World’s tallest tower is back on track

24 October 2024

 

The chairman of Saudi Arabia’s Kingdom Holding, Prince Alwaleed Bin Talal Al-Saud, published a two-word message on social media platform X on 2 October. The message, which said, “We’re back,” was accompanied by an animated video of a fly-through rendering of the world’s next tallest building, the 1,000-metre-plus Jeddah Tower. 

The post was made shortly after a pivotal event for the tower. Earlier that day, the company developing the project, Jeddah Economic Company (JEC), in which Kingdom Holding is a shareholder, signed a contract with the local Saudi Binladin Group (SBG) to resume construction work on the scheme. The SR7.2bn ($2bn) contract includes SR1.1bn for works already completed on the tower. 

SBG was the original contractor on the project before construction work stalled in 2018. This left the tower’s superstructure about one-third complete, with 63 floors built out of 157. 

Speaking to MEED after the contract signing, Kingdom Holding’s CEO Talal Ibrahim Almaiman echoed and expanded on Prince Alwaleed’s post. 

“We’re back. People have been asking questions about the project after it froze in February 2018. We had the patience, but also the determination to finish it. We will deliver what we promised to deliver at the highest possible quality, with a contractor with a long history of success when it comes to handling such huge projects,” he says.

Contractor selection

Appointing a firm to build a tower that will be the world’s tallest is more than just a major contract signing. 

“There are plenty of successes. Saudi Arabia will soon have the record for the tallest tower in the world. Kingdom Holding is doing what it does best, completing projects at the highest level. Saudi Binladin is going to get back its glory. And the people of Jeddah will have the tallest tower in the world,” says Almaiman.

The appointment of the original contractor after having started a fresh tender process for the project in late 2023 has taken some in the market by surprise. 

“Rather than talk about the past, I would like to talk about the future,” says Almaiman.

“SBG has gone through some technical and financial difficulties in the past. The latest announcement, when the Ministry of Finance said it would support them with their issues with the banks, gave them huge financial credibility. The government of Saudi Arabia being a partner and shareholder in SBG gives us huge confidence,” he adds.

With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower. “The contractor spent a lot of time with our designers, quantity surveyors and other experts and went through each part of the tower and how they plan to build it by moving from floor to floor, and this method was approved by us,” says Almaiman. 

Programme and price were also key factors. “The other consortium we spoke to was planning to finish in 58 months, whereas Binladin was saying 42 months, which is three and a half years,” Almaiman explains, adding: “For pricing, we got a good deal.”

In addition, there were several practical reasons for selecting the original contractor on the project, according to Almaiman. SBG already has offices established on site and, as a Jeddah-based company with a long history of delivering major projects in Saudi Arabia, it has well-established connections with the local supply chain.

With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower

Future vision

Although the Jeddah Tower project has a history that can be traced back over a decade, its ambitions are very much in tune with those of modern Saudi Arabia. 

“It is in line with the government’s Vision 2030 to create attractions for Saudi Arabia,” says Almaiman.

Vision 2030 reinforces the importance of the three-and-a-half-year programme that SBG offered because it puts the tower comfortably on course to be delivered in mid-2028, well ahead of 2030.

Completing the world’s tallest tower is just the start for the wider Jeddah Economic City development. 

“The tower is part of phase one, which is about 1.1 million square metres,” says Almaiman. 

“We are now in discussions with investors about coming in and developing. We will contribute land. We will not be selling land at phase one for the sake of selling. We will control the development and the building code,” he adds.

Securing the title

Building the world’s tallest tower inevitably prompts conversations and speculation about other rival towers being planned around the world. 

However, Almaiman is confident that Jeddah Tower’s reign as the world’s tallest will be lengthy, as he, perhaps better than anyone else, understands the challenges involved in building record-breaking towers. 

“The reason for calling the tower 1,000-plus-metres is because we will add more height. The final height of the tower will be decided by HRH Prince Alwaleed Bin Talal,” he says. 

“The other developers will probably need around 10 years to catch up, and if we keep the title for that long, I will be happy.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12787969/main.gif
Colin Foreman
Related Articles
  • Focus shifts to delivery of Iraq utilities expansion

    12 May 2026

     

    Iraq’s power and water sector recorded its largest year of investment on record in 2025, with more than $17bn in combined contract awards.

    Several long-planned water infrastructure schemes finally reached contract award stage amid mounting supply pressures in the south of the country and a growing reliance on new desalination projects.

    Iraq awarded $10bn-worth of water infrastructure contracts between January 2025 and May 2026, according to regional projects tracker MEED Projects.

    This compares with just $1.8bn in total awards across 2022, 2023 and 2024, when only one seawater desalination plant reached the contract award stage.

    Desalination projects

    Attention is now turning to the delivery phase of new plants led by a series of major desalination and water treatment projects in Basra governorate.

    In February, Iraqi officials said the flagship $2.42bn Basra seawater desalination plant could be financed through the Iraqi-Chinese Fund, weeks after the main engineering, procurement and construction (EPC) contract was awarded to PowerChina.

    Located on the Arabian Gulf coast in Al-Faw, the plant is designed to produce 1 million cubic metres a day (cm/d) of potable water. The project also includes a water transmission network supplying 11 cities and a dedicated 300MW power plant.

    Baghdad had earlier announced plans for four additional desalination plants across the province in July 2025. These include the Shatt Al-Arab plant, planned to produce 120,000 cm/d of desalinated water, and the Al-Faw and Al-Siba plants, each with a capacity of 72,000 cm/d.

    The joint venture of Baghdad-headquartered Al-Rida Investment Group and PowerChina has been appointed as the main contractor for each project, with construction expected to begin in the third quarter of 2026.

    Additional schemes include the $72m Safwan desalination plant and the $70m Abu Flous desalination project. Abu Flous is being undertaken by the Ministry of Water Resources and is designed to have a capacity of 72,000 cm/d.

    The push to advance new projects follows warnings issued last year by Iraq’s High Commission for Human Rights about a worsening humanitarian situation linked to declining river flows and rising salinity levels in the Shatt Al-Arab waterway.

    Alongside municipal water projects, Iraq is also advancing large industrial water infrastructure schemes tied to the energy sector. Last August, Iraq approved the award of the Common Seawater Supply Project package for the Artawi oil field to South Korea’s Hyundai Engineering & Construction.

    The estimated $3.16bn contract covers the engineering, procurement, supply, construction, commissioning and operation of a major seawater treatment facility. Construction is expected to begin in 2026, further reflecting the scale of projects now in the execution stage.

    Power expansion

    In parallel, Iraq’s power sector is undergoing one of its largest expansion programmes in decades as the government attempts to address chronic electricity shortages, diversify fuel sources and strengthen regional grid connectivity. Over $40bn-worth of projects are under execution, following $4.2bn in new contracts last year.

    In August 2025, the Iraqi cabinet approved five major power generation schemes with a combined capacity exceeding 10GW. The projects represent one of the country’s largest-ever single rounds of power project approvals.

    The centrepiece of the programme is three independent power producer (IPP) combined-cycle plants at Al-Faw, Abu Ghraib and Kirkuk, with a total capacity of 7,500MW.

    The largest schemes are the 3,000MW Al-Faw plant in southern Iraq, with US-based General Electric as the EPC contractor, and the 3,000MW Abu Ghraib facility near Baghdad. Both projects will be implemented under 25-year build-own-operate models.

    A 1,500MW combined-cycle plant in Kirkuk will also be developed under long-term power purchase agreements backed by sovereign guarantees from the Finance Ministry. US-based GE Vernova is the technology provider for all three projects.

    Furthermore, the government has approved two thermal power plants in Najaf and Youssifiyah, with planned capacities of 1,500MW and 1,800MW, respectively.

    This is part of a wider 20-year electricity strategy unveiled last year in partnership with Siemens Energy and GE Vernova. The programme aims to add 57GW of new generation capacity through a mix of gas-fired, thermal and renewable energy projects.

    Electricity shortfall

    The scale of the challenge means timely project execution will be critical. Iraq currently produces about 28GW of electricity, according to the Electricity Ministry, but demand during peak summer periods is estimated at more than 50GW. The shortfall continues to result in widespread outages and pressure on the national grid.

    The fragility of the system was exposed again in March, when Iraq suffered nationwide electricity blackouts after a sudden drop in gas supplies to the Rumaila power plant in Basra. The disruption led to the loss of about 1,900MW of generation capacity and triggered a nationwide grid collapse.

    The incident highlighted Iraq’s continued dependence on associated gas production from the oil sector. With regional geopolitical tensions affecting oil exports and production, gas availability for power generation has become increasingly vulnerable.

    Solar plants

    As part of a strategy to diversify energy sources, the country inaugurated the first phase of the 300MW Karbala solar IPP plant in September 2025, marking Iraq’s first utility-scale solar scheme connected to the national grid.

    Developed by a consortium of Norway’s Scatec, Egypt’s Orascom Construction and Iraq’s Al-Bilal Group, the project forms part of the government’s target to add 10GW of solar energy by 2030.

    These plans also include the 1GW solar IPP in Najaf, now under construction and scheduled for commissioning in 2028.

    Looking further ahead, the Iraqi government announced in February that it has allocated more than 140 sites for new solar power plants, following a six-month identification process. The locations are distributed across several regions, including the outskirts of Baghdad and areas such as Nahrawan, Al-Nasr, Al-Salam, Al-Hamamiyat, Taji and Al-Husseiniya.

    Meanwhile, regional interconnection projects are also becoming increasingly important. Iraq is progressing with plans to integrate into the GCC electricity grid through a new 400kV transmission link between Kuwait’s Al-Wafra station and Iraq’s Al-Faw station.

    The first phase of the project will allow 500MW of electricity imports into Iraq, rising to 1,800MW over time. Iraq is targeting full integration of the GCC-Iraq grid by the end of 2026.


    MEED’s June 2026 report on Iraq also includes:

    > OVERVIEW: Iraq enters era of resilience, reform and rising risks
    > OIL & GAS: Iraqi oil and gas sector in crisis

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16797622/main.gif
    Mark Dowdall
  • Abu Dhabi announces $15bn infrastructure PPP projects

    12 May 2026

    The Abu Dhabi Investment Office and the Abu Dhabi Projects and Infrastructure Centre have launched a AED55bn ($15bn) public-private partnership (PPP) pipeline of 24 projects to be tendered in 2026 and 2027.

    The projects will be tendered across the transport, infrastructure and social sectors.

    According to a statement published by the Abu Dhabi Media Office, the transport sector accounts for 11 road projects, with AED35bn ($9.5bn) of construction capex, covering more than 300 kilometres of new and upgraded roads, tunnels, intersections and related network works.

    The infrastructure pipeline includes five projects budgeted at AED11bn ($3bn), covering dams, water storage, flood control, stormwater upgrades and urban landscaping.

    Social infrastructure includes eight projects budgeted at AED9bn ($2.5bn), covering sports facilities, specialist healthcare assets, schools and university campuses.

    The statement added that the pipeline forms part of Abu Dhabi’s infrastructure delivery plan and will be executed through PPP structures.

    It is also intended to support company establishment in the emirate, local content objectives, and supply-chain and industrial capacity.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16793904/main.jpg
    Yasir Iqbal
  • Saudi Arabia tenders GCC rail link from Kuwait to UAE border

    12 May 2026

     

    Saudi Arabia has begun the procurement process to deliver its portion of the GCC railway, which will connect all six member states.

    Saudi Arabia Railways (SAR) issued a tender for design consultancy services for the project on 7 May, with a bid submission deadline of 30 June.

    It includes the concept design, preliminary design and Issued for Construction (IFC) design stages of the network.

    SAR requires the selected consultant to review, update and complete the existing preliminary design of the network.

    The kingdom’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, at Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Türkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have been progressing with renewed impetus since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, the Qatari cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will span 2,186 kilometres, beginning in Kuwait, passing through Dammam in Saudi Arabia, reaching Bahrain via a planned causeway, and continuing from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman.

    The network’s route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but divided between its constituent parts.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16793841/main.jpg
    Yasir Iqbal
  • Kuwait tenders upstream oil project

    12 May 2026

    State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to develop power infrastructure to provide electricity to the country’s Bahra oil field.

    The project focuses on constructing an 11kV, 72MW main intake in the Bahra-A area.

    It also includes the development of 11kV, 20MW substations in the Bahra-A2 area, and the conversion of a substation in the Bahra-A1 area in northern Kuwait.

    An initial meeting for the project is scheduled for 7 June, and bids are due by 9 August.

    Kuwait’s oil and gas sector has been severely impacted by the blockade of the Strait of Hormuz, through which all of its crude exports are normally shipped.

    The country recorded zero crude oil exports in April for the first time since the end of the Gulf War in 1991, according to shipping monitor TankerTrackers.com.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792080/main.png
    Wil Crisp
  • Chinese company signs deal to develop Syria cement plant

    12 May 2026

    China’s Jiangsu Pengfei Group has signed a deal with Damascus-based Al-Hasan Holding Group (HHG) to develop a cement plant in Syria’s Raqa governorate.

    The “strategic agreement” was signed on 29 April, according to a statement from HHG.

    The clinker production line will have a capacity of 5,000 tonnes a day (t/d).

    Syria is seeking to expand cement production capacity to meet demand from the domestic construction sector.

    HHG is an integrated investment conglomerate headquartered in Damascus with a portfolio of companies across sectors including industry, trade, energy, construction, tourism and services.

    It was founded by the Syrian businessman Hassan Kamel Al-Hasan.

    Jiangsu Pengfei Group is a manufacturer of rotary kiln and grinding equipment.

    The company is involved in the design, manufacture and service of equipment in the fields of building materials, metallurgy and the chemical industry.

    It is also an engineering, procurement and construction service provider that has completed more than 100 cement production line projects.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16792079/main.jpg
    Wil Crisp