World’s tallest tower is back on track
24 October 2024

The chairman of Saudi Arabia’s Kingdom Holding, Prince Alwaleed Bin Talal Al-Saud, published a two-word message on social media platform X on 2 October. The message, which said, “We’re back,” was accompanied by an animated video of a fly-through rendering of the world’s next tallest building, the 1,000-metre-plus Jeddah Tower.
The post was made shortly after a pivotal event for the tower. Earlier that day, the company developing the project, Jeddah Economic Company (JEC), in which Kingdom Holding is a shareholder, signed a contract with the local Saudi Binladin Group (SBG) to resume construction work on the scheme. The SR7.2bn ($2bn) contract includes SR1.1bn for works already completed on the tower.
SBG was the original contractor on the project before construction work stalled in 2018. This left the tower’s superstructure about one-third complete, with 63 floors built out of 157.
Speaking to MEED after the contract signing, Kingdom Holding’s CEO Talal Ibrahim Almaiman echoed and expanded on Prince Alwaleed’s post.
“We’re back. People have been asking questions about the project after it froze in February 2018. We had the patience, but also the determination to finish it. We will deliver what we promised to deliver at the highest possible quality, with a contractor with a long history of success when it comes to handling such huge projects,” he says.
Contractor selection
Appointing a firm to build a tower that will be the world’s tallest is more than just a major contract signing.
“There are plenty of successes. Saudi Arabia will soon have the record for the tallest tower in the world. Kingdom Holding is doing what it does best, completing projects at the highest level. Saudi Binladin is going to get back its glory. And the people of Jeddah will have the tallest tower in the world,” says Almaiman.
The appointment of the original contractor after having started a fresh tender process for the project in late 2023 has taken some in the market by surprise.
“Rather than talk about the past, I would like to talk about the future,” says Almaiman.
“SBG has gone through some technical and financial difficulties in the past. The latest announcement, when the Ministry of Finance said it would support them with their issues with the banks, gave them huge financial credibility. The government of Saudi Arabia being a partner and shareholder in SBG gives us huge confidence,” he adds.
With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower. “The contractor spent a lot of time with our designers, quantity surveyors and other experts and went through each part of the tower and how they plan to build it by moving from floor to floor, and this method was approved by us,” says Almaiman.
Programme and price were also key factors. “The other consortium we spoke to was planning to finish in 58 months, whereas Binladin was saying 42 months, which is three and a half years,” Almaiman explains, adding: “For pricing, we got a good deal.”
In addition, there were several practical reasons for selecting the original contractor on the project, according to Almaiman. SBG already has offices established on site and, as a Jeddah-based company with a long history of delivering major projects in Saudi Arabia, it has well-established connections with the local supply chain.
With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower
Future vision
Although the Jeddah Tower project has a history that can be traced back over a decade, its ambitions are very much in tune with those of modern Saudi Arabia.
“It is in line with the government’s Vision 2030 to create attractions for Saudi Arabia,” says Almaiman.
Vision 2030 reinforces the importance of the three-and-a-half-year programme that SBG offered because it puts the tower comfortably on course to be delivered in mid-2028, well ahead of 2030.
Completing the world’s tallest tower is just the start for the wider Jeddah Economic City development.
“The tower is part of phase one, which is about 1.1 million square metres,” says Almaiman.
“We are now in discussions with investors about coming in and developing. We will contribute land. We will not be selling land at phase one for the sake of selling. We will control the development and the building code,” he adds.
Securing the title
Building the world’s tallest tower inevitably prompts conversations and speculation about other rival towers being planned around the world.
However, Almaiman is confident that Jeddah Tower’s reign as the world’s tallest will be lengthy, as he, perhaps better than anyone else, understands the challenges involved in building record-breaking towers.
“The reason for calling the tower 1,000-plus-metres is because we will add more height. The final height of the tower will be decided by HRH Prince Alwaleed Bin Talal,” he says.
“The other developers will probably need around 10 years to catch up, and if we keep the title for that long, I will be happy.”
Exclusive from Meed
-
Lowest bidder emerges for Kuwait Airport Terminal 2 operations19 October 2026
-
Dubai tenders Al-Maktoum-Dubai South drainage scheme19 October 2026
-
Contractor wins $44m Morocco rail stations deal19 October 2026
-
Firms submit Dubai multibillion-dollar road scheme interest19 October 2026
-
Libya seeks offshore contractors for $8bn gas project19 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Lowest bidder emerges for Kuwait Airport Terminal 2 operations19 October 2026

Ireland’s DAA International has emerged as the lowest bidder for the contract to operate, manage and maintain the new passenger Terminal 2 (T2) at Kuwait International airport, submitting an offer of KD419m ($1.35bn).
Official price-opening records released by Kuwait’s Central Agency for Public Tenders on behalf of the Directorate General of Civil Aviation show three international airport operators submitted commercial bids for the tender.
DAA International’s proposal undercut its nearest rival by about 45%. Turkiye’s TAV Airports Holding submitted the second-lowest offer at KD764.15m ($2.46bn), while South Korea’s Incheon International Airport Corporation bid KD959.48m ($3.1bn).
All three proposals were marked as approved in the tender committee’s price disclosure.
The contract entails the operation, management and improvement of training, maintenance and development services across Terminal 2 and its associated aircraft parking aprons.
The remit also includes corporate management of centralised operation and maintenance across the broader Kuwait International airport model, centralising operational procedures, systems integration and service delivery across the aviation hub.
Technical documents indicate the winning operator will oversee facility management, terminal operational readiness, passenger processing systems, apron operations and staff development programmes before and after the complex’s commercial launch.
MEED reported in June 2023 that six airport operators had initially been invited to bid for the Terminal 2 operating concession.
Terminal 2 is the centrepiece of Kuwait International airport’s multibillion-dollar expansion, aimed at boosting total handling capacity to 25 million passengers a year.
Turkish contractor Limak Insaat is executing the main terminal building under an estimated $4.34bn contract awarded in 2016.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20747061/main.png -
Dubai tenders Al-Maktoum-Dubai South drainage scheme19 October 2026
Dubai Municipality has invited contractors to submit bids by 5 November for the construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
The project, designated TF-06-C2, involves approximately 20 kilometres of pipelines with diameters ranging from 400mm to 3,000mm. The works will use deep trenchless construction and conventional open-cut methods.
The scheme is one of four projects, for which a project management consultancy (PMC) tender was issued earlier this month.
The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.
The consultancy covers the following projects:
- TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
- TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
- TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
- TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand
The projects are part of Dubai Municipality’s wider Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.
Investment in the UAE water sector has been dominated by stormwater drainage and network resilience schemes this year, as Dubai Municipality advances procurement under its AED30bn ($8.1bn) Tasreef programme.
TF-07-C1
As previously reported, contractors are preparing to submit bids on 22 October for the main construction contract for TF-07-C1.
The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.
It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.
TF-24-C1
Bids for TF-24-C1 were submitted on 1 October, with Nael Construction & Contracting, Al-Nasr Contracting Company and Al-Kharafi & Sons understood to be among the bidders.
The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18km of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.
As MEED understands, the main contract tender for TF-06-C1 has yet to be released.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20746611/main.jpg -
Contractor wins $44m Morocco rail stations deal19 October 2026
Morocco’s national railway operator, Office National des Chemins de Fer (ONCF), has awarded a MD437.6m ($44.5m) contract to local firm Jet Contractors to build five railway stations along the Benguerir-Marrakech corridor.
The project forms part of the wider Kenitra-Marrakech high-speed rail development programme.
Jet Contractors will build one high-speed rail station and four regional express rail stations.
These include two stations in Benguerir, and one each at Sidi Bou Othmane, Sidi Ghanem and Marrakech Stadium.
The scope of work includes construction and fit-out of the stations and associated infrastructure, including concrete structures, platforms, ancillary facilities, passageways, circulation areas and connection zones within the stations.
It also covers architectural finishing works; testing and commissioning of electrical networks; and all mechanical, electrical and plumbing services.
The contractor will also provide all safety, security and protection systems, including alarms, fire detection and firefighting systems, and surveillance systems.
Morocco awarded multiple civil works contracts in 2024 to international and local firms to build its Kenitra-Marrakech high-speed railway line.
The rail project is part of a $37bn strategy to connect more of Morocco’s cities, ports and airports by rail. It will stretch 375 kilometres from Kenitra on the northwest coast to Marrakech in the south.
The project is divided into seven lots, each measuring 36km to 64km. The rail link will pass through cities including Rabat, Sale and Casablanca.
The link will extend the Al-Boraq high-speed rail line between Tangier, Rabat and Casablanca. The line began operating in 2018 and was Africa’s first high-speed railway system.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20745963/main.jpg -
Firms submit Dubai multibillion-dollar road scheme interest19 October 2026

Register for MEED’s 14-day trial access
Contractors submitted expressions of interest on 10 October for a design-and-build contract for a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.
Dubai’s Roads & Transport Authority (RTA) held an online meeting after the submissions to prepare for the prequalification phase of tendering, expected to start in a few weeks.
The scope covers about 30 kilometres (km) of works.
These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.
The RTA floated the expression of interest notice to contractors in early September.
The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.
Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.
The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through traffic while existing at-grade lanes served local access.
The plans ultimately became standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.
The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.
Planning for growth
Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.
In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan.
In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.
The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20745908/main.jpg -
Libya seeks offshore contractors for $8bn gas project19 October 2026
Libya’s Mellitah Oil & Gas Company (MOG) has invited companies to prequalify for a major offshore package as part of its Mellitah Complex Expansion & CO2 Management Integrated Development Project, which is estimated to be worth about $8bn.
The package is estimated at around $3bn and focuses on developing offshore pipelines and subsea systems for the “E” Offshore Installation Project and CO2 project.
The deadline to submit prequalification documents is 5 November. The contract will use the engineering, procurement, installation and commissioning (EPIC) model.
MOG is a joint venture of Libya’s National Oil Corporation and Italian oil and gas company Eni.
This is not the first time MOG has invited submissions for the offshore pipelines and subsea systems package. The company originally launched a prequalification process for the EPIC contract in 2021, but the project experienced delays and the process was eventually cancelled. The prequalification process was restarted nearly three years later, but it was also ultimately abandoned.
Complex expansion
As part of the Mellitah Complex Expansion & CO2 Management Integrated Development Project, two offshore structures – Structure A and Structure E – will be developed in Libya’s offshore block NC 41.
Structure A is in the central-western part of the area, about 80 kilometres (km) from the Libyan coast, with a water depth of 95-105 metres.
Structure E is located in the central-eastern part of the area, about 130km from the Libyan coast, in a water depth of 205-235 metres.
The scope of the wider project includes:
- A new wellhead platform installed in 96 metres of water as part of the development of Structure A
- A new production platform installed in about 220 metres of water depth as part of the development of Structure E
- Modification of the existing Sabratha platform
- Sealines and subsea systems for structures A and E
- Upgrading the existing onshore Mellitah complex
Project contract awards
In June 2024, MOG awarded an offshore engineering, procurement and construction (EPC) contract worth €1.2bn ($1.28bn), which was part of the Mellitah Complex Expansion & CO2 Management Integrated Development Project.
The contract was awarded to a consortium of three Italian companies: Rosetti Marino, Kerry Project Logistics and Gruppo Antonini.
In a statement, Rosetti Marino said its share of the project contract was worth €400m ($428m), comprising 33% of the total contract value.
Rosetti Marino said its scope of work includes EPC and load-out activities to deliver the topside of the approximately 6,000-tonne gas production wellhead platform, named WHP-A, to be installed off the coast of Libya.
Project setbacks
During 2023 and 2024, several setbacks affected the Mellitah Complex Expansion & CO2 Management Integrated Development Project.
In November 2023, MOG restarted the prequalification process for an upstream offshore package worth an estimated $700m.
The project scope involves modifications to the offshore Sabratha platform at the Bahr Essalam field.
Less than two months later, MOG restarted prequalification for a second package as part of the integrated development project.
The scope of the second package covers key sealine and subsea systems.
No reason was given for restarting the prequalification process for two of the project’s packages.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20738707/main.jpg