World’s tallest tower is back on track

24 October 2024

 

The chairman of Saudi Arabia’s Kingdom Holding, Prince Alwaleed Bin Talal Al-Saud, published a two-word message on social media platform X on 2 October. The message, which said, “We’re back,” was accompanied by an animated video of a fly-through rendering of the world’s next tallest building, the 1,000-metre-plus Jeddah Tower. 

The post was made shortly after a pivotal event for the tower. Earlier that day, the company developing the project, Jeddah Economic Company (JEC), in which Kingdom Holding is a shareholder, signed a contract with the local Saudi Binladin Group (SBG) to resume construction work on the scheme. The SR7.2bn ($2bn) contract includes SR1.1bn for works already completed on the tower. 

SBG was the original contractor on the project before construction work stalled in 2018. This left the tower’s superstructure about one-third complete, with 63 floors built out of 157. 

Speaking to MEED after the contract signing, Kingdom Holding’s CEO Talal Ibrahim Almaiman echoed and expanded on Prince Alwaleed’s post. 

“We’re back. People have been asking questions about the project after it froze in February 2018. We had the patience, but also the determination to finish it. We will deliver what we promised to deliver at the highest possible quality, with a contractor with a long history of success when it comes to handling such huge projects,” he says.

Contractor selection

Appointing a firm to build a tower that will be the world’s tallest is more than just a major contract signing. 

“There are plenty of successes. Saudi Arabia will soon have the record for the tallest tower in the world. Kingdom Holding is doing what it does best, completing projects at the highest level. Saudi Binladin is going to get back its glory. And the people of Jeddah will have the tallest tower in the world,” says Almaiman.

The appointment of the original contractor after having started a fresh tender process for the project in late 2023 has taken some in the market by surprise. 

“Rather than talk about the past, I would like to talk about the future,” says Almaiman.

“SBG has gone through some technical and financial difficulties in the past. The latest announcement, when the Ministry of Finance said it would support them with their issues with the banks, gave them huge financial credibility. The government of Saudi Arabia being a partner and shareholder in SBG gives us huge confidence,” he adds.

With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower. “The contractor spent a lot of time with our designers, quantity surveyors and other experts and went through each part of the tower and how they plan to build it by moving from floor to floor, and this method was approved by us,” says Almaiman. 

Programme and price were also key factors. “The other consortium we spoke to was planning to finish in 58 months, whereas Binladin was saying 42 months, which is three and a half years,” Almaiman explains, adding: “For pricing, we got a good deal.”

In addition, there were several practical reasons for selecting the original contractor on the project, according to Almaiman. SBG already has offices established on site and, as a Jeddah-based company with a long history of delivering major projects in Saudi Arabia, it has well-established connections with the local supply chain.

With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower

Future vision

Although the Jeddah Tower project has a history that can be traced back over a decade, its ambitions are very much in tune with those of modern Saudi Arabia. 

“It is in line with the government’s Vision 2030 to create attractions for Saudi Arabia,” says Almaiman.

Vision 2030 reinforces the importance of the three-and-a-half-year programme that SBG offered because it puts the tower comfortably on course to be delivered in mid-2028, well ahead of 2030.

Completing the world’s tallest tower is just the start for the wider Jeddah Economic City development. 

“The tower is part of phase one, which is about 1.1 million square metres,” says Almaiman. 

“We are now in discussions with investors about coming in and developing. We will contribute land. We will not be selling land at phase one for the sake of selling. We will control the development and the building code,” he adds.

Securing the title

Building the world’s tallest tower inevitably prompts conversations and speculation about other rival towers being planned around the world. 

However, Almaiman is confident that Jeddah Tower’s reign as the world’s tallest will be lengthy, as he, perhaps better than anyone else, understands the challenges involved in building record-breaking towers. 

“The reason for calling the tower 1,000-plus-metres is because we will add more height. The final height of the tower will be decided by HRH Prince Alwaleed Bin Talal,” he says. 

“The other developers will probably need around 10 years to catch up, and if we keep the title for that long, I will be happy.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12787969/main.gif
Colin Foreman
Related Articles
  • Contractors compete for Riyadh airport Terminal 6 work

    2 November 2026

     

    Contractors are preparing bids for the main construction contract for Terminal 6 at King Salman International airport (KSIA) in Riyadh.

    MEED understands that the consortiums have been given until January to submit their proposals.

    The participating consortiums are:

    • Al-Gihaz Holding / TAV Construction / Webuild (local/Turkiye/Italy)
    • Modern Building Leaders / Powerchina / Metallurgical Corporation of China (loca/China/China)
    • UCC Holding / Consolidated Contractors Company (Qatar/Greece)

    Last month, MEED exclusively reported that contractor teams have completed the early contractor involvement phase of the project.

    Under the completed phase, the shortlisted teams submitted detailed construction methodologies and technical design proposals.

    King Salman International Airport Development Company (KSIADC) is a subsidiary of Saudi sovereign wealth vehicle the Public Investment Fund.

    Terminal 6 is planned to boost the airport’s annual capacity by 40 million passengers. KSIADC aims to complete the terminal ahead of Expo 2030 Riyadh.

    In May 2025, MEED reported that US-based Bechtel had been appointed as delivery partner for the passenger terminals at KSIA.

    UK-based Foster + Partners designed the masterplan, including the terminals, six parallel runways and a multi-asset real estate district.

    US-based engineering firm Jacobs is providing specialist consultancy services for the masterplan and runway design, while UK-headquartered Mace is acting as delivery partner for the broader development. Local firm Nera secured the airspace design consultancy contract.

    The KSIA project covers about 57 square kilometres (sq km) and incorporates the existing terminals at King Khalid International airport. The scheme will feature 12 sq km of airport support facilities, residential and recreational zones, retail assets and logistics parks.

    The development is targeted to handle up to 120 million passengers a year by 2030 and 185 million passengers by 2050, in addition to an annual cargo throughput of 3.5 million tonnes by 2050.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21087339/main.jpg
    Yasir Iqbal
  • Contractors prepare bids for Morocco power line

    2 November 2026

     

    Contractors are preparing bids for a 160-kilometre (km), 400kV transmission line linking Guercif and Fes East in Morocco, following a site visit on 1 October.

    The project is being developed by the Office National de l'Electricite et de l'Eau Potable (Onee) to connect the Saka solar photovoltaic power plant to the national electricity grid.

    According to sources, at least eight contractors attended the site visit last month, including:

    • Butec (Lebanon)
    • CEEC Northeast Electric No.2 (China)
    • Cegelec (France)
    • EPME Electric (Morocco)
    • Hideleco (Egypt)
    • Kec International (India)
    • PowerChina (China)
    • Transrail (India)

    The project comprises two lots. The first involves a 90km transmission line between Guercif and Taza, while the second covers a 70km section between Taza and Fes East.

    The scope of work includes the construction of tower foundations, installation of transmission supports and conductors, and associated high-voltage equipment. It also includes optical fibre cables for communications and monitoring, access roads and other supporting infrastructure.

    The tender was issued in September with bids originally due by 21 October. The deadline has now been extended to 25 November.

    The project is part of a wider programme by Onee to expand Morocco's electricity transmission network and accommodate additional renewable energy capacity.

    In June, the utility commissioned a 274km, 400kV transmission line linking Chemaia and Mediouna, near Casablanca.

    Onee plans to expand its high- and extra-high-voltage transmission network from more than 30,700km to 37,000km by 2030.

    In August, it approved a $26.4bn investment programme for the 2026-30 period, covering electricity and drinking water infrastructure.

    The programme has allocated about $21.9bn to electricity projects and $4.5bn to drinking water infrastructure, with about 72% of the investment to be financed by the private sector, according to Onee.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21083507/main1257.jpg
    Mark Dowdall
  • Adnoc Onshore allows more time for Bab gas cap well tie-in bids

    2 November 2026

     

    The onshore business of Abu Dhabi National Oil Company (Adnoc Onshore) has allowed contractors more time to prepare proposals for a project to tie in gas-producing and injection wells at the gas cap reservoirs of Abu Dhabi’s onshore Bab field.

    The well tie-in scope, estimated to be worth more than $800m, forms part of Adnoc Group’s wider integrated Bab gas cap development programme.

    The overall programme is being led and overseen by Adnoc Gas, another Adnoc Group subsidiary. Its central element is the construction of gas-processing infrastructure to handle incremental gas output expected from developing the Bab gas caps.

    Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on the project in late September, MEED previously reported.

    Contractors have been given until 16 November to submit technical bids for the project, according to sources. The previous deadline was 29 October.

    MEED previously reported that Adnoc Onshore issued an expressions of interest (EoI) notice for the Bab gas production and injector well tie-in project on 13 May, with contractors submitting responses by 20 May.

    The scope of work on the project covers the following:

    • Tie-in of 99 new wells from Bab gas cap reservoirs KH-2, SH-1 and LK-1 (60 gas producers and 39 gas injectors);
    • Installation of well gathering structures: 10 gas pads, six well bays and three virtual pads;
    • Installation of a gas gathering network and a gas injection network;
    • Rerouting of the LK-3 production from the existing trunkline in Remote Manifold Station 3 (RMS-3) to the project’s production trunkline, Bab Gas TL-2;
    • Demolition of the existing 10-inch trunkline from RMS-3 to onshore gas development phase one.

    In the EoI document, Adnoc Onshore said it intends to award the EPC contract in the last quarter of the year, with a 45-month duration of works.

    Bab gas cap project infrastructure

    As part of its 2030 upstream production increase goals, Adnoc Group is working to extract gas from four underdeveloped gas cap reservoirs at the Bab onshore field development – Thammama A, Thammama B, Thammama F and Thammama H.

    While the Thammama A, B and H reservoirs are estimated to collectively produce 1.45 billion cubic feet a day (cf/d) of gas, output from the Thammama F gas cap is expected to be at a rate of 396 million cf/d.

    Existing trains at the Habshan processing complex in Abu Dhabi will be unable to handle the new gas volumes. Therefore, Adnoc Gas is required to build new facilities to process an additional volume of up to 1.85 billion cf/d of raw gas.

    Adnoc Gas is planning to build a gas processing plant in the Bab area, about 170 kilometres from Abu Dhabi, along with associated pipeline networks and other ancillary units, as part of the broader Bab gas cap development project. It has divided the EPC scope of work on the project into four packages:

    • EPC package 1 – Main Bab gas cap plant
    • EPC package 2 – Early civil works
    • EPC package 3 – Pipelines
    • EPC package 4 – Non-process area works

    Abu Dhabi Securities Exchange-listed Adnoc Gas issued the tender for the main Bab gas cap plant on 25 June and set an initial deadline of 17 July for contractors to submit technical bids. The company then extended the technical bid submission deadline by four months, until 16 November, MEED previously reported.

    Following a reshuffle of the consortiums gearing up to bid for the main Bab gas plant EPC package, estimated to be worth more than $6bn, the following teams have formed to compete in the main contract tendering round:

    • Larsen & Toubro Energy Hydrocarbon (India) + Petrofac Emirates (UAE)
    • Technip Energies (France) + JGC Corporation (Japan) + Sinopec (China)
    • Tecnimont (Italy) + China Petroleum Engineering and Construction Corporation (CPECC)

    The other three packages of the Bab gas cap project are also in the main contract tendering stages.

    Prior to issuing the EoIs for the project packages, Adnoc Gas completed an early engagement process with contractors in September and October last year, as MEED previously reported.

    In December last year, Adnoc Gas awarded the front-end engineering and design (feed) works for the development project  to Australia-based consultancy Worley. The feed contract has a duration of more than 1.2 million man-hours, making it the largest-ever engineering job awarded by Adnoc Gas.

    Bab Gas Cap concession

    In addition to Adnoc Gas overseeing the main EPC tendering exercise for the gas processing plant, Abu Dhabi’s Supreme Council for Financial and Economic Affairs (SCFEA) awarded concession agreements in June for the development and production of the Bab gas cap reserve.

    Adnoc will hold the majority 60% participating interest in the concession. The remaining stakes will be held by France’s TotalEnergies (10%), the UK’s BP (10%), China National Petroleum Corporation International (8%), Japan Oil Development Company Onshore (5%), China ZhenHua Oil (4%) and Korea GS E&P (3%).

    According to the SCFEA, the Bab gas cap development and production concession represents the largest gas cap development project of its kind globally, the Abu Dhabi Media Office said in a report.

    A gas cap refers to the free natural gas that sits above an underlying oil reservoir – in this case, the Bab onshore oil field in Abu Dhabi.

    The project, operated by Adnoc Onshore, is expected to have a production capacity of approximately 1.5 billion cf/d of natural gas, equivalent to about 15% of Adnoc Gas’ total operational gas processing capacity.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21083343/main.jpg
    Indrajit Sen
  • Gulf ministers insist Hormuz is still essential

    2 November 2026

    Register for MEED’s 14-day trial access 

    Senior Gulf officials have rejected suggestions that new pipelines and rail links will allow the region to do without the Strait of Hormuz, arguing that the waterway will remain essential to the GCC and the global economy.

    Speaking at the Gateway Gulf investment forum in Manama on 1 November, GCC secretary-general Jasem Mohamed Albudaiwi said keeping the strait open is the responsibility of the international community, not of any one country or group of partners. "We hear some voices that maybe we should seek alternatives to Hormuz," he said. "Fine, we will get the pipelines. We will get the GCC railway. But that doesn't mean Hormuz is nobody's business."

    Albudaiwi called for the strait to remain open in line with international law, including the 1982 UN Convention on the Law of the Sea.

    Shipping through the strait has been severely restricted since the US and Israel launched strikes on Iran on 28 February and Iran retaliated with attacks on GCC states and commercial vessels.

    Bahrain's Finance & National Economy Minister, Sheikh Salman Bin Khalifa Al-Khalifa, said building redundancy makes sense, but treating the strait as dispensable does not. He said the waterway carries 30% of global liquefied natural gas (LNG) exports, 20% of aluminium exports and 30% of fertiliser exports. "Any thinking about the alternative of Hormuz, as in we won't need it, is illogical, because we will need it for the world economy," he said.

    UAE Economy & Tourism Minister Abdulla Bin Touq Al-Marri said that "Hormuz matters, and Hormuz will keep mattering", adding that an economy dependent on a single trade route is exposed if that route closes.

    Sheikh Salman said the crisis has compressed years of GCC customs negotiations into weeks. During the conflict, containers cleared at Jeddah with final destinations in Bahrain or Kuwait moved on without further checks, and the same applied to cargo routed through Salalah and Fujairah, he said. GCC ministers have since agreed to make these emergency measures permanent.

    He also cited Gulf Air operating out of Saudi airports for more than 40 days without a written agreement, and a $5bn swap between the UAE and Bahraini central banks to stabilise currencies.

    Bin Touq said the bloc should use 2027 and 2028 to push through reforms, including removing remaining customs barriers between member states.

    Albudaiwi said GCC leaders meeting in Jeddah on 28 April had tasked the secretariat with advancing water connectivity, expanding the GCC electricity grid, planning new logistics infrastructure including ports, accelerating the GCC railway and enhancing oil and gas pipeline links.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21080732/main4958.jpg
    Colin Foreman
  • Bahrain’s Gateway Gulf brings $20bn of deals

    2 November 2026

    More than 110 announcements worth over $20bn will be made at the Gateway Gulf Investment Forum in Bahrain, according to the country's finance minister.

    "Over the next two days at Gateway Gulf, more than 110 announcements worth over $20bn will be made," Sheikh Salman Bin Khalifa Al-Khalifa, Finance & National Economy Minister, said at the opening of the forum's fourth edition on 1 November in Bahrain.

    He said the announcements will cover new partnerships, investments, projects and jobs. Sheikh Salman addressed an audience that included Bahrain's Crown Prince and Prime Minister, Prince Salman Bin Hamad Al-Khalifa.

    The minister said the region's economies have been "tested as never before" since the previous edition of the forum a year earlier.

    "In the face of unprecedented attacks, we did not waver," he said. He added that Bahrain has chosen to work more closely with its allies and partners to defend what it has built.

    Sheikh Salman said the Gulf economy has grown to $2.4tn in GDP. Non-oil sectors account for more than 86% of Bahrain's GDP and more than 77% across the Gulf, he said.

    He said Gulf banks hold more than $4tn in assets, while the region's sovereign wealth funds manage more than $5tn of investments. "These numbers describe a region that has chosen to build a more stable, a more prosperous future for its people," he said. "Bahrain is the gateway to that region."

    The minister said Bahrain is focusing on regulation, infrastructure and people to attract investment.

    He said the country has developed a regulatory framework over several decades that is "clear, modern and fast", allowing investors to commit with confidence.

    On infrastructure, he highlighted logistics, connectivity, digital networks and industrial land as areas where Bahrain is building the foundations for businesses to expand. He also named finance, logistics, tourism, manufacturing, technology and telecommunications, and oil and gas as the sectors into which he expects domestic, regional and international capital to flow.

    He said the investments will create jobs for young graduates and support the growth of family businesses.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21080593/main2015.jpg
    Colin Foreman