Working towards a common energy-transition goal

28 November 2022

Published in partnership with

In the end, it went right to the wire. Just as it looked like the UN’s 27th Conference of the Parties (Cop27) would conclude without an accord, the weary delegates announced that they had reached a landmark agreement on setting up a fund to help compensate poorer nations for the economic and social destruction caused by climate change. 

The statement, two days after the Sharm el-Sheikh summit’s original 18 November end date, was a culmination of some 30 years of negotiations between developed economies and developing nations. The latter had long argued that the damage they have experienced from global warming should be paid for by richer countries responsible for the crisis in the first place.

Although far from perfect, the global ‘loss and damage’ fund was hailed as an important and symbolic step towards hitting the agreed target of limiting global temperature increases to 1.5C above pre-industrial levels by 2030. It also marked the continuing engagement and collaboration by governments across the globe.

“We rose to the occasion,” said Egypt’s Minister of Foreign Affairs and president of Cop27 Sameh Shoukry. 

“We worked around the clock, day and night, but united in working for one gain, one higher purpose, one common goal. In the end, we delivered. We listened to the calls of anguish and despair.”

Private sector involvement

While Cop27 has been and will continue to be a policy-setting mechanism negotiated at the highest level, companies played a critical role during the conference. 

Firms representing a broad range of sectors, including Vodafone, Microsoft, Boston Consulting Group and Bloomberg, partnered with the event, and many more participated in the main conference and exhibition areas. 

Ultimately, governments understand that the private sector will lead the drive towards net zero. Without corporates worldwide investing in clean energy projects and technology, there is little hope that targets will be reached.

Five consistency points

A key supporter of Cop27 was Siemens Energy. Sharing its expertise through panels covering subjects as varied as the Mediterranean’s North-South Energy Partnership, improving power access in Africa by unlocking its green hydrogen potential, and overcoming the challenges of decarbonisation, the energy technology company played a pivotal role in discussions and thought leadership.

It also participated in the world leader’s summit at a roundtable discussing green hydrogen, reinforcing its positioning of energy transition at the heart of its strategy. 

Before the Sharm el-Sheikh conference, Siemens Energy president and CEO Christian Bruch outlined five points of consistency that his company considers to be unifying elements in the decarbonisation drive.

The first is the acceleration of renewables. Replacing conventional power generation systems with solar, wind, hydro and other forms of renewable energy is essential to reduce greenhouse emissions.

Despite a considerable increase in the overall share of renewables in the past three years on the back of ever-lowering costs and more efficient technology, more must still be done.

For example, the US needs to triple its share of renewable energy as a proportion of the energy mix by 2050 for the energy transition to succeed. The Asia-Pacific region, meanwhile, will have to increase this figure fourfold. 

Regional targets

In the Middle East, every country has now set ambitious targets to increase renewable energy. The likes of Saudi Arabia, Morocco and the UAE are aiming for renewables to account for up to 50 per cent of total production by 2030. To reach these objectives, almost all new power generation projects come in the form of renewables.

However, the impact of greener electricity production could be somewhat offset by continuing demand growth caused by an increasing global population and economic growth. 

In this context, the second point is the requirement for improved energy conservation measures, such as policies to incentivise the electrification of industry and transport. 

Regionally, the industrial electrification of energy-intensive industries is an optimal opportunity to reduce harmful emissions by harnessing electric boilers and/or electricity-based fuels. Future large-scale blue and green hydrogen production will also have a role to play in industrial processes.

Siemens Energy’s third point of consistency is improving electrical efficiency. The increase in renewable energy capacity and the growth in power capacity, in general, require significant investment in transmission and distribution networks. 

This is particularly important in areas such as sub-Saharan Africa, where almost 25 per cent of the population has little to no access to electricity. 

The fourth point covers the requirement to use existing conventional power infrastructure to help bridge the gap between the fossil-fuelled economies of today and the net zero of tomorrow. 

Progress cannot be made in one step alone and requires a gradual transition. In the meantime, existing thermal plants can employ measures such as combined-cycle technology and carbon capture to make them as efficient and environmentally friendly as possible.

The energy transition is the biggest investment programme since the dawn of industrialisation. If governments, business and society work together, energy transition is a massive opportunity

Christian Bruch, Siemens Energy president and CEO

Mineral production

Finally, to achieve all of this, it is necessary to improve supply chains and increase the production of necessary minerals and rare earth metals required in net-zero technologies, such as lithium, nickel, cobalt and chromium. 

Bruch gives the example of a typical electric car, which requires six times more mineral inputs than one powered by an internal combustion engine. He also cites onshore wind plants, which need nine times more than a gas-fired power plant. 

If mineral production is not increased and geographically diversified, there is a risk of future supply bottlenecks.

In the Middle East, a good illustration of this is the potential future supply gap for electrolyser systems, and the anodes and cathodes typically made from metals such as zinc, nickel and lithium. 

MEED estimates that about 75GW of electrolyser production capacity will be required by 2030 to meet the demand for the raft of planned green hydrogen plants in the region alone, compared with a total global output capacity of just 8GW today.

Industrial decarbonisation alliance

All five consistency points make salient arguments. However, they can only be achieved with close cooperation between the private and public sectors. While the former can spearhead and implement the decarbonisation drive, the latter can provide the regulations and incentives to encourage these initiatives. 

The newly formed Alliance for Industry Decarbonization initiated by Siemens Energy and coordinated and facilitated by the Abu Dhabi-based International Renewable Energy Agency (IRENA) is an example of greater collaboration between the public and private sectors. 

The 28-member alliance – which encompasses a range of global energy, renewable, consulting and manufacturing companies – met for the first time during Cop27 to outline its joint vision and implementation plan. Its strategy focuses on six pillars and enablers that tie into the points of consistency: renewables, green hydrogen, bioenergy with carbon capture, utilisation and storage (CCUS), heat process optimisation, human capital and finance.

Only through this kind of stakeholder dialogue can the immense and existential challenges posed by global warming be overcome. Governments or companies acting in isolation will only achieve so much on their own. The points of consistency must be considered as a whole and in unison if the world’s climate objectives are to succeed.

As Bruch says: “The energy transition is the biggest investment programme since the dawn of industrialisation. If governments, business and society work together, energy transition is a massive opportunity. There is no excuse for waiting any longer.”

Related reads:

Click here to visit Siemens Energy 
https://image.digitalinsightresearch.in/uploads/NewsArticle/10387284/main.gif
MEED Editorial
Related Articles
  • Kuwait receives bids for Al-Khairan phase one IWPP

    2 June 2026

     

    Two developer consortiums have submitted bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, according to a source.

    Bids were received by the Kuwait Authority for Partnership Projects (Kapp) on 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The bidders include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The Al-Khairan IWPP is being procured by Kapp in partnership with the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate in the tender.

    Ernst & Young, BNP Paribas, AtkinsRealis and Addleshaw Goddard are financial advisers on the project. Chadbourne & Parke is acting as legal adviser.

    The winning bidder will sign a set of public-private partnership agreements covering financing, design, construction, operation and transfer of the project. The energy conversion and water-purchase agreement is expected to cover a 25-year supply period.

    Future phases

    The Al-Khairan IWPP project is expected to run on low-sulphur fuel oil as the primary fuel and to accommodate crude oil, gas oil and natural gas as backup fuels. Future phases will further expand capacity.

    It is understood that the estimated $750m second phase of the Al-Khairan IWPP project will add a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant.

    The project, first mooted over a decade ago, remains in the early development stages, with no plans currently to advance to procurement in 2026, a source said.

    According to the source, the immediate focus is on advancing plans for the 3,600MW Nuwaiseeb power and water desalination IWPP project.

    The Nuwaiseeb IWPP plant will have a desalination capacity of 75 million imperial gallons a day.

    Kapp plans to release a transaction advisory tender for the project by the end of the year.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072685/main.jpg
    Mark Dowdall
  • Doosan confirms Saudi Jafurah 2 cogen contract

    2 June 2026

    South Korea’s Doosan Enerbility has confirmed it has signed an engineering, procurement and construction (EPC) contract worth about $556m for the second phase of the Jafurah combined heat and power (CHP) plant in Saudi Arabia.

    The project is being developed by Korea Electric Power Corporation (Kepco) in partnership with Saudi Aramco.

    Doosan said the contract covers design, equipment supply, installation, construction and commissioning of the facility.

    The Jafurah CHP phase 2 project will be built near the Jafurah gas field, about 400 kilometres east of Riyadh. Once operational, it will generate 330MW of electricity and produce 465 tonnes of steam an hour for the nearby gas field.

    According to the firm, the project’s main steam turbine will be supplied by Doosan Skoda Power, a subsidiary of Doosan Enerbility.

    WSP is acting as the project management consultant for the project, which is scheduled for completion in 2029.

    The Jafurah gas development is part of Aramco’s $3.2bn unconventional resources programme, which aims to develop shale gas in three areas. Jafurah lies southeast of Ghawar, the world’s largest conventional oil field.

    The programme is part of Riyadh’s plans under Vision 20230 to ensure the kingdom remains self-sufficient in gas supply amid rising demand from the residential and industrial power sectors.

    Jafurah phase one

    In February 2025, MEED exclusively reported that talks were under way to expand the capacity of the $500m Jafurah cogeneration independent steam and power plant (ISPP).

    Construction works were completed on the facility last November.

    At the time of its procurement, the plant’s first phase was to have a power capacity of 270-320MW, and a low-pressure (LP) steam demand of 77-166 thousand pounds an hour (klb/hr) and high-pressure (HP) steam demand of 29-126 klb/hour by 2023.

    The LP and HP steam demand will increase to 283-373 klb/hr and 66-321 klb/hr by 2027, respectively.

    The oil giant issued the letter of award to Kepco for the contract to develop the Jafurah ISPP scheme in July 2022.

    Kepco subsequently awarded South Korea’s Doosan Heavy Industries & Construction the project’s EPC contract.

    US/India-based Synergy Consulting provided financial advisory services to Kepco on its bid.

    Sumitomo Mitsui Banking Corporation (SMBC) served as the client’s financial adviser for the project. Germany’s Fichtner Consulting Engineers is technical consultant, while the UK’s Wood Group is project management consultant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072199/main.jpg
    Mark Dowdall
  • Lack of truck-loading facilities in Iraq restricts oil exports

    2 June 2026

     

    A lack of truck-loading facilities at oil fields in southern Iraq is restricting the country’s exports, according to industry sources.

    Since the US and Israel attacked Iran on 28 February, Iraq’s exports shipped through the Strait of Hormuz have been severely disrupted, increasing the country’s reliance on exporting crude using trucks and pipelines.

    In April, Iraq’s state-owned oil marketing company, Somo, said it had awarded contracts to supply about 650,000 metric tonnes of fuel oil a month for overland trucking across Syria.

    On top of this, Iraq is also transporting oil by truck from the south of the country to export pipeline infrastructure in the north.

    One industry source said: “Moving crude by truck is very inefficient and expensive compared to using a big pipeline or large ships.

    “Iraq’s infrastructure was not designed with the idea of using trucks to move crude at the current scale.

    “The current level of exports is a fraction of what was being exported before the disruption to shipping through the Strait of Hormuz started.

    “There are a lot of problems that are emerging and these include a lack of truck-loading facilities at oil fields in the south of the country.

    “Many fields don’t have the truck loading stations, loading arms, pumps and meters that are needed to increase truck export volumes.”

    Iraq exported 10 million barrels of crude in April, an 89% drop from the 93 million barrels exported the month before the Iran conflict.

    READ: Gulf races to reroute trade

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17063350/main.jpg
    Wil Crisp
  • Iraq’s reform window narrows

    2 June 2026

    Commentary
    John Bambridge
    Analysis editor

    Iraq enters mid-2026 with the most expansive projects pipeline in its post-2003 history, with more than $420bn in planned and active work, but an increasingly narrow fiscal margin within which to deliver it.

    The cumulative pipeline builds on a 2025 performance that witnessed a record $17bn in contract awards in the power and water sector and looks forward to a construction industry forecast to expand at 4.8% annually through 2028. In the energy sector, the Gas Growth Integrated Project is advancing towards its 2028 commissioning, while the country’s North-South logistics expansion remains in active procurement.

    The pipeline is very real, but the conditions that were expected to fund it no longer exist in the wake of the Iran war.

    April oil exports ran 90% below the previous year’s monthly average as Strait of Hormuz transit remained effectively suspended. The IMF projects Iraq’s real GDP to contract by 6.8% in 2026 – the sharpest regional revision after Qatar. Even before the conflict, Iraq’s reserves were falling by about $10bn every year. The three-year budget framework expired in 2025 with no 2026 successor in place, leaving forward-looking spending uncertain. Ali Al-Zaidi was sworn in as prime minister on 14 May with fragile coalition support and nine cabinet portfolios still unfilled.

    The structural collision is between an infrastructure ambition built for 4 million barrels a day of exports and a fiscal reality running at a fraction of that. Iraq’s oil revenue funds over 90% of the federal budget. An exports collapse of the scale now visible will strip more from the budget in months than any reform programme can replace in years. And some of the production lost may not return. Many of Iraq’s southern fields have been running at reduced rates rather than fully shut in – the better strategy for preserving well integrity – but the longer the downtime, the higher the share of capacity that may not recover in the coming months. The revenue base on which Iraq’s pipeline was assembled is not just suspended; some of it is structurally imperilled.

    The current situation will force reform. Every Iraqi government since 2014 has faced reform pressures, but 2026 has not just tested the underlying assumptions; it has shattered them. Past reform programmes attempted to optimise governance amid volatile oil revenues; the current one must contend with existential risk to the revenue base.

    Al-Zaidi’s first task will not be the budget or the Hormuz crisis in isolation; it will be to convert a fragile mandate into the policy leadership and governance necessary to sustain the projects pipeline. The window for this is open, but it will not stay open long.

     


    MEED’s June 2026 report on Iraq includes:

    > GOVERNMENT: Al-Zaidi takes Iraq’s premiership under US shadow
    > BANKING: Financial challenge tests Iraq’s resolve
    > ECONOMY: Iraq enters era of resilience, reform and rising risks 
    > OIL & GAS: 
    Iraqi oil and gas sector in crisis

    > POWER & WATER: Focus shifts to delivery of Iraq utilities expansion
    > CONSTRUCTION: Momentum builds in Iraq’s post-war construction sector

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17061271/main.gif
    John Bambridge
  • Saudi firm to build Al-Henakiyah solar IPP grid link

    1 June 2026

     

    Saudi Services for Electro Mechanic Works has won the main contract to build a 380kV overhead transmission line in Saudi Arabia’s Medina region, according to market sources.

    The project includes the construction of a 354-kilometre-long overhead transmission line that will connect the Al-Henakiyah 3 solar independent power producer (IPP) to several main substations and export power from the plant into the national transmission network.

    The scheme is being developed by Saudi Energy, formerly Saudi Electricity Company.

    The scope covers the supply and erection of transmission towers and foundations, as well as associated grid interface and termination works.

    The Al-Henakiyah 3 solar IPP is part of Saudi Arabia’s wider pipeline of utility-scale solar projects being developed under the Public Investment Fund’s (PIF’s) renewables programme, which runs parallel to the National Renewable Energy Programme (NREP), now in its seventh round.

    In 2025, the PIF outlined plans to advance second- and third-phase extensions to five existing solar plants, including Al-Henakiyah, totalling 9GW of additional capacity.

    According to official documents, the negotiation process for the directly-awarded concessions was due to start last year.

    Saudi Services for Electro Mechanic Works, meanwhile, is continuing to advance several transmission line projects for Saudi Energy.

    In June 2025, it was appointed as the main contractor to build a separate 380kV overhead transmission line linking the 2GW Afif 1 solar IPP to the national grid.

    Works on this project are not expected to be completed until at least 2027.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17058114/main.jpg
    Mark Dowdall