World’s tallest tower anchors Jeddah Economic City plans
6 October 2026

Development is accelerating at Jeddah Economic City. Jeddah Economic Company (JEC) will start formal talks with third-party developers for the first phase of the masterplan this year, as construction of the world’s tallest tower at the centre of the scheme rises past the 116th floor.
Fabien Toscano, chief executive officer of JEC, told MEED at its Shaping Mega Projects Conference on 29 September that infrastructure for the 1.7 million-square-metre (sq m) first phase is complete, with all plots serviced and individually titled. The tower, which will be the first building to exceed 1 kilometre in height, is due for completion in 2028, and JEC plans to release residential units for sale in 2027.
How big is the Jeddah Economic City masterplan?
Jeddah Economic City is in north Jeddah, adjacent to Obhur Creek and the Red Sea. The approved masterplan covers 5.3 million sq m and includes more than 14 million sq m of gross floor area (GFA), so that’s quite considerable. It is a full city with residential, retail and office assets, as well as extensive public realm to support the development.
The current focus is phase one. The first phase comprises 1.7 million sq m of land and just over 4 million sq m of GFA. For context, phase one is slightly larger than King Abdullah Financial District and is anchored by the tower. The tower is the heart of the project, and the priority is to deliver phase one before later focusing on phase two.
What stage is phase one at?
Phase one is largely ready from a master developer perspective. All the infrastructure is in place, including roads, traffic lights, sidewalks with granite kerbstones, electricity and water networks, and the district cooling network.
All phase one plots are serviced and have been individually titled.
When building the infrastructure, JEC elevated the roads to place the utilities. As a result, what would typically be ground level will function as a basement parking level for future developments. This will save developers time and cost because they won’t have to dewater. A further benefit is that, even at the ground floor level of the masterplan, the Red Sea is clearly visible because the site sits more than 14 metres above sea level in places.
How is construction of the tower progressing?
As of late September 2026, the tower had reached the 116th floor, about 466 metres above sea level, so it’s moving very well. More than 6,000 people are working on the tower each day. The project has surpassed 20 million hours without a lost-time incident, which is very important for us as a developer. The tower is moving at full speed, and we are making strong progress, so we’re very happy with that.
What’s your floor cycle rate right now?
For the core, the current rate is about five days per core. We are doing pretty well.
What are the technology challenges when building that high?
Times have changed since Burj Khalifa. Concrete can now be pumped to 1 kilometre. The tower is largely concrete up to the top, except for the last spine, and differs from Burj Khalifa in design. While there are always challenges on a project of this scale, construction technology has evolved, and we have a great team of architects and consultants to support us throughout the project, as well as a great contractor.
What are the components within the tower?
The tower will include a Four Seasons hotel with 182 keys, 97 Four Seasons-branded residences, and 325 Jeddah Tower apartments ranging from one-bedroom units to penthouses. The penthouses will be the highest residential units in the world.
It will also include duplexes, an observation deck with indoor and outdoor areas, more than 14,000 sq m of office space, and a range of resident and hotel amenities inside and outside the tower.
Can you reveal the final height of the tower?
Not today. It is 1 kilometre-plus, and will be the first building to actually exceed the 1-kilometre mark, making it the world’s tallest tower when completed. It is also important to say that this is only what you see. We ended up driving 270 piles down to 105 metres to support the building. A lot of work has gone into things people don’t see today, but we’re not yet ready to announce the height. It will come in time.
What is coming next for Jeddah Economic City?
There are two important dates for us. The first is Cityscape this year, where JEC will showcase the tower and the wider masterplan, with particular emphasis on phase one. This will also mark the start of more formal engagement with developers, as phase one land plots are ready for immediate development.
The second date will be in 2027, when JEC expects to release some of the tower’s residential units for sale.
Could you explain the relationship between the tower and the broader development?
They all complement each other. The reality is the tower is the icon. It’s the heart of the project. In fact, that will be the icon for Jeddah in the future. So the value is there. It will attract people. The broader city – its amenities and mixed-use offering – will encourage people to stay and support long-term value.
As JEC prepares to release plots, it plans a phased approach that prioritises essential amenities such as schools, hospitals, retail and residential uses to support the tower and the wider development. The masterplan also includes a water feature and public gathering spaces.
Jeddah is an incredible city that many people visit, but if you look at the numbers, very few people actually spend time in Jeddah. They come, they go to Mecca, they go to Medina. With a compelling attraction, we can create an anchor that encourages more people to visit and experience Jeddah through this project – and, of course, to come to live and work here as well.
With the right mix in place, you want people to have amenities from day one – and also the ability to live and work here, and to enjoy the destination as a vibrant public realm. Getting that mix right from the outset is essential, and that’s exactly what we’re focused on.
We have a plan. I’m not going to share it today, but it’s the framework we’re working to – and it will guide how we phase and cap development. When we speak with developers, it’s always within the context of that plan and our land-release strategy.
What heights will the other buildings reach?
Buildings across the development will range from mid-rise to high-rise. Some towers will eventually reach 450 metres, while other buildings will typically range from G+5 or G+6 upwards. This is a city centre-type project with density, a concentration of amenities and walkability; everything people talk about today is integrated into this masterplan.
How can investors participate in the project?
We are the master developer, so people can contact us. We are happy to discuss available opportunities and land plots, and we have a process that starts with a site visit, reviewing opportunities, and discussing whether it’s a land purchase or another type of structure. And of course, at Cityscape, we will be there. We will have a team there. We’ll be able to engage with people directly at Cityscape.
What construction opportunities lie ahead?
There is a lot of real estate to be built around all asset classes. Some of it may be done by us. Some of it will be done by a third party. Some of it may be done as a joint venture, but there will be opportunities across all asset classes, and eventually infrastructure for phases two and three when the time is right. Most of the tower work is now locked in, and we are now into delivery. The fit-out will come. The designs have been fixed. Right now, it’s mostly MEP, finishing the tower, and closing it out.
Jeddah is an established city that has been built up over a long time. What are you offering that’s different for investors? What kind of interest have you got so far?
A couple of elements will make this project a success. First, if you look west of our site, there is the sea; to the east is the mountain. If you go further south, there is an industrial zone. All the growth in Jeddah will happen to the north. It’s already happening, and I think that’s very important. Second, Jeddah is very well positioned today for growth.
In terms of our project specifically, we will have the tallest tower in the world. It has all the amenities, the social infrastructure, the water body, the retail, etc, to make it an interactive place. Second, we have quality infrastructure today, and third, it’s ready. We’re not talking about something that may happen. It is ready today. People can take a plot today and develop tomorrow. It’s there, all connected, all the utilities, the district cooling, everything that I mentioned earlier – it’s ready, and I think that is the big difference.
We’re also right on the sea. In fact, some of our plots are directly on the waterfront. We have two plots along the creek as well as plots on the open sea, so the site is fully connected along the water. That’s something I don’t think is really available anymore today.
Second, on density: when I think about Jeddah – and I’m fairly new to the city – it’s clearly evolving into a multi-centric city, growing in a way that will create several distinct centres over time. I believe our development will consolidate its position as one of those centres, especially given its density and its character as a city-centre-style project, supported by strong amenities.
How do your priorities change as the project moves toward completion?
The focus is very clear. The tower must be delivered to the right quality, on time, and on budget. We have to launch the tower to the world and keep our promises to the potential buyers. As for the city, anyone who works with us – whether an investor, a joint-venture partner or another stakeholder – is, in practice, a partner in building the destination.
It’s about choosing the right partners and releasing the right amount of land for sale at the right time. We need to manage the pace of release as we create value – that’s a key objective going forward. Everything we do adds value, but we have to do it thoughtfully and sensibly, and bring the right partners with us.
Ultimately, partnership is critical: we need the right capabilities for each asset class. Some things we will deliver ourselves, and for others we should rely on specialists who can do them better than we can. We have to be realistic about that.
Going back to that city idea, cities are not built by one person; they are built by a collective of people.
We’ll all learn from one another, and the destination will benefit overall from having different product types and different approaches to delivery. As master developer, though, we have a responsibility to put the right infrastructure in place, manage the city effectively, and release land in a disciplined, sensible way – so we create value both for ourselves and for everyone participating in the development.
Just to refresh, what are the key dates for the tower?
In terms of construction time, it is 2028.
Exclusive from Meed
-
Dubai evaluates Tasreef drainage bids24 November 2026
-
Muscat financial centre opens for business24 November 2026
-
Mecca university tenders water infrastructure projects24 November 2026
-
Oman’s OQT formalises Pakistan fuel supply agreement24 November 2026
-
Contractors bid for Aramco-backed logistics hub24 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai evaluates Tasreef drainage bids24 November 2026

Up to eight stormwater and drainage projects under the next phase of Dubai Municipality’s AED30bn ($8.2bn) Tasreef programme have moved into the bid evaluation stage in recent weeks as procurement activity continues to drive the wider water infrastructure sector.
The projects cover major stormwater drainage networks, pumping stations, storage tanks and sewerage infrastructure. They include schemes serving Dubai South, Abu Hail, the area surrounding Dubai International airport, Dubailand and Al-Awir.
According to regional project tracker MEED Projects, the eight tenders have an estimated combined value of at least $800m. The tenders cover the following projects:
- DS-316-C1: Drainage networks serving Hind 4
- TF-24-C1: Connections to the stormwater network in Dubailand
- TF-25-C1: Stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman
- TF-07-C1: Strategic stormwater drainage network between Sheikh Mohammed bin Zayed Road and Emirates Road
- TF-21-C1: Stormwater system upgrade and rehabilitation in Abu Hail
- TF-30-C1: Stormwater storage tanks serving the Dubai International airport area
- TF-06-C2: Stormwater drainage system connecting Al-Maktoum International airport and Dubai South
- DS317-C1: Sewerage and stormwater infrastructure in New Al-Awir 1st
According to sources, local firms Nael Construction & Contracting, Al-Nasr Contracting and Arifco Building Contracting are among those that submitted bids for the Dubailand stormwater network project (TF-24-C1) in October. The bidders for this tender do not include the local DeTech Contracting, which won the estimated $350m engineering, procurement and construction contract for a package on Al-Wasl Road (TF-15-C1), earlier this year.
On 29 October, DeTech, Mohammed Abdulmohsin Al-Kharafi & Sons and Green Oasis General Contracting Company were among those that submitted bids for TF-07-C1, sources told MEED.
It is undersood that both DeTech and Kharafi also submitted offers on 12 November for a contract to upgrade and rehabilitate the stormwater system in Abu Hail (TF-21-C1). The Abu Hail project comprises a stormwater pumping station with a total discharge capacity of 26 cubic metres a second. The wider project involves a major stormwater gravity drainage network, including large-diameter pipelines, and is estimated to cost up to $163m.
Meanwhile, the the municipality is preparing to receive bids for a further scheme (TF-06-C1) on 26 November, involving the construction of a stormwater pond connecting Al-Maktoum airport and Dubai South. Al-Nasr Contracting and Green Oasis are among those preparing to bid, sources said.
In October, the municipality confirmed it had awarded four contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.
The projects will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. The works include constructing and extending main stormwater drainage lines with diameters of up to 3 metres.
The Tasreef programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21756439/main.jpg -
Muscat financial centre opens for business24 November 2026
The International Financial Centre of Oman (IFC Oman) has opened its headquarters at Al-Mouj Business Park in Muscat and registered its first 13 companies.
Sayyid Theyazin bin Haitham Al-Said, Oman's Deputy Prime Minister for Economic Affairs and chairman of IFC Oman, opened the headquarters on 23 November. The ceremony also marked the official start of company registration, which allows local and international businesses to set up within the centre's jurisdiction.
The first 13 companies received their certificates of incorporation at the event. The centre was set up by Royal Decree No. 8/2026 in January, so the move from setting up a legal framework to taking in businesses has taken 10 months.
Registration follows royal decrees that put in place IFC Oman's operating law, regulatory law and courts law. Five core regulations sit alongside them and cover operations, companies, partnerships, foundations and interpretation. Together they set the rules for setting up and running a business in the centre, including corporate governance, regulatory obligations and dispute resolution.
Businesses can apply through a new digital registry platform. A separate regulatory framework for financial services is still being drafted, and licensing for those activities is expected to start in early 2027.
Finance Minister Sultan bin Salim Al-Habsi, who is vice-chairman of IFC Oman, said the decision by 13 companies to join from the start "reflects the strength of the business and investment environment the centre offers".
"We will maintain this momentum as we complete the regulatory framework ahead of the start of financial services licensing early next year," he said.
Sayyid Theyazin said the framework "lays the foundation for a stable and competitive business environment" and will strengthen Oman's appeal to international investors and financial institutions.
He also chaired a board meeting. It reviewed progress on finishing the centre's legal, regulatory and operational infrastructure and set priorities for attracting companies and investment.
IFC Oman aims to connect the national economy more closely to international capital and to support growth in financial and professional services, in line with the Oman Vision 2040 economic diversification programme.
The centre goes up against established regional financial hubs, including Dubai International Financial Centre, Abu Dhabi Global Market and Qatar Financial Centre.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21756636/main5305.gif -
Mecca university tenders water infrastructure projects24 November 2026
Mecca-based Umm Al-Qura University has issued two tenders for wastewater and water storage infrastructure at its student campus in the Al-Abidiyah district.
The first tender covers the second phase of the university’s main water storage scheme. The project involves building seven tanks with a combined capacity of 14,700 cubic metres.
The scope includes three ground-level tanks with a total capacity of 7,500 cubic metres and four elevated tanks with a combined capacity of 7,200 cubic metres.
It also includes a 2.1-kilometre backup water supply pipeline with a diameter of 400 millimetres, as well as pumping stations, inlet and outlet pipework, valves and water control systems.
The second tender covers the construction of a wastewater treatment plant with a capacity of 4,000 cubic metres a day at the university’s student campus. The contract duration is listed as two years.
The projects will expand the campus’s water infrastructure, adding storage capacity and wastewater treatment facilities to support its operational requirements.
Both tenders were issued in November. Bids for the water storage tanks and wastewater plant are due by 14 December and 13 December, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21752745/main.jpg -
Oman’s OQT formalises Pakistan fuel supply agreement24 November 2026
Oman's state-owned commodity trader OQT has signed a petroleum products supply agreement with Pakistan State Oil (PSO), the South Asian country's national oil marketing company.
The deal was signed on 8 October and formally marked at a ceremony in Muscat on 22 November. It was made under the Oman-Pakistan intergovernmental framework and gives OQT a structured arrangement for supplying petroleum products to PSO.
The two companies have yet to disclose the agreement's value, volumes or duration.
The agreement builds on an existing trading relationship. OQT says it has supplied more than 1 million tonnes of gasoline to PSO in 2026.
OQT also supplies Pakistan's liquefied petroleum gas (LPG) market, selling to both state-owned and private buyers. The company expects its LPG deliveries to Pakistan to pass 120,000 tonnes by the end of the year.
"This agreement gives us a stronger framework to build on that relationship, combining OQT's international trading capabilities with PSO's position in the Pakistani market," said OQT chief executive Wail Al-Jamali.
PSO chief executive Jawwad Ahmed Cheema said the partnership is now "formal, government-backed and built for the long term under the Oman-Pakistan Intergovernmental Agreement".
"For PSO, this is about more than supply. It is about ensuring that Pakistan has the fuel it needs, when it needs it, on terms that protect our national interest," he said.
Oman's Energy & Minerals Minister Salim Al-Aufi and Pakistan's Petroleum Minister Ali Pervaiz Malik attended the ceremony, along with Mulham Al-Jarf, deputy president of investment at the Oman Investment Authority, which owns OQT.
The companies said the agreement will support reliable supply at a time of continued volatility in regional energy markets. They will now focus on implementation and deliveries, and will continue talks on wider petroleum and energy cooperation.
OQT trades crude oil, refined products, petrochemicals, LPG, liquefied natural gas, fertilisers and carbon-related products, and is expanding into metals. It has offices in Muscat, Dubai, London, Rotterdam, Singapore, Houston and Shanghai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21750539/main1214.jpeg -
Contractors bid for Aramco-backed logistics hub24 November 2026

Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, received proposals from contractors on 15 November for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.
The logistics hub will add over 124,000 square metres (sq m) at Spark.
Al-Khobar-based engineering firm House of Consulting Office is the project consultant.
The tender for the expansion works comes after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.
The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.
Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.
The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21747071/main.gif