World’s tallest tower is back on track

24 October 2024

 

The chairman of Saudi Arabia’s Kingdom Holding, Prince Alwaleed Bin Talal Al-Saud, published a two-word message on social media platform X on 2 October. The message, which said, “We’re back,” was accompanied by an animated video of a fly-through rendering of the world’s next tallest building, the 1,000-metre-plus Jeddah Tower. 

The post was made shortly after a pivotal event for the tower. Earlier that day, the company developing the project, Jeddah Economic Company (JEC), in which Kingdom Holding is a shareholder, signed a contract with the local Saudi Binladin Group (SBG) to resume construction work on the scheme. The SR7.2bn ($2bn) contract includes SR1.1bn for works already completed on the tower. 

SBG was the original contractor on the project before construction work stalled in 2018. This left the tower’s superstructure about one-third complete, with 63 floors built out of 157. 

Speaking to MEED after the contract signing, Kingdom Holding’s CEO Talal Ibrahim Almaiman echoed and expanded on Prince Alwaleed’s post. 

“We’re back. People have been asking questions about the project after it froze in February 2018. We had the patience, but also the determination to finish it. We will deliver what we promised to deliver at the highest possible quality, with a contractor with a long history of success when it comes to handling such huge projects,” he says.

Contractor selection

Appointing a firm to build a tower that will be the world’s tallest is more than just a major contract signing. 

“There are plenty of successes. Saudi Arabia will soon have the record for the tallest tower in the world. Kingdom Holding is doing what it does best, completing projects at the highest level. Saudi Binladin is going to get back its glory. And the people of Jeddah will have the tallest tower in the world,” says Almaiman.

The appointment of the original contractor after having started a fresh tender process for the project in late 2023 has taken some in the market by surprise. 

“Rather than talk about the past, I would like to talk about the future,” says Almaiman.

“SBG has gone through some technical and financial difficulties in the past. The latest announcement, when the Ministry of Finance said it would support them with their issues with the banks, gave them huge financial credibility. The government of Saudi Arabia being a partner and shareholder in SBG gives us huge confidence,” he adds.

With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower. “The contractor spent a lot of time with our designers, quantity surveyors and other experts and went through each part of the tower and how they plan to build it by moving from floor to floor, and this method was approved by us,” says Almaiman. 

Programme and price were also key factors. “The other consortium we spoke to was planning to finish in 58 months, whereas Binladin was saying 42 months, which is three and a half years,” Almaiman explains, adding: “For pricing, we got a good deal.”

In addition, there were several practical reasons for selecting the original contractor on the project, according to Almaiman. SBG already has offices established on site and, as a Jeddah-based company with a long history of delivering major projects in Saudi Arabia, it has well-established connections with the local supply chain.

With financial issues put to one side, SBG was able to put together a winning proposal to complete the tower

Future vision

Although the Jeddah Tower project has a history that can be traced back over a decade, its ambitions are very much in tune with those of modern Saudi Arabia. 

“It is in line with the government’s Vision 2030 to create attractions for Saudi Arabia,” says Almaiman.

Vision 2030 reinforces the importance of the three-and-a-half-year programme that SBG offered because it puts the tower comfortably on course to be delivered in mid-2028, well ahead of 2030.

Completing the world’s tallest tower is just the start for the wider Jeddah Economic City development. 

“The tower is part of phase one, which is about 1.1 million square metres,” says Almaiman. 

“We are now in discussions with investors about coming in and developing. We will contribute land. We will not be selling land at phase one for the sake of selling. We will control the development and the building code,” he adds.

Securing the title

Building the world’s tallest tower inevitably prompts conversations and speculation about other rival towers being planned around the world. 

However, Almaiman is confident that Jeddah Tower’s reign as the world’s tallest will be lengthy, as he, perhaps better than anyone else, understands the challenges involved in building record-breaking towers. 

“The reason for calling the tower 1,000-plus-metres is because we will add more height. The final height of the tower will be decided by HRH Prince Alwaleed Bin Talal,” he says. 

“The other developers will probably need around 10 years to catch up, and if we keep the title for that long, I will be happy.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12787969/main.gif
Colin Foreman
Related Articles
  • Iraq boosts oil exports after talks with Iran

    7 September 2026

    Iraq has boosted its oil export capacity to more than 3 million barrels a day (b/d) after holding talks with Iran, according to Oil Minister Basim Mohammed Khudair.

    In a video statement released on 5 September, he said the country has been able to ship more than 3 million b/d since the start of this month.

    He also said: “The government plans to raise export capacity to 5 million b/d after completing the strategic pipelines extending towards Fishakhpur and Banias, as well as the export outlets in the Strait of Hormuz.”

    Iraq’s oil exports rose to around 2.34 million b/d in August, according ⁠to ⁠officials.

    The increase came after Iran granted special permission for a number of Iraqi oil tankers to pass through the Strait of Hormuz in August, following repeated requests from Baghdad.

    On 22 August, Iraqi President Nizar Amidi said Iran had facilitated the passage of “some ships carrying Iraqi oil in the strait” in recent days, and Baghdad had discussed exporting Iraqi oil through Hormuz with Iranian officials.

    The details of Iraq’s agreement have not been released by officials, but Amidi said that his government “will not accept Iraqi territory being used to launch attacks against any other country”.

    The Iraqi president said attacks launched from inside Iraq against countries in the region “have no justification”.

    Prior to the deal being announced, Iraqi exports had been dramatically reduced amid fallout from the regional war that started when the US and Israel attacked Iran on 28 February 2026.

    The regional war has led to significant disruption to shipping through the Strait of Hormuz, which is a key export route for Iraqi oil.

    Iraq’s crude exports fell from more than 3.3 million b/d before the war to a low of about 330,000 b/d in April, while exports from its southern terminals were temporarily halted altogether in March.

    Tensions still remain high in the region, and some shipping is still being disrupted by the ongoing conflict.

    On 2 September, Saudi Arabia condemned an Iranian attack on an oil tanker owned by its national shipping company that resulted in the deaths of two citizens of the Philippines.

    In a statement, Saudi Arabia’s Foreign Ministry said Iran targeted the Sidr tanker, owned by national carrier Bahri, while it was transiting the Strait of Hormuz two days earlier.

    It said: “The kingdom stressed the necessity of halting escalations and respecting international maritime safety and the security of global energy supplies.”

    Kuwait and Qatar’s foreign ministries said the attack violated international law and freedom of maritime navigation.

    Qatar called the attack a “flagrant violation of the rules of international law and freedom of maritime navigation”. Doha further rejected the use of the Strait of Hormuz as a “bargaining chip”.

    Iran has repeatedly attacked and threatened tankers attempting to sail through the strategic waterway without authorisation, impeding energy exports from neighbouring oil-rich Gulf countries.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19424826/main.jpg
    Wil Crisp
  • Customs clearance delays Iraqi oil field development

    7 September 2026

     

    Problems getting critical equipment through customs are delaying a key part of Iraq’s $27bn Gas Growth Integrated Project (GGIP), according to industry sources.

    Phase one of the GGIP is expected to be worth about $10bn. France’s TotalEnergies holds a 45% stake in the project, while Iraq’s Basra Oil Company (BOC) and QatarEnergy hold 30% and 25% respectively.

    The specific part of the project that is being delayed by customs issues is known as Ratawi phase 1.

    It is focused on developing Iraq’s Ratawi oil and gas field as part of the wider GGIP.

    Previously, this project was expected to come online before the end of June this year.

    Speaking on 23 July 2026, TotalEnergies CEO Patrick Pouyanne said that Ratawi phase 1 was being delayed due to issues related to the conflict with Iran, but he still expected it to start up before the end of September 2026.

    Although recent complications are expected to delay the project further, it is on track to come online in mid-to-late October at the earliest, according to industry sources.

    One source said: “Right now, the main issue causing delays to the project isn’t the crisis in the Strait of Hormuz; it’s Iraqi customs clearance.

    “TotalEnergies is having trouble getting critical equipment released.”

    TotalEnergies did not respond to a request to comment on the progress of Ratawi phase 1.

    In November last year, the French company said that phase 1 aimed to increase production to 120,000 barrels a day (b/d).

    At the time, it also said that it was expected to come on stream “by early 2026”.

    It also said that the launch of phase 2 of the project, which would be considered “full field development”, would enable the company to increase production to 210,000 b/d starting in 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19424624/main.png
    Wil Crisp
  • Firms prepare bids for NWC sewage treatment package 14

    4 September 2026

     

    At least three contractors are preparing to make offers for package 14 of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, according to sources.

    Known as Eastern A Cluster (LTOM14), the package was tendered by the state-owned National Water Company (NWC) in April, with a bid submission deadline of 30 September.

    The contract covers the upgrade of six existing sewage treatment plants (STPs), with a capacity expansion of 30,000 cubic metres a day (cm/d) at the Al-Jarodia STP.

    This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.

    According to sources, the firms preparing to submit bids include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • Miahona (Saudi Arabia)

    The latest phase follows the formal signing of a $347m contract between NWC and a Saudi-Chinese consortium for Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) on 2 September.

    The same consortium led by United Water (China) is not planning to bid for LTOM14 and is expected to formally sign a contract for LTOM11 in the coming months, a source said.

    In April, MEED exclusively reported that the group had won the contract for package 11, which will have a combined capacity of about 440,000 cm/d.

    It is also understood that Beijing Enterprises, a bidder for North Western B Cluster (LTOM12), is not preparing to bid for package 14.

    In the meantime, the contract for LTOM12 is moving towards award, with bids currently under evaluation.

    The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d. As previously reported, NWC opened financial bids for the project in April.

    US/India-based Synergy Consulting is Financial Advisor to NWC for the full LTOM programme.

    Future phases

    In total, the LTOM programme comprises 19 packages split into two phases. In May 2024, NWC announced it had awarded $2.5bn-worth of contracts in the first phase. Phase two of the programme includes 10 packages covering 117 treatment plants.

    In April, MEED exclusively reported that NWC had held several discussions regarding changes in scope details and potential expansions to upcoming projects. This involved “grouping some upcoming projects”.

    The request for proposals for LTOM13 was subsequently put on hold and it is now understood that this tender has likely been merged with other packages in the programme.

    According to a source, Eastern B Cluster (LTOM15) has also been cancelled and has likely been merged. LTOM15 had comprised two STPs with a total capacity of 152,000 cm/d.

    The next contract to be tendered will be Central Cluster (LTOM16), potentially in November, a source added.

    Under the original scope, LTOM16 covers the construction of 14 STPs with a total capacity of 153,000 cm/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19358188/main.jpg
    Mark Dowdall
  • Egyptian contractor wins Abu Dhabi Ramhan Island deal

    4 September 2026

    Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.

    The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.

    The development comprises two residential towers offering 187 residential units.

    The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.

    The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Mohamed Alabbar launched the Ramhan Island development in May 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg
    Yasir Iqbal
  • Dubai sets deadline for Jebel Ali waste-to-energy PPP

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.

    The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.

    The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.

    The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.

    Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.

    It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.

    That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.

    The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.

    Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.

    In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.

    Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.

    The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation. 

    The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg
    Mark Dowdall