Contractors submit prices for Master Gas System package
29 May 2024

Register for MEED's guest programme
Saudi Aramco has received revised commercial bids from contractors for package 9 of the third expansion phase of the Master Gas System network (MGS-3) in Saudi Arabia.
Contractors submitted revised prices for the package by 26 May, according to sources. The previous bid submission deadlines were 15 April, 6 May and 20 May.
The estimated $10bn MGS-3 project consists of 17 engineering, procurement and construction (EPC) packages. Aramco received technical bids for the 15 pipeline packages of the MGS-3 project, including package 9, during the third and fourth weeks of August. Contractors submitted commercial bids for the pipeline packages during the last two weeks of September, MEED previously reported.
While Aramco has selected contractors for 14 EPC packages of the MGS-3 project, prices submitted by bidders for package 9 are understood to have “exceeded Aramco’s budget”, according to sources.
Sources said this is understood to be the main reason Aramco sought revised commercial proposals for the package, adding that the scope of work on the package has also been modified.
The original scope of work on package 9 involved laying a 56-inch pipeline covering 458 kilometres from booster gas compression station 10 to sector 1 STS-2.
Master Gas System-3 EPC packages
Aramco has divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines across various locations in the kingdom.
The following contractors have been selected by Aramco for 15 EPC packages of the MGS-3 project:
- Package 1 – China Petroleum Engineering & Construction Company (China)
- Package 2 – Sepco (China)
- Packages 3 and 12 – Gas Arabian (Saudi Arabia)
- Package 4 – Mapa (Turkiye)
- Package 5 – Bin Quraya (Saudi Arabia)
- Packages 6 and 7 – Sinopec Petroleum Services (China)
- Package 8 – Larsen & Toubro Energy Hydrocarbon (India)
- Packages 10 and 14 – Nesma & Partners (Saudi Arabia) / Sicim (Italy)
- Package 11 – Max Streicher (Germany) / National Basics Company (Saudi Arabia)
- Packages 13, 15 and 17 – Kalpataru Projects International Limited (India)
Three of the selected contractors – China Petroleum Engineering & Construction Company (CPECC), Sepco Electric Power Construction Corporation (Sepco) and Kalpataru Projects International Limited – said they received official letters of award from Aramco for their packages.
Other successful bidders, including Indian contractor Larsen & Toubro Energy Hydrocarbon and Saudi Arabia-based Gas Arabian Services Company, have confirmed that they have received letters of intent from Aramco for their respective EPC packages, although they are yet to receive formal contracts.
Aramco is due to hold an official contract signing ceremony with contractors it has selected for the various packages of the MGS-3 project on 30 June, MEED recently reported.
Meanwhile, package 16, originally part of the tendering process for the MGS-3 project, has been carved out as a separate tender by Aramco. Contractors are preparing bids for package 16, which are due to be submitted by 30 May.
The original Master Gas System (MGS) was built in the 1970s and commissioned in 1982. Since then, Aramco has been supplying natural gas to its customers across Saudi Arabia via the network, mainly channelling associated gas from Ghawar and other oil fields.
Over the past decade, amid rising gas demand from Saudi Arabia’s industrial and household sectors, Aramco has undertaken projects to increase its non-associated gas production. In 2015, it launched the second expansion phase of the MGS (MGS-2).
Local contractor Arkad Engineering & Construction won the three main pipeline packages of MGS-2, worth an estimated $1.3bn, in early 2016.
EPC works were completed in 2021, increasing the MGS network’s gas handling and transport capacity from 8.4 billion cubic feet a day (cf/d) to 12.5 billion cf/d.
Exclusive from Meed
-
Chinese firm wins $265m Saudi hospital contract24 June 2026
-
Kuwait extends deadline for $718m drainage tender24 June 2026
-
Contractor wins Emaar Dubai Harbour project deal24 June 2026
-
-
Kuwait tenders oil manifold project24 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese firm wins $265m Saudi hospital contract24 June 2026
Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.
Construction is expected to take three years from the start date.
Prince Mohammed Bin Fahd University awarded the contract.
Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.
The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.
Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.
The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.
Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.
China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.
GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg -
Kuwait extends deadline for $718m drainage tender24 June 2026

Kuwait’s Ministry of Public Works (MPW) has extended the deadline for a major drainage tender estimated to be worth about KD222m ($718m).
The new bid submission deadline is 19 July.
The tender scope covers the construction of rainwater drainage networks across the residential areas of Sabah Al-Ahmad, South Sabah Al-Ahmad, Al-Khairan and Al-Wafra.
The MPW floated the tender on 22 March. The most recent deadline was 21 June.
According to regional projects tracker MEED Projects, the works include the construction of a major concrete sewer, three collection basins and extensive stormwater drainage basins.
Rainwater collection tanks will be connected through an independent network, with outlets to the sea via the Nuwaiseeb exit to manage overflow.
The infrastructure will also filter pollutants such as oils, minerals and sediments to protect water quality and support environmental sustainability.
The project aims to reduce surface runoff, prevent street and urban flooding, and improve groundwater recharge.
Kuwait’s MPW currently has several contracts out for tender for infrastructure works across various parts of the country.
Also, in March, the client released two additional tenders covering the construction of a treated water system in Kuwait’s southern region and another in Kuwait’s northern region.
Bids for both projects are due by 28 June.
Meanwhile, the MPW is planning to begin construction of the $3.3bn North Kabd sewage treatment plant, which has a planned capacity of up to 1 million cubic metres a day.
China State Construction Engineering Corporation (CSCEC) won the contract to build the plant earlier this year.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17411675/main.jpg -
Contractor wins Emaar Dubai Harbour project deal24 June 2026

Register for MEED’s 14-day trial access
Local construction firm Al-Sahel Contracting Company has won a contract to build The Bristol Luxury Hotels & Resorts project in Dubai.
The contract was awarded by local real estate developer Emaar Properties.
The Bristol Luxury Hotels & Resorts is located at Emaar Beachfront in Dubai Harbour.
The project comprises a 54-storey mixed-use building with about 150 hotel keys and 227 one- to four-bedroom apartments.
Enabling works have been completed by local firm Dutch Foundation.
Dubai-based Mirage Leisure & Development is the project’s consultant.
Construction is expected to be completed by 2028.
The contract award follows Emaar’s appointment of Dubai-based Aroma International Building Contracting to build the Address Grand Downtown tower.
The award also comes shortly after Emaar reported strong operating momentum in 2025, led by record property sales of AED80.4bn ($21.9bn), up 16% year on year.
The company’s revenue backlog from property sales rose to AED155bn ($42bn), supporting visibility on future revenue recognition.
Total revenue for 2025 reached AED49.6bn ($13.5bn), a 40% year-on-year increase. Earnings before interest, taxes, depreciation and amortisation grew 33% to AED25.6bn ($7bn), while net profit before tax rose 36% to AED25.7bn ($7bn).
Emaar’s platform continued to support performance across property development, malls, hospitality, leisure and international operations.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17411104/main.jpg -
Saudi Arabia launches new mineral exploration licensing round24 June 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Ministry of Industry & Mineral Resources (MIMR) has launched its tenth round of a mineral exploration licensing competition, qualifying 24 local and international companies and consortiums to participate.
The exploration opportunities offered under Round 10 cover about 13,000 square kilometres across the regions of Medina, Mecca, Riyadh, Qassim and Hail. They encompass several highly prospective mineralised belts that are said to contain significant deposits of gold, copper, silver, zinc and nickel.
One of the key areas offered in the round is the Nabithah-Ad Duwayhi (Dahlat Shabeb) Belt, which hosts the Ad-Duwayhi Mine, one of Saudi Arabia’s largest gold-producing operations, with annual production of approximately 180,000 ounces of gold.
Other notable exploration zones include the Sukhaybarat-Al-Safra Belt, recognised for its gold and base metals potential and home to the Sukhaybarat and Bulghah mining operations, as well as the Al-Nuqrah Belt, known for substantial gold resources and volcanogenic massive sulphide mineralisation rich in copper and zinc.
According to MIMR, 17 companies that previously qualified under Round 9 have retained their eligibility, while seven additional companies and consortiums successfully completed the Round 10 prequalification process.
The newly qualified bidders in Round 10 are:
- Anaam Al-Qarat for Trading / Sahara Mining Company consortium
- Danakali / Masadar Al-Zamarda for Mining consortium
- Power Metallic Mines
- PT ANTAM Tbk
- Saudi Arabian Mining Company (Maaden)
- Thurb Al-Hayya for Trading Company
- Wildsky Resources
The previously qualified participants from Round 9 are:
- Al-Ghazal Al-Arabi Mining Company
- Almasar Minerals Holding
- Al-Tasnim Enterprises
- Aurum Global Group
- Batin Al-Ard for Gold Company
- China National Geological and Mining Corporation
- DesertEx
- Eqleed-Indotan Mining Company
- Helderberg
- Jacaranda Minerals
- Midana Exploration
- Royal Road Arabia
- Saudi Gold Refinery
- Sierra Nevada Gold
- Sun Peak Metals
- The Distinguished Consortium Mining Company
- Vedanta
In a statement carried by the official Saudi Press Agency, MIMR said exploration licence competitions are conducted through a structured three-stage process designed to ensure transparency, competitiveness and equal opportunity for all participants.
The process begins with prequalification assessments covering technical expertise and financial capability, followed by a site-selection phase through the ministry’s digital mining platform, Taadeen. Where multiple bidders compete for the same exploration site, the process advances to a public, multi-round bidding stage, with licences awarded based on exploration expenditure commitments and predefined evaluation criteria.
The next phase of Round 10 will allow qualified bidders to select available exploration sites via the Taadeen platform, in accordance with established procedures that promote fair competition and enable companies to pursue opportunities aligned with their technical capabilities and investment strategies.
ALSO READ: Aramco and Maaden seek to form joint venture
“The continued participation of major international and regional mining companies reflects growing confidence in Saudi Arabia’s mining sector and the effectiveness of its transparent licensing framework,” MIMR said in its statement.
Jarrah Aljarrah, a ministry spokesperson, said increasing participation in successive exploration licensing rounds demonstrates growing investor confidence in the kingdom’s mining ecosystem, supported by regulatory reforms, improved availability of geological data, transparent licensing mechanisms and a steadily expanding pipeline of exploration opportunities.
Saudi Arabia’s metals and mining sector is pivotal to the country’s non-oil growth trajectory. Commercial exploitation of the kingdom’s mineral resource base – most of which remains untapped – is a key component of the Saudi Vision 2030 socio-economic transformation strategy.
The kingdom took a first step towards realising the commercial potential of its mineral resources when it enacted the Mining Investment Law in 2021. Since the law came into effect, MIMR has awarded about 3,248 mining permits to local and foreign firms under its accelerated exploration initiative, including alone.
Addressing the Future Minerals Forum in Riyadh in January 2024, Bandar Alkhorayef, the kingdom’s minister of industry and mineral resources, said Saudi Arabia’s natural resources are worth $2.5tn – an increase of more than 90% compared to the 2016 estimate.
This near-doubling of natural resource estimates – which exclude fossil fuels and include phosphate, gold and rare earths – is expected to provide a stimulus to the kingdom’s nascent mining industry.
ALSO READ: Maaden mineral resources grow by 7.8 million ounces
https://image.digitalinsightresearch.in/uploads/NewsArticle/17398549/main.jpg -
Kuwait tenders oil manifold project24 June 2026
State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to construct remote header manifolds and associated works in the southern and eastern regions of Kuwait.
A meeting with prospective contractors has been scheduled for 21 July 2026, and bids are due to be submitted ahead of a deadline on 20 September 2026.
Manifolds are devices used in the oil sector to divide the flow of liquids from a single source to several outlets, or to collect liquids, or vice versa.
Previously, a project with a similar scope in the same region was awarded to the Kuwaiti contractor Al-Ghanim International General Trading & Contracting.
In 2016, it signed a contract worth $435m to construct remote header manifolds and associated works in the south and east Kuwait areas.
The scope of that contract included design, procurement, construction and commissioning of 25 remote manifold stations and associated pipelines in south and east Kuwait using multi-phase pumps to deliver liquids to gathering centres.
Kuwait’s oil fields are connected to more than 25 gathering centres, which serve as collection points for crude oil produced by several wells connected by flowlines, providing initial treatment by separating associated gas and removing salt.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17409564/main.jpg