Force majeure will not cure pre-existing construction industry breaches
9 April 2026
As the 2026 Iran War disrupts critical maritime chokepoints and aviation corridors, the GCC construction sector faces unprecedented logistical challenges. Consequently, regional engineering, procurement and construction (EPC) contractors are being inundated with force majeure notices.
International suppliers claim the geopolitical crisis prevents them from fulfilling contracts, arguing this shields them from liability and allows them to retain massive advance payments. However, a contentious legal dilemma has emerged: Can a supplier weaponise an active conflict to camouflage a pre-existing breach, such as manufacturing defective materials or missing critical deadlines before the crisis erupted?
For construction executives, GCC civil law provides a highly unforgiving answer. By examining a landmark judgment from the Dubai Court of First Instance (Judgment No. 695/2023) concerning the 2023 Sudan war, contractors can find a definitive legal playbook for the current environment.
The Sudan precedent
The factual matrix of the 2023 Sudan dispute serves as a perfect analogue for today’s supply chain fracturing. A regional contractor paid a 30% advance ($1.27m) for the offshore manufacture of structural steel water tanks destined for Sudan. In March 2023, an independent SGS inspection revealed critical life-safety and structural defects in the steel columns.
Faced with a formal breach notice, the supplier proposed a “fix-it on-site” workaround, planning to fly engineers to Khartoum to alter concrete foundations to compensate for the defective steel. Just two days before this site visit, the Sudanese civil war erupted, shutting down airports.
The supplier preemptively sued in Dubai, claiming the sudden outbreak of war was an unforeseeable event that made it physically impossible to rectify the defects or deliver the goods. They demanded to terminate the contract under force majeure and keep the advance payment.
The Dubai Court fundamentally rejected this conflation. Relying on UAE Civil Transactions Law, the court established a bright-line rule: a subsequent force majeure event cannot cure, excuse or erase a pre-existing contractual breach.
The supplier had breached the contract the moment the SGS report confirmed the defects. The fact that war broke out subsequently, preventing their travel for an ad-hoc fix, was legally irrelevant. The court ordered the supplier to refund the entire $1.27m advance payment, alongside a 5% annual delay interest.
The bank guarantee trap
The judgment also highlights a profound warning regarding financial hygiene. The contractor initially attempted to liquidate the supplier’s unconditional bank guarantee but failed.
The contractor had erroneously wired the advance payment to the supplier’s Bank of China account, rather than the specific Abu Dhabi Islamic Bank account explicitly stipulated in the guarantee draft. This simple administrative routing error meant the guarantee was technically never activated, forcing the contractor into a lengthy substantive lawsuit to recover its funds.
Wider GCC implications
While originating in Dubai, this jurisprudential DNA applies universally across the GCC. The newly codified Saudi Civil Transactions Law, alongside Qatari and Omani civil codes, views construction supply contracts as rigid obligations of result.
Across the region, courts uniformly reject the concept of “concurrent excuse”. If a supplier fails to build structural steel correctly in March, they cannot blame airspace closures in April for their failure to deliver.
A strategic playbook for 2026
For conglomerates battling the commercial fallout of the 2026 Iran War, this precedent offers a clear risk mitigation roadmap:
- Eradicate the “fix-it on-site” culture: In wartime, accepting minor manufacturing defects with a promise of on-site rectification is a fatal misallocation of risk. If borders close, projects are left with unusable materials. Acceptance must be explicitly tied to absolute conformity prior to embarkation.
- Elevate Factory Acceptance Testing (FAT): Never allow suppliers to ship materials blindly to beat port closures. Mandate strict third-party inspections at the point of origin. A failed FAT report legally severs the supplier’s access to a subsequent force majeure defence.
- Issue immediate breach notices: Timing is the difference between a total loss and a full refund. Do not engage in informal workaround discussions while a crisis escalates. Issue formal legal default notices immediately to paper the breach before the fog of war obscures the facts.
- Strict guarantee hygiene: Ensure finance departments route advance payments exactly to the SWIFT text or IBAN stipulated in the guarantee. A minor error can leave millions unsecured.
- Draft pre-existing breach carve-outs: New contracts must explicitly state that suppliers cannot invoke force majeure to excuse delays or non-conformities that originated prior to the onset of the military event.
The escalation of the 2026 conflict offers failing suppliers a tempting shield to hide supply chain mismanagement. However, regional jurisprudence sees through this illusion. By enforcing rapid default notices and rigorous inspections, project owners can ensure the financial risk of non-conformity remains exactly where it belongs: with the defaulting supplier.

Exclusive from Meed
-
-
UAE cuts trade and financial links with Iran19 August 2026
-
Abu Dhabi begins Dar Al-Funoon Saadiyat construction19 August 2026
-
Contractor wins Dubai Canal drainage deal19 August 2026
-
Maaden and Aramco sign deal to create joint venture18 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Libya and Tunisia reschedule joint oil and gas licensing round19 August 2026
The Libyan-Tunisian Joint Oil Exploration, Exploitation and Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.
The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.
Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.
The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.
Significant data are available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.
The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.
Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).
LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.
Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.
The key dates from the new schedule for the licensing round are:
- 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
- 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
- 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
- 31 December 2026: Bid round closes
- 8 January 2027: Bid submissions due
- 26 February 2027: Winning bidders notified
- 30 April 2027: Formal awards expected
Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.
Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.
A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.
Despite this, the field has remained undeveloped for over three decades.
One of the key challenges to developing the reserve is its high carbon dioxide content.
Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main.jpg -
UAE cuts trade and financial links with Iran19 August 2026
Register for MEED’s 14-day trial access
The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.
The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.
The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.
It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.
The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.
The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg -
Abu Dhabi begins Dar Al-Funoon Saadiyat construction19 August 2026

Register for MEED’s 14-day trial access
Abu Dhabi-based piling contractor APCC Piling & Marine Contracting has started the enabling works on Dar Al-Funoon, a cultural development near the Saadiyat Cultural District.
The project, commissioned by the Department of Culture & Tourism – Abu Dhabi, was designed by the late Canadian-American architect Frank Gehry.
The venue is scheduled to open in 2030.
MEED understands that the main contract bids are under evaluation and the project is slated for award soon.
The complex will feature a multipurpose hall with more than 2,000 seats, a 3,500-seat open-air amphitheatre, a 400-seat studio theatre and a 250-seat jazz venue, bringing total capacity to more than 6,000 across its performance spaces.
The venue will host leading international productions, delivering high-quality cultural experiences for audiences locally, regionally and globally.
Upon completion, it will become one of the region’s largest performing arts venues.
The project was announced by Sheikh Khaled Bin Mohamed Bin Zayed Al-Nahyan, Crown Prince of Abu Dhabi and Chairman of the Abu Dhabi Executive Council in June, as MEED reported.
During a review of the plans, he was briefed on the architectural concept and the development and construction phases, as well as the venue’s advanced technical capabilities, which are being designed to meet the highest international standards for staging major global productions.
The announcement is part of the ongoing development of Saadiyat Island, which already includes Louvre Abu Dhabi, Zayed National Museum, Natural History Museum Abu Dhabi, teamLab Phenomena Abu Dhabi and the upcoming Guggenheim Abu Dhabi.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18852155/main4145.jpg -
Contractor wins Dubai Canal drainage deal19 August 2026

Register for MEED’s 14-day trial access
Local firm Detech Contracting has won an engineering, procurement and construction (EPC) contract to upgrade and rehabilitate the East Dubai Canal stormwater system.
The project, known as TF-16-C1, is part of Dubai’s Tasreef strategic plan to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
According to a source, Lebanon's Khatib & Alami has also been appointed as a consultant on the project.The works will focus on upgrading existing stormwater infrastructure to increase capacity and improve reliability during heavy rainfall.
The scope includes upgrading the stormwater drainage system, laying pipelines and constructing manholes and gullies. It also includes the construction of pumping stations and diversion works, site clearance and other associated facilities.
In February, MEED reported that the municipality had invited consultants to qualify for a contract to supervise three stormwater drainage projects (TF-16-C1, TF-15-C2 and TF-13-C1)
China State Construction Engineering Corporation announced in July that it had won the EPC contract for the TF-15-C2 stormwater drainage network project located on Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
MEED understands contractor bids are still being evaluated for the TF-13-C1 project, which focuses on developing a drainage system for the Al-Marmum area.
Detech has been awarded several packages under the Tasreef programme in the past 18 months.
These include:
- TF-16-C1: upgrading and rehabilitation of East Dubai Canal stormwater system
- TF-15-C1: stormwater drainage system at Al-Wasl Road for communities west of Dubai Canal
- TF-05-C1: stormwater drainage system in Jebel Ali
- TF-04: stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road
- DS-419: Tasreef rainwater drainage network: West Deira stormwater system upgrade and rehabilitation
As MEED exclusively reported, the municipality recently issued a letter of award for the TF-15-C1 project, covering the construction of a stormwater drainage system on Al-Wasl Road and communities west of Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
This week, Dubai Municipality also issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.
The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.
All three have bid submission deadlines of 10 September.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18850438/main.jpg -
Maaden and Aramco sign deal to create joint venture18 August 2026
Register for MEED’s 14-day trial access
Saudi Arabian Mining Company (Maaden) and Saudi Aramco have signed a shareholders’ agreement to form a joint venture (JV). Maaden will hold a 51% stake in the JV, while Aramco will own the remaining 49%.
Before signing the shareholders’ agreement, the two Saudi state-owned companies signed a non-binding heads of agreement in January 2025 aimed at establishing the JV.
“Combining the strengths of two leaders in their respective fields, the JV will focus on copper and other minerals critical to the energy transition,” the two parties said in a joint statement.
The JV will focus on exploration across Zone 4, also known as the Transition Zone, within the Arabian Platform in Saudi Arabia. Spanning approximately 182,000 square kilometres – nearly 10% of the kingdom’s total land area – the expected exploration area stretches along a 100-kilometre-wide corridor running parallel to the Arabian Shield.
“It represents a major new opportunity for mineral discovery in the kingdom,” Maaden and Aramco said.
Copper, which is increasingly significant for electric vehicles, power networks, energy storage and renewable energy systems, will be a main focus of the JV.
Copper accounts for more than 20% of the $1.2tn mined-metals market. The copper market is currently valued at about $250bn and is projected to grow to more than $400bn by 2035.
The JV will also explore for other energy transition minerals, including zinc, lead and rare earth elements, “that are expected to be crucial to industries of the future”.
“Leveraging advanced computational algorithms, [artificial intelligence] AI, and high-performance computing, the JV intends to target areas most likely to contain copper and valuable minerals, accelerating the path from regional screening to target definition and discovery. This is expected to support long-term sector development, reinforce the kingdom’s role in the global minerals value chain, and help meet rising demand for transition minerals,” the partners said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18833329/main.jpg