterranean coastline, about 240 kilometres west of Alexandria.
Last year, Abu Dhabi-based holding company ADQ appointed Modon Holding as the master developer for the Ras El-Hekma project.
According to an official statement, Modon will act as the master developer for the entire development, which will cover more than 170 million sq m.
Modon Holding will develop the first phase of the project, which will cover 50 million sq m.
The remaining 120 million sq m will be developed in partnership with private developers under the supervision of the recently established ADQ subsidiary Ras El-Hekma Urban Development Project Company and Modon Holding.
In September 2024, Modon signed several memorandums of understanding (MoUs) with local and international firms to join the development. It signed a framework agreement with Orascom Construction to serve as the primary contractor for the project’s first phase.
Ras El-Hekma is planned as a combined business and leisure destination, with hotels, leisure facilities, a free zone, a financial district and residential components.
The master development has been billed as capable of attracting over $150bn in investment.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593388/main.jpg -
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
Commercial International Bank Egypt (CIB) has provided €58m in credit facilities to local firm Elsewedy Electric for the construction of a combined-cycle gas turbine (CCGT) power plant in Hungary.
Located in Visonta, the plant will be the largest combined-cycle facility built in Hungary in decades and the country’s first power plant capable of using hydrogen.
Once complete, hydrogen will be able to supply up to 30% of the plant’s fuel needs.
The project is being developed through a consortium comprising Energy Projects, a subsidiary of Elsewedy Electric, and local firms Status KPRIA and West Hungaria Bau (WHB).
It was awarded by MVM Matra Energia, a subsidiary of Hungary’s state-owned power holding company Magya Villamos Muvek (MVM).
As MEED understands, the plant is expected to have a power generation capacity of between 500MW and 650MW.
Total investment in the scheme is estimated at about €700m, with CIB acting as the sole financier for Elsewedy Electric’s portion of the project.
Construction officially began last September, with commercial operations scheduled for 2028.
The scheme also represents Elsewedy Electric’s first major investment in Europe, adding to other foreign investment interests.
Last May, it was reported that Elsewedy Electric intends to build a $100m electrical cable manufacturing plant in Iraq. This project has yet to advance beyond the initial stages.
In 2024, the contractor connected three additional hydro turbine generators to Tanzania’s national power grid in partnership with The Arab Contractors.
This brought the total power supply from the Julius Nyerere hydroelectric power project to 705MW.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593289/main.jpg -
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
Abu Dhabi’s AD Ports Group has signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.
AD Ports will manage and operate the port under a 30-year concession agreement.
Under the agreement, AD Ports and ADC will establish a joint venture to oversee port operations.
AD Ports will hold a 70% stake in the joint venture, with the remaining 30% held by ADC.
AD Ports Group will also invest AED141m ($38.4m) in the joint venture.
The signing ceremony was held at the Aqaba Special Economic Zone Authority headquarters in Aqaba on 5 February.
The agreement was signed by Hussein Safadi, CEO of ADC, and Ahmed Al-Mutawa, regional CEO of AD Ports Group.
Aqaba port handles about 80% of Jordan’s exports and 65% of its imports.
It serves as a key transit point for Jordan’s neighbouring countries, including Saudi Arabia and Iraq. The port has an annual handling capacity of 11 million tonnes, supported by nine berths, a quay length of 2 kilometres and a draft of 13.5 metres.
In 2025, the terminal handled over 5.3 million tonnes of cargo and nearly 85,000 car equivalent units of Ro-Ro imports.
Abu Dhabi has been deeply involved in making investments in Jordan’s infrastructure sector. In February last year, AD Ports Group signed an agreement to manage and operate the Al-Madouneh customs centre in Amman, as MEED reported.
The Al-Madouneh customs centre covers about 1.3 million square metres (sq m) and was inaugurated in June last year.
The announcement followed AD Ports Group’s signing of a shareholders’ agreement in January 2024 between its digital arm, Maqta Gateway, and Jordan’s Aqaba Development Corporation regarding their existing joint-venture company, Maqta Ayla.
The joint venture company will upgrade operations at the Aqaba port complex in Jordan by implementing a port community system “that leverages Maqta Gateway’s expertise, also marking the first-ever export of Abu Dhabi’s key port digitalisation solution”, AD Ports said in a statement.
AD Ports Group operates the Aqaba cruise terminal, and selected Dubai-based real estate developer Mag Group to lead the first phase of the Marsa Zayed mixed-use project.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592973/main.jpg -
Chinese firm wins Ceer automotive supplier park deal6 February 2026

Beijing-headquartered Metallurgical Construction Corporation (MCC) has won a contract to undertake the steel structure works on the Ceer automotive supplier park in King Abdullah Economic City (KAEC).
The supplier park is located next to Ceer’s electric vehicle (EV) production facility in KAEC.
The automotive supplier park will include production and ancillary facilities for various suppliers and provide the material supply infrastructure for Ceer’s EV plant.
The facilities include:
- Cold stamping, body-in-white assembly and stamping facility – Shin Young (South Korea)
- Hot stamping, sub-frames and axles subsystem supply facility – Benteler Group (Austria)
- Façade and exterior-trim supply facility – JVIS (US)
- Instrument panel, trims and console supply facility – Forvia (France)
- Seat supplier – Lear Corporation (US)
Earlier this week, MEED exclusively reported that Ceer had awarded a contract to build the automotive supplier park to Jeddah-based construction firm Modern Building Leaders (MBL).
Netherlands-based engineering firm Arcadis is the project consultant, and Pac Project Advisors is the project management consultant.
Ceer retendered the project in September last year.
The latest contract award is another significant contract win for MCC in Saudi Arabia. In January, MEED reported that MCC had won a contract to undertake the steel structure works on Mohammed Bin Salman Stadium at the Qiddiya City project on the outskirts of Riyadh.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
In January, MCC won another contract to undertake steel structure works for the expansion of Medina airport in Saudi Arabia.
The scope covers work on boarding bridges, Terminal Two and the renovation of Terminal One.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592955/main.gif